HomeMy WebLinkAboutChange Order 15, City Shops, HRDC Bus Barn, BN Buildersdowfing sandholm architects I Project: City ShopsY HRDC Bus Barn 1821 N. Rouse Ave Bozeman, MT 59715 To Contractor: BN Builders, Inc 2066 Stadium Dr., Ste 102 Bozeman, MT 59715 The Contract is changed as Increase Contract Sum. Date: October 14, 201 Architect's Project No: 08-265 Contract Date: November 4, 2009 Contract For; General Construction Reason for change: Please see attached Summary of Mechanical Change Orders ma p CP #17; CP #33- CP #35; CP #38 CP #39: CP #40- CP #41- CP #42; CP #44; CP #46 Total Contract Sum Adiustment C.O. #16 Owner M Architect M Contractor M Field Other The original Contract Sum was 1,907,600.00 The net change by previously authorized Change Orders 106,045.09 The Contract Sum prior to this Change Order was $_2�013,645.09 The Contract Sum wink be increased by this Change Order by the amount of $ 13,206.01 The new Contract Sum including this Change Order will be $ 2,026.851 10 City of Bozeman Contract Sum Adiustment: The original Contract Sum was The net change by previously authorized Change Orders The Contract Sum prior to this Change Order was The Contract Sum will be increased by this Change Order by the amount of (57,07% of Total Change Order) The new Contract Sum including this Change Order will be HRDC. Contract Sum Adiustmeft The original Contract Sum was The net change by previously authorized Change Orders The Contract Sum prior to this Change Order was The Contract Sum will be increased by this Change Order by the amount of (42.93% of Total Change Order) The new Contract Sum including this Change Order will be $. _ 41 $ 56.953,91 $ 1,106,185.32 7,536,38 $ 113,721.70 858, 368.59 49,091 16 $ 907,459.75 $- - 5,669.64 913,129.39 Contract Time Adjustment: The Contract Time will be increased by _Rbet six (90) days. The date of Substantial Completion as of the date of this Change Order therefore is: November 19. 201