HomeMy WebLinkAboutApprove Resolution No. 4339, change orders for Shop ComplexCommission Memorandum REPORT TO: Honorable Mayor and City Commission FROM: James Goehrung, Director of Facility Services Chuck Winn, Assistant City Manager SUBJECT: Approve Resolution 4339 authorizing the City Manager to sign Change Orders 41R, 2R, 3R, 4, and 5 for the Remodel and Renovation of the City Shop Complex at 814 North Bozeman. The combined Change Orders for this resolution is for the dollar amount of $6,924.00. MEETING DATE: October 3, 2011 AGENDA ITEM TYPE: Consent RECOMMENDATION: Approve Resolution 4339 authorizing the City Manger to sign Change Orders 41R, 2R, 3R, 4, and 5 for the Remodel and Renovation of the City Shop Complex at 814 North Bozeman in the amounts of. Change Order 41R, for electrical changes, $423.00; Change Order 42R, for relocation of the washer and dryer, $2,993.00; Change Order 43R, changes for IT closet electrical, $725.00; Change Order 44, for added flooring in the hallway and men's restroom, $1,648.00; Change Order 45, for two hollow metal doors and frames, $1,108.00. Total dollar amount for these changes is $6,924.00. BACKGROUND: After completion of the new vehicle maintenance facility the second phase of the planned construction was the renovation of the City Shop Complex. The remodel work will address accessibility issues and reconfigure some of the work areas to deal with the large number of staff that work out of this facility. Work on the project started in June and is progressing well. The attached resolution includes 5 Change Orders. The bulk of the changes are owner initiated and will address the overall layout and arrangement of the facility. An explanation of each of the changes follows: Pg 1 19 Change Order 41R is for some additional electrical changes that will improve the operation of a garage door and provide power for a utility area. The "R" designation for this change is because the original change request was modified. It was pointed out that some of the electrical changes in this request were the contractor's responsibility. The price came down from the original proposal of $845.00. A new electrical service panel was installed in the mechanical room area. The service for the overhead door in that room was supplied from another box on the other end of the building. The electrical service was rerouted from the new box and the control switch for the door was moved to a new location so it can be operated from inside the room. The second electrical change is to add a receptacle box above an office area. The area over the office ceiling has some phone and data lines running along the main roof of the building. Should work need to be done on these lines there was no power supply in this area. The box was added so a trouble light can be plugged in providing a light source to work on the phone and data lines. The cost for these two electrical changes is $423.00. Change Order 42R is an owner initiated change for the relocation of the washer and dryer. The washer and dryer are used by staff in different departments to clean their work clothes that are soiled in the field. The units were originally in the mechanical room which is not a good location because of the foot traffic into the room with the heating and cooling equipment. The drain line for the washer went into a mop sink that was going to be removed in order to accommodate a new forestry office. Because the equipment needed new drain lines staff looked into the best possible location for access by staff from different departments. A location in the locker room next to the new men's ADA restroom was identified. The costs for the relocation of the washer and dryer includes plumbing, electrical, mechanical, and framing. This price came down a few dollars because a shorter route for the drain line was found. Total relocation cost is $2,993.00. Change Order 43R is an owner initiated change for the modification of the electrical service for the new IT closet. This revised change came down in price from the original quote of $1,175.00. The electrical contractor did not consider the electrical outlets that were shown on the original plans when they priced out the additional service. The IT Department and the Water Department requested a secure location for the phone and data equipment and for the radio controlled monitoring unit that serves the Water Department. Once the closet was framed in the IT Department was brought down to look at what the final layout would be. It was determined that some of the equipment would require dedicated electrical circuits to avoid any possible power surges to the equipment. Two dedicated electrical services were added to power the server rack and the water SCADA system. Total for these electrical changes is $752.00. Pg 2 20 Change Order 44 is an owner initiated change for some additional flooring to be installed on one of the main hallways and in the men's restroom. The two areas are currently concrete floors. The other hallways were scheduled for sheet flooring. The additional hallway flooring provides a better termination point at the entrance to the men's locker room. The men's restroom floor is a concrete floor with a dyed finish that is in rough shape. The contractor was willing to provide the additional flooring at the bid price which was very competitive. The flooring will clean up the room quite a bit and will be easier to maintain. Total cost for this added flooring is $1,648.00. Change Order 45 is for two new metal doors and metal door frames. The plans call for the reuse of any moved door frames as a cost saving measure. One of the doors had to be removed in order to be replaced with a fire rated door. The frame was grouted into the concrete masonry unit wall. The frame had to be removed in pieces because it was also tied in with rebar therefore this door frame could not be reused. The hinges on the door that was removed were different that the layout on the new metal door frames so the door could not be reused without a good deal of modification. The second door frame that was removed was configured for a wood framed wall and would have to be reinstalled into a concrete masonry unit framed wall. The door assembly was also a different height from the door right next to it which would not look right. Cost for these two new door assemblies is $1,108.00. UNRESOLVED ISSUES: None at this time. The bulk of the demolition work is complete. There is one more area scheduled for demolition work where the Forestry Office will be relocated. There may be some unanticipated items found requiring attention once this demolition is complete. The Walker bid shows Alternate 42, in the amount of $36,600.00, which is to replace 6 overhead garage doors with newer more energy efficient units. The contractor has been asked to hold this price and should all the money not be spent in the dollar figures shown, or another source of funds identified this work will be added through a change order. Once the project is nearing completion some of these doors may be installed. ALTERNATIVES: As suggested by the City Commission. FISCAL EFFECTS: The costs associated with the items in these Change Orders will be paid out of the project contingency fund. The Project Budget is shown below. The amount in the contingency fund is $34,986.00. Pg 3 21 Shops Complex Remodel Project Budget Walker Contract $254,950.00 Plan Review Fee $599.30 Permit Fee $927.50 Water Inspection $100.00 Sewer Inspection $20.00 Architectural Fees $19,999.00 Advertising and Printing $5,000.00 Contingency Fund $34,986.00 Furniture, Fixtures, Equipment and Owner Provided Items $23.418.20 TOTAL $340,000.00 Project Contingency Change Order #1R Change Order # 2R Change Order 43R Change Order 44 Change Order 45 $34,986.00 Electrical Changes ($423.00) Relocation of Washer and Dryer ($2,993.00) IT Electrical Changes ($752.00) Additional Sheet Flooring ($1,648.00) 2 Additional Metal Doors and Frames ($1,108.00) Total Change Orders ($6,924.00) REMAINING CONTINGENCY BALANCE: $28,062.00 Attachments: Change Order Forms #IR, #2R, #3R, 4, and 5 Change Order Resolution # 4339 Report compiled on: September 11, 2011 22 COMMISSION RESOLUTION NO. 4339 A RESOLUTION OF THE CITY COMMISSION OF THE CITY OF BOZEMAN, MONTANA, APPROVING ALTERATION /MODIFICATION OF CONTRACT WITH WALKER CONSTRUCTION, BELGRADE, MONTANA. WHEREAS, the City Commission did, on the 6th day of June 2011, authorize award of the bid for the Remodel and Renovation of the City Shop Complex at 814 North Bozeman Ave. to Walker Construction, Belgrade, Montana; and WHEREAS, Section 7 -5 -4308, Montana Code Annotated, provides that any such alterations or modifications of the specifications and /or plans of the contract be made by resolution; and WHEREAS, it has become necessary in the prosecution of the work to make alterations or modifications to the specifications and /or plans of the contract. NOW, THEREFORE, BE IT RESOLVED by the City Commission of the City of Bozeman, Montana, that the proposed modifications and /or alterations to the contract between the City of Bozeman, a municipal corporation, and Walker Construction, Belgrade, Montana, as contained in Change Orders 41R, 2R, 3R, 4, and 5 attached hereto, be and the same are hereby approved; and the City Manager is hereby authorized and directed to execute the contract change order for and on behalf of the City; and the City Clerk is authorized and directed to attest such signature. 1 of 2 23 Resolution No. 4339, Change 0rderIR,2R,R3,4,5 PASSED AND ADOPTED by the City Commission of the City of Bozeman, Montana, at a regular session thereof held on the 3rd day of October, 2011. JEFFREY K KRAUSS Mayor ATTEST: STACY ULMEN, CMC City Clerk APPROVED AS TO FORM: GREG SULLIVAN City Attorney Page 2 of 2 24 CHANGE ORDER REQUEST # 1R ---= . . . .. . .... . .......... ..... . . .......... . . . ATTENTION: FROM: Eryn Mikelson Josh Anderson PROJECT: DATE � City Shops Remodel 08/15/11 REQUESTED BY� Owner SUBCONTRACTOR:: RESPONSE I)ATE� I-laubrich Electric RE OREQUEST13YOWNFR D REQUEST RY CONTRACTOR 1:1 REQUEST 13Y SUBCONTRACTOR 0 REQUEST FOR CHANGE ORDER ❑ URGENT Add a outlet above office Materials $ 50.00 Labor 120.00 Power for North overhead door. Materials $ 70.00 Labor 145.00 Hatibrich Electric $385.00 Bond/his $ 7.00 01P 7% $ 27.00 1% TAX $_ 4.00 TOTAL $423.00 This Change Order / Proposal Request will not add additional days to the contract 270 FLOSS FLAT ROAD, STE A, BELGRADE, MONTANA 59714 T: 406.38&5575 F: 406,388,5585 25 CHANGE ORDER REQUEs'r # 2R AT"T ENTJONt FROM: Eryn Mik Josh Anderson lanai C r : DATE: ",ity Shops Remodel 08/1 5/11 REQUESTED ,Y: Owner SUBCONTRACTOR: RESPONSE DATE: 1 1 REQUEST BY OwNI R ❑ Rr3QUEST BY C'ONTRAC:TOR ❑ REQUEST BY SUBCONTRACTOR ❑ REQUEST FOR CHANGE ORDER ❑ URGENT Move washer and dryer from mcclrar ical room to nTen "s locker roorn. Plirrnbing Subcontractor FI"VAC 'Subcontractor Electrical Subcontractor Concrete canting 9sf @ 6.40 Concrete coring 4" 6" Nall (complete) Ceiliii tile e repair/replace TOTAL $ 940,00 $ 250.00 $ 669,00 $ 57.60 (as per rnait prices on 'bid for in) $ 290.00 ($30.00 per inch + 50.00 trip charge)' $ 369.00 $ 150.00 $2 „725.00 Total firom above $ 2,725.00 Bond /Ins $ 46,00 0/1' 7% $ 193.00 1 % TAX $ 29.00 TOTAL $ 2,993.00 This Change Order / Proposal Request will not add additional clays to the contract 270 FLOSS FLAT ROAD, STE. A, BELGRADE, MONTANA 59714 T: 406.388.5575 F: 406.388.5585 26 CHANGE ORDER REQUEST # 3R ATTEN I JA 0 N: VRONI: Eryn Mikelsoll Josh Anderson PROJECT: DATE: City Shops Remodel 09/8/11 REQUESTEI) jiy: Owner SUBCONTRACTOR: RESPONSE DAZE: Haubrich Electric RE: 121 REQUEST BY OWNER El REQUEST BY CONTRACTOR El REQUEST BY SUBCONTRACTOR El REQUEST FOR CHANGE ORDER ❑ URGENT Electrical changes to IT room Haubrich Electric $685.00 Haubrich Total $ 685.00 Bond/his $ 11.00 O/P 7'% $ 49.00 1 % TAX $ TOO 'TOTAL $ 752.00 This Change Order / Proposal Request will not add additional days to the contract 270 FLOSS FLAT ROAD, STE, A, BELGRADE, MONTANA 59714 T: 406,388.5575 F: 406.388.5585 27 CHANGE ORDER REQUEST # 4 (RFP #01) ATTENTION: FROM: E ryll Mik Josh And . . ......... _ ..................... ..... ..... .._..... ..... ................. ............ ...... ................ _ ._._.. ........ ___....__ ... � IIROJEC "P a DATE: Ci ty Shops R 09 /(1/11 nay: Ow ner _. .......... _...........�,.,. SU13CONTRAC "FOR: RESPONSE DATE: Rich's .Flooring M +f REQUEST BY OWNER 0 REQUEST BY CONTRACTOR EI R QUEST BY SUBCONTRACTOR El REQUEST FOR CHANCE ORDER El URGENT Additional Marmolemn flooring Hallway 94sf (cry, $3.30 = $310.00 301f rubber base = $45.00 Men's Toilet Room 220sf @b, $3.30 $726.00 521f cove base = $340.00 4 inside corners = $80.00 Rich's Flooring Total 1,501,00 Bond/Ins 25.00 O/P 7% 106.00 I% TAX $ 1.6.00 TOTAL $ 1,648.00 This Change Order / Proposal Request will not add additional days to the contract 27017:.(7551'LKF ROAD STE. A, BELGRADE, MONTANA 59714 T: 406.388.5575 F: 406.3886585 i CHANGE OR E S T ATTENTION: F KOM: Eryra Milcelson «lode Anderson .__... � ................ ............__................_ _ .... _ ............. ____ _.... _.._ ... ®._. ...... ._.._.._ ..... . _ _...._.........._. PROJECT:: s DATE: City Shop Remo 09/8/11 . ... 111 QU E 5r, ll> It V: Owner S U BC'ONTTtAC"1'011: RESPONSE IJh TEI IM REQUEST BY OWNER ll REQUEST BY CONTRACTOR U REQUEST BY SUBCONTRACTOR d REQUEST ] CHANCE ORDER ❑ URGENT Adding two hollow metal doors and flames Door s11PPlier 1,008.00 Door Supplier $ 1;008.00 Bond /Ins $ 17.00 0/1' 7% 72.00 1 % TAX $ 11.00 TOTAL $ 1,1018.00 This Change Order / Proposal Request will not add additional (lays to the contract 270 FLOSS FLAT ROAD, STE. A, BELGRADE, MONTANA 59714 T: 406.388.5575 F: 400,388.5585 29