HomeMy WebLinkAbout11- Change Order 3 with Duneman for College & Huffine PathwayPROJECT TITLE: College & Huffine Shared-Use Pathway — Bozeman (a CTEP proiect)__-
RPA PROJECT NO.: 08506,000
CTEP PROJECT NO.: STPE 1299(22)
CHANGE ORDER NUMBER:
DATE {JF CHANGE ORDER,
CONTRACT DATE: September 3, 201 (Notice to Proceed: October 4, 201 Project underwent a Winter Shutdown.
As of July 10, 201 the Contractor has been charged with 59 days in the current 50 day contract. This Change Order will
provide additional working days as further described for the changing work.
OWNER: City of Bozeman
CONTRACTOR: Duneman Construction, Inc.._,
Change orders must ba accompanied byan itemized cost breakdown, i.u: unit prices, negotiated lump sum prices,
negotiated cost plus basis. Note all cost plus pricing to be supported by documentation which supports the cost of that
Item
Description
Quantity
Units
Unit Price
Amount
Basis of Unit Price
Number
1
Muck Excavation of rotting
60
CY
$4.50
+$27000
Negotiated unit price under
stumps, muck and deleterious
Change Order No, I for
material, Sta. 27+00 to
Muck Excavation
27+90, Alignment "C"
2
Import/place pitrun cobble
60
CY
$18,00
+$1,080.00
Negotiated unit price under
backfill for Item 1
Change Order No. 1 for
replacement material
Muck Excavation
re lacement
3
Geotextile separation
240
SY
$5,00
+$1,200.00
Negotiated
fabric/Geolon High Strength
4
Subgrade separation
1,509
SY
$5,00
+$7,545.00
Negotiated
geotextile to eliminate
additional subexcavation,
Alignment "B", Sta. 31+87 to
5
Same as Item 4, Alignment
2,480
SY
$5.00
+$12,400.00
Negotiated
excluding road approaches
and Item No. 1
JUSTIFICATION OF CHANGE ORDER:
Items 1.2 and 8: |n preparing the path foundation along Alignment ^C"from8bsUum27+O0tn27+9O.rot n8tneeobumpa
and organic material were encountered requiring muck excavation to build a suitable path base. Genteuti|eGnn|onfabric
was used to wrap the rock and gravel backfill to provide a firm foundation.
|hynnu 4 and 5� The claymmbgrade material encountered is very susceptible to moisture; when wet making the material
unworkable tn obtain foundation preparation and compaction. Wet, lasting spring weather compounded the issue of
working the nubgnado. In order to limit subexcavation of the material and backfill replacement (limit project oosUandto
expedite the process of working with soft, yielding subgrade, the Geolon Geotextile fabric was installed, Thegenboxtila
was deemed the appropriate solution as the Owner, Engineer and Contractor are all concerned about project de|ivery
(contract time), The installation allowed the work to proceed on the foundation material that would have required
Change Order
Page 1
aubuxcavationand replacement oeUheo|harnaUYn,aLooububsntial|engthieromoumtofinstoU1inaandcos if this Item
was not used,
SUMMARY OF COST AND TIME:
COST BREAKDOWN: TIME BREAKDOWN:
ORIGINAL CONTRACT PRICE: $439,719.15 START C)FCONSTRUCTION: October 4, 2101
PREVIOUS CHANGE ORDER AMOUNT: - CALENDAR DAYS BYCONTRACT:
CURRENT CONTRACT PRICE: $441,025,65 CONTRACT COMPLETION DATE: As of JuIV 10, 201 the
Contractor is 9 days over the 50 day.,contract time, Substantial
Completion is estimated at July 11 201 1
AMOUNT OF THIS CHANGE ORDER: — NUMBER OF DAYS GRANTED THIS CHANGE ORDER: 5___
NEW CONTRACT PRICE: $463,520.65 NEW CONTRACT COMPLETION DATE: At 55 Calendar Days
The completion date ea set forth in the contract documents shall be(unchanged by !calendar
days. The date for completion of all work will be , on expected Substantial Completion of Tuly 15, 201 With the
additional contract days aranted herein (to 55 calendar days total), the Contractor is still subiect to liauidated damaaes as
substantial nompletionis oroiected tobeetG4 calendar days.mQdaysbevodconhacthme.Asmmmamofthm5
additional contract days to be granted herein follows
5 days hosmbexoavote backfill and install ggotexUVe as described herohn. In addition, the Contractor installed numerous
irrigation sleeves along MSU frontage and at Technology Boulevard at the request of those owners for future irrigation
runs under the path. The Contractor provided labor for install which removed some labor forces from project work,
APPROVALS:
Surety consent is required if the net increase of this change order and all previous change orders exceeds 20% of the
original contract amount.
Note: The following Surety Consent is NA as the sum of Change Orders 1, 2 and 3 does not exceed 20% of the
original contract amount.
SURETY CONSENT
The surety hereby consents to the aforementioned contract change order and agrees that its bond or bonds shall apply
and they extend to the contract as thereby modified or amended per this change order. The ' ' a[andNhe surety
further agree that on or after execution of this consent, the penalty of the applicable performance bonds or bonds is
hereby increased 0OY6uf the change order amount) and the penalty mf the applicable
labor and material bond or bonds ia hereby increased by (18O96of the change order amount).
COUNTERSIGNED BY MONTANA RESIDENT AGENT SURETY
Seal
(Engineer) Reoommen
(Contractor) Accepted
(Owner) Approved by:
a Date
�
/ Date
Change Order
Page 2
I F111PLAW I
ROBERT PECCIA & ASSOCIATES
REGARDING Change Order No. 3
TO:
FIRM/AGEN'CY-
ADDRESS:
CITY/STATE/ZIP:
TELEPHONE:
Mr. Ron Dingman
Director of Parks and Recreation
City of Bozeman
PO Box 1230
Bozeman, MT 59771
(406) 582 - 3222
Transmitted are the following items:
Item Number
Copies
[
•♦ , Box 5653
I
Change Order NO,3
825 CusIter Avenue
:�7�
65 Eoss Broadway
Ron-
Enclosed is Change Order No. 3. If you concur, please have authorized (signed) and dated by the City where
noted on the last page,
In summary, the installation of geotextile separation fabric has allowed the project delivery to be expedited in
comparison to if the subgrade material were removed (subexcavated) and replaced with gravel. The use of
geotextile not only increased the labor output that the Contractor could achieve, in comparison to a
subexcavation process, but is a less costly process. As an example, a square yard (SY) of subexcavation, at
2 feet deep, amounts to approximately 0.7 cubic yards (CY) of subexcavation. Subexcavation costs $4.50/CY
and the replacement gravel for this process is $18.00/CY. A lesser quality geotextile to line the excavation is
$1.25/SY. For the 1 square yard of area in a subexcavation process, the total estimated cost is approximately
$17.00/SY for all materials (subexcavation, replacement and geotextile).
By comparison, with this change order, the use of the more robust Geolon Geotextile, at $5,00/SY eliminated
the subexcavation process, and had an install cost of $5.00/SY, or approximately 1/3 of the subexcavation
alternative cost. If you have any further questions on this in addition to our previous coordination, please feel
free to contact me at (406) 447-5000 or email: tom @—rpa-hJn. om,
Regards-
Tom C.
c: file
F:\highways\
HELENA - CORPORATE OFFICF
KALISPELL
BUTTE
•♦ , Box 5653
Ro Box 5100
Thomton Building
825 CusIter Avenue
102 ♦Cooperdlive Way, Suite 300
65 Eoss Broadway
Helena, MT 59604
Kalispell, MT 599o3
Butte, MT 59701
(406) 44T5000
(406) 752-5025
(406) 533-6770
FAX (406) 447-5036
1/m/M. Off
11""'
FAX (406) 752 5024
Wi
111 111 1 fi:i! II I
FAX (406) 533-6830
Commission Memorandum
REPORT TO: Honorable Mayor and City Commission
FROM: Dustin Johnson, Project Engineer
Ron Dingman, Parks and Recreation Director
SUBJECT: Approve Resolution 4330 authorizing the Cite Manager to sign Change
Order #3 for the use of geotextile separation fabric due to unfavorable soil
conditions for the College /Huffne Community Transportation
Enhancement Program (CTEP) Pathway project.
MEETING DATE: August 1, 2011
AGENDA ITEM TYPE: Consent Agenda
RECOMMENDATION: Approve Resolution 4330 authorizing the City Manager to sign
Change Order #3 in the about of +$22,495.00, for the
College /Huffine Pathway CTEP Pathway project.
BACKGROUND: The College /Huffine Pathway originally started construction in the fall of
2011, When the weather became too prohibitive to work last winter, there
was a winter shut down that temporarily halted the work for the season.
When construction started back up this spring there were areas where the
pathway was to be constructed that had unsuitable soils for paving the
pathway and could not meet specifications. In one area rotting tree stumps
were discovered and needed to be excavated and clean pit run had to be
imported in their place.
Due to the wet weather of the construction season this spring the
contractor and engineer decided to use geotextile fabric instead of waiting
for the material to adequately dry for construction. Since this project is
funded through CTEP and is on a very tight schedule, it was deemed
appropriate to take these measures to assure the project was completed on
schedule.
A total of 60 cubic yards of material needed to be removed and replaced,
and 4,229 square yards of geotextile fabric was used. A complete break-
down of quantities and unit prices has been provided by the engineer and
the contractor in the attached Change Order #3.
UNRESOLVED ISSUES: None at this time.
ALTERNATIVES: As suggested by the City Commission.
FISCAL EFFECTS: This project is funded through the CTEP program. If this project
does not finish on schedule the City and the contractor potentially
face reduced funding from CTEP due to the reporting requirements
and the commitments outlined in the original contract. The use of
geotextile fabric, for the wetter portions of the pathway, have
allowed faster construction:, since the contractor does not have to
wait for the material to dry out.
This change order increases the contract price by $22,495.00. The
new total contract price is $463,520.65.
Attachments
Change Order 43
Commission Resolution 4330
Report compiled on. 7/19/2011
COMMISSION RESOLUTION NO. 4330
A RESOLUTION OF THE CITY COMMISSION OF THE CITY OF BOZEMAN,
MONTANA, APPROVING ALTERATION /MODIFICATION OF CONTRACT
WITH DUNEMAN CONSTRUCTION, OF BELGRADE, MONTANA.
WHEREAS, the City Commission did, on the 1 6th day o August 2010, authorize award of the bid
for the construction of the College /Huffine Pathway to Duneman Construction, Belgrade, Montana; and
WHEREAS, Section 7 -5 -4308, Montana Code Annotated, provides that any such alterations or
modifications of the specifications and/or plans of the contract be made by resolution; and
WHEREAS, it has become necessary in the prosecution of the work to make alterations or
modifications to the specifications and/or plans of the contract.
NOW, THEREFORE, BE IT RESOLVED by the City Commission of the City of Bozeman,
Montana, that the proposed modifications and /or alterations to the contract between the City of Bozeman, a
municipal corporation, and, Duneman Construction, Belgrade, Montana, as contained in Change OrderNo. 3
attached hereto, are hereby approved; and the City Manager is hereby authorized and directed to execute the
contract change order for and on behalf of the City; and the City Clerk is authorized and directed to attest
such signature.
PASSED AND APPROVED by the City Commission of the City of Bozeman, Montana, at a
regular session thereof held on the I st day of August 201
0
ATT
Stacy I
city
"0
-x
l'Gl r