Commission Memorandum
REPORT TO: Honorable Mayor and City Commission
FROM: Tim Cooper, Assistant City Attorney
Dustin Johnson, Project Engineer
SUBJECT: Bogert Pool Renovations: Resolution of Determination that Statutory
Criteria for Alternative Project Delivery Contract Are Met.
MEETING DATE: August 29, 2011
AGENDA ITEM TYPE: Consent
RECOMMENDATION: Adopt Resolution and Authorize City Manager to execute on behalf
of the City of Bozeman an alternative delivery project contract for the Bogert Pool renovations.
BACKGROUND: In 2005, the Montana Legislature created an alternative project delivery
contract process for certain construction projects of state agencies and certain local governments.
The legislation established requirements that must be met in order to use an alternative project
delivery contract, including a written justification. City staff feels that the Bogert Pool
renovations project justifies the use of this process, as set forth in the Resolution.
Bogert Pool is in need of several renovations including ladder replacements, gutter replacements,
and replacement of the existing liner. Many of these improvements will need to be field fit and
designed by a qualified contractor once the pool has been drained for the season. These
improvements must be completed before the pool reopens for the 2012 season. This creates a
time crunch for any contractor and city staff to assure the pool is protected from the freezing
temperatures and the work is completed on schedule. The alternative delivery process allows the
City of Bozeman to select a qualified contractor to complete this project as a “design/build” by
one contractor instead of selecting a separate designer and a separate contractor. This will
contribute to significant time savings and possible cost savings by shortening the construction
schedule.
FISCAL EFFECTS: The entire project will be funded through the Bogert Pool’s Capital
Improvements Project (CIP) budget that has previously been
approved by the commission.
ALTERNATIVES: No action
Attachments: Commission Resolution 4334
Report compiled on: 8/18/2011
20
COMMISSION RESOLUTION NO. 4334
A RESOLUTION OF THE CITY COMMISSION OF THE CITY OF BOZEMAN,
MONTANA, AUTHORIZING THE AWARD OF AN ALTERNATIVE PROJECT
DELIVERY CONTRACT FOR THE BOGERT POOL RENOVATION
WHEREAS, § 18-2-502, MCA, authorizes the City to use and alternative project delivery
contract. A governing body that uses an alternative project delivery contract shall determine that the proposal
meets at least two of the sets of criteria described in § 18-2-502, MCA, subsections (2)(a) through (2)(c) and
the provisions of subsection (3).
WHEREAS, Bogert Pool Renovations must be completed within the time constraints specified in §
75-10-736, MCA, and therefore the project has significant schedule ramifications and using the alternative
project contract is necessary to meet critical deadlines by shortening the duration of construction.
WHEREAS, the type of this project includes aspects of value engineering and construction
planning that would contribute to significant cost savings by allowing the contractor to complete the final
design and construction of the project.
WHEREAS, the scope of the project is highly specialized in nature, such that only contractors
qualified to design and construct pool renovations of this type, the project therefore presents significant
technical complexities that necessitate the use of an alternative delivery project contract.
NOW, THEREFORE, BE IT RESOLVED by the City Commission of the City of Bozeman,
Montana:
Section 1
That Chris Kukulski, Bozeman City Manager, is authorized to execute on behalf of the City of
Bozeman an alternative delivery contract for the Bogert Pool Renovation.
21
Section 2
That Chris Kukulski, Bozeman City Manager, will ensure that the contract will be awarded in an
appropriate manner that will not encourage favoritism or bias nor substantially diminish competition, by
conducting the process in such a manner that only qualified contractors will be eligible, and that the award
will be based upon experience and expertise of the applicants.
PASSED AND APPROVED by the City Commission of the City of Bozeman, Montana, at a
regular session thereof held on the 29th day of August 2011.
__________________________________________
Jeffrey K. Krauss, Mayor
ATTEST:
________________________________________
Stacy Ulmen, CMC
City Clerk
APPROVED AS TO FORM:
___________________________________________
Greg Sullivan
City Attorney
22