COMMISSION RESOLUTION NO. 4255
A RESOLUTION OF THE CITY COMMISSION OF THE CITY OF BOZEMAN,
MONTANA, APPROVING ALTERATION/MODIFICATION OF CONTRACT
WITH WILLIAMS BROTHER CONSTRUCTION, LLC., BILLINGS,
MONTANA.
WHEREAS, the City Commission did, on the 10th day of November 2008, authorize award of the
bid for the Bozeman Water Reclamation Facility Phase I Improvements project, to Williams Brother
Construction, LLC., Billings, Montana; and
WHEREAS, Section 7-5-4308, Montana Code Annotated, provides that any such alterations or
modifications of the specifications and/or plans of the contract be made by resolution; and
WHEREAS, it has become necessary in the prosecution of the work to make alterations or
modifications to the specifications and/or plans of the contract.
NOW, THEREFORE, BE IT RESOLVED by the City Commission of the City of Bozeman,
Montana, that the proposed modifications and/or alterations to the contract between the City of Bozeman, a
municipal corporation, and Williams Brother Construction, LLC., as contained in Change Order No. 6,
attached hereto, be and the same are hereby approved; and the City Manager is hereby authorized and directed
to execute the contract change order for and on behalf of the City; and the City Clerk is authorized and
directed to attest such signature.
1 of 2
Ro olito on \ o 4255, Change 0j-der 6 for' WRP
PASSED AND APPROVED by the City Commission of the City of Bozeman, Montana, at a
regular session thereof held on the 17th day of May 2010.
S
ATTEST: 0 ZZ
0
STXC
City Clerk•,, i
.0
G' SULLIVAN
City Attorney
2 of 2
MdRR9 -
, _'LL MAtERLE rH
CHANGE ORDER
DATE OF ISSUANCE Aril 20 2010 EFFECTIVE DATE
No.
OWNER Ci of Bozeman CONTRACTOR Williams Brother Construction LLC
Contract: Bozeman WRF Phase I Improvements
Project: Bozeman Water Reclamation Facility OWNER's Contract No. SRF C303105 -01
ENGINEER HDR/MMI ENGINEER's Contract No. 00..60746
You are directed to make the following changes in the Contract Documents:
Description: Implement numerous changes as described in the Change Order No. 6 Summary.
Reason for Change Order: Minor modifications to contract work.
Attachments: Change Order No. 6 Summary with referenced attachments.
CHANGE IN CONTRACT PRICE:
Original Contract Price
$ 36
Net Increase (Decrease) from previous Change
Orders No. 0 to 5
$ 90 , 704.76
Contract Price prior to this Change Order:
$ 36 452 937,76
Net increase (decrease) of this Change Order:
$ ( 2,122.86)
Contract Price with all approved Change Orders:
$ 36,450 814.90
CHANGE IN CONTRACT TIMES:
Original Contract Times:
Substantial Completion: October 5, 2011
Ready for final payment: January 8, 2012
(days or dates
Net change from previous Change Orders No. 0 to
No. 5
Substantial Completion: 0
Ready for final payment: 0
da s
Contract Times prior to this Change Order:
Substantial Completion: October 5, 2011
Ready for final payment: January 8, 2012
( days or dates
Net increase (decrease) this Change Order:
Substantial Completion: 0
Ready for final payment: 0
(days)
Contract Times with all approved Change Orders:
Substantial Completion: October 5 2011
Ready for final payment: Januaa 8 2012
(days or dates)
Contractor certifies and agrees that there are no additional costs or claims for extra work, additional tithe, delays or
omitted items, of any nature whatsoever, associated with the subject change order items, except as identified and set
forth herein and ,unj ss expressly stated otherwise in the Change Order. And further, that the price agreed -upon herein
represents t 11 c st and value for the subject work performed and the materials supplied under the terms of the
contraL tt t work quantities and value were properly determined and are correct.
K� r 3,
CON CTOR Authorized Signature) Date
RECOMMENDED BY: A VED B
�1 EM - Signature) Date OWNER (Authori ed Signature)
054
Date
EJCDC 1910 -8 -B (1996 Edition
Prepared by the Engineers Joint Contract Documents Committee and endorsed by The Associated General Contractors of America and the
Construction Specifications Institute,