HomeMy WebLinkAbout11- Change Order 2, Water Treatment Facility Membrane Procurement, Pall Corporation jolso CHANGE ORDER
�A h RLE tx No. 2
DATE OF ISSUANCE 9-13-11 EFFECTIVE DATE 9-13-11
BUYER City of Bozeman SELLER Pall Corporation
Contract:
Project:BOZEMAN WATER TREATMENT FACILITY
Membrane Procurement BUYER's Contract No.
ENGINEER HDRfMMI ENGINEER's Contract No.0000088114
You are directed to make the following changes in the Contract Documents:
Description: Change in scope of supply,see attached summary.There is no change in contract time resulting from
this change order.
Reason for Change Order: Changes due to detail design and shop drawing review following procurement.
Attachments: (List documents supporting change)
CHANGE IN CONTRACT PRICE: CHANGE IN CONTRACT TIMES:
Original Contract Price Original Contract Times:
5,558,3()0.00 Substantial Completion: NA
Ready for final payment; NA
(days s or dates)
Net Increase(Decrease)from previous Change Orders Net change from previous Change Orders No. I to No. 2
No. 0 to 1 Substantial Completion: NA
Ready for final payment:NA
0.00 (days)
Contract Price prior to this Change Order: Contract Times prior to this Change Order:
Substantial Completion: NA
$ $5,558,300.00 Ready for final payment:NA
(days,or dates
Net increase(decrease)of this Change Order: Net increase(decrease)this Change Order:
Substantial Completion:NA
$(44,698.00) Ready for final payment: NA
(days)
Contract Price with all approved Change Orders: Contract Times with all approved Change Orders:
Substantial Completion:NA
$ $5,513,602.00 Ready for final payment:PIA
(days or dates)
Seller certifies and agrees that there are no additional costs or claims for extra work, additional time, delays or omitted
items,of any nature whatsoever,associated with the subject change order items,except as identified and set forth herein and
unless expressly stated otherwise in the Change Order, And further, that the price agreed-upon herein represents the full
cost an value for the subject work performed and the materials supplied under the terms of the contract and that the work
y a t' es nd value were properly determined and are correct.
(Authorized ignature) Date
RE ENDED BY: PROV D B
NGINE R-Signature) Date BUYER(Authorized Signature) Date
0088114 City of Bozeman
Hyatim/Sourdough"treatment PlanC Membrane Equipment Procurement
City of Bozeman, 01.00163,Adders/Deducts Summary
Date: 8124111 CHANGE Order 2
Item# Item Description Cost per Unit Units Cost
I Deduct Auto-Strainer Control Panel Deduct ($9,338) 8 ($74,704)
2 Add Pneumatic Butterfly valve/control to CIP process for draining $740 1 $740
CIP Return Pipe located in the trench, 1
3 Deduct HV-4405A, sample ball valve ($25) 1 ($25)
4 Deduct HV-4406A, actuated butterfly valve, 12" ($710) 1 ($710)
5 Deduct HV-4407A, 2" butterfly valve ($50) 1 ($50),
6 Deduct LSHH-4404A, LSLL-4403A ($260) 2 ($520)
7 Deduct LIT-4402A ($1,700) 1 ($1,700)—
8 Deduct BWW Equilization Tank T-4400A, reference#142 ($1 ,500) 1 ($18")00)
..........
9 Add FIT-8203 (14 inch Magmeter), reference#1 $17,500 1 $17,500
10 Add FIT-8204(12 inch Magmeter), reference#1 $12,750 1 $12,750
11 Deduct Particle Counters (1 each) AIT4006 and Mobile Particle ($7,000) 2
Counter, reference#276
12 Deduct F14022 Flow Indicators for particle counters, reference p8o) 2 ($160)
#276
13 Deduct Isolation HV-4062 Ball Valves for particle counters, ($25) 2 ($50)
reference#276 1
14 Add Upsize to a 1 1/2 inch strainer for Sodium Hypochlorite (CIP $80 1 $80
Chemical Transfer Strainers), reference#66
15 Deduct Bisulfite needs to be a 1/2 inch strainer, reference#67 ($50) 1 ($50)
16 Add test connection point to feed pump suction/discharge PI $220 10 $2,200
gauges, reference#136
17 Add pressure differential across each strainer, reference#138 $900 8 $7,200
18 Deduct reduce the feed pump suction valve size from 20"to 16", ($900) 5 ($4:1500)
reference#139
Deduct RIF pump suction valve reduced from 12"to 8", reference
19 #145 ($2(1 2 ($400)
Add Diaphram valves in place of various ball valves, manual/HV
20 5052, HV-5125, HV-5126, HV-5163 AND HV-5180 (all 1/2" ball $25 5 $125
valves), reference#156
21 Add Diaphrarn valves in place of ball valves, actuated valves, V- $400 2 $800
5120 and V5124 (both 1/2"ball valves), reference#156
22 Deduct backflow preventer(CV6150), reference#157 ($2,100) 1 ($2J00)
23 Upgrade Compressor -upsize from the GA5 to the GA7, upsize $14,500 1 $14,500
air receiver from 620 to 1040, reference#68
24 Adder oversized termination box for RIF pump motors, reference $200 2 $400
#57
25 Add level transmitter flange fittings, reference#37 $750 4 $3,000
26 Add 18" butterfly valve HV-3194 A-D $2,000 4 $8,000
27 Deduct V-5009 butterfly valve, reference#153. ($320) 1 ($320)
28 Add HV-401 1, HV-4013, HV-3013- all upsized to 1 $20 3 $60
29 Deduct HV-5181 Acid stock tank discharge isolation valve ($24) 1 ($24)
30 Add camlok fittings to feedside module manifold pipinhg $960 6 $5,760
Total $9,763 ($44,698)