HomeMy WebLinkAboutBuilding Inspection Third Quarter Report.pdfPage | 1 ` Commission Memorandum REPORT TO: Honorable Mayor and City Commission FROM: Bob Risk, Chief Building Official Jason Shrauger, Fire Chief Chuck Winn, Assistant City Manager SUBJECT: Building Inspection 3rd Quarter FY10 Update January 1 – March 31, 2010 MEETING DATE: April 26, 2010 AGENDA ITEM TYPE: Action RECOMMENDATION: Accept this report detailing the financial and workload position of the Building Inspection Division for the quarter ending March 31, 2009. BACKGROUND: Because of the difficulties with estimating Building Inspection revenues and workloads, we committed to make quarterly reports regarding revenues, staffing levels and operating costs within the department. The FY10 Budget was balanced with the following assumptions: A. REVENUES: Without an increase in current fees, we estimated receiving approximately $71,000/month. This estimate was based on average monthly building permit activity during FY2009 and equals our estimated monthly expenditures for FY10. Last fiscal year, the average monthly revenue was $73,000 with actual monthly revenues ranging between $108,000 and $28,000. For this fiscal year, the monthly average for the first three quarters was $50,200. 70 Page | 2 Customarily, the 2nd and 3rd quarters of the fiscal year are the lowest revenue producing months in the Division. The total revenue for the 3rd quarter of FY10 was $139,100. Third Quarter Monthly Revenues January $44,000 February $45,300 March $49,800 Average Monthly Revenues: $46,400 B. EXPENDITURES: Our monthly expenditures averaged $59,270 for the 3rd Quarter. Our total expenditures for the 3rd Quarter of FY10 were $177,820. Third Quarter Expenditures January $62,400 February $57,750 March $57,670 Average Monthly Expenditures: $59,270 Now that we are three quarters through the fiscal year our total revenue stands at $452,000 which is $187,000 short of our estimated revenue amount of $639,000, and our total expenditure amount equals $547,520 which is $91,480 less than our original expenditure estimate of $639,000. 71 Page | 3 Building Division Revenue/Expenditure Comparison- Fiscal Year 2010 0 10,000 20,000 30,000 40,000 50,000 60,000 70,000 80,000 90,000 100,000 Revenues Expenditures At this time, we calculate that our actual monthly expenditures will average approximately $68,000 per month at the end of the year which is about $3000 per month less than our original estimate. This monthly saving is primarily due to the entire building division staff being very conservative when considering and implementing all budgeted building division spending. A. CASH RESERVE: The Administrative rules of Montana allow the building division to maintain a “cash reserve fund” derived from building permit fees provided that the reserve amount does not exceed the building division operating costs for a 12 month period. Our original Estimate of the building division operating costs for FY10 was $852,000. During this fiscal year, due to careful planning and very conservative spending, the building division has been able to reduce those original estimated costs and has revised our estimated operating cost for this year to $816.000. At the beginning of the 3rd quarter the Building Inspection Fund Cash Reserve was $566,819. At the end of the 3rd Quarter the cash reserve balance was $528,872, a drop of $37,947. This reserve balance represents 62% of our original estimated division operating cost ($852,000) and 65% of our revised estimated operating costs ($816,000) for FY10. 72 Page | 4 The 3rd quarter of this fiscal year saw Reserve declines similar to the 2nd quarter which averaged $22,500/month. However, we still anticipate that the 4th quarter revenues from spring building activity will cover the current division costs for that quarter. During the FY09 budget development, the Commission was not in support of raising Building Division fees until the Fund’s reserve level hit 50% of annual expenditures. Last spring, as we were nearing that level in the FY09 budget, we brought the issue of a Building Division fee increase to the Commission. At that time they declined to raise fees. B. BUILDING PERMIT NUMBERS: The total number of new permits for the 3rd Quarter FY10 was 622 which is up 68 permits from the same period last year. FY09 Quarterly Permit Totals with FY Quarterly Averages Permit Type July, August, September October, November, December January, February, March April, May, June Quarterly Averages Building 358 298 184 419 314.75 Plan Check 205 141 101 183 157.5 Electrical 181 141 99 125 136.5 Plumb/Mech 259 148 146 158 177.75 Fire Systems 19 21 17 17 18.5 Moving 3 0 0 1 1 Demolition 8 3 7 10 7 Total Permits 1033 752 554 913 813 Permit and Inspection Staffing Level 12 11 8 7 73 Page | 5 FY10 Quarterly Permit Totals with Quarterly Averages to Date Permit Type July, August, September October, November, December January, February, March April, May, June Averages To Date- Building 450 191 176 272 Plan Check 183 125 139 149 Electrical 157 93 123 124 Plumb/Mech 175 184 145 168 Fire Systems 20 19 14 18 Moving 0 0 0 0 Demolition 4 7 6 6 Total Permits 989 619 622 743 Permit and Inspection Staffing Level 7 7 7 C. INSPECTION WORKLOAD: “Inspections per Inspector Day” has historically been used to measure the workload of building inspectors. The accepted standard for inspections per inspector day is 15. Fiscal Year 2010 – 3rd QTR Inspections/Inspector Day Standard 15 January 12.83 February March 12.48 12.02 3rd QTR average inspections per day 12.44 To date for FY10, the average number of inspections per day for each inspector was 16.93. In addition to the daily inspection workload, the field inspection staff have used our traditionally slower 3rd quarter to take advantage of state required continuing education and in house cross training. It is important to note that all of the building division staff is required by the state to participate in continuing education classes and that this training takes place in the slower winter months whenever possible. 74 Page | 6 STAFFING PLAN: At this time, the Building Division staff consists of the Chief Building Official, 2 Plans Examiners, 3 Building Inspectors, 1 Code Compliance Officer, and 1 Permit Coordinator. Commercial fire plan review and commercial fire inspections are completed by the Fire Marshal/Deputy Chief/Inspections whose salary and benefits come from the general fund/Fire Department budget. The City of Bozeman Fire Chief serves as the Department Head for the Building Division. Currently, 25% of the Fire Chief’s salary and benefits come from the Building Division budget. With our current and projected workload, the Building Division is currently at the minimum staffing level needed to provide the minimum services mandated by the Administrative Code of Montana, City of Bozeman Ordinances, the International Building Code and Current Building Division Policies. UNRESOLVED ISSUES: None. ALTERNATIVES: As suggested by the City Commission. FISCAL EFFECTS: Our revenues for the 3rd Quarter FY10 averaged $46,400/month while our actual monthly expenditures for the quarter averaged $59,270/month. The Building Division Reserve Fund balance at the end of the 3rd Quarter was $528,872 which represents 65% of our revised estimated operating costs for the year. Attachments: None Report Compiled On: April 9, 2010 75 76 77 78 79