HomeMy WebLinkAboutResolution No. 4272 Change Order 11 for Lower yard vehicle maintenance - HRDC bus barn.pdf Commission Memorandum
REPORT TO: Honorable Mayor and City Commission
FROM: James Goehrung, Director of Facility Services
Chuck Winn, Assistant City Manager
SUBJECT: Approve Resolution 4272 authorizing the City Manager to sign Change
Order #11 for the Lower Yard Vehicle Maintenance and HRDC Bus Barn to install a shutoff
valve for the compressed air line servicing the shop space and the vehicle lift, (CP #25).
Remove alternate No. 5 which was the installation of skylights.
MEETING DATE: August 2, 2010
AGENDA ITEM TYPE: Consent
RECOMMENDATION: Approve Resolution 4272 authorizing the City Manger to sign
Change Order #11 for the Lower Yard Vehicle Maintenance and HRDC Bus Barn to install a
shutoff valve for the compressed air line servicing the shop space and the vehicle lift, (CP #25),
$424.60; and remove alternate No. 5 which was the installation of the skylights, a deduct of
($12,200.00). The total for this change order is a decrease of $11,775.40. This is all on the city
side of the project so the credit will be to the city.
BACKGROUND: The equipment used to lift the vehicles for servicing in the shop areas are
powered with air pressure. The lifts are piped with air lines that allow the lifts to be raised and
lowered. Staff has identified some optional equipment that can be added at the work stations that
will increase both the range and efficiency of the service work performed. Some of the optional
tools are also operated with pneumatic pressure. CP #25 will add an additional air valve during
the initial plumbing that will provide locations so that the optional equipment can be plugged
into the main air lines right at the work station. Adding the valve now will be more cost
effective than trying to come back later and add the valve after everything is already plumbed in.
The second portion of the change is to remove an additive alternate that was bid for the project to
add skylights to the building. Alternate number 5 was originally bid and accepted for the project.
From a building maintenance perspective we have experienced problems with skylights. The
slope of the roof and the potential snow loads on the roof has called into question the long term
benefit of the skylights. The recent hail storm damaged most of the skylights that are installed
23
on other buildings. All these factors came together to make the decision to remove the skylights
from the building.
UNRESOLVED ISSUES: No others related to this proposed Change Order.
ALTERNATIVES: As suggested by the City Commission.
FISCAL EFFECTS: The two items on this change order fall under the category of
owner initiated changes. The costs and credit for Change Order #11 will be charged against the
contingency fund for the project. The overall credit will be $11,775.40. This leaves a balance in
the contingency fund of $123,149.50. The summary of activity is shown below.
Pre-Construction Change Orders $15,650.00
CO #4 Fire Alarm Design ($1,994.50)
CO#4 Welding Vent Hood ($5,000.00)
CO#5 Hose Bibs ($913.00)
CO#5 Utility Separation ($522.50)
CO#9 Electrical Panel and Heat Tape ($1,369.10)
TOTAL Pre–Const CO Balance Remaining $5,850.90
Project Contingency $128,501.70
Change Order #1 HRDC $0
Change Order #2 Asbestos Remediation ($3,294.32)
Asbestos Disposal ($1,545.50)
($4,839.82)
Chance Order #3 Added Site Work ($2,362.30)
Change Order #4 Costs above estimate for Welding Hood
(revised) Included in the Pre-Const COs ($2,560.23)
Change Order #5 Hose Bibs and Utility Separation
costs addressed in Pre-Construction
Change Order budget $0
Change Order #6 HRDC $0
Change Order #7 Modify the height of the parts counter and
install a sliding glass window between the
two work areas. ($1,097.80)
24
Change Order #8 Revise foundation sub-grade preparation
due to discover of unstable soils; Replace
fill material in clarifiers; Add a second
conduit run for phone and data. ($4,897.26)
Change Order #9 Electrical panel and heat tape Addressed
in the Pre-Construction Change Order
budget $0
Change Order #10 Grout plug on clay pipe in storm water
tank pit, $980.38; add three steel
bollards for building protection
$389.82 ($1,370.19)
Change Order #11 Add an additional shutoff air valve
for the compressed air valve, $424.60;
Remove alternate No. 5 for the installation
of the skylights, ($12,200.00). $11,775.40
Non-budget changes Pre-bid items charged to project ($3,310.93)
Contingency Balance Remaining $119,838.57
Attachments: Change Order Form #11
Change Order Resolution # 4272
Report compiled on: July 20, 2010
25
1 of 2
COMMISSION RESOLUTION NO. 4272
A RESOLUTION OF THE CITY COMMISSION OF THE CITY OF
BOZEMAN, MONTANA, APPROVING ALTERATION/MODIFICATION OF
CONTRACT WITH BN BUILDERS, BOZEMAN, MONTANA.
WHEREAS, the City Commission did, on the 5th day of October 2009, authorize award of the
bid for the Construction of the Vehicle Maintenance Building and HRDC Bus Barn to BN Builders,
Bozeman, Montana; and
WHEREAS, Section 7-5-4308, Montana Code Annotated, provides that any such alterations or
modifications of the specifications and/or plans of the contract be made by resolution; and
WHEREAS, it has become necessary in the prosecution of the work to make alterations or
modifications to the specifications and/or plans of the contract.
NOW, THEREFORE, BE IT RESOLVED by the City Commission of the City of Bozeman,
Montana, that the proposed modifications and/or alterations to the contract between the City of Bozeman,
a municipal corporation, and BN Builders, Bozeman, Montana, as contained in Change Order #11,
attached hereto, be and the same are hereby approved; and the City Manager is hereby authorized and
directed to execute the contract change order for and on behalf of the City; and the City Clerk is
authorized and directed to attest such signature.
26
Resolution No. 4272 Change order #11
Page 2 of 2
PASSED AND ADOPTED by the City Commission of the City of Bozeman, Montana, at a
regular session thereof held on the 2nd day of August, 2010.
__________________________________________
JEFFREY K. KRAUSS
Mayor
ATTEST:
________________________________________
STACY ULMEN, CMC
City Clerk
APPROVED AS TO FORM:
__________________________________________
GREG SULLIVAN
City Attorney