Commission Memorandum
REPORT TO: Honorable Mayor and City Commission
FROM: Chris Kukulski, City Manager
Anna Rosenberry, Finance Director
SUBJECT: Adoption of Parts of the Recommended Capital Improvements Plan (CIP)
for FY2012-2016 – WASTEWATER IMPACT FEE FUND
Item Type: Consent
MEETING DATE: January 3, 2011
RECOMMENDATION: Adopt the attached portion of the Capital Improvements Plan for
FY2012-2016 for the Wastewater Impact Fee Fund
BACKGROUND: On December 13, 2010, we presented and discussed the attached plan for
capital projects paid for with Wastewater Impact Fees. No changes were made to these
recommended schedules as a result of that meeting.
Advisory Committee: The City’s Impact Fee Advisory Committee (IFAC) met on November
18th and November 23rd to develop and discuss these recommended schedules. The committee
currently does not contain a quorum, so these recommendations were not formally voted on.
FISCAL EFFECTS: This step in the process has no immediate fiscal effect – although
scheduled impact fee projects may be eligible for impact fee credits under BMC 3.24.100. Once
111
adopted, the Capital Improvements Plan becomes the basis of the City Manager’s Recommended
Budget for FY12.
ALTERNATIVES: The attached plan can be modified, or not adopted at all.
Report compiled on: December 22, 2010
Recommended – Wastewater Impact Fee CIP
112
Wastewater Impact FeeCapital Improvement PlanFinancial Summary Current YearFY11 FY12 FY13 FY14 FY15 FY16Projected Beginning Reserve Balance Dedicated to CIP‐$ ‐$ ‐$ ‐$ ‐$ ‐$ Plus: Impact Fee Revenues Dedicated to CIP 400,000$ 404,000$ 408,040$ 416,201$ 424,525$ 433,015$ Less: Scheduled CIP Project Costs (400,000)$ (404,000)$ (408,040)$ (416,201)$ (424,525)$ (433,015)$ Projected Year‐End Cash Dedicated to CIP‐$ ‐$ ‐$ ‐$ ‐$ 0.00$ Assumptions Made for Revenue Estimates: Current YearFY11 FY12 FY13 FY14 FY15 FY16Estimated Annual Wastewater Impact Fee Revenues 400,000$ 400,000$ 404,000$ 408,040$ 416,201$ 424,525$ Estimated Annual Increase 0.0% 1% 1% 2% 2% 2%Total Estimated Revenues 400,000$ 404,000$ 408,040$ 416,201$ 424,525$ 433,015$ Current Revenues Dedicated to CIP % 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% Plus: Increase Dedicated to Wastewater Capacity Expansion CIP 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% Total % Dedicated to CIP 100.0% 100.0% 100.0% 100.0% 100.0% 100.0%ProjectedProjectedTotal Estimated Revenues Dedicated to CIP 400,000$ 404,000$ 408,040$ 416,201$ 424,525$ 433,015$ 6,000,0005,000,0004,000,0003,000,0002,000,0001,000,0000FY12 FY13 FY14 FY15 FY16 UnscheduledWastewater Impact Fee Projects 113
CIP PROJECT FUNDPROJ.DEPARTMENPROJECT NAMEFY12FY13FY14FY16UnscheduledFY15Impact Fees WastewaterWW28WRF PLANTDESIGN PHASE II ‐ WRF PLANT IMPROVEMENTS$2,615,000WWIFWWATER IFWRF PHASE I DEBT RETIREMENT$404,000$408,040$416,201$424,525$433,015WWIF05WWATER IFHOSPITAL TRUNK LINE: HAGGERTY TO KAGY$1,062,000WWIF11WWATER IFREPLACE FRONT STREET: TAMARACK/ROUSE$1,800,000WWIF12WWATER IFGRAF STREET EXTENSION$50,000Summary for Impact Fees Wastewater (5 items)Totals by year:$404,000 $408,040 $416,201 $424,525$433,015$5,527,000FY12FY13FY14FY15FY16Unscheduled114
CIP Project Fund
Impact Fees Wastewater
PROJECT NUMBER
WW28
DEPARTMENT
WRF PLANT
PROJECT NAME
DESIGN PHASE II - WRF PLANT IMPROVEMENTS
FY12 FY13 FY14 FY15 FY16 Unscheduled
$2,615,000
DESCRIPTION OF PROJECT
In January 2006 Morrison & Maierle Consulting Engineers completed a comprehensive Wastewater Facilities Plan. The plan
recommends the City proceed with a 3-phased project schedule that includes the construction of the new Water Reclamation
Facility (WRF), capable of handling our increased flows while also reducing the amount of Total Nitrogen discharged to the East
Gallatin River. Phase two is expected to include one new primary clarifier, more BNR reactor basins, clarifiers, tertiary deep bed
filtration, liquid sludge storage tanks, anaerobic digestion, and effluent re-use pumping station. The capacity expanding (impact fee
eligible) elements are: reactor basins, clarifiers, and pumping station. It is possible that this phase of the project could be further
divided into phase 2A and phase 2B, if necessary.
ALTERNATIVES CONSIDERED
A variety of treatment technologies and alternatives are presented in the January 2006 Wastewater Facilities Plan.
ADVANTAGES OF APPROVAL
Major capital expansion of the Bozeman WRF will enable the City to meet its estimated demand for wastewater services and still
produce a high quality effluent that is in full compliance with the City’s MPDES discharge permit. Expansion of the Bozeman WRF
is consistent with the City’s long-term need to accommodate rapid growth and economic development in the Gallatin Valley.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating & Maintenance Costs: no estimates at this time.
FUNDING SOURCES
Total Design Cost: $5,230,000. We estimate that half of the costs are related to regulation and maintenance issues and would be
borne by the Utility Fund. Half are related to capacity expansion, and would be borne by Impact Fees. 50% Wastewater Fund,
50% Wastewater Impact Fee Fund.
New
Replacement
Equipment
Project
115
CIP Project Fund
Impact Fees Wastewater
PROJECT NUMBER
WWIF05
DEPARTMENT
WWATER IF
PROJECT NAME
HOSPITAL TRUNK LINE: HAGGERTY TO KAGY
FY12 FY13 FY14 FY15 FY16 Unscheduled
$1,062,000
DESCRIPTION OF PROJECT
Construct ~7,900 LF of 12" and 15" sewer collector from manhole C0507 to 1E22.
ALTERNATIVES CONSIDERED
Limit future development in the area.
ADVANTAGES OF APPROVAL
If constructed to the line sizes master planned in the City’s Wastewater Facilities plan, capacity will be provided for anticipating
the long-term future growth in this area.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Impact fees can not fund operating and maintenance costs. The city’s wastewater
utility will pay for these costs, which are estimated to be a small increment of the city’s system as a whole.
FUNDING SOURCES
70% Wastewater Impact Fees = $743,400
30% Developer Contribution = $318,600
New
Replacement
Equipment
Project
116
CIP Project Fund
Impact Fees Wastewater
PROJECT NUMBER
WWIF11
DEPARTMENT
WWATER IF
PROJECT NAME
REPLACE FRONT STREET: TAMARACK/ROUSE
FY12 FY13 FY14 FY15 FY16 Unscheduled
$1,800,000
DESCRIPTION OF PROJECT
This project consists of construction of ~11,000 LF 18", 21" & 24" sewer pipe from manhole F0330 to C0507.
The lower portion of the existing sewer is at capacity. Additional capacity is needed to serve the future Bozeman Deaconess
Hospital development and lands to the south.
It is estimated that 70% of this project costs will be due to capacity expansion and will be eligible for Wastewater Impact Fees.
The remaining 30% of the project costs will need to be provided by a developer contribution or other source. At this time, the
City’s Wastewater Utility does not have a need to replace the existing facility; as such, no utility dollars are scheduled to be spent.
ALTERNATIVES CONSIDERED
Limit development to only that capacity of the existing sewer.
ADVANTAGES OF APPROVAL
This project will significantly increase the service area and capacity of the trunk sewer.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Impact fees can not fund operating and maintenance costs. The city’s wastewater
utility will pay for these costs, which are estimated to be a small increment of the city’s system as a whole.
FUNDING SOURCES
70% Wastewater Impact Fees = $1,260,000
30% Developer Contribution = $540,000
New
Replacement
Equipment
Project
117
CIP Project Fund
Impact Fees Wastewater
PROJECT NUMBER
WWIF12
DEPARTMENT
WWATER IF
PROJECT NAME
GRAF STREET EXTENSION
FY12 FY13 FY14 FY15 FY16 Unscheduled
$50,000
DESCRIPTION OF PROJECT
This project is to extend Wastewater Mains below Graf Street approximately ¼ mile in order to connect infrastructure east
from 19th Avenue.
This is an important connection for public safety purposes – allowing fire service to meet their response time requirements in
areas where they currently cannot. The Wastewater infrastructure should be installed at the same time the street connection is
made.
ALTERNATIVES CONSIDERED
Do nothing and wait for development to connect the infrastructure.
ADVANTAGES OF APPROVAL
Improved traffic flow and better emergency response to the local area.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
100% Wastewater Impact Fee – to be recovered by developer payback.
New
Replacement
Equipment
Project
118
CIP Project Fund
Impact Fees Wastewater
PROJECT NUMBER
WWIF14
DEPARTMENT
WWATER IF
PROJECT NAME
WRF PHASE I DEBT RETIREMENT
FY12
$404,000
FY13
$408,040
FY14
$416,201
FY15
$424,525
FY16
$433,015
Unscheduled
DESCRIPTION OF PROJECT
Total adjusted project price for the Water Reclamation Facility (WRF) construction of phase one is estimated at $53.8 Million.
Of that amount, $17.9 Million is for capacity expanding costs of construction. The impact fee account will not have enough cash
on hand to pay the costs of construction when the facility is built. As such, impact fee revenues will be dedicated to pay the
outstanding debt in future years, as fee revenues are collected.
At this point, approximately $4.87 Million of impact fee eligible costs will be paid with a long-term loan (20 years, 3.75%) through
the State’s Revolving Loan Fund.
A debt schedule will be updated semi-annually with the amount of impact fee dollars that have been dedicated to debt payments
until the full amount owed is paid.
ALTERNATIVES CONSIDERED
ADVANTAGES OF APPROVAL
Major capital expansion of the Bozeman WRF will enable the City to meet its ever growing demand for wastewater services and
still produce a high quality effluent that is in full compliance with the City’s MPDES discharge permit. Expansion of the Bozeman
WRF is consistent with the City’s long-term need to accommodate rapid growth and economic development in the Gallatin Valley.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
FY07 Design: Total $3.9 Million
67% Wastewater Utility Cash = $2.33 Million
33% Wastewater Impact Fee Cash = $1.57 Million
FY09 & FY10 & FY11 Construction: Total $49.9 Million
67% Wastewater Utility = $33.5 Million
New
Replacement
Equipment
Project