HomeMy WebLinkAbout06- Wastewater treatment plant maint. building, Change order #1CHANGE ORDER
No. _One (1)
DATE OF ISSUANCE March 6 2006 EFFECTIVE DATE March 6 2006
OWNER City of Bozeman
... ®_ „_......,_.,---
CONTRACTOR In am- Cleven er Inc.
Contract: Bozeman Wastewater Treatment Plant Maintenance Building Addition
Project: Equipment Stora e Buildin
OWNNER's Contract No, 56052 ENGINEER's Contract No. 0417.049
ENGINEER Morrison - Maierle Inc.
You are directed to make the following changes in the Contract Documents.:
Description:
(See attached change order proposal)
Reason for Change Order:.
Owner requested changes and Contractor initiated credits..
Attachments: (List documents supporting change)
CHANGE IN CONTRACT PRICE:
Original Contract Price
$ $3,98,000
Net Increase (Decrease) from previous Change
Orders: None
-0-
Contract Price prior to this Change Order:
$ $398 000
Net increase (decrease) of this Change Order;
$ ($1,967.96
Contract Price with all approved Change Orders:
$ $396 032.04
RECOMMENDED:
By n
(ENGINEER - Signature)
Date: C G
EICDC 1910 -8 -B (1996 Edition
Prepared by the Engineers Joint Contrac
Construction Specifications Institute.
CHANGE IN CONTRACT TIMES:
Original Contract Times:
Substantial Completion: 75 Days s
Ready for final payment: 90 Days
( days or dates
Net change from previous Change Orders: None
Substantial Completion: - 0 -
Ready for final payment: - 0 -
da s)
Contract Times prior to this Change Order:
Substantial Completion: 75 Days
Ready for final payment: 90 Days
( days or dates
Net increase (decrease) this Change Order:
Substantial Completion: - 0 -
Ready for final payment: 0
( days )
Contract Times with all approved Change Orders:
Substantial Completion: 75 Days
Ready for final payment: 90 Days
(days or dates)
APPROVED: ACCEPTED:
OWNER (Authorized Signature) CONTRACTOR(Authorzed Signature)
Date: March 20, 2006 Date: ` `?
I Documents Committee and endorsed by The Associated General Contractors of America and the
Page 1 of 1
H ;1041710491docstSPECS1Construct Docs\Change Order Gne.doc 05.29.01
INGRAM-C
7000 Green Meadow Drive
: 0, Box 5387
- elena, MT 59604
NC.
Phone: (406) 442-5102
FAX: (406) 442-5105
Droject Name: Bozeman Waste Water Treatment Plant
Maintenance Building Addition
:)roject Number 0417.049,040.0315 Date: 02.24,06
Item #1 Install Owner Furnished Unit Heater In new Equipment Storage Building
Metal Works of Montana Install and Venting
$550.00
Metal Work of Montana Furnish & Install Thermostat
$200-00
Willaims Plumbing make final gas connection
$150.00
ICI OH & P
$108.00
Item Total
$1,008.00
Item #2 Delete Requirement to furnsih and install
treated plate with lag bolts at perimeter of
concrete forundation wall
ICI Labor
($570.54)
ICI Materials
($326.00)
ICI OH & P
($107,58)
Item Total
($1,004,12)
lem #3 Add thresholds, weatherstrip and door bottoms at doors #2 and #3
Change Locksets to stainless steel heavy duty corrision resistant finish
Andeerson Steel Supply Locksets $689.00
Anderson Steel Supply Weatherstrip & etc $161.00
ICI Labor $68.00
ICI OH & P $110.16
Item Total $1,028.16
Item * 4 Contingency Provide credit to Owner ($3,000.00)
Total these items ($1,967.96)