HomeMy WebLinkAbout10- Change Order 2, Lyman Creek Water System InfrastructureCHANGE IN CON" RACT TIMES:
Original Contract Price
346,677.00
Original Contract Times:
Substantial Completion: 60/30
Ready for final payment: 90/60
0.00
(days or dates)
Net change from previous Change Orders No. 0
to
No. 1
Substantial Completion: 0
Ready for final payment: 0
(days)
Contract Times prior to this Change Order:
Substantial Completion: 60/30
Ready for final payment: 90/60
(days or dates)
Net increase this Change Order:
Substantial Completion: 7/0
Ready for final payment: 7/0
(days)
Contract Times with all approved Change Orders:
Substantial Completion: 67/30
Ready for final payment: 97/60
(days or dates)
CHANGE IN CONTRACT PRICE:
Original Contract Price
346,677.00
Net. Increase (Decrease) from previous Change
Orders No. 0 to 1
0.00
Contract Price prior to this Change Order:
346,677.00
Net increase (decrease) of this Change Order:
10,527.36
Contract Price with all approved Change Orders:
357,204.36
CHANGE ORDER
No. 2
DATE OF ISSUANCE EFFECTIVE DATE
OWNER: City of Bozeman CONTRACTOR: Edstrom Construction. Inc.
Contract: Lyman Creek Water System Infrastructure Improvements
Project: Lyman Creeek Water Sys. Infrastructure Imp. OWNER's Contract No. N/A
ENGINEER: Morrison Maierle, Inc, ENGINEER's Contract No. 0417.055
You are directed to make the .following changes in the Contract Documents:
Description: Addition of Elbows on the 12" PVC Supply Line, Changes to the Sourdough Vaults #1 and #2
Reason for Change Order: Unforeseen fittings necessary to complete the system.
Attachments: Change Order Backup Sheets; Addition of Elbows, Install Dresser Vault #1, Building Spool Fit
Valves Vault #2, Install new Flange Spool Vault #1 and Contract Time Increase Justification.
C :\tlsf
Contractor certifies and agrees that there are no additional costs or claims for extra work, additional time, delays or
omitted items, of any nature whatsoever, associated with the subject change order items, except as identified and set
forth herein and unless expressly stated otherwise in the Change Order. And further, that the price agreed -upon herein
represents the full cost and value for the subject work performed and the materials supplied under the teti'ts of the
coy and that the w rk quant'tie and value were properly determined and are correct.
X7- /1 per
CTOR (Authorized ignature) Date
APB' OVED B
WNER (Au
horized Signature)
Date
EJCDC 1910 -8 -B (1996 Edition
Prepared by the Engineers Joint Contract Documents Convnittee and endorsed by The Associated General Contractors of America and the
Construction Specifications Institute.
Page 1 of 2
\Lisa ColeslAppDatalLooallMicrosoft \Windows \Temporary Internet Files \Content.Outlook\I2WJ7FFRICOB Change Order 2 (2).doc