HomeMy WebLinkAbout12- Tetra Tech Monitoring Well Installations at the Bozeman Sanitary Landfill TASK ORDER MONITORING WELL INSTALLATIONS BOZEMAN SANITARY LANDFILL February 3, 2012 CLIENT; CONSULTANT: The City of Bozeman Tetra Tech, Inc. P.O. Box 1230 851 Bridaer Drive, Ste 6 Bozeman, Montana 59711-1230 Helena, MT 59715 Attention: Mr. Dustin Johnson Attention: Mr, Mark F. Pearson SCOPE OF SERVICES: Tetra Tech is pleased to submit this task order for four (4) additional well installations at the Bozeman Landfill (Figure 1). This task order is presented in response to our recent meeting (January 4, 2012) and correspondence from the Montana Department of Environmental Quality (DEQ) dated November 18, 2011' requesting that additional monitoring wells be drilled/installed to determine the extent of impacted groundwater at the site. Specifically, the DEQ requests that one well (to approximately 60 feet depth) be drilled/installed north of the shop building to monitoring the downgradient extent of impacted groundwater, and two 'deep'wells (to approximately 100 feet depth) be drilled/installed near MW-6 and MW-SA/B and become point of compliance (POC)wells monitoring the condition of groundwater from a deeper interval of the underlying aquifer. In addition, the City of Bozeman accepts a suggestion by DEQ in their November 18, 2011 letter to drill/install one monitoring well near methane monitoring point BLG-10 for the purpose of evaluating the condition of groundwater in the vicinity of the south/southwest margin of the Unlined Closed Cell (Figure 2). It is anticipated that this well will have a completion depth of 70 feet depth. Details of our proposed work are presented below: Task 1: Task Order Preparation, Project Management, and Drilling Contractor Selection Tetra Tech has recommended to the City of Bozeman that the monitoring wells be drilled and completed using the hollow-stem auger (HSA) technique, however, drilling companies with these types of drilling rigs are out of town and would incur mobilization and per diem costs. The HSA drilling technique allows for sampling of the geologic materials in a relatively undisturbed condition while the drilling progresses. The documentation of the geologic materials will complement subsurface geologic information of the site. Therefore, Tetra Tech has solicited bids from HazTech Drilling in Billings, Montana and O'Keefe Drilling in Butte, Montana both of whom have HSA drilling rigs. A third bid was also solicited from Red Tiger Drilling in Logan, Montana. Tetra Tech considers all of the contractors well suited for the work. Bids are contained in Attachment A. Tetra Tech recommends using HazTech Drilling based on their lower bid price and use of a more powerful drilling rig (HazTech's BK-81 vs. O'Keefe's BK-61). Task 2: Clearance of Underground Utilities and Health and Safety Plan Update Prior to well drilling and installation, each drill location will be cleared of underground utilities at the site. Utilities will be located using the Montana 811 underground utility locate service, This may Page 1 of 3 also necessitate a custom locate of facility underground utilities by this service. Tetra Tech will verify that each drill location has been cleared prior to drilling. Tetra Tech's Health and Safety Plan (HASP) will be updated to accommodate the monitoring well installation activities and manage the drilling subcontractor accordingly. Task 3: Drilling and Installation of Monitoring Wells The drilling and installation of the monitoring wells will consist of the following activities: • Borings for the wells will be drilled using HSA drilling techniques. Soil samples will be collected at approximate five-foot intervals while drilling using a split-barrel sampler in general accordance with the procedure described in ASTM D-15862. • Lithology of the recovered soil samples will be described. Sampled intervals will be containerized in sealable plastic bags and stored on-site. • Between drill holes, downhole drilling and sampling equipment will be decontaminated on- site using a high pressure, hot water washer. • Soil borings will be completed as 2-inch diameter monitoring wells. The screened interval will be determined following a review of site well logs, prior to the drilling and installation of monitoring wells. Table 1 (Attachment A) presents prospective casing and screened intervals that was used for subcontractor bidding. • The wells will be constructed using an interval of factory slotted (0.01 or 0.020-inch slot openings), Schedule 40 PVC well screen and Schedule 40 PVC well casing. A 10-20 grade silica sandpack will be installed adjacent to the screened interval from the total depth of each well to approximately one or two feet above the top of the well screen. The remainder of the borehole will be filled with bentonite chips. Cement grout will be used at the surface of each well to secure a stick-up, locking well protector. • Each well will be developed with either a submersible pump or bailer to remove fine- grained sediment • Well development water, decontamination wash water, and drill cuttings will not be collected. Wash water and drill cuttings will be dispersed adjacent to each well location. • Well elevations will be determined using a rod and level measuring the difference in elevation from other nearby wells. Task 4: Reporting A brief report will be prepared summarizing the monitoring well installations. The report will include monitoring well logs, a location map, and other related observations. The driller will be expected to file well logs with MBMG as required under ARM 36.21.809 Page 2 of 3 SCHEDULE AND BUDGET Tetra Tech will schedule this work upon receiving authorization to proceed from City of Bozeman and DEQ. Drill rig mobilization costs in the Schedule of Fees (Attachment B) are from Billings, Montana and return. We will present a report of our field activities within 14 days of the well completions. Estimated costs to complete the foregoing scope of services will not exceed $27,782. The work described above will be conducted with invoicing based on actual time and expenses according to the attached Schedule of Fees (Attachment B). These fees are estimates only and may vary according to site conditions. Drilling/well installation costs have also been estimated according to anticipated subsurface conditions and interception of groundwater. However, Tetra Tech will not exceed these estimates without City of Bozeman approval. With approval, additional costs or costs for additional services will be incurred on a time and material basis using the rates and time estimates presented in Attachment B. Execution of this task order constitutes acceptance of all terms and conditions contained in Tetra Tech's Professional Services Agreement with the City of Bozeman, dated January 3, 1994 and Amendment Nos_ 1, 2, 3, and 4 of the Professional Services Agreement dated July 31, 1995; January 1, 1996; March 17, 1997; and December 10, 2001, respectively. AUTHORIZATION To authorize implementation of this task order, please sign in the space below and return this task order to our Billings, Montana office. CLIENT: CONSULTANT: City of Bozeman Tetra Tecb. ` f i By: By: Its: tA Qh A d e ` NJ Date: Date: 2U 1 November 18, 2011, DEQ, City of Bozeman Landfill -- Gallatin County — License #196, Report of Groundwater Monitoring Activities—June 2011. Correspondence to City of Bozeman. NOTICE OF CONFIDENTIALITY This Task Order(including attachments) contains infonnation confidential to Tetra Tech, Inc., its subsidiaries, and subcontractors. it is intended only for City of Bozeman to consider Tetra Tech providing professional services at the Bozeman Landfill. Any other use is prohibited, without the prior'written consent of Tetra Tech. Page 3 of 3 1T ♦ �' i 1442A+; `♦� f CLASS IV e_• CELL C"�1�9 X465 --ec\♦_ o C j� . a r Inn Z el I a •i , � I r 80Z \ E 31 i i � s� 4706 '? Driy �ti 479 ■'f.'' f i �A/K 1 �' \ _ ;�-� , ••is g T \ •• - ti ceM 17 , S C ( a,k s ♦� tl aa. to Joe i �;& I ! -1 3 ; �I a r- W 'i r ! i miss 97 ST -�� � — �. _ t r ` S IF . STy 4 I 1 � 7pwFK �X �78aAT,� L'IR7 ,� 1 r{ wf t . It r cc� Q t 'Ah�l . r F 976 1 !.i p 0 Feet 20 bTM pM MW tln .1h.•119fti e,pmddd d TET TECH.ThM drrvdng=not h Mnoaft prk tW.—nt.ITETFtA TECH.AlAft.NA•M T.d (tETpkm M. U 1,1 wPYM,PUq.,.orthk X.J TETATECM do.--K.V.hntn noMbnk-6. Decomb ei-2010 From USGS 7,5"Bozeman Quad(1987) Site Location Map MWO Bozeman Sanitary Landfill Bozeman, Montana 114.710303.400 FIGURE 1 d m CV Or_ LL z ca C N JIlW ItIN Oj IN n R � m M C q p ff v Y� o t • ■ E 9" I x � o �r m --,g e�+ River Ga i »'li�'+x6 �VIVL�ourwd LVILta49 VS 6wvI0e1,�-0o—l�w[n�VS\m\�wc-awc wewl w+.raoe cocoa—ill\�'xaw'l� og�,w.eoe w�1[�w�Iad�:� ATTACHMENT A N O N h m!71 7 C H Q ca m m m N i {1 II II ll C L 0 w � W m u C V y d d Y 0 N �0 ? L N N N N O C C7 N m N tryd 'N-I v^-t tM0 Ol a P Y Y A � a Z u u n n m v v °n c V � m M m co V) C Q m Z 4 N N ON ON O 4 a Z G H 0 4 0 0 V W F N r-I li O N in � a 4 Z z M u o t o d o 0 az M m o ^ o � rW.lz 0 Qm O C7 rn — vl o Q M M a a �- m x a o 0 n° ID v a L a+ C C m W > w CL u U it u o nn on v A A b m m a�i v a�i O O Q ♦• G Y O G Z C fb 1l�1 m U UI H (i5 UY ICH DrE[!lw ng,Inc. P.O.Hog 30622 2916 Hannon Road,Suite#6 Hillings,MT 59107 Phoae:406-8964164 or 800-354-1502 FAX:40196-146,2 Proyos8Y TO: Tetra Tech, Inc. ATTN: Marls Pearson DATE: 1/10/2012 851 Bridger Drive, Suite 6 INVOICE 9: Bozeman, MT 59715 PROJECT:North of Shop Well Ph-406-592-8780 Bozeman, MT Description, P.O.*: North of Shop We11-1-60ft with 20ft of TERMS: Net 30 Days screen, UNITS UNIT AMOUNT EST, PRICE EST. r•�#6POti4pASSr►frrrrri�p„r rrywMwlW4 Cwanerwraa• rt4v9g9$soaoae Mob/Demob, Lump Sum 1 $150.00 $150.00 Support Truck, Per Day 2 $75.00 $150.00 Perdiern, Per Crew Day 2 $48.00 $82.00 Lodging, Per Night, Estimated 1 $200.00 $200.00 Auger Drilling, Per Ft,2 Inch Wells 60 $16.00 S1,C)50.00 Well Installation, Per Ft,2 Inch Wells 60 $17.00 $1.020.00 Decon, Par Hr 1 $150.00 $150.00 Steel Stick Up covers with concrete, Each 1 $150.40 $150.00 Wall Development, l=atch 1 $250.00 $250.00 Standby 0 $135.00 $0.00 ESTIMATED TOTAL: $3,242.00 Notes: 1)This job is bid In Conjuctlon with tho other wells on the landfill. 2)Well Development will be with a Hurricane down hole puonp. 3)We will use our 1983 Longyoar SK-01 drill Fdg an this project. 1)Client is responsible to clear location of utilities. 2) Client is responsible For disposal of drift cuttings. 3)Client will be invoiced only the amounts used. 4)We assume that site is accessible by truck mount drill rig. Proposal By, Paul Bray TTECH�*nnp,im- P.O.But 30622 2916 Hannon Road,Suite#6 Billings,MT 59107 f Phone.406-896-1384 ar 800-3591502 Pat; 406-896-1462 Pr TO: 'Petra Tech, Inc. ATTN.' Mark Pearson DATE: 111012012 951 Brldger Drive, Suite 5 INVOICE#: Bozeman, MT 69715 PROJECT:Landfill Ph-4OM82-8780 Sozeman, MT Description: P.O.# 2.100ft wells and 1-70ft yell. TERMS: Net 30 Days UNITS UNIT AMOUNT EST. PRICE EST. YaraOmf90p�paP9@ir i.FraMra OvK4µfiN aas�aq�saav 1•ara�aww aaa Mobl Demob, Lump Sum 1 $1,100.00 $1,100.00 Support Truck, Per Day 5 $75.00 $375.00 Perdiem, Per Crew Day 5 $46.00 '$230.00 Lodging, Per blight, Estimated 5 $200.00 $1,000.00 Auger Drilling, Per Ft,2 Inch Wells 270 $18,00 $4,860.00 Well Installation, Per Ft,2 Inch Wells 270 $17.00 $4,590.00 Decon, Per Hr 3 $150.00 $450,00 Steel Stick Up covers with concrete, Each 3 $150.00 $454.00 Well Development, Each 3 $250.40 $750.00 Standby 0 $135.00 $0,00 n►aasMaa+ltYO ESTIMATED TOTAL; $13,806.00 Notes; 1)This Job Is bid In Conjuction with the other vroll Hoilh of the Sinop. 2)Well Development will be with a Hurricane down dole pump, 3)We will use our 1993 Longyear BK-911 Drill Rig on this project. 1) Client is responsible to clear location of utilities. 2)Client is responsible for disposal of drill cuttings. 3)Client will be invoiced only the amounts used. 4)We assume that site is accessible by truck mount drill rig. Proposal By, Paul Bray 1 P.O.Box 3810 Butte Montana 59702 Office:(405}494-3310 Fax:(406)494-3301 Client: Tetra Tech Dale: 06-Jan-12 Attention: Mark Pearson Phone; 406-582.6780 Project: Bozeman Landfill-North of Shop Fax- 406.562-6790 Cell: 406.459-4169 PROJECT SPECIFICATIONS: Type of Rig; Mobile B-61 Auger Number of Wells: 1 Location: Bozeman Landfill-North of Shop�Expected Footage: 60 Formation: Gravels Completion PVC Slze: 2 Sampling; Y s Screen Length: 20 Decontamination: YYes,�wl hot pressurized wal r� Flushmounts Other Details: .010 Bid for Sol]Boring/Monitoring Well Installation Unit Cost Worksheet Task Unit Number of Total Cost Cost Units Mobil izationlDemobilization• 000 Rig:Butte 5 2.25 Miles $ _ Support VehiclelCrew Travel:Butte $ 1.75 Mlles $ Per Diem Crew Members _ Per Person Motel 2 $ 70.00 Per Day $ Per Person Food 2 $ 32.00 Per.Day ^� Soil Boring Installation Drilling 0-50 ft range S 22.00 Perroot 60 $ 1,320,00 Other Monitor Well Installation 2" Drilling 0-50 h range S 24.00 Per Fool 60 $ 1.440.00 Other $ Drilling Standby&Safety Meeting Prior Approval Needed $ 165.00 Per-Hour $ Well DevetopmentSurge Block or Bail Well Development $ 250.00 Per Well 1 S 250.00 Total Project Expenses $ 3,010.00 "Mob is based on completing project as a whole P.Q.Box 3810 Butte Montana 59702 Office:(406)494-3310 Fax:(406)494-3301 Client: Tetra Tech Date: 06-Jan-12 Attention: Mark Pearson Phone: 406-582-8780 Project Bozeman Landfill Fax: 406.582-8790 Celt: 406-459-4169 PROJECT SPECIFICATIONS: Type of Rig: Mobile B-61 Auger Number of Wells: 3 Location: 8axeman 1.ndfill Expected Footage: 100, 100,70 Formation: Sil Cla _ Completion PVC Size: 2 Sampling: Yes _ Screen Length: 10,10, 15 Decontamination: Yep,w hot pressurized water Flushmounts Other Details: .020 Bid for Soil Boring/Monitoring Well Installation Unit Cost Worksheet Task Unit Number of Totaf Cost Cost units Mobilization/Demobilization Drill Rig:Butte S 215 Miles 168 S 378.00 Support VehicieiCrew Travel:Butte $ 1.75 Mites 168 5 294.00 Per Diem Grew Members Per Person Motel 2 $ 70.00 Per Day 5 S 700.00 Per Person Food 2 $ 32.00 Per pay 5 $ 320.00 Soil Boring Installation Drilling 0-50 ft range S 22.00 Per Foot 270 5 5,940.00 Other Monitor Well Installation 2" Drilling 0-50 ft range $ 24.00 Per Foot 270 S 6,480.00 Other 5 Drilling Standby 8 Safety Meeting Prior Approval Needed $ 165.00 Per Hour 5 Well Development-Surge Block or Bail Well Development $ 25100 Per Well 3 $ 750.00 Total Project Expenses $ 14,862.00 RED TIGER DRILLING, INC. PROPOSAL PO BOX 659 MANHATTAN, MT 59741-0659 Bate 2/1/2012 Flame/Address Tetra Tech Inc Attn Mark F Pearson 851 Bridger Drive Suite 6 Bozeman MT 59715 Phone# Project Location MT DRILL LIC##598 MWC#365 582-8780 Bozeman LF Description Qty Cost Pe.., fatal 6"X 2"X 60'MONITOR WELL(NORTH OF SHOP) Mobilization/Equipment 0.00 0.00 Drill&Drive 6 5/8".250 A53 Steel Casing,Set 2"X 20'0.10 Slot Monitor Screen%vl 40' 60 55.54 I°7 3,330.00 X 2"Flush Joint Riser Pipe/Pull back 6"Steel Casing&pack Screens iv/10-20 Silica Sand T above Screens/3/8"Bentonite Chips to Surface`v/Protector Pipe&Locking Caps Rig Time for Air Development/Stand by$250.00 per hour,no charge Ist hr... Total Well Estimate$3330.00 6"X 2"X 100'MONITOR WELL(6) Drill&Drive 6 518".250 A53 Steel Casing,Set 2"X 10'0.20 Slot Monitor Screen w/90' 100 55.50 FT 5.550.00 X 2"Flush Joint Riser Pipe/Pull buck 6"Steel Casing&pack Screens w/10-20 Silica Sand 3'above Screens/ 3/8"Bentonite Chips to Surface w/6"Protector Pipe&Locking Caps 6"X 2"X 100'Monitor Well(8A1B) 104 55.50 FT 5.550.00 6"X 2"X 70'MONITOR WELL(BLG-10) Drill&Drive 6 518".250 A53 Steel Casing/Set 2"X 15'0.20 Slot Monitor Well Screen w/ 70 55.50 FT 3,885.00 55'X 2"Flush Joint Riser Pipe/Pull back 6"Steel Casing&pack Screens w/10-20 Silica Sand 3"above Screens/ 3/8"Bentonite Chips to Surface w/6"Protector Pipe&Locking Caps ***WELLS INCLUDE CENTRALIZERS AS NEEDED,LOCKING 6"MONITOR WELL CAPS&2"LOCKING EXPANSION PLUGS W/2"CASING BOTTOMS,DRILL PIPE, TOOLS AND STEEL CASING STEAM CLEANED PRIOR TO DRILLING WELLS, Date/Signature ofAcceptancc Total s18.315.00 All quantities listed above arc estimate only. Some may have higher or lower quantities.The above prices, Signature/Date of acceptance specifications and conditions are satisfactory and arc hereby accepted. Phone# 406-284-69I6 ATTACHMENT B Task Order-Monitoring Well Installations Bozeman Sanitary Landfill City of Bozeman, Gallatin County, Montana SCHEDULE OF ESTIMATED FEES February 3,2012 Schedule of fees submitted by Mark P.Pearson,Tetra Tech,Inc.,Bozeman,Montana TASK RATE QUANTITY COST Task 1:Task Order Preparation,Project Management,and Drilling Contractor Selection Senior Scientist,per hour $100.00 1.0 $100.00 Project Scientist,per hour $88.00 16.0 $1,408.00 Administrative Assistant,per hour $60.00 2A $120.00 SUBTOTAL $1,628.00 Task 2:Clearance of Underground Utilities and Health and Safety Plan Update Project Scientist,per hour $88.00 4.0 $352.00 Vehic[e mileage,per mile $0.80 10,0 $8.00 Custom Utility Locate,estimate $200.000 1.0 $200.00 SUBTOTAL $560.00 Task 3:Drilling and Installation of Monitoring Wells Project Scientist,per hour $88.00 60.0 $5,280.00 Vehicle mileage,per mile $0.80 30.0 $24.00 Miscellaneous materials,estimate $60.00 1.0 $60.00 Surveying equipment rental,estimate $40.00 1.0 $4100 SUBTOTAL $5,404.00 Drilling Subcontractor Activities Installation of three monitoring wells for a sum of 330 feet drilling and well completion Haz Tech Drilling,Billings,Montana January 10,2012 Proposal(Attachment A) $17,047.00 1.0 $17,047.00 Tetra Tech subcontractor invoice processing markup(10%) $1,704.700 1.0 $1,704.70 SUBTOTAL $18,761.70 Task 4:Reporting Senior Scientist,per hour $100.00 1.0 $100.00 Project Scientist,per hour $89.00 12.0 $1,068.00 Drafter CAD,per hour $75.00 2.0 $150.00 Administrative Assistant,per hour $60.00 2.0 $120.00 SUBTOTAL $1,438.00 TOTAL $27,781.70 Tetra Tech Page 1 of 1 Commission Memorandum CO REPORT TO: Honorable Mayor and City Commission FROM: Dustin Johnson, Project Engineer Debbie Arkell, Director of Public Services SUBJECT: Amendment to Professional Services Agreement with Tetra Tech Inc. for Installation of four additional groundwater monitoring wells. MEETING DATE: February 27, 2012 AGENDA ITEM TYPE: Consent RECOMMENDATION: Authorize City Manager to sign the Amendment to Professional Services Agreement with Tetra Tech Inc. for installation of four additional groundwater monitoring wells for the amount not to exceed$27,782. BACKGROUND: The City of Bozeman has been required by the Montana Department of Environmental Quality(DEQ)to sample and monitor the environmental effects of the Story Mill Landfill since 1994. Tetra Tech (previously Maxim Technologies) has been contracted with the City to assist in the work from the beginning. The nature of the contract has been to assist the City of Bozeman in sampling, maintaining, and monitoring post closure parameters at the Story Mill Landfill to keep the landfill in compliance with State and Federal regulations. The landfill utilizes several ground water monitoring wells that have been strategically placed around the landfill and surrounding property to determine if the landfill impacts the underground aquifer. DEQ has questioned whether the existing wells provide adequate monitoring information. To provide answer to those questions,they required a work plan proposing where additional monitoring wells would be located. The DEQ agreed that the attached work plan would adequately address their concerns. The work plan calls for the installation of four additional wells. Two shallow depth wells would be installed in areas of the landfill where monitoring isn't currently taking place. One well would be 60 feet deep and located north of the shop building. One well would be 70 feet deep and located near an existing gas probe (BLG-10) along the southern boundary of the landfill. Two deep depth wells would be installed near existing monitoring wells. One well would be 100 feet deep and located near the northeast corner of the shop building. One well would be 100 feet deep next to the southern boundary of the landfill property. The monitoring of these four new wells will provide information on whether contaminants from the landfill are entering the aquifer. 1 UNRESOLVED ISSUES: None. ALTERNATIVES: As suggested by the City Commission. FISCAL EFFECTS: With the drilling of the wells, project management,reporting, and data analysis, the total cost of this task order is $27,782. The entire project will be funded through the Solid Waste Landfill Closure/Post-Closure Fund. This fund is required by the DEQ to be maintained to ensure there are adequate fiends for closure/post-closure activities required at landfills. There is currently $1,613,076.53 in this fund. Attachments: Tetra Tech Task Order/Proposal DEQ correspondence approving the proposed work plan Report compiled on: February 9, 2012 2