REPORT TO: Honorable Mayor and City Commission
FROM: James Goehrung, Director of Facility Services
Chuck Winn, Assistant City Manager
SUBJECT: Approve Resolution 4303 authorizing the City Manager to sign
Change Order #17 for the Lower Yard Vehicle Maintenance and HRDC Bus Barn for
mechanical and plumbing modifications and sub-base improvements for the site road system.
MEETING DATE: December 13, 2010
AGENDA ITEM TYPE: Consent
RECOMMENDATION: Approve Resolution 4303 authorizing the City Manger to sign
Change Order #17 in the amount of $5,873.05, for the Lower Yard Vehicle Maintenance and
HRDC Bus Barn.
The changes include: CP #37 modifications to the radiant heat floor system, $5,608.15; CP #47
credit for the removal of the mechanical screens, ($540.00); CP #51 relocation of the air
compressor, $804.90.
BACKGROUND: This change order includes three mechanical and plumbing related items.
CP #37 is for modifications to the radiant heat floor system. The original layout of the system
ran through the central office area of the building. A question was raised by the owner as to
what that extra heat gain would do for the offices. The lines were modified so that they did not
loop through the offices. This change required the addition of two new supply lines and
manifolds for the floor system. The original change request has been reduced in cost and the
change is being processed with the reduced amount. Staff has directed the architects on the
project to address this change and some other mechanical related changes that have been brought
up by the contractor as an error and omission on the part of the mechanical engineer and any
follow up will be addressed in future changes.
57
CP #47 is a credit for the removal of the mechanical screens for the rooftop mechanical
equipment. The screens are standard aesthetic requirements for rooftop systems requested by the
Planning Department. Because the units are not visible from the ground and are already
enclosed in an acceptable visual enclosure the Planning Department was willing to waive the
installation of additional screens. The result was a credit to the project.
CP #51 is for the relocation of the vehicle maintenance shop air compressor. The compressor
was originally shown to be located in the building mechanical room in the central office area.
The confined space in the mechanical room would not allow easy access to the unit for servicing.
Also the noise from the compressor would be disruptive for the offices. The City worked out a
deal with HRDC to locate the compressor in the HRDC bus bays in exchange for an air line they
HRDC could access from their garage. The additional charge covers some plumbing, electrical
and a support pad for the compressor to sit on and to attach the unit to the wall.
UNRESOLVED ISSUES: The owner’s representatives are negotiating with the
subcontractors, the mechanical and electrical engineer, regarding some design oversights and
who specifically will cover some of the added costs that have been requested by the contractor.
ALTERNATIVES: As suggested by the City Commission.
FISCAL EFFECTS: The costs associated with the items in this change order will be
paid out of the project contingency fund. Through Change Order #17, the current balance for the
Pre-Construction Change Orders is $5,465.62. The balance for the 12% Project Contingency
Change Order is $67,932.98. The summary of activity for the contingency fund is shown below.
Pre-Construction Change Orders $15,650.00
CO #4 Fire Alarm Design ($1,994.50)
CO#4 Welding Vent Hood ($5,000.00)
CO#5 Hose Bibs ($913.00)
CO#5 Utility Separation ($522.50)
CO#9 Electrical Panel and Heat Tape ($1,369.10)
CO#15 Fire Alarm/Smoke Detector ($385.28)
TOTAL Pre–Const CO Balance Remaining $5,465.62
Project Contingency $128,501.70
Change Order #1 HRDC $0
Change Order #2 Asbestos Remediation ($3,294.32)
Asbestos Disposal ($1,545.50)
($4,839.82)
58
Chance Order #3 Added Site Work ($2,362.30)
Change Order #4 Costs above estimate for Welding Hood
(revised) Included in the Pre-Const COs ($2,560.23)
Change Order #5 Hose Bibs and Utility Separation
costs addressed in Pre-Construction
Change Order budget $0
Change Order #6 HRDC $0
Change Order #7 Modify the height of the parts counter and
install a sliding glass window between the
two work areas. ($1,097.80)
Change Order #8 Revise foundation sub-grade preparation
due to discover of unstable soils; Replace
fill material in clarifiers; Add a second
conduit run for phone and data. ($4,897.27)
Change Order #9 Electrical panel and heat tape Addressed
in the Pre-Construction Change Order
budget $0
Change Order #10 Grout plug on clay pipe in storm water
tank pit, $980.38; add three steel
bollards for building protection
$389.82 ($1,370.19)
Change Order #11 Add an additional shutoff air valve
for the compressed air valve, $424.60;
Remove alternate No. 5 for the installation
of the skylights, ($12,200.00). $11,775.40
Change Order #12 Additional footing, foundation, and
reinforcement based on final building
structural analysis. ($6,059.27)
Change Order #13 Structural fill for footings, foundation,
road and parking areas. ($12,170.40)
Change Order #14 Sump and strainer valve ($1,815.55)
Unit heater change ($2,167.72)
Revised fresh air duct ($3,758.10)
Shop ceiling fan ($12,537.92)
Rainwater tank slab ($670.48)
Sand storage light ($4,168.68)
($25,118.45)
Repay from streets for light $4,168.68
Repay from streets for electrical $1,675.00
($19,274.77)
59
Change Order #15 ADA Shower ($1,112.10)
Lift Air Supply ($1,003.20)
Recirc Pump 228.00
Impound Lot Road ($3,772.78)
Washer Dryer Hook-up ($1,818.41)
Revise Ceiling Height ($110.00)
Remove Fire Wall $437.39
($7,151.10)
Change Order #16 HRDC $0
Change Order #17 Radiant Manifold $5,608.15
Mechanical Screens ($540.00)
Compressor Relocation $804.90
$5,873.05
Non-budget changes Pre-bid items charged to project $4,687.92
Expenditures to Date $60,568.72
Contingency Balance Remaining $67,932.98
Attachments: Change Order Form #17
Change Order Resolution # 4303
Report compiled on: December 1, 2010
60
1 of 2
COMMISSION RESOLUTION NO. 4303
A RESOLUTION OF THE CITY COMMISSION OF THE CITY OF
BOZEMAN, MONTANA, APPROVING ALTERATION/MODIFICATION OF
CONTRACT WITH BN BUILDERS, BOZEMAN, MONTANA.
WHEREAS, the City Commission did, on the 5th day of October 2009, authorize award of the
bid for the Construction of the Vehicle Maintenance Building and HRDC Bus Barn to BN Builders,
Bozeman, Montana; and
WHEREAS, Section 7-5-4308, Montana Code Annotated, provides that any such alterations or
modifications of the specifications and/or plans of the contract be made by resolution; and
WHEREAS, it has become necessary in the prosecution of the work to make alterations or
modifications to the specifications and/or plans of the contract.
NOW, THEREFORE, BE IT RESOLVED by the City Commission of the City of Bozeman,
Montana, that the proposed modifications and/or alterations to the contract between the City of Bozeman,
a municipal corporation, and BN Builders, Bozeman, Montana, as contained in Change Order #17,
attached hereto, be and the same are hereby approved; and the City Manager is hereby authorized and
directed to execute the contract change order for and on behalf of the City; and the City Clerk is
authorized and directed to attest such signature.
61
Resolution No. 4303 Change order #17
Page 2 of 2
PASSED AND ADOPTED by the City Commission of the City of Bozeman, Montana, at a
regular session thereof held on the 13th day of December, 2010.
__________________________________________
JEFFREY K. KRAUSS
Mayor
ATTEST:
________________________________________
STACY ULMEN, CMC
City Clerk
APPROVED AS TO FORM:
__________________________________________
GREG SULLIVAN
City Attorney