HomeMy WebLinkAbout11- Change Order 1 with Pall for Bozeman Water Treatment FacilityUL, 0 7 2011
.' , MORRISON
as MAIERLE.isc
CHANGE ORDER
No.. I
DATE OF ISSUANCE 6 -17 -11
BUYER City of Bozeman
Contract:
Project: BOZEMAN WATER TREATMENT FACILITY
Membrane Procurement
ENGINEER HDR/MMI
EFFECTIVE DATE 6-17-11
SELLER Pall CoMoration
BUYER's Contract No.
ENGINEER's Contract No. 0000088114
You are directed to make the following changes in the Contract Documents:
Description: See Attached Summary
Reason for Change Order: To Modify Insurance Requirements
Attachments: (List documents supporting change)
CHANGE IN CONTRACT PRICE:
Original Contract Price
$ 5.558.300.00
Net Increase (Decrease) from previous Change Orders
No. 0 to 1
$ 0.00
Contract Price prior to this Change Order:
$ $ 5,558,300.00
Net increase (decrease) of this Change Order:
$ 0.00
Contract Price with all approved Change Orders:
$ $ 5,558,300-00
CHANGE IN CONTRACT TIMES:
Original Contract Times:
Substantial Completion: NA
Ready for final payment: NA
( days or dates)
Net change from previous Change Orders No. 0 to No. I
Substantial Completion: NA
Ready for final payment: N — A
(days)
Contract Times prior to this Change Order:
Substantial Completion: NA
Ready for final payment: NA
(days o dates)
Net increase (decrease) this Change Order:
Substantial Completion: NA
Ready for final payment: NA
(days)
Contract Times with all approved Change Orders:
Substantial Completion: NA
Ready for final payment: NA
(days or dates)
Seller certifies and agrees that there are no additional costs or claims for extra work, additional time, delays or omitted
items, of any nature whatsoever, associated with the subject change order items, except as identified and set forth herein and
unless expressly stated otherwise in he Change Order. And further, that the price agreed -upon herein represents the full
cost and value for the s ject wor p rformed and the materials supplied under the terms of the contract and that the work
quantiti and v ue w properl ermineq and are correct.
S ER ( Authorized Signature) Date
RFC0 DFD BY C) ED
- (ENGINEER -Signature) Date 9VYER (Authorized Signature) Date
0089114 City of Bozeman
Hyalite /Sourdough Treatment Plant Membrane Equipment Procurement
'F
COMMISSION RESOLUTION NO. 4326
A RESOLUTION OF THE CITY COMMISSION OF THE CITY OF BOZEMAN,
MONTANA, APPROVING ALTERATION[MODIFICATION OF CONTRACT
WITH PALL CORPORATION, PORT WASHINGTON, NEW YORK.
WHEREAS, the City Commission did, on the 24th day of May 2410, authorize award of the bid for
the City of Bozeman Hyalite /Sourdough Water Treatment Plant — Membrane Equipment Procurement project,
to Pahl Corporation, Port Washington, New York; and
WHEREAS, Section 7- 5- 4308, Montana Code Annotated, provides that any such alterations or
modifications of the specifications and/or plans of the contract be made by resolution; and
WHEREAS, it has become necessary in the prosecution of the work to make alterations or
modifications to the specifications and/or plans of the contract.
NOW, THEREFORE, BE IT RESOLVED by the City Commission of the City of Bozeman,
Montana, that the proposed modifications and/or alterations to the contract between the City of Bozeman, a
municipal corporation, and Pall Corporation, as contained in Change Order No. 1, attached hereto, be and the
same are hereby approved and the City Manager is hereby authorized and directed to execute the contract
change order for and on behalf of the City; and the City Clerk is authorized and directed to attest such
signature..
1 of 2
Resolution No. 4326, Change Order l for Zi TP Membrane .Procurement
PASSED AND APPROVED by the City Commission of the City of Bozeman, Montana, at a
regular session thereof held on the 25th day of July 2011.
ATTEST:
JEFF USS
May r
K
B0 "
STAY
City Clerk
1883 0 ,
Ca`�' A PPROVED AS TO FORM:
" G SULLIVAN
Attorney
2 of 2