Loading...
HomeMy WebLinkAboutResolution No. 4301, Change order 1 for CTEP College/Huffine Shared use pathway Commission Memorandum REPORT TO: Honorable Mayor and City Commission FROM: Ron Dingman, Parks and Recreation Director Chuck Winn, Assistant City Manager SUBJECT: Resolution 4301authorizing the City Manager to sign Change Order #1 for the CTEP College/Huffine Shared Use Pathway project. MEETING DATE: November 29, 2010 AGENDA ITEM TYPE: Consent RECOMMENDATION: Approve Resolution 4301authorizing the City Manger to sign Change Order #1 in the amount of $13,056.50, for Quest cable relocation, additional excavation, fill, and geo-textile material, and added concrete removal and disposal costs related to the CTEP College/Huffine Shared Use Pathway project. BACKGROUND: Duneman Construction began construction on the CTEP College/Huffine Shared Use Pathway project on October 4, 2010. Since beginning construction there has been a need for a change order related to sidewalk removal, pathway realignment, and unstable soils. The thickness of the existing sidewalk along Huffine that was removed by the contractor was discovered to be 6 to 10 inches in thickness which resulted in additional hauling and disposal costs. Sidewalks are normally 4 inches thick and bids came in based on that assumption. Another part of this change order involves realignment of the Pathway, eliminating the need to move irrigation lines and a sign. Additionally, the contractor discovered mucky, unstable material in the sub-base beneath the sidewalk adjacent to the Bozeman Daily Chronicle building. This required additional excavation and fill, and geo-textile in order to stabilize the base, as well as a relocation of a phone cable. Below is Robert Peccia and Associate’s breakdown of the change order items and their associated costs. Item Number Description Quantity Units Unit Price Amount Basis of Unit Price 1 Additional Clear/Grub/Excavation 45 CY $12.71 +$572.00 Derived from Schedule of Values 2 Non-Removal USDA Sign 1 Each $55.00 (-$55.00) Bid Item 11 3 Non-Install USDA Sign 1 Each $425.00 (-$425.00) Bid Item 10 4 Remove Thickened Sidewalk 639 SY $3.50 +$2,236.50 Bid Item 2 Proportioned 5 Relocate Qwest Phone Line 1 LS $1,728.00 +$1,728.00 Negotiated LS Cost 6 Muck Excavation in Front of Chronicle Building 360 CY $4.50 +$1,620.00 Negotiated 7 Install Separation/Stabilization Geotextile 720 SY $1.25 +900.00 Negotiated 50 8 Import/Place Pitrun Cobble/Gravel Backfill 360 CY $18.00 +$6,480.00 Negotiated Items 1 – 3: Work Directive Change to shift path alignment on Align “A”, east of Ferguson to eliminate having to remove and relocate the USDA sign at Station 24+43. Alignment shift from approximate Station 22+50 to 25+50. Shifting 2’ south off of planned alignment created estimated 45 cubic yards (CY) of additional clearing, grubbing and excavation. Based on the Schedule of Values and Engineer’s estimate of overall project excavation, a $12.71/CY unit cost was derived. The alignment shift eliminated having to remove one sign (USDA) and install new (USDA). Net work cost Items 1-3 = +$92.00. The work is deemed appropriate as the USDA understood and approved the planned sign relocation, but preferred not, and shifting the alignment slightly improved project schedule by limiting irrigation impacts. Item 4: Throughout Alignment “A” the Contractor encountered thickened concrete sidewalk over and above typical installation standard of 6” thick for a sidewalk to allow vehicle access (City of Bozeman and Montana Public Works (MPW) standards). The sidewalk removed averaged 8 inches thick thus slowing the process of sidewalk removal, and increasing disposal costs. An 8”/6” ratio is applied (or +33% volume increase), for a net cost of +$3.50 per square yard (SY) greater than the $10.75 per SY bid to remove 6” thick concrete sidewalk. Net work cost = +$2,236.50. Item 5: Contractor encountered a Qwest phone line (marked on plans) within the planned excavation limits running longitudinally along Alignment “B” in front of the Bozeman Daily Chronicle. The depth was much shallower than typical installation, at about 6” – 18” below bottom of sidewalk. Expectations are that this utility should have been about 30” below grade per standards. As the line was in direct conflict with the work and needed to be buried deeper to resume project excavation, a cost of $1,728 was negotiated to trench the line deeper between approximate Stations 11+35 to 16+74. Items 6 – 8: The material encountered while excavating along Alignment “B”, from approximate Station 11+35 to 16+74 was very moist clay. The material does not support the weight of construction equipment and therefore would be problematic to support the planned pavement and crushed aggregate base course. The material rutted and offers no solid support for building upon and is considered needing “muck excavated”. To support the weight of construction equipment, it was determined that the most cost effective solution is to use a separation/stabilization geotextile with 18” deep cobble/gravel bank pit run backfill to build the proposed path base on. Net work cost = + $9,000.00 SUMMARY OF COST AND TIME: COST BREAKDOWN: TIME BREAKDOWN: ORIGINAL CONTRACT PRICE: $439,719.15 START OF CONSTRUCTION: October 4, 2010 PREVIOUS CHANGE ORDER AMOUNT: $0 CALENDAR DAYS BY CONTRACT: 45 CURRENT CONTRACT PRICE: $439,719.15 CONTRACT COMPLETION DATE: November 17, 2010 AMOUNT OF THIS CHANGE ORDER: +$13,056.50 NUMBER OF DAYS GRANTED THIS CHANGE ORDER: 05 NEW CONTRACT PRICE: $452,775.65 NEW CONTRACT COMPLETION DATE: November 22, 2010 The completion date as set forth in the contract documents shall be (unchanged, increased, decreased) by 05 calendar days. The date for completion of all work will be November 22, 2010 . 51 UNRESOLVED ISSUES: As the project proceeds east, it is unknown whether or not the sub- base soil will be stable as the existing sidewalk is removed. ALTERNATIVES: As suggested by the City Commission. FISCAL EFFECTS: The original Construction contract price is $439,719.15. This change order totals $13,056.50 bringing the Construction contract total to $452,875.65. This will increase the City’s CTEP match by $1,752.18 resulting in the City’s total out-of-pocket matching commitment being $27,034.23. Projects funded by CTEP Allocation (held by the MDT) require a 13.42% Local Match. As a reminder, the City’s original match was $81,082.05 for this project. Easement donations were obtained from adjacent property owners and the value of those easements is $55,800. This is eligible for use toward the CTEP match which reduced our obligation to $25,282.05. Attachments: Change Order Form #1 Change Order Resolution # 4301 Report compiled on: November 3, 2010 52 1 of 2 COMMISSION RESOLUTION NO. 4301 A RESOLUTION OF THE CITY COMMISSION OF THE CITY OF BOZEMAN, MONTANA, APPROVING ALTERATION/MODIFICATION OF CONTRACTWITH DUNEMAN CONSTRUCTION, BELGRADE, MONTANA. WHEREAS, the City Commission did, on the 23rd day of August 2010, authorize award of the bid for the Construction of the College/Huffine Shared Use Pathway, to Duneman Construction, Belgrade, Montana; and WHEREAS, Section 7-5-4308, Montana Code Annotated, provides that any such alterations or modifications of the specifications and/or plans of the contract be made by resolution; and WHEREAS, it has become necessary in the prosecution of the work to make alterations or modifications to the specifications and/or plans of the contract. NOW, THEREFORE, BE IT RESOLVED by the City Commission of the City of Bozeman, Montana, that the proposed modifications and/or alterations to the contract between the City of Bozeman, a municipal corporation, and Duneman Construction, Belgrade, Montana, as contained in Change Order #1, attached hereto, be and the same are hereby approved; and the City Manager is hereby authorized and directed to execute the contract change order for and on behalf of the City; and the City Clerk is authorized and directed to attest such signature. 53 Resolution No. 4278 Change order #13 Page 2 of 2 PASSED AND ADOPTED by the City Commission of the City of Bozeman, Montana, at a regular session thereof held on the 29th day of November, 2010. __________________________________________ JEFFREY K. KRAUSS Mayor ATTEST: ________________________________________ STACY ULMEN, CMC City Clerk APPROVED AS TO FORM: __________________________________________ GREG SULLIVAN City Attorney 54 55 56 57