HomeMy WebLinkAboutHyalite-Sourdough Water Treatment Plant Replacement Project Notice of Award.pdf
Commission Memorandum
REPORT TO: Honorable Mayor and City Commission
FROM: Bob Murray, Project Engineer
Rick Hixson, City Engineer
Chuck Winn, Assistant City Manager
SUBJECT: Hyalite/Sourdough Water Treatment Plant Replacement Project Notice of
Award
MEETING DATE: July 25th, 2011
AGENDA ITEM TYPE: Action
RECOMMENDATION: Approve and authorize the City Manager to sign the notice of award to
Apollo, Inc for bid items A1 and A2 in the amount of $26,879,130.00 contingent upon SRF
Program approval.
BACKGROUND: Attached is a copy of the Notice of Award for the above referenced project.
The existing water treatment plant is reaching the end of its useful life. The water facility plan
recommended replacement of the existing plant with a new pressurized membrane filtration
treatment plant with chlorine contact disinfection and a new downstream contact channel with
additional storage capacity for treated water. The plan also recommended an increase in capacity
with the initial phase able to produce 22 million gallons per day, and room for expansion in a
future phase to 36 million gallons per day. This project will achieve those facility plan
recommendations.
Bids for the above-referenced project were opened on June 7, 2011. The project was bid with
two schedules. Schedule A with its alternates was for the treatment facility itself. Schedule B
was for the replacement of the Sourdough intake facility. There were 11 bidders on Schedule A,
and 9 on Schedule B. The low bid for Schedule A was submitted by Apollo, Inc from
Kennewick, WA in the amount of $27,004,400.00. Initially the low bidder on Schedule B was
Williams Brother Construction, but as allowed under the contract, they provided evidence of a
substantial error in their bid within 24 hours of the opening and withdrew their bid. With their
withdrawal, the low bidder became RSCI from Meridian, ID. There were many minor bid
irregularities on the bids submitted, but after the corrections were made in accordance with the
contract documents, the low bidders remained the same.
A bid protest was received from the third low bidder on the project, Dick Anderson
Construction, Inc. They were requesting that both the low and second low bid be thrown out.
The basis of the protest was issues that they raised in response to a few items in the information
required of bidders. This is a series of questions that must be answered within 10 days of the bid
opening in order to help the City and Consultants evaluate the low bidder. Prior to receiving the
273
protest, we had already raised a question with two of the three items raised by Dick Anderson,
and they raised a third. We asked for clarification and additional information from Apollo on the
items in question which they provided. The information and response from Apollo was reviewed
by City Engineering and Legal staff, and the Consultants and it was determined that the
additional information satisfied our concerns. We recommend the issues that were raised be
deemed minor irregularities and that the award be made to Apollo. A copy of the protest letter,
Apollo’s response, and an additional follow up from council for Dick Anderson are included for
your review.
The recommendation in regard to Schedule A is to only make award to Apollo, Inc for bid items
A1 and A2 in the amount of $26,879,130.00. Bid item A2 is a deductive bid item to eliminate
construction of 2 of the residual drying beds. The recommendation for Schedule B is to not
award it at this time. This is primarily for budgetary reasons. By not making award at this time,
we will be able to go into the overall project with a 5% contingency within the original overall
project budget. Once we are well into the project, if the budget allows, we will rebid the intake
work as a standalone project. The Bid Tabulation and engineers award recommendation for the
project is attached.
UNRESOLVED ISSUES: None
ALTERNATIVES: Disapprove
FISCAL EFFECTS: The project is being funded through a combination of Water Enterprise
Fund, Water Impact Fee Fund, and a loan from the State Revolving Fund. Based on the award
recommendation above, the overall project budget would be:
Construction Schedule A1 $27,007,400.00
Bid Item A2 Drying Bed Reduction $ (128,270.00)
Pall Membrane Equipment $ 5,558,300.00
Pilot Costs $ 385,000.00
Engineering $ 6,307,500.00
System Integration $ 438,925.00
Contingency 5% Item A and Pall $ 1,621,872.00
Total $41,190,727.00
Attachments: Engineers Recommendation, Bid Protest Correspondence
Report compiled on: 7/12/11
274
275
276
277
278
279
280
281
282
283
284
285
286
287
288
289
290
291
292
293
294
295
296
297
298
299
300
301
302
303
304
305
306
307
308
309
310
311
312
313
314
315
316
317
318
319
320
321
322
323
324
325
326
327
328
329
330
331
332
333
334
335
336