HomeMy WebLinkAboutResolution No. 4361, Change order 1 for Main Pool Pump replacement project at swim center Commission Memorandum
REPORT TO: Honorable Mayor and City Commission
FROM: James Goehrung, Superintendent of Facility Services
Chuck Winn, Assistant City Manager
SUBJECT: Approve Resolution 4361 authorizing the City Manager to sign
Change Orders #1, for the main pool Pump Replacement Project at the Bozeman Swim Center
1211 West Main Street. The combined Change Orders for this resolution is for the dollar
amount of $1,070.00.
MEETING DATE: January 9, 2012
AGENDA ITEM TYPE: Consent
RECOMMENDATION: Approve Resolution 4361 authorizing the City Manger to sign
Change Order #1 for the main pool Pump Replacement Project at the Bozeman Swim Center
1211 West Main Street in the amounts of $1,070.00
BACKGROUND: Facilities has been working with Dan McCarthy at the Swim Center to
fully close out the pump replacement project. The main pool pump malfunctioned in September
of 2009. During the process of getting the pool back on-line the aquatic staff met with many
parties (repairmen, water dept., and engineers) to determine the best fix. The pump was repaired
well enough to get through the remaining fiscal year. The consensus was to replace the pump as
soon as possible.
The pump system was replaced with a high efficiency pump that is 10% more efficient than the
current pump. This will reduce the amount of electricity needed to keep the pool water
circulating. A variable frequency drive (VFD) was installed to control the speed of the pump
depending on the need for flow. This drive will be controlled by the flow rate of the water going
into the pool. The advantage to this system is that the pump is only spinning as fast as it needs to
maintain the water flow rate that is needed at the time. The previous pump ran at full speed at all
times and then a manual butterfly valve was used to scale back the volume of water.
Pg 1
43
In the VFD system as the filters become more plugged with dirt, the VFD will provide a greater
amount of power to maintain the proper amount of water flow. The opposite situation is also
true, that as the filters are cleaned the amount of power needed is reduced, and then the VFD will
provide less power, therefore less energy consumption.
During the installation of the pump there were some reviews and recommendations made to
change the installation of the pump. The pump discharge assembly was raised to allow for a new
flex connector. These changes, recommended by the contractor and approved by the engineer,
were to maintain the efficiency of the system are the reason for the change order.
UNRESOLVED ISSUES: In reviewing the project there were some items that needed to be
formalized. Even though the Change Order did not exceed the budget the change does need to
be approved through Commission action, thus the reason for this agenda item. Staff is still
monitoring the operation of the pump. One of the connections was not seated properly and was
changed out under warranty.
ALTERNATIVES: As suggested by the City Commission.
FISCAL EFFECTS: The pump and lighting change out included a provision for
liquidated damages in order to minimize closure of the Swim Center. There were some problems
with some of the suppliers. Substantial completion as granted on April 5, 2011 which was 11
calendar days after the substantial completion date listed in the contract.
Some additional engineering costs were also paid on the project. The engineer provided some
additional services to the city to prepare the needed documentation to receive a rebate from
NorthWestern Energy under their E+ Program for the anticipated energy savings from the more
efficient pump. The rebate on the project was $2,200.00. On one occasion the engineer was
called in by staff to provide troubleshooting and operational support to keep the system running.
The engineer was also instrumental in validating the liquidated damage charges and provided
additional services during the 11 additional days it took to complete the project. Staff checked
with the Engineering Department to confirm that the charges for additional services were
acceptable. Engineering confirmed that the additional engineering fees of $1,653.63 were
reasonable.
The added Change order cost and the additional engineering fees for some extra work that was
requested and some additional time to close out the project are covered by the $5,500.00 in
liquidated damages.
A summary of costs is outlined below:
Pg 2
44
Swim Center Equipment Change Out Project Budget
Total Budget: $52,142.00
Contractor: $40,342.00
Engineer: $11,800.00
Change Order #1: $1,070.00
Additional Engineering: $1,653.37
Amount Spent: $54,865.37
Liquidated Damages: +$5,500.00
Energy Rebates: +$2,200.00
Subtotal: $47,165.37
Balance Remaining: $4,976.63
Attachments: Change Order Form #1
Change Order Resolution # 4361
Report compiled on: December 20, 2011
Pg 3
45
1 of 2
COMMISSION RESOLUTION NO. 4361
A RESOLUTION OF THE CITY COMMISSION OF THE CITY OF
BOZEMAN, MONTANA, APPROVING ALTERATION/MODIFICATION OF
CONTRACT WITH F.L. DYE, BOZEMAN, MONTANA.
WHEREAS, the City Commission did, on the 6th day of December 2010, authorize award of
the bid for the Replacement of the Pump System at the Bozeman Swim Center at 1211 West Main Street
to F. L. Dye, Bozeman, Montana; and
WHEREAS, Section 7-5-4308, Montana Code Annotated, provides that any such alterations or
modifications of the specifications and/or plans of the contract be made by resolution; and
WHEREAS, it has become necessary in the prosecution of the work to make alterations or
modifications to the specifications and/or plans of the contract.
NOW, THEREFORE, BE IT RESOLVED by the City Commission of the City of Bozeman,
Montana, that the proposed modifications and/or alterations to the contract between the City of Bozeman,
a municipal corporation, and F. L. Dye, Bozeman, Montana, as contained in Change Orders #1, attached
hereto, be and the same are hereby approved; and the City Manager is hereby authorized and directed to
execute the contract change order for and on behalf of the City; and the City Clerk is authorized and
directed to attest such signature.
46
Resolution No. 4361, Change Order#1
Page 2 of 2
APPROVED by the City Commission of the City of Bozeman, Montana, at a regular session
thereof held on the 9th day of January 2012.
__________________________________________
SEAN E. BECKER
Mayor
ATTEST:
________________________________________
STACY ULMEN, CMC
City Clerk
APPROVED AS TO FORM:
__________________________________________
GREG SULLIVAN
City Attorney
47
48
49