Loading...
HomeMy WebLinkAboutResolution No. 4272 Change Order 11 for Lower yard vehicle maintenance - HRDC bus barn.pdf Commission Memorandum REPORT TO: Honorable Mayor and City Commission FROM: James Goehrung, Director of Facility Services Chuck Winn, Assistant City Manager SUBJECT: Approve Resolution 4272 authorizing the City Manager to sign Change Order #11 for the Lower Yard Vehicle Maintenance and HRDC Bus Barn to install a shutoff valve for the compressed air line servicing the shop space and the vehicle lift, (CP #25). Remove alternate No. 5 which was the installation of skylights. MEETING DATE: August 2, 2010 AGENDA ITEM TYPE: Consent RECOMMENDATION: Approve Resolution 4272 authorizing the City Manger to sign Change Order #11 for the Lower Yard Vehicle Maintenance and HRDC Bus Barn to install a shutoff valve for the compressed air line servicing the shop space and the vehicle lift, (CP #25), $424.60; and remove alternate No. 5 which was the installation of the skylights, a deduct of ($12,200.00). The total for this change order is a decrease of $11,775.40. This is all on the city side of the project so the credit will be to the city. BACKGROUND: The equipment used to lift the vehicles for servicing in the shop areas are powered with air pressure. The lifts are piped with air lines that allow the lifts to be raised and lowered. Staff has identified some optional equipment that can be added at the work stations that will increase both the range and efficiency of the service work performed. Some of the optional tools are also operated with pneumatic pressure. CP #25 will add an additional air valve during the initial plumbing that will provide locations so that the optional equipment can be plugged into the main air lines right at the work station. Adding the valve now will be more cost effective than trying to come back later and add the valve after everything is already plumbed in. The second portion of the change is to remove an additive alternate that was bid for the project to add skylights to the building. Alternate number 5 was originally bid and accepted for the project. From a building maintenance perspective we have experienced problems with skylights. The slope of the roof and the potential snow loads on the roof has called into question the long term benefit of the skylights. The recent hail storm damaged most of the skylights that are installed 23 on other buildings. All these factors came together to make the decision to remove the skylights from the building. UNRESOLVED ISSUES: No others related to this proposed Change Order. ALTERNATIVES: As suggested by the City Commission. FISCAL EFFECTS: The two items on this change order fall under the category of owner initiated changes. The costs and credit for Change Order #11 will be charged against the contingency fund for the project. The overall credit will be $11,775.40. This leaves a balance in the contingency fund of $123,149.50. The summary of activity is shown below. Pre-Construction Change Orders $15,650.00 CO #4 Fire Alarm Design ($1,994.50) CO#4 Welding Vent Hood ($5,000.00) CO#5 Hose Bibs ($913.00) CO#5 Utility Separation ($522.50) CO#9 Electrical Panel and Heat Tape ($1,369.10) TOTAL Pre–Const CO Balance Remaining $5,850.90 Project Contingency $128,501.70 Change Order #1 HRDC $0 Change Order #2 Asbestos Remediation ($3,294.32) Asbestos Disposal ($1,545.50) ($4,839.82) Chance Order #3 Added Site Work ($2,362.30) Change Order #4 Costs above estimate for Welding Hood (revised) Included in the Pre-Const COs ($2,560.23) Change Order #5 Hose Bibs and Utility Separation costs addressed in Pre-Construction Change Order budget $0 Change Order #6 HRDC $0 Change Order #7 Modify the height of the parts counter and install a sliding glass window between the two work areas. ($1,097.80) 24 Change Order #8 Revise foundation sub-grade preparation due to discover of unstable soils; Replace fill material in clarifiers; Add a second conduit run for phone and data. ($4,897.26) Change Order #9 Electrical panel and heat tape Addressed in the Pre-Construction Change Order budget $0 Change Order #10 Grout plug on clay pipe in storm water tank pit, $980.38; add three steel bollards for building protection $389.82 ($1,370.19) Change Order #11 Add an additional shutoff air valve for the compressed air valve, $424.60; Remove alternate No. 5 for the installation of the skylights, ($12,200.00). $11,775.40 Non-budget changes Pre-bid items charged to project ($3,310.93) Contingency Balance Remaining $119,838.57 Attachments: Change Order Form #11 Change Order Resolution # 4272 Report compiled on: July 20, 2010 25 1 of 2 COMMISSION RESOLUTION NO. 4272 A RESOLUTION OF THE CITY COMMISSION OF THE CITY OF BOZEMAN, MONTANA, APPROVING ALTERATION/MODIFICATION OF CONTRACT WITH BN BUILDERS, BOZEMAN, MONTANA. WHEREAS, the City Commission did, on the 5th day of October 2009, authorize award of the bid for the Construction of the Vehicle Maintenance Building and HRDC Bus Barn to BN Builders, Bozeman, Montana; and WHEREAS, Section 7-5-4308, Montana Code Annotated, provides that any such alterations or modifications of the specifications and/or plans of the contract be made by resolution; and WHEREAS, it has become necessary in the prosecution of the work to make alterations or modifications to the specifications and/or plans of the contract. NOW, THEREFORE, BE IT RESOLVED by the City Commission of the City of Bozeman, Montana, that the proposed modifications and/or alterations to the contract between the City of Bozeman, a municipal corporation, and BN Builders, Bozeman, Montana, as contained in Change Order #11, attached hereto, be and the same are hereby approved; and the City Manager is hereby authorized and directed to execute the contract change order for and on behalf of the City; and the City Clerk is authorized and directed to attest such signature. 26 Resolution No. 4272 Change order #11 Page 2 of 2 PASSED AND ADOPTED by the City Commission of the City of Bozeman, Montana, at a regular session thereof held on the 2nd day of August, 2010. __________________________________________ JEFFREY K. KRAUSS Mayor ATTEST: ________________________________________ STACY ULMEN, CMC City Clerk APPROVED AS TO FORM: __________________________________________ GREG SULLIVAN City Attorney 27 28 29 30 31 32 33 34 35