Loading...
HomeMy WebLinkAboutResolution No. 4300, Change Order 15 for Vehicle Maintenance and HRDC Bus Barn.pdf Commission Memorandum REPORT TO: Honorable Mayor and City Commission FROM: James Goehrung, Director of Facility Services Chuck Winn, Assistant City Manager SUBJECT: Approve Resolution 4300 authorizing the City Manager to sign Change Order #15 for the Lower Yard Vehicle Maintenance and HRDC Bus Barn for mechanical and plumbing modifications and sub-base improvements for the site road system. MEETING DATE: November 8, 2010 AGENDA ITEM TYPE: Consent RECOMMENDATION: Approve Resolution 4300 authorizing the City Manger to sign Change Order #15 in the amount of $7,536.38, for the Lower Yard Vehicle Maintenance and HRDC Bus Barn. The changes include: CP #17 added cost for an ADA compliant shower, $1,112.10; CP #33 additional air supply line for the Mohawk vehicle lift, $1,003.20; CP #35 credit for recirculation pump on domestic hot water line, ($228.00), CP #38 sub-base road preparation and material for area near the impound yard, $3,772.78, CP #40 add utility connections for a washer and dryer hook-up, $1,818.41; CP #41 relocate the fire control panel and install additional pull stations and smoke detectors, $385.28; CP # 44 change in ceiling height to accommodate roof drains and mechanical ducting, $110.00; CP #46 credit for the removal of a fire wall that was no longer needed now that the old wastewater treatment plant building is fully out of use, ($437.39). BACKGROUND: This change order includes four mechanical and plumbing related items. CP #17 is for the difference between the standard shower unit that was bid and an ADA compliant unit. CP #33 is for an additional air line for the supply connection on the Mohawk vehicle lift. CP #41 is for the relocation of the fire alarm panel into the secure IT closet. The owners also decided to add some additional pull stations and smoke sensors in other parts of the building. This change item will be charged against the Pre-Construction Change Order Fund. CP #44 is to change some of the ceiling heights due to conflicts between some mechanical ducting and the roof drain lines. 31 CP #38 is a site related change order. The exit road onto East Griffin Drive is over a portion of the old Impound Yard. During site excavation the vehicle traffic demonstrated that the road surface was inadequate. This change is the cost to build up the road base to the standards matching adjacent road beds, minus the cost to restore the area to its original condition which is the contractor’s responsibility. CP #40 is an owner initiated change. The Vehicle Maintenance Department requested the addition of a washer and dryer for their clothing and shop rags. This change is to add the necessary utility connections for electrical, water, and venting. There are two credits included on this change order. CP #35 is for the elimination of the continuous recirculation of domestic hot water by the use of a pump. This change is for the cost of the pump. CP #46 is for the removal of a fire wall in the vehicle maintenance bay. A two hour fire break was required for the adjoining building. That old wastewater treatment building, also used as a fire training building, is now out of service so there is no need for the 1 hour fire rating on the wall. CP #39 is an official date change for the completion of the project. The schedule shows occupancy on November 18, 2010. The delay was due to the problems with the metal building manufacturer. The contractor severed the agreement with this sub-contractor and hired a new firm. The new supplier has lived up to their schedule and we are still on line for the revised completion date. There are no dollar costs associated with this change proposal. All the redesign costs were covered by the contractor. UNRESOLVED ISSUES: None related to the items listed on this change order. ALTERNATIVES: As suggested by the City Commission. FISCAL EFFECTS: The costs associated with the items in this change order will be paid out of the project contingency fund. Through Change Order #15, the current balance for the Pre-Construction Change Orders is $5,465.62. The balance for the 12% Project Contingency Change Order is $73,806.03. The summary of activity for the contingency fund is shown below. Pre-Construction Change Orders $15,650.00 CO #4 Fire Alarm Design ($1,994.50) CO#4 Welding Vent Hood ($5,000.00) CO#5 Hose Bibs ($913.00) CO#5 Utility Separation ($522.50) CO#9 Electrical Panel and Heat Tape ($1,369.10) CO#15 Fire Alarm/Smoke Detector ($385.28) TOTAL Pre–Const CO Balance Remaining $5,465.62 32 Project Contingency $128,501.70 Change Order #1 HRDC $0 Change Order #2 Asbestos Remediation ($3,294.32) Asbestos Disposal ($1,545.50) ($4,839.82) Chance Order #3 Added Site Work ($2,362.30) Change Order #4 Costs above estimate for Welding Hood (revised) Included in the Pre-Const COs ($2,560.23) Change Order #5 Hose Bibs and Utility Separation costs addressed in Pre-Construction Change Order budget $0 Change Order #6 HRDC $0 Change Order #7 Modify the height of the parts counter and install a sliding glass window between the two work areas. ($1,097.80) Change Order #8 Revise foundation sub-grade preparation due to discover of unstable soils; Replace fill material in clarifiers; Add a second conduit run for phone and data. ($4,897.27) Change Order #9 Electrical panel and heat tape Addressed in the Pre-Construction Change Order budget $0 Change Order #10 Grout plug on clay pipe in storm water tank pit, $980.38; add three steel bollards for building protection $389.82 ($1,370.19) Change Order #11 Add an additional shutoff air valve for the compressed air valve, $424.60; Remove alternate No. 5 for the installation of the skylights, ($12,200.00). $11,775.40 Change Order #12 Additional footing, foundation, and reinforcement based on final building structural analysis. ($6,059.27) Change Order #13 Structural fill for footings, foundation, road and parking areas. ($12,170.40) 33 Change Order #14 Sump and strainer valve ($1,815.55) Unit heater change ($2,167.72) Revised fresh air duct ($3,758.10) Shop ceiling fan ($12,537.92) Rainwater tank slab ($670.48) Sand storage light ($4,168.68) ($25,118.45) Repay from streets for light $4,168.68 Repay from streets for electrical $1,675.00 ($19,274.77) Change Order #15 ADA Shower ($1,112.10) Lift Air Supply ($1,003.20) Recirc Pump 228.00 Impound Lot Road ($3,772.78) Washer Dryer Hook-up ($1,818.41) Revise Ceiling Height ($110.00) Remove Fire Wall $437.39 ($7,151.10) Non-budget changes Pre-bid items charged to project ($4,687.92) Expenditures to Date ($54,695.67) Contingency Balance Remaining $73,806.03 Attachments: Change Order Form #15 Change Order Resolution # 4300 Report compiled on: September 26, 2010 34 1 of 2 COMMISSION RESOLUTION NO. 4300 A RESOLUTION OF THE CITY COMMISSION OF THE CITY OF BOZEMAN, MONTANA, APPROVING ALTERATION/MODIFICATION OF CONTRACT WITH BN BUILDERS, BOZEMAN, MONTANA. WHEREAS, the City Commission did, on the 5th day of October 2009, authorize award of the bid for the Construction of the Vehicle Maintenance Building and HRDC Bus Barn to BN Builders, Bozeman, Montana; and WHEREAS, Section 7-5-4308, Montana Code Annotated, provides that any such alterations or modifications of the specifications and/or plans of the contract be made by resolution; and WHEREAS, it has become necessary in the prosecution of the work to make alterations or modifications to the specifications and/or plans of the contract. NOW, THEREFORE, BE IT RESOLVED by the City Commission of the City of Bozeman, Montana, that the proposed modifications and/or alterations to the contract between the City of Bozeman, a municipal corporation, and BN Builders, Bozeman, Montana, as contained in Change Order #15, attached hereto, be and the same are hereby approved; and the City Manager is hereby authorized and directed to execute the contract change order for and on behalf of the City; and the City Clerk is authorized and directed to attest such signature. 35 Resolution No. 4300 Change order #15 Page 2 of 2 PASSED AND ADOPTED by the City Commission of the City of Bozeman, Montana, at a regular session thereof held on the 13th day of September, 2010. __________________________________________ JEFFREY K. KRAUSS Mayor ATTEST: ________________________________________ STACY ULMEN, CMC City Clerk APPROVED AS TO FORM: __________________________________________ GREG SULLIVAN City Attorney 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83 84 85 86 87 88 89 90