Loading...
HomeMy WebLinkAbout04- West Side Sewer Rehab, Change order 2 with PECHKM ENGINEERING INC. TO: — PEC, Inc. 3400 Centennial Drive Helena, MT 59601 Change Order No: Date Project No.: Contract For: 2 6/26/2004 4m229.138 West Side Sewer Rehab It has been determined necessary and in the best interest of the Owner to modify certain portions of the Project above and the Contract dated 24-Nov-03 and in accordance with the General Provisions. The following changes are hereby agreed to, 1. Reconciliation of final quantities ATTACHMENT: 1, Table of final quantity balance. ESTIMATE AND COST Note: The quantities shown are not guaranteed. Payment will be based on actual quantities used. ITEM QUANTITY UNIT DESCRIPTION UNIT PRICE AMOUNT $0.00 CO2-1 1 LS Reconciliation of Final Quantities -$42,118.20 -$42,118.20 $0.00 $0.00 $0.00 Time (extension) (decrease) 0 days Total Cost -$42,118-�20 H:1091Master\chqorder2,xls\PaaeI Not valid until signed by both the Owner and Engineer. herewith, including any adjustment in the Contract Sum or Contract Time. By signing below each party agrees that this Change Order is a complete and equitable adjustment for aH proposals or claims whatsoever arising out of, resulting from, and/or directly related to the above occurrences, revisions to the Contract, and/or this Change Order and hereby releases the others from all liability under this contract for further adjustments in Contract Price or Contract Time for said occurrences, revisions, and/or this supplemental agreement. The original Contract Sum was Net change by previously authorized Change Orders The Contract Sum prior to this Change Order was The Contract Sum will be )by this Change Order The new Contract sum including this Change Order will be The Contract Time will bm(inoreaoed) by The Date nf Substantial Completion oaof the date ofthis Change Order therefore iu $ 585,927.50 � - $ 585,927.50 $ 543,809.30 0 days pEC.|no UM���� CITY OF BOZEMAN OWNER By er Representatlr�" Title NOTE: Fill aU spaces. In not applicable, write N/A CITY OF BOZEMAN 2003 WEST SIDE SEWER REHABILITATION PROJECT EPA PRIORITY GRANT 2 Attachment A - Reconciling Change Order BID FORM ITEM 101 DESCRIPTION Mob/Demob. UNIT LS PLAN QUANTITY 1 FINAL QUANTITY 1 UNIT PRICE 6500.00 $ TOTAL 0.00 102 Taxes, Bonds, Insurance LS 1 1 $ 2000.00 $ 0,00 103 8" CIPP LF 9,740 9,447 $ 22.50 $ -6592.50 104 10" CIPP LF 3,840 3,835 $ 25.50 $ -127.50 105 18 CIPP LF 1,520 1,443 $ 48-50 $ -3734.50 106 8" SDR35 Sewer Pipe LF 50 28 $ 34.00 $ -748.00 107 4" - 6" SDR35 Sewer Pipe LF 950 430.5 $ 28.00 $ -14546.00 108 Sanitary Sewer Service Replacement EA 50 62 975.00 $ 11700.00 109 Sewer Service Reinstatement EA 196 211 $ 75.00 $ 1125.00 110 Sewer Service Root Removal EA 20 1 $ 135.00 $ -2565.00 I'll New 48" MH EA 1 1 $ 4500.00 $ 0.00 112 Replace Manhole Frame & Cover - In Asphalt or Concrete 1 EA 19 12 $ 575.00 $ -4025-00 113 Replace Manhole Frame & Cover - In Gravel or Turf EA 15 9 $ 400.00 $ -2400.00 114 Replace Manhole Cover Only EA 34 29 $ 200.00 $ -1000.00 115 Replace Manhole Steps EA 170 133 $ 85.00 $ -3145.00 116 Utility Crossing EA 30 28 $ 120,00 $ -240.00 h:1041M2291381constructjon\ CO2Table,xls 6/28/2004 ITEM 117 DESCRIPTION Exploratory Excavation UNIT HR BID FORM (cont) QUANTITY 20 0.5 $ UNIT PRICE 200.00$ TOTAL -3900.00 118 Traffic Control LS 1 1 $ 4500.00 $ 0.00 119 Gravel Surface Restoration (Service Lines Only) SY 900 751 $ 20.00$ -2980.00 120 Asphalt Surface Restoration (Service Lines Only) SY 270 80.9 $ 32.50 $ -6145.75 121 Curb & Gutter Restoration LF 60 19.2 16.00$ -652.80 122 Sidewalk/Driveway Restoration SF 315 -$ 63.1 $ 8.50 $ -2141.15 Bid Alternate No. 1 of 1 - Slipline 24" & 30" Alt. 1 24" & 30" CIPP TOTAL BASE BID (Change) $ Pipelines At Wastewater Treatment Plant LS 1 1 $ 7000 $ -42,118.20 0.00 TOTAL BID (BASE BID + ALTERNATE 1) = $ -42,118.20 h:1041m2291381constructjon\ CO2Table.xls 6128/2004