HomeMy WebLinkAboutResolution 4272 Modification of Contract with BN Builders, Change Order 11, City Shops/HRDC Bus BarnCOMMISSION RESOLUTION NO. 4272
A RESOLUTION OF THE CITY COMMISSION OF THE CITY OF
BOZEMAN, MONTANA, APPROVING ALTERATION/MODIFICATION OF
CONTRACT WITH BN BUILDERS, BOZEMAN, MONTANA.
WHEREAS, the City Commission did, on the 5th day of October 2009, authorize award of the
bid for the Construction of the Vehicle Maintenance Building and 11RDC Bus Barn to BN Builders,
Bozeman, Montana; and
WHEREAS, Section 7-5-4308, Montana Code Annotated, provides that any such alterations or
modifications of the specifications and/or plans of the contract be made by resolution and
WHEREAS, it has become necessary in the prosecution of the work to make alterations or
modifications to the specifications and/or plans of the contract.
NOW, THEREFORE, BE IT RESOLVED by the City Commission of the City of Bozeman,
Montana, that the proposed modifications and/or alterations to the contract between the City of Bozeman,
a municipal corporation, and BN Builders, Bozeman, Montana, as contained in Change Order #11,
attached hereto, be and the same are hereby approved; and the City Manager is hereby authorized and
directed to execute the contract change order for and on behalf of the City; and the City Clerk is
authorized and directed to attest such signature.
t of 2
Rc.whttion \o 42 ChwNc order 11
PASSED AND APPROVED by the City Commission of the City of Bozeman, Montana, at a
regular session thereof held on the 2nd day of August, 201
" " " " "' I
ATT�#TB 0
1 :v c(-) "'-"
G SULLIVAN
City Attorney
Page 2 of 2
dowling I sandhotm I architects
r
Project: City Shops/ HRDC Bus Barn
1821 N. Rouse Ave
Bozeman, IVIT 59715
To Contractor: BN Builders, Inc
2066 Stadium Dr., Ste 102
Bozeman, MT 59715
The Contract is changed as follows:
Decrease Contract Sum.
Date: July 7, 2010
Architect's Project No: 08-265
Contract Date: November 4, 2009
Contract For: General Construction
MOMM
Owner E
Architect 0
Contractor M
Field ❑
Other ❑
Reason for change:
Owner requested a shutoff valve for the compressed air line servicing the shop space. (CP #25)
Owner decided not to install skylights, alternate No.5 in the bid documents, (-$12,200)
Attachment(s).
CP# 25
Bid Alternate Form from BN Builders
Contract Sum Adiustment:
The original Contract Sum was $_..1049,23141
The net change by previously authorized Change Orders $ 25,381,20
The Contract Sum prior to this Change Order was $ 1,074,612.61
The Contract Sum will be decreased by this Change Order by the amount of $__ 11775,40
The new Contract Sum including this Change Order will be $ . ........ 1,062,837.21
Contract Time Adjustment:
The Contract Time will be increased by zero 0) days.
The date of Substantial Completion as of the date of this Change Order therefore is: July
Not valid until signed by Architect, Contractor, and Owner.
Signatures:
Architect: Dowling Sandholm Architects
15 West 14 Street - Suite 103
Helena, Mt 59601
Contractor: BN Builders, Inc
2066 Stadium Dr., Ste 102
Bozeman, IVIT 59715
Owner: City of Bozeman
P.O. Box 1230
Bozeman, MIT 59771
By: a_ Date: - 7/6 , 46
- Aike Wiseman