HomeMy WebLinkAboutChange Order 11, City Shops/HRDC Bus Barn, BN Buildersdowfing I sandhotm architects CITY OF BOZEMAN CHANGE ORDER Project City Shops/ HRDC Bus Barn 1821 N. Rouse Ave Bozeman, MT 59715 To Contractor: BN Builders, Inc 2066 Stadium Dr., Ste 102 Bozeman, MT 59715 The Contract is changed as follows: Decrease Contract Sum. Date: July 7, 201 Architect's Project No: 08-265 Contract Date: November 4, 2009 Contract For: General Construction LWOW"KI Owner M Architect M Contractor M Field F Other 1:1 Reason for change: Owner requested a shutoff valve for the compressed air line servicing the shop space, (CP #25) Owner decided not to install skylights, alternate No.5 in the bid documents. (-$12,200) Attachment(s): CP# 26 Bid Alternate Form from BN Builders Contract Sum Adiustment: The original Contract Sum was $ 1,049,231.41 The net change by previously authorized Change Orders $ 25,381 The Contract Sum prior to this Change Order was $ 1,074,612.61 The Contract Sum will be decreased by this Change Order by the amount of $ 11,775.40 The new Contract Sum including this Change Order will be $ 1,062,837.21 Contract Time Adiustment: The Contract Time will be increased by zero (0) days. The date of Substantial Completion as of the date of this Change Order therefore is July 28, 201 Not valid until signed by Architect, Contractor, and Owner. Signatures: Architect: Dowling Sandholm Architects 15 West 14' Street — Suite 103 Helena, Mt 59601 Contractor: BN Builders, Inc 2066 Stadium Dr., Ste 102 Bozeman, IVIT 59715 Owner: City of Bozeman P.O. Box 1230 Bozeman, MT 59771 By: �, - �) Date: 716116 ike Wiseman - Mursday, June 24, 2010 Mike Wiseman Dowling Sandholm Architects 55 West 14th Street Helena, MT 59601 # bear Mike Wiseman, This letter is to request authorization to proceed with the following extra work: C�P Number: 25 Description: Compressed Air Shutoff Valve in Mechanical Roo Proposed Amt'. $424.60 I Days Requested' a , ggqpg,f Work (see attached for detailed cost summary): Provide material, labor, and equipment to add a shutoff valve, piping, and hangers to the mechanical room compressor for a complete system as per details in AS I #12 and Mike Wiseman's sketch. See attached. Please sign below and return a COPY Of this letter to indicate your acceptance of this extra work and approve the ce for this work. Additional costs may apply if authorization is received after BNBuilders has proceeded with this work per previous ROM approval (attached). This change proposal represents the final price for this work. ONSuilders has proceeded with this work based on owner approval via email (see attached) or verbal direction. This change proposal represents the final price for this work. Submitted by: Accepted by: Date: t 0 717/10 An4ner. Mike Wiseman LtNftildem, kc DoWing Sandholm Architects Contractor Description moun & T Plumbing and Mechanical Plumbing $386,00 BNBuilders, Inc. Overhead & Profit $ BNBuilders, Inc. OH & ProFite Subcontractors $38,60 Total $424X0 G&T PLUMBING AND MECHANICAL INC P.O. BOX 21613 BILLINGS MONT. 59101 PHONE: 406-256-6016 FAX: 406-256-6393 DATE: 6/8/10 Revised: 6/23/10 TO: BNBuilders Project: HRDC BUSBARN Change Order per AST #12 Provide wid insta I I piping, hangers and valve per plan P1.1 revised 6/8110. Labor $286,00 Materital: $100.00 Price of change order: Please call if any questions. Approved by-- Date: dowling I sandholm I architects Date: May 27, 2010 Project: City of Bozeman/ HRDC City Shops/ Bus Barn 1812 N. Rouse Ave, Bozeman, MT 59715 Job Number. #08-265 issued To: Scott Jay BN Builders 2066 Stadium Dr., Ste 102 Bozeman, MT 59715 Regarding: Compressed air shutoff in Mechanical room information; A shutoff valve should be provided in the compressed air line that allows air supply to the City Shops to be shut off while the boiler pump remains on. A description of this item is provided by DC Engineering: "on sheet P1.1 provide a shut-off vale on the compressed air line with drops so the valve is at an easily accessible height, between 4'6" and 66". The shut-off valve needs to be installed in the mechanical room and downstream of the last take-off serving items in the mechanical room. The shut-off valve should only interrupt service to the City Shops side of the facility." F-M Issued By Dowling Sandholm Architects By:_ Date: 5/27110 Michael Wiseman End of Architect's supplemental instructions YIDRlaldiS:li 5VL65VNV1NOWNWOZNB 3Sf�f1d "NZG9l SNV1dMW03E)UYIN3 �7Ni8mid lc" I t ;k ��x:;.� CL 'UITQVf Nuvoing 00UH 1 SdQHS �1� Y YID � �� $. 4 N — g o b r G 1 ) N f ` $ 7 p 'N +�-�� —���� m � 'r, ,. � ��. �. ' � X ^r�, T �� �_ it ?' 4 ,� d. a� 08-265 / Vehicle Maint & Bus Barn - CD Spec Dowling S2ndholm Architects SECTION 004323 ALTERNATES FORM PARTICULARS 1.01 The following is the list of Alternatives referenced in the bid submitted by; 1,02 (Bidder) 210 . 1.03 TO (Owner) . ............................... Op 1.04 Dated 441) 1 1 b ff and which is an Integral part of the Bid Form. ALTERNATIVES LIST 2.01 The following amounts shall be added to or deducted from the Bid Amount. Refer to Section 012300 - Alternatives: Schedule of Alternatives. 2.02 Alternative 1: (Add p (Deduct) $ , 60c3.67!tZ_ 2.03 Alternative# 2:(jA�d(Deduct) $ �0, 2.04 Alternative 4 3: (Ad (Deduct) (Deduct) $ ), (10,K2�2 2.05 Alternative #4 Add )(Deduct)$ 2 'e7o, co 7r 2.06 Alternative 5. Ad ( Deduct) END OF SU 7/1712009 ALTERNATES FORM 004323-1 COMMISSION RESOLUTION NO. 4272 * r r WHEREAS, the City Commission did, on the 51h day of October 2009, authorize award of the bid for the Construction of the Vehicle. Maintenance Building and l-IRDC Bus Barn to BN Builders, Bozeman, Montana; and WHEREAS, Section 7 -5 -4308, Montana Code Annotated, provides that any such alterations or modifications of the specifications and /or plans of the contract be made by resolution; and WHEREAS, it has become necessary in the prosecution of the work to make alterations or modifications to the specifications and /or plans of the contract. NOW, THEREFORE, BE IT RESOLVED by the City Commission of the City of Bozeman, Montana, that the proposed modifications and /or alterations to the contract between the City of Bozeman, a municipal corporation, and BN Builders, Bozeman, Montana, as contained in Change Order 411, attached hereto, be and the same are hereby approved; and the City Manager is hereby authorized and directed to execute the contract change order for and on behalf of the City; and the City Clerk is authorized and directed to attest such signature. I of 2 Roolution \o 42 Chaagc order I I PASSED AND APPROVED by the City Commission of the City of Bozeman, Montana, at a regular session thereof held on the 2nd day of August, 2010. AT UT33 - 0 Al m - ST APPROVED AS TO FORM. G SULLIVAN City Attorney Page 2 of 2