Loading...
HomeMy WebLinkAboutResolution 4295 Change order 1, WRF Digester 3 and Solids Dewatering, McAlvainCOMMISSION RESOLUTION NO. 4295 A RESOLUTION OF THE CITY COMMISSION OF THE CITY OF BOZEMAN, MONTANA, APPROVING ALTERATION/MODIFICATION OF CONTRACT WITH MCALVAIN CIVIL CONSTRUCTORS, INC., BOISE, IDAHO. WHEREAS, the City Commission did, on the 17th day of February 2010, authorize award of the bid for the Bozeman WRF Digester No. 3 and Solids Dewatering project, to McAlvain Civil Constructors, Inc., Boise, Idaho; and WHEREAS, Section 7-5-4308, Montana Code Annotated, provides that any such alterations or modifications of the specifications and/or plans of the contract be made by resolution; and WHEREAS, it has become necessary in the prosecution of the work to make alterations or modifications to the specifications and/or plans of the contract, NOW, THEREFORE, BE IT RESOLVED by the City Commission of the City of Bozeman, Montana, that the proposed modifications and/or alterations to the contract between the City of Bozeman, a municipal corporation, and McAlvain Civil Constructors, Inc., as contained in Change Order No. 1, attached hereto, be and the same are hereby approved; and the City Manager is hereby authorized and directed to execute the contract change order for and on behalf of the City; and the City Clerk is authorized and directed to attest such signature. 1 of 2 Resolution No, 4295, Change Order I for HIRF Digester No. 3 & Solids Dewatering PASSED AND APPROVED by the City Commission of the City of Bozeman, Montana, at a regular session thereof held on the 25th day of October 201 ATTEST: ot4v�' iIl STA:� City � APPROVED AS TO FORM: WIN HAI MORRISON CHANGE ORDER AMMEw.e. m No. DATE OF ISSUANCE September 23, 2010 EFFECTIVE DATE September 8 2010 OWNER City of Bozeman CONTRACTOR McAlvain Civil Constructors Inc. Contract: Boz eman WRF Digester No. 3 and Solids Dewaterintx Buildint.* Proiect Project: Digest er No. 3 and Solids Dewatering Building Proiect OWNER's Contract No. SRF 0301229 ENGINEER HDR/MMI ENGINEER's Contract No. 00..60746 You are directed to make the following changes in the Contract Documents: Description: Make changes identified in Work Change Directives 1 and 2 and Change Proposal Requests 2.1, 4. 1, 6, 7, 13, 15, 16/16A as described in the attached documents. Reason for Change Order: Cost savings and miscellaneous additional work. Attachments: Change Order No. 1 Summary with referenced attachments. CHANGE IN CONTRACT PRICE: Original Contract Price $ 5,298,965.00 Net Increase (Decrease) from previous Change Orders No. 0 to 0 $ 0.00 Contract Price prior to this Change Order: $ 5,298,965.00 Net increase (decrease) of this Change Order: $ 22,826.10 Contract Price with all approved Change Orders: $ 5,321,791.10 CHANGE IN CONTRACT TIMES: Original Contract Times: Substantial Completion: May 10, 2011 . Ready for final payment: July 9, 2011 (days or dates) Net change from previous Change Orders No. 0 to No. 0 : Substantial Completion: 0 Ready for final payment: 0 da s Contract Times prior to this Change Order: Substantial Completion: May 10 2011 Ready for final payment: !!Jly 9 2011 ( days or dates Net increase (decrease) this Change Order: Substantial Completion: 0 Ready for final payment: 0 (days) Contract Times with all approved Change Orders: Substantial Completion: May 1.0 2011 Ready for final payment: July 9 2011 (days or dates) Contractor certifies and agrees that there are no additional costs or claims for extra work, additional time, delays or omitted items, of any nature whatsoever, associated with the subject change order items, except as identified and set forth herein and unless expressly stated otherwise in the Change Order. And further, that the price agreed -upon herein represents the full cost and value for the subject work performed and the materials supplied under the terms of the conpact,and that the work quantities and value were properly determined and are correct. Date EJCDC 1910 -8 -B (1996 Edition Prepared by the Engineers Joint Contract Documents Committee and endorsed by The Associated General Contractors of America and the Construction Specifications Institute.