Commission Memorandum
REPORT TO: Honorable Mayor and City Commission
FROM: Bob Murray, Project Engineer
Rick Hixson, City Engineer
Chuck Winn, Assistant City Manager
SUBJECT: Bozeman Water Reclamation Facility, Phase 1 Improvements – Change
Order No. 5
MEETING DATE: April 12, 2010
AGENDA ITEM TYPE: Consent
RECOMMENDATION: Motion and vote to approve and authorize City Manager to sign
Bozeman Water Reclamation Facility, Phase 1 Improvements – Change Order No. 5.
BACKGROUND: Attached is a copy, of change order number 5 for the above referenced
project which modifies the wage rates for this project. Change order 4 added federal wage rates
to the project due to funding requirements. At that time, only the rates for Heavy Construction
Projects, General Decision MT080001, Modification 5, published on August 15, 2008 were
added. This didn’t cover all of the job classifications on the project, and as a result, this change
order is to add the rates for Building Projects, General Decision MT080034, Modification 2,
published on August 15, 2008.
FISCAL EFFECTS: The costs for this change were included in change order no 4, so this is
no cost.
ALTERNATIVES: As suggested by the City Commission.
Attachments: Change Order No. 5
Resolution 4252
Report compiled on: 4/5/10
58
1 of 2
COMMISSION RESOLUTION NO. 4252
A RESOLUTION OF THE CITY COMMISSION OF THE CITY OF BOZEMAN,
MONTANA, APPROVING ALTERATION/MODIFICATION OF CONTRACT
WITH WILLIAMS BROTHER CONSTRUCTION, LLC., BILLINGS,
MONTANA.
WHEREAS, the City Commission did, on the 10th day of November 2008, authorize award of the
bid for the Bozeman Water Reclamation Facility Phase I Improvements project, to Williams Brother
Construction, LLC., Billings, Montana; and
WHEREAS, Section 7-5-4308, Montana Code Annotated, provides that any such alterations or
modifications of the specifications and/or plans of the contract be made by resolution; and
WHEREAS, it has become necessary in the prosecution of the work to make alterations or
modifications to the specifications and/or plans of the contract.
NOW, THEREFORE, BE IT RESOLVED by the City Commission of the City of Bozeman,
Montana, that the proposed modifications and/or alterations to the contract between the City of Bozeman, a
municipal corporation, and Williams Brother Construction, LLC., as contained in Change Order No. 5,
attached hereto, be and the same are hereby approved; and the City Manager is hereby authorized and directed
to execute the contract change order for and on behalf of the City; and the City Clerk is authorized and
directed to attest such signature.
59
Resolution No. 4252, Change Order 5 for WRF
2 of 2
PASSED AND APPROVED by the City Commission of the City of Bozeman, Montana, at a
regular session thereof held on the 12th day of April, 2010.
__________________________________________
JEFFREY K. KRAUSS
Mayor
ATTEST:
________________________________________
STACY ULMEN, CMC
City Clerk
APPROVED AS TO FORM:
_____________________________________________
GREG SULLIVAN
City Attorney