HomeMy WebLinkAbout2 WEB Binder Spring Creek Village PreappSpring Creek Village
Subdivision Pre-App
Spring Creek Village LLC
delaneynco@earthlink.net
Bitnar Architects
www.bitnararchitects.com
C&H Engineering and
Surveying, Inc.
www.chengineers.com
Jami Morris
planningbozeman@yahoo.com
Table of Contents
Tab 1 – Subdivision Pre-Application
Tab 2 – Project Description
Contact Information
Existing Site Conditions
Sheet 1.0 Site Image
Sheet 1.1 Vicinity Map
Conservation District Email
Tab 3 - Development Plan
Development Proposal
Requested Relaxations & Variances
Waivers from Section 18.78.060
Subdivision Pre-App
Sheet 3.1 Street Plan
Sheet 3.2 Street Cross Section
Tab 3 - Parks & Recreation Facilities
Sheet 1.3 Site Plan: Park & Open Space
Tab 4 - Affordable Housing
Letter to CAHAB
Tab 5 – Traffic Study
Initial Traffic Study
Page 1 Appropriate Review Fee Submitted
CITY OF BOZEMAN
DEPARTMENT OF PLANNING AND COMMUNITY DEVELOPMENT
Alfred M. Stiff Professional Building
20 East Olive Street
P.O. Box 1230
Bozeman, Montana 59771-1230
phone 406-582-2260
fax 406-582-2263
planning@bozeman.net
www.bozeman.net
DEVELOPMENT REVIEW APPLICATION
1. Name of Project/Development:
2. Property Owner Information:
Name: E-mail Address:
Mailing Address:
Phone: FAX:
3. Applicant Information:
Name: E-mail Address:
Mailing Address:
Phone: FAX:
4. Representative Information:
Name: E-mail Address:
Mailing Address:
Phone: FAX:
5. Legal Description:
6. Street Address:
7. Project Description:
8. Zoning Designation(s): 9. Current Land Use(s):
10. Bozeman 2020 Community Plan Designation:
11. Gross Area: Acres: Square Feet: 12. Net Area: Acres: Square Feet:
Page 2
(Development Review Application – Prepared 11/25/03; Amended 9/17/04, 5/1/06; 9/18/07)
13. Is the subject site within an urban renewal district? Yes, answer question 13a No, go to question 14
13a. Which urban renewal district? Downtown Northeast (NURD) North 7th Avenue
14. Is the subject site within an overlay district? Yes, answer question 14a No, go to question 15
14a. Which Overlay District? Casino Neighborhood Conservation Entryway Corridor
15. Will this application require a deviation(s)? Yes, list UDO section(s): No
16. Application Type (please check all that apply): O. Planned Unit Development – Concept Plan
A. Sketch Plan for Regulated Activities in Regulated Wetlands P. Planned Unit Development – Preliminary Plan
B. Reuse, Change in Use, Further Development Pre-9/3/91 Site Q. Planned Unit Development – Final Plan
C. Amendment/Modification of Plan Approved On/After 9/3/91 R. Planned Unit Development – Master Plan
D. Reuse, Change in Use, Further Development, Amendment /COA S. Subdivision Pre-application
E. Special Temporary Use Permit T. Subdivision Preliminary Plat
F. Sketch Plan/COA U. Subdivision Final Plat
G. Sketch Plan/COA with an Intensification of Use V. Subdivision Exemption
H. Preliminary Site Plan/COA W. Annexation
I. Preliminary Site Plan X. Zoning Map Amendment
J. Preliminary Master Site Plan Y. Unified Development Ordinance Text Amendment
K. Conditional Use Permit Z. Zoning Variance
L. Conditional Use Permit/COA AA. Growth Policy Map Amendment
M. Administrative Project Decision Appeal BB. Growth Policy Text Amendment
N. Administrative Interpretation Appeal Other:
This application must be accompanied by the appropriate checklist(s), number of plans or plats, adjoiner information and materials, and fee
(see Development Review Application Requirements and Fees). The plans or plats must be drawn to scale on paper not smaller than 8½-
by 11-inches or larger than 24- by 36-inches folded into individual sets no larger than 8½- by 14-inches. The name of the project must
be shown on the cover sheet of the plans. If 3-ring binders will be used, they must include a table of contents and tabbed dividers between
sections. Application deadlines are Wednesdays at 5:00 pm. This application must be signed by both the applicant(s) and the property
owner(s) (if different) before the submittal will be accepted.
As indicated by the signature(s) below, the applicant(s) and property owner(s) submit this application for review under the terms and
provisions of the Bozeman Municipal Code. It is further indicated that any work undertaken to complete a development approved by the
City of Bozeman shall be in conformance with the requirements of the Bozeman Municipal Code and any special conditions established by
the approval authority. I acknowledge that the City has an Impact Fee Program and impact fees may be assessed for my project. Further, I
agree to grant City personnel and other review agency representatives access to the subject site during the course of the review process
(Section 18.64.050, BMC). I (We) hereby certify that the above information is true and correct to the best of my (our) knowledge.
Applicant’s Signature: Date:
Applicant’s Signature: Date:
Property Owner’s Signature: Date:
Property Owner’s Signature: Date:
Page 3
(Subdivision Preapplication Checklist – Prepared 11/26/03; revised 9/20/04; revised 5/10/05; revised 7/24/07)
SUBDIVISION PREAPPLICATION CHECKLIST
These checklists shall be completed and returned as part of the submittal. Any item checked “No” or “N/A” (not applicable)
must be explained in a narrative attached to the checklist. Incomplete submittals will be returned to the applicant.
A. Subdivision Type. First Minor Subdivision from a Tract of Record
First Minor Subdivision from a Tract of Record with a Variance
Second or Subsequent Minor Subdivision from a Tract of Record
Major Subdivision
B. Total Number of Lots.
C. Proposed Uses. Indicate the number of lots (or spaces subdivisions for rent or lease, or units for condominiums) for
each of the following uses:
Residential, single household Park/Recreation/Open Space
Residential, multi household Manufactured Home Space
Planned Unit Development Recreational Vehicle Space
Condominium Unit Commercial
Townhouse Industrial
Other:
D. Preapplication Requirements. The preapplication plan may be a freehand sketch, legibly drawn, showing approximate
boundaries, dimensions, areas and distances. The plan may be drawn directly on a print of a topographic survey
required for the preliminary plat. Please refer to Section 18.78.030, BMC for the specific requirements for each item.
Preapplication Requirements Yes No N/A
1. The name of adjoining subdivisions and numbers of adjoining certificates of survey,
along with adjacent lot and tract lines
2. Location, name, width and owner of existing or proposed streets, roads and
easements within the proposed subdivision; existing streets, roads and easements
within adjacent subdivisions and tracts; and the name of street or road that provides
access from the nearest public street or road to the proposed subdivision
3. Location of all existing structures, including buildings, railroads, power lines, towers,
and improvements inside and within 100 feet of the proposed subdivision
4. Zoning classification within the proposed subdivision and adjacent to it. The zoning
proposed for the subdivision, if a change is contemplated
5. A current U.S. Geological Survey Topographic map at the largest scale available with
the subdivision clearly outlined
6. Embankments, water courses, drainage channels, areas of seasonal water ponding,
areas within the designated floodway, marsh areas, wetlands, rock outcrops, wooded
areas, noxious weeds and areas of active faults. Include copies of any permits listed in
Section 18.78.020 (Streambed, Streambank and/Wetlands Permits), BMC that have
been obtained for the project
7. Location, size, and depth of sanitary and storm sewers, water mains and gas lines
✔
95
95
11
✔
✔
✔
✔
✔
✔
✔
Page 4
Preapplication Requirements, continued Yes No N/A
8.Location of fire hydrants, electric lines, telephone lines, sewage and water treatment,
and storage facilities
9. Subdivision block, tract, and lot boundary lines, with numbers, dimensions, and areas
for each block, tract and lot
10. Street location, right-of-way width, and name
11. Easement location, width and purpose
12. Sites to be dedicated or reserved as park, common open space, or other public areas;
with boundaries, dimensions and areas
13. Sites for commercial centers, churches, schools, industrial areas, condominiums,
manufactured housing community, and uses other than single family residences
14. Describe how the subdivision will satisfy the requirements of Section 17.02, BMC,
Affordable Housing
15. An overall development plan indicating future development of the remainder of the
tract, if the tract is to be developed in phases
16. A title block indicating the proposed name, quarter-section, section, township, range,
principal meridian, and county of subdivision
17. Scale, north arrow, name and addresses of owners and developers, and date of
preparation
18. A list of variance requests which will be submitted with the application for
preliminary plat
19. List of waivers requested from the requirements of Section 18.78.060 (Additional
Subdivision Preliminary Plat Supplements), BMC, shall be submitted with the
preapplication. The City of Bozeman shall notify the developer in writing of any
waivers granted from Section 18.78.060, BMC, after the preapplication meeting or
plan review
E. Section 76-3-504(1)(q)(iv) of the Montana Code Annotated requires that a preapplication meeting take place no more
than 30 days from the date that the agent or agency receives a written request for a preapplication meeting by the
subdivider.
The City of Bozeman strongly encourages Planning Board and City Commission review of preapplications for major
subdivisions. Planning Board and City Commission review of preapplications provides invaluable comments and
recommendations to aid in the preparation of preliminary plat applications. However, Planning Board and City
Commission review makes it difficult to comply with the 30-day review deadline specified in state law.
By marking the checkbox below, the developer agrees to a voluntary extension of the 30-day review deadline for this
preapplication. If the checkbox is not marked, the preapplication WILL NOT be reviewed by the Planning Board or
City Commission.
By marking this checkbox I agree to a voluntary extension of the 30-day review deadline for this
preapplication.
Applicant’s Signature: Date:
Applicant’s Signature: Date:
✔
✔
✔
✔
✔
✔
✔
✔
✔
✔
✔
✔
✔
Project Description
Contact Information
Spring Creek Village LLC
Tony Renslow
Project Manager
101 E. Main St., Ste. D
Bozeman, MT 59715
406.586.3132 (office)
406.586.8692 (fax)
406.539.7374 (cell)
delaneynco@earthlink.net
Bitnar Architects
502 S. Grand Avenue
Bozeman, MT 59715
406.587.1983 (office)
406.587.2125 (fax)
bitnar@imt.net
C&H Engineering and Surveying, Inc.
1091 Stoneridge Drive
Bozeman, MT 59718
406.587.1115 (office)
406.587.9768 (fax)
mcotterman@chengineers.com
Jami Morris
2440 Etta Place
Bozeman, MT 59718
406.570.6209
planningbozeman@yahoo.com
Existing Site Conditions
Spring Creek Village PUD consists of 31 acres zoned
Urban Mixed Use with a Community Commercial
Mixed Use land use designation and located within
the West Main Street (Class I) Entryway Corridor.
The flat vacant land within Spring Creek Village has
been historically used for hay and is predominantly
grassland. The Maynard Border Ditch runs north to
south through the western portion of the property.
There is an existing 15 foot ditch easement on the
west side of Maynard Border ditch and 5 feet on the
east side. The vegetation bordering the ditch is
mostly cottonwood, willow, dogwood and wild
rose.
Maynard Ditch looking south from
Fallon Street
The property is located in the northwest portion of town on the northwest corner
of the signalized intersection of Huffine Lane and Ferguson Avenue. The project
site is bound by Huffine Lane, Ferguson Avenue, Resort Drive and Fallon Street.
The adjacent roadways have been improved with
the original platting of Spring Creek Village Minor
Subdivision. Huffine Lane is improved to a 5 lane
arterial highway and the remaining streets are
designed and constructed as 2 lane local streets.
Currently, the site is accessed from Fallon Street at
the Resort Drive intersection and the 2 curb cuts east
of the ditch. Although curb and gutter has already
been installed along Fallon Street and Resort Drive
the sidewalks will be installed with the subdivision
infrastructure that will connect to the existing asphalt
trail along Ferguson Avenue.
Ferguson Avenue trail looking south
toward the Huffine intersection
Utilities and community facilities such as gas, electric, telephone, water and sewer
were installed with the original platting of the Spring Creek Village Minor
Subdivision. The utilities will be accessed from their existing locations within the
utility easements surrounding the property. Water and sewer will be provided to
the subdivision from the 12” water and 8” sewer mains in Fallon Street; 8” water
and 10” sewer mains in Resort Drive; and the 10” water main in Ferguson Avenue.
The area within the ½ mile radius of the property is
an eclectic mix of residential and commercial uses.
Spring Creek Village was originally subdivided as a
minor subdivision over 10 years ago. Since then the
adjacent property within the city limits has
developed into a small neighborhood commercial
area with a bank and a gas station to the east and
professional offices, a health and exercise
establishment, restaurant and residential
condominiums to the
north. The adjacent
land to the west remains vacant but further west and
within a ½ mile radius of the property is an
automobile sales, service and washing complex, a
veterinary clinic and a bank. The land across Huffine
Lane to the south of Spring Creek Village lies within
the county and includes Mountain Meadow Estates
trailer park and Allied Waste.
Cottonwood Condos and linear trail
looking north from Fallon Street
Bank on corner of Huffine and
Cottonwood
From: Murnion, Marcie - Bozeman, MT [mailto:Marcie.Murnion@mt.nacdnet.net]
Sent: Monday, August 16, 2010 10:26 AM
To: Delaney & Company
Subject: Ditch Info
Mr. Mike Delaney,
The waterway you asked me to look up in Section 10, Township 2S, Range 5E, between
Resort Road and Ferguson Road is the Maynard Border Ditch. The CD does not take
jurisdiction over ditches. We do advise that the ditch company be contacted pending any
proposed work on the ditch. Let me know if I can be of further assistance.
Marcie Murnion
Gallatin Conservation District
406-522-4011
www.gallatincd.mt.nacdnet.org
Development Plan
Development Proposal
Spring Creek Village PUD is a 5 phase subdivision providing a flexible
environment for commercial, office and residential development. The proposed
95 lot subdivision will provide a mix of uses including a lodge, restaurants, bars, a
grocery store, a bank, a variety of retail uses, a movie theater, offices, residential
condominiums, live/work units, a 1.4 acre private park/neighborhood center and
a golf course with a driving range.
Infrastructure improvements for phase 1 are planned for spring 2011 upon
preliminary plat approval. Building construction within phase 1 will likely
commence shortly after final site plan/COA approval is granted. Concurrent
construction will be requested for phase 1 to allow the first tenants to start
construction by summer 2011. Spring Creek Village LLC intends to build the lodge
and the restaurant-bar as phase 1 of the development. In addition to the building,
sidewalk, parking and access improvements expected with phase 1 we also intend
to construct the phase 1 and 2 stormwater improvements. A majority of the
remaining construction will likely be completed by future lot owners in
subsequent phases.
The unique lot design is similar to modular lotting. The expansion lots afford
additional flexibility in building design. The narrow lot can either be purchased
by an adjacent lot owner for additional building area, to allow patio seating and
other private outdoor amenities or to be constructed as a throughway between
buildings.
Located within the center of the subdivision is the 1.4 acre park for the
subdivision. The private park is the nexus of the subdivision and our
neighborhood center. All too often parks and open space areas within
commercial developments go unused and become neglected eyesores. In addition
to functionality the park has been designed to integrate commercial uses with the
park to encourage greater use of the outdoor amenity. The 4 tenants which
anchor the park could be a sandwich shop, coffee shop, art gallery, fly fishing
store or other endless possibilities. The park will also provide subdivision tenants
with an area for various sponsored functions such as concerts, promotional events,
exhibits, dining, movies, ice skating, craft fairs and markets.
Requested Relaxations & Variances
Zoning
18.19.020.A Authorized Uses-
Table of principal, conditional and accessory uses.
Golf course and driving range as a principal permitted use.
18.19.020.D Mixed Uses Required and Limited-
The ground level gross building area shall be at least 75% non-residential in
use.
Two condominium buildings proposed with 100% residential use.
18.19.050.B Maximum Setback-
Buildings shall be oriented to the adjacent street.
Buildings proposed to orient towards the interior private streets with
similar design and character on all street facing sides.
18.19.060.A Minimum Building Height-
Minimum building height is three stories and 32 feet.
One and two story buildings also proposed with design and
fenestration to coordinate with the taller buildings within the
development. A minimum building height of 25 feet proposed.
Subdivision
18.42.020.C Neighborhood Center Frontage-
The neighborhood center shall have frontage along 100 percent of its
perimeter on public or private streets.
Developed lots are proposed for the 4 corners of the park.
18.42.030.C Double/Through and Reverse Frontage-
Double/through frontage lots shall be avoided except where essential.
Lots are designed with private street adjacency on multiple sides.
18.42.040.B Block Length-
Block length shall not be designed, unless otherwise impractical, to be more
than 400 feet in length or less than 300 feet in length.
Blocks are less than 300 feet in length.
18.42.040.C Block Width-
Blocks shall not be less than 200 feet for more than 400 feet in width.
Blocks are designed at less than 200 feet in width.
18.44.020.A Private Streets-
A local private street right of way requirement is 31, 33 or 35 feet from
back-of-curb to back-of-curb.
The private streets are proposed as standard drive aisle width of 27 fe
from back-of-curb to back-of-c
et
urb.
18.44.0 Public Street, Approved Private Street,
lley Required-
cal access from a public street, approved private street or
90.B Drive Access from Improved
A
Each lot is required to have twenty five feet of frontage as well as, legal
and physi
greenway corridor.
Primary lot access and frontage will be provided from 26 foot w
drive aisles.
ide
Subdivision Variance Requested:
dards-
Unsignalized intersections shall have a minimum acceptable LOS of “C”.
18.44.060.D Level of Service Stan
Improvements to Valley Commons Drive-
ley
install improvements within
Based on the level of service the traffic study suggests improving Val
Commons Drive. The Ridge was required to
Valley Commons Drive as a condition of subdivision and planned unit
development approval. A pork chop was installed to limit Valley
Commons Drive to right in/right out only turning movements. Upon
completion of the improvements within the right of way there was
considerable public disapproval. In response the City Commission had the
pork chop removed and deemed the condition satisfied. Therefore, the
owner requests that in fulfilling the requirements of the traffic study a
condition to make similar improvements to the roadway be avoided
entirely.
Waivers from Section 18.78.060
The property owner requests the following waivers from 18.78.060 Additional
Subdivision Preliminary Plat Supplements.
18.78.060.T Affordable Housing-
Describe how the subdivision will satisfy the requirements of Title 17, Chapter 2, BMC
(Workforce Housing Units).
No workforce housing units are proposed within this development. See letter
requesting exemption Tab 4 – Affordable Housing.
September 27, 2010
CAHAB
City Affordable Housing Advisory Board
Brian LaMeres
PO Box 1230
Bozeman, MT 59771
RE: Spring Creek Village Workforce Housing
Dear CAHAB Board,
This letter is to request a waiver of workforce housing requirement by the City of Bozeman for
Spring Creek Village. Our research indicates that workforce housing is not necessary within the
development for the following reasons:
1. Proximity of Existing Housing
There are two (2) existing developments that currently market to this
demographic. For example, within a ½ mile radius of the Cottonwood and
Ravalli intersection there is an existing apartment complex and a new complex
under construction that is marketed as Affordable Housing. There will be in
excess of 100 units within a short walking distance to Spring Creek Village.
Within approximately one (1) mile, of our proposed development, located at
College and Professional Drive, are 2 more existing complexes that also provide
affordable housing. Adequate affordable housing is already in existence.
Requesting more workforce housing would, in our opinion, over saturate our
market.
2. Creativity & Flexibility
Spring Creek’s “Urban Mixed Use” zoning is intended to encourage a creative
and flexible environment, utilizing the live/work model. It is our intent to provide
mixed use pad sites for individual purchase. The motivation to create a mixed
use building for their professional and residential needs will vary from Buyer to
Buyer. Business owners will have the opportunity to own the building they
operate out of and also reside at, if they should choose. We are certain that a wide
variety housing opportunities will be available within Spring Creek Village.
These opportunities will range from condo/hotel sales, small studios to larger
apartments for lease and more elegant and larger residential units.
3. Impossible to Accurately Assess total number of Residential Units:
The proposed Spring Creek Village is a master planned subdivision and PUD.
The emphasis is on smaller individual mixed use Lots for sale and to be
developed by end users. Once we develop and sell an individual lot, we cannot
guarantee to the City of Bozeman if that end user will in fact be building any
residential units and/or office units on the 2nd or 3rd floors. Some lots will have
residential and some will not have any residential uses. We are creating a mixed
use land development with each and every lot having a wide variety of building
designs and uses. It is impossible to impose an artificial residential mandate on
any part of this Spring Creek Village PUD. Some buildings may in fact be a
single use, such as a retail use or restaurant / bar use or a bank / office use. Often
buildings will in fact be mixed-uses on separate floors.
It is our goal to have Spring Creek Village to be an efficient model of Urban Mixed Use zoning
within Bozeman.
Sincerely,
Michael W. Delaney
March 24, 2010 Mike Tierney Montana Department of Transportation P.O. Box 201001 Helena, MT 59620-1001 RE: Spring Creek Village Resort Preliminary Traffic Analysis Dear Mike, At the request of the developer, Delaney & Company, ATS has reviewed the proposed development plan for the Spring Creek project in Bozeman and performed a preliminary analysis of the area intersections. Please note that this analysis is based only on the initial development plans at this site and is not intended as a formal traffic impact study. The purpose of this letter is to help identify improvements that may be necessary at area intersections and determine if these improvements are viable based on City of Bozeman and MDT road design policies. The estimated total trip generation from the current Spring Creek Village Resort development plan is 8,000 VPD, which is down from 15,000 VPD estimated from the original plan created in 2003. Existing traffic volumes in the area have decreased around 25% along Huffine Lane since they were last analyzed for this project in 2006. Traffic volumes on Ferguson have remained approximately the same. Pedestrian and bicycle safety will be a focus for this project and many roadway improvements will be implemented with that goal in mind. The main roads which will be affected by this project are Huffine Lane (principal arterial), Ferguson Road (collector), Fallon Street (local), Resort Drive (local), and Valley Commons Drive (local). All of the roads within the development would be privately maintained. The impacts from the proposed project have been broken down by intersection. The critical intersections around this project are follows: 1. Huffine Lane & Resort Drive– This intersection currently has a channelized right-turn lane to restrict vehicles to right-out only movements onto Huffine Lane. Right- and left-turning movements are currently allowed into Resort Drive and Huffine Lane currently has a designated left-turn lane at this location. No changes are planned at this intersection from this development. 2. Resort Drive & Spring Creek Village Drive – This intersection is located 420 feet from Huffine Lane and has been proposed as a four-way STOP intersection with raised pedestrian crosswalks. This will be the primary access point for the developments on both sides of Resort Drive. The purpose of the four-way STOP will be to help control the traffic flow through the heart of the development site and help encourage pedestrian movement between the medical and office land 130 South Howie Street Helena, Montana 59601 406-459-1443
uses west of Resort Drive and the commercial and residential land uses east of Resort Drive. A four-way STOP at this location would fit with the overall goals of the development by slowing traffic and providing a safe and easy location for pedestrians to cross the two main roads within the development. 3. Resort Drive & Fallon Street – The projected traffic volumes at this location indicate that the intersection will function adequately with a simple two-way STOP control on Fallon Street. Raised crosswalks at the intersection may be beneficial to promote pedestrian safety. 4. Fallon Street & Ravalli Street/The Ridge - The projected traffic volumes at these intersections indicate that a simple two-way STOP control will be adequate. Raised crosswalks on Fallon Street at the intersections may be beneficial to promote pedestrian safety. 5. Fallon Street & Fergusson Road– The intersection of Ferguson Road and Fallon Street would work adequately with the existing lane configuration and the two-way STOP control for the initial development of the Spring Creek Village Resort, up to 40% build-out. If additional turn lanes were installed and the intersection was converted to a 4-way STOP, the intersection would function well through full-development of the Spring Creek property at 100% buildout. It is unlikely that the traffic generation for the Spring Creek Village Resort alone would cause any peak-hour signalization warrants to be met at full build-out, but the addition of traffic from other developments in this area in the future may create a need for additional traffic controls at this intersection. A modern roundabout may be desirable at this intersection in the future to address the access needs along Fergusson Road, but is not necessary at this time. 6. Spring Creek Drive & Ferguson Road – At this location the development plans suggest creating an additional access into the Spring Creek development site which would allow right/left in and right-out only traffic movements. All of the traffic movements on this new west approach should function adequately assuming a two-way left-turn lane was installed along Ferguson. Please note that this new turning lane may need to be constructed adjacent to the existing left-turning lane at Huffine Lane (the intersection is 280 feet from Huffine Lane). The additional traffic going into the Spring Creek development site at Valley Commons Drive will increase the delay for drivers turning left onto Ferguson on the eastern approach and the LOS for that leg will go to F before full build-out of the Spring Creek Village Resort. However, the LOS at this intersection will eventually go to LOS F regardless of the construction of this development. The construction of the Spring Creek Village Resort would hasten the need for improvements along Ferguson Road and would help bring about positive and permanent solution to the existing problems at the Valley Commons Drive intersection. A right-out only at Valley Commons Drive would address this issue but would need to be implemented along with a future roundabout at Fallon Street
to address the access needs in this area. It is also recommended that the existing approach to the gas station between Valley Commons and Fallon be eliminated in favor of a new approach onto Fallon from the gas station. 7. Huffine Lane & Fergusson Road– This intersection should function adequately through full 100 % build-out of the Spring Creek Village Resort with the existing as-built signal and lane configurations. Based on existing traffic volumes at this location, it is likely that a right-turn deceleration lane may be currently warranted for westbound traffic on Huffine Lane, without any development of the Spring Creek Village Resort property. The construction of this turning lane should be considered in conjunction with all of the other developments planned for this area. At this time we would like MDT to review these conceptual plans and provide feedback as to the appropriateness of these intersection treatments as they relate to MDTs planning goals for Huffine Lane. A formal TIS with detailed phasing plans will be prepared for this development, but it would be extremely helpful to receive some feedback from MDT in regards to these preliminary plans so that the intersection mitigation options are more defined as we go in the formal TIS process. If you have any questions please feel free to call me at 406-459-1443. Sincerely, Bob Abelin, P.E. Abelin Traffic Services