HomeMy WebLinkAboutChange Order 03, City Shops/HRDC Bus Barn, BN Builders h„
dowting I sandhotm I architects
JOINT OWNER CHANGE ORDER C.O. #03
Project: City Shops/ HRDC Bus Barn Date: January 8, 2010 Owner
1821 N. Rouse Ave Architect
Bozeman, MT 59715 Architect's Project No: 08 -265 Contractor
Field
To Contractor: BN Builders, Inc Contract Date: November 4, 2009 Other
2066 Stadium Dr., Ste 102
Bozeman, MT 59715 Contract For: General Construction
The Contract is changed as follows:
Increase Contract Sum.
Reason for change:
Removal of City's dirt stockpile to construct stormwater detention pond (CP #09: $1,306.80)
Removal of fencing and placement of temporary fencing to accommodate storm drain construction. This
portion of the fence was mis- located on site plan. (CP #10: $1,334.03)
The gas line running through the property was not as deep as anticipated, and the storm drain had to be
modified at the intersection and a manhole added. (CP #11: $2,083.77)
Attachment(s):
CP# 09
CP #10
CP #11
Total Contract Sum Adjustment:
The original Contract Sum was 1,907,600.00
The net change by previously authorized Change Orders 14,585.64
The Contract Sum prior to this Change Order was 1,922,185.64
The Contract Sum will be increased by this Change Order by the amount of 4,724.60
The new Contract Sum including this Change Order will be 1,926,910.24
City of Bozeman Contract Sum Adjustment:
The original Contract Sum was 1,049,231.41
The net change by previously authorized Change Orders 3,294.32
The Contract Sum prior to this Change Order was 1,052,525.73
The Contract Sum will be increased by this Change Order by the amount of 2,362.30
(50% of Total Change Order)
The new Contract Sum including this Change Order will be 1,054,888.03
HRDC Contract Sum Adjustment:
The original Contract Sum was 858,368.59
The net change by previously authorized Change Orders 11,291.32
The Contract Sum prior to this Change Order was 869,659.91
The Contract Sum will be increased by this Change Order by the amount of 2,362.30
(50% of Total Change Order)
The new Contract Sum including this Change Order will be 872,022.21
Contract Time Adjustment:
The Contract Time will be increased by zero (0) days.
The date of Substantial Completion as of the date of this Change Order therefore is: July 28, 2010
JOINT OWNER CHANGE ORDER C.O. #03
Not valid until signed by Architect, Contractor, and Owners.
Signatures:
Architect: Dowling Sandholm Architects By:_�(,,1,n7 Date: t heVia
15 West 14 Street Suite 103 Mike Wiseman
Helena, Mt 59601
Place Architecture By: Date: l�¢l
118 E. Main St Sa Kazemine'ad
Bozeman, MT, 59715
Contractor: BN Builders, Inc By: I/ Date: I c(//6
2066 Stadium Dr., Ste 102 Scott Jay r3,rarij 4M
Bozeman, MT 59715
Owner: City of Bozeman By /`4 Date: I/ i'I/Ip
P.O. Box 1230 Chris Kukulski
Bozeman, MT 59771
Human Resource Date: Oil /J
Development Council Lee Hazel
32 South Tracy
Bozeman, MT 59715
Page 2 of 2
File 21f
CO #03 Joint.doc
B N B
BNBuilders, Inc.
Thursday, December 17; 2009
Mike Wiseman
Dowling Sandholm Architects
55 West 14th Street
Helena, MT 59601
RE: Change Proposal CP# 9
Bozeman City Bus Barn 509012
Dear Mike Wiseman,
This letter is to request authorization to proceed with the following extra work:
CP Number: 9
Description: Removed City stockpiled material at Bus Barn Det. Pond
Proposed Amt: 1,306.80
Days Requested: 0 days
Scope of Work (see attached for detailed cost summary):
Provide labor, equipment, materials to remove .a berm and extra misc. material that had been stockpiled
over the detention pond location.
0 Please sign below and return a copy of this letter to indicate your acceptance of this extra work and approve the
price for this work. Additional costs may apply if authorization is received after
BNBuilders has proceeded with this work per previous ROM approval (attached). This change proposal
represents the final price for this work.
BNBuilders has proceeded with this work based on owner approval via email (see attached) or verbal direction.
This change proposal represents the final price for this work.
Submitted by: Accepted by: Date:
1 /8/10
Scott Jay Mike Wiseman
BNBuilders, Inc Dowling Sandholm Architects
CHANGE PROPOSAL DETAIL BACKUP
Project 509012 CP 9
B N B Bozeman City Bus Barn
1812 N. Rouse Avenue
Bozeman, MT 59715
BN Builders, Inc. Phone: 406 582 -7412
Fax: 406 582 -7436
Contractor Description Amount
Sime Material Removal $1,188.00
BNBuilders, Inc. Overhead Profit $0.00
BNBuilders, Inc. OH Profite Subcontractors $118.80
Total: $1,306.80
c .i. I
5inti6 Pg.tpo*L 501e,,,,,,of4
co
IQ rs)
0 C
0 0
0 tra
0
.07 LO
vi ex)
0
0
0
0
fa
ft) i
5 .0.
O CO
Co
Co I•r1=
in g
5 0
m
E. K m 0
.0
0
V1
a) a) 'CI
,-.1- -,-4- 01,
i5 fp
rD rD
CU V)
C1.1 CIJ 0 rr
co
rn
-1-4 MI
O fa
-1
0 0
0 0
r) n
f.
X/
r.
CO C C LSI (.11 "X
Z Lf) ..1 0 0
O I.A 0 00 l'''
0
0 r- -i -I
0 0
'0 "V rn rn
r- r.4-4 r.n x x 4
4
o 0 4.1 o
III ID
IL V
frt ri
O 0
I-A I-k N.I NI
I.0
Ln 0
0
00 0 CO 0 QD 00
co Fo 0 1,,r1 tri p9
b b b 00
O 8 b
o 00 00
B N B
BNBuilders, Inc.
Thursday, December 17, 2009
Mike Wiseman
Dowling Sandholm Architects
55 West 14th Street
Helena, MT 59601
RE: Change Proposal CP# 10
Bozeman City Bus Barn 509012
Dear Mike Wiseman,
This letter is to request authorization to proceed with the following extra work:
CP Number: 10
Description: RFI #6 Remove Approx. 200If of Fencing /Install Temp Fence
Proposed Amt: 1,334.03
Days Requested: 0 days
Scope of Work (see attached for detailed cost summary):
Provide labor, equipment materials to remove approx. 200If of fencing and install temporary fencing so new
sewer line installation could continue as detailed in RFI 6.
0 Please sign below and return a copy of this letter to indicate your acceptance of this extra work and approve the
price for this work. Additional costs may apply if authorization is received after
BNBuilders has proceeded with this work per previous ROM approval (attached). This change proposal
represents the final price for this work.
0 BNBuilders has proceeded with this work based on owner approval via email (see attached) or verbal direction.
This change proposal represents the final price for this work.
Sub red f ed by: Accepted by: Date:
a r i� —O 1 /8/1 0
Cott Jay Wiseman
BNBuilders, Inc 11 Dowling Sandholm Architects
CHANGE PROPOSAL DETAIL BACKUP
Project 509012 CP 10
B N B Bozeman City Bus Barn
1812 N. Rouse Avenue
Bozeman, MT 59715
BNBuilders, Inc. Phone: 406 582 -7412
Fax: 406 -582 -7436
Contractor Description Amount
Fence Removal /Reinstall $1,212.75
BNBuilders, Inc. Overhead Profit $0.00
BNBuilders, Inc. OH Profite Subcontractors $121.28
Total: $1,334.03
1
a§ 8 2 f
69 64 o o 69 CO
69. t9 t
6t
sr 8
CO 0 0 0
oi 0 e j k J
a c
.2 c.:),,
J
2
a
i
I--
g
ti
E
E ƒ 3 03
o
t 7 7 a (5 a
o a
o
9 a 7
r ƒ e Z t
k k 0
U... u.9 f .0
-I -J -I
0
CI
0
0
7;...e.. 2
I 62
B.N g Request for Information
BNBuiiders, Inc.
RFI No: 6
Bozeman City Bus Barn BNB Project 509012
1812 N. Rouse Avenue
Bozeman, MT 59715
Date: November 24, 2009
Submitted To: Mike Wiseman
Submitted Sy: Jenae Benner
Dowling Sandholm Architects BNBuilders, Inc
55 West 14th Street 293 Rodeo Drive
Helena, MT 59601 Florence, MT 59833
Tel: 406-556-0113 Tel: 406-375-6920 Fax: 406-375-6921
Subject: East Property Line Fence
Discipline: Architectural
Document Re C1.0 Spec Section:
Subcontractor.' Slme Construction Subcontractor RFI No:
Question Date Required: 12/1/2009
On drawing C1.0, the east property line fence is shown running on the property line on the east.side of the Police Impound Lot, but
this is not the case. The fence actually jogs and is about two feet off the property line when it•reaches the North East corner of the
Impound Lot. The issue is that the new sewer line runs about 18" of the existing fence and is about 3.5 feet deep which will
undermine the fence and cause it to collapse. Approximately 200 feet of fence to the east of the.impound lot will need to come down
during construction of the sewer line. Does the Owner want a fencing contractor to directly do this work to reinstall the fence or have
BNB do It at our cost plus rates? Also, should the fence be reinstalled at its original location or on the propert line as the existing
plans show?
*Approximately -31- 25' of fence section has been removed so She can continue work without delays.
Answer
The Owner has Indicated that BN can remove the fence during construction. The existing fence material may be used as a
temporary fence at BN's discretion for site security and to maintain a horse fence for the adjoining property. The City will install
a permanent fence at a future date, or make arrangements for the work to be done.
Answered by: Mike Wiseman, Dowling Sandholm Architects Date Answered: 12/3/09
Copes To: Company Contact Fax Notes
Page 1 of 1
BNBuilders, Inc.
Thursday, December 17, 2009
Mike Wiseman
Dowling Sandholm Architects
55 West 14th Street
Helena, MT 59601
RE: Change Proposal CP# 11
Bozeman City Bus Barn 509012
Dear Mike Wiseman,
This letter is to request authorization to proceed with the following extra work:
CP Number: 11
Description: ASI 3 Revised Storm Sewer Manhole
Proposed Amt: 2,083.77
Days Requested: 0 days
Scope of Work (see attached for detailed cost summary):
Provide labor, equipment material to complete additional work associated with ASI 3.
o Please sign below and return a copy of this letter to Indicate your acceptance of thls extra work and approve the
price for this work. Additional costs may apply if authorization is received after
BNBuilders has proceeded with this work per previous ROM approval (attached). This change proposal
represents the final price for this work.
BNBuilders has proceeded with this work based on owner approval via email (see attached) or verbal direction.
This change proposal represents the final price for this work.
Sub fitted by: Accepted by: Date:
c r (2, 1/8/10
Scott Jay Mike Wiseman
BNBuilders, Inc Dowling Sandholm Architects
I
CHANGE PROPOSAL DETAIL BACKUP
Project 509012 CP 11
B N B Bozeman City Bus Barn
1812 N. Rouse Avenue
Bozeman, MT 59715
BNBuilders, Inc. Phone: 406 582 -7412
Fax: 406- 582 -7436
Contractor Description Amount
Sime- Revised Sewer /MH $1,89434
BNBuilders, Inc. Overhead Profit $0.00
BNBuilders, Inc. OH Profite Subcontractors $189.43
Total: $2,083.77
Oo p p
ifi" N
O O CIO Q O 2 O O' O O. 0 0 O O Q O ry 0 to P O N N! M
T to C O C O r-: 21Y 2A to to O: O V d' C' m O. O o VD 4 Ill c i N N. i 4
t us 1A IA 2D C' 20 C' I. n N 20 211
e-1 N. ri'N N. C
-l' -4
F VI. ii,. VI. •I. V, V, VI. VS tn. 1 tn. VI. VI. VI.. VI. N VI. V? VI. VI. VI. y V1 V}.
O O 8 O 0 0 0 0 O. O O O 8 O O O O N O to 1: Cl �1
C1 2A O c1 Q C7 2A 2A d ci 6 C 6 O 21Y C O tD CO 4 of C)
0 2D to IA N1 a 4 a 211 LA tom N o V C' Q1 O O l0 1/1 VI -.O.)-•
N. N N
C
D t/I. VI. 14 VI. .VI. VI. t/I. VI. VS 1/T in VI. Vl tn. VI. 'VI. VI. K. i4 V? tit. VI.
e-1 ri el ri VI e-1 211 ri h V1 i1/ N CA 1•'1 t-•I e-I el .-I I-4 ri r.i
C.
N ey. ■-1 N p
F
l co a tea
e'rWz
ce
u a cc
Z 1 w u.,
o Z z to U
U M M
cc cc oZ 3 1- o 1
a W C ZZ; m h
c
CL
N
el ri el 1-1 N N N V C t
C: C C C
0000
L. a 7 d
a 11.1 y
a 0 u St 2 2 2 Z to
"r) H 2g22 v w it to
J J to ui to vs
en
cc
Z IX
10 VI CA VI IA
Q. a0 L 2 O I L 14 Y CC
3;
ea L c c
k.7 Lue
N v v
Z ti0 U. a ,:u icu c r0: R, CC m a 4 4 Y y 5
Q c DI E E U m
g, v a 2 2 a a w c p 0 a' a a. a
to E s i s o a a c c 3 a o: d
Y t7: V. O. O O O' Q u .0 y' h Q +1. h VI 2A N CC
CV u. r R to u. u a. D q d. N
TO.. to w 114 L L c C
0 o m a� C y
it N L C
L G
g a a a a a o o H i l
76 X J J: J A 2 C 2 C 2 z m
u ‘u a a W W -4 J J J. 0
U.' 0 W Sc G 2
N y yy
00 C c 210
00 00" tfii
2 L O o H G
Ly u 6 0
O
0 5.
W
O o o o O j r.
0 1... n ,-1 0 co
0 0 0' 1 O p ..-.1
p ci
N O p r1 co
V ry
O O OI C cO
m
N co F W r ma y co N GO est
0 M N ti
H
M N t
O
ri Q
CO
CC
dowting I sandhoim 1 architects
ARCHITECT'S SUPPLEMENTAL INSTRUCTION ASI #03
Date: November 30, 2009 Job Number: #08 -265
Project: City of Bozeman/ HRDC Issued To: Scott Jay
City Shops/ Bus Barn BN Builders
1812 N. Rouse Ave. 2066 Stadium Dr., Ste 102
Bozeman, MT 59715 Bozeman, MT 59715
Regarding:
Revised storm sewer and manhole
Information:
Please see the attached information from Cordell. This info has already been supplied to Sime. Pleaes notify
of any changes to cost.
Attachments:
Manhole shop drawing
04-1 GRADING AND DRAINAGE DETAILS.
Issued By:
i n
Dowling Sandholm Architects By: Date: 11/30/09
Michael Wiseman
End of Architect's Supplemental Instructions
m
zg o
a 1
o xz y
Mal
DRAWG IN PROJECT
Zoo o r
--.1p m Cn
Cn En o
Z i
n 0
D
m m n
N m cA Np Sill
T) N i 7
Z 0 0 0 go m
F
z N
tt
I c b Z
ill y lJ 0
CONTRACTOR ENGINEER M N
d
CO CI) al Cn
0 0 c '-3 rn r t- z
n 2` ro �r t a) 0 4 0 2 p a o d 0 E o
cp Z p y Y N
n, n, t z cn trl r v,
n
cn
o 0 0 x n Z
03 r NA O y
Er
cn
t-
z
nB 4 y
i oo c w p C
b
0
CI)
6
e >•r� d "gr T•1-3 1w'LIe�.•••1311 -3
eW swum ONeleeM 68 -61 -11 B
I O 6J l..d
.4 6P•w�e SGLBS IW'NtlW3Z09
a.,
10986 L eOMOFI 9 IA •xowozeL OD-M-9 m9 BD -00-11i, 1 -e qQ
r0 I9luegvq [9
0f
•wa lue4Wx5 SSSL doa rumens a, ee --9 3AV 3S110a 1 SLSG i
IS
e03 198 Duna 6N11 -9 C o
sioAemns v eca ,3 MB 63-1x -9 z A11113V4 Nays sna paaH Sd U ONS ALTO 0
Z: siasul6u3 lsuolsss;oid AO 1•1331•133003 a N MSn9 age 60 -61-•
"maw'
a9 319 a! 571V130 ROVNIvtia ONv ONIOvue 3 1 N
�S31dI00SSV 'd pNIH33NION3 Alms 3r� g g a
ij 1i I tJ3J
w Y:? Bh5 I e 1 Of t i 1411 1 1 j 1 iiv! r s NI), ,4� r i ii i k
1 �11� 1 1Y e% e$ 50 1011 ae w a6
r 6 e i l 1 1 1 1 l i a z N db e
i E I i ill I kit, t
r
i a,a ig; n �e 43
E6 N Z�� •Y: B b NDr H08 i�� yys �u
8 111 it! 1@ 1 :r ;C11`'$ wge I. m
1 l i i 1 1i gig 1 1 r n WP V 1 9 8 n I! l I s 6 b o I 1 I 1 I I P l' ar th I 14 L 111 H 1 s u l. I 1 I 1 I I I I i I I I I I I I I 8 1 i 1 1 Iii 1 1
r, z 1. II r s L J t
W g k j!!J I 1 I
4 4 �1k i ,c 5 4110 1_ I 1 10�a1 w I I I I I I
a 11._1 W p II
_a E gg s 1 I
ir— 11 -4m IA MINF a. z .�i W g,____
•I e
ewe ,u�� v� R Y r s. i +io I l i H 8
I 111
1 L
j litt
1 kl I II
g, -1.., 1 r 1
A: ivb.-- .,..4 IhacipmmItro!,i,
yp r. i R
L 7- llll I I 1 1 1 I I g. t 1 I 1 1 1 1
B wb Yo-- WOC.--- .lva'GGlfd--- VJVw-e WAW \Y--mu.uC9RWtUBe\91 J
Cr
0
COMMISSION RESOLUTION NO. 4239
A RESOLUTION OF THE CITY COMMISSION OF THE CITY OF BOZEMAN,
MONTANA, APPROVING ALTERATION/MODIFICATION OF CONTRACT
WITH BN BUILDERS, BOZEMAN, MONTANA.
WHEREAS, the City Commission did, on the 5th day of October 2009, authorize award of the bid
for the Construction of the Vehicle Maintenance Building and HRDC Bus Barn to BN Builders, Bozeman,
Montana; and
WHEREAS, Section 7 -5 -4308, Montana Code Annotated, provides that any such alterations or
modifications of the specifications and /or plans of the contract be made by resolution; and
WHEREAS, it has become necessary in the prosecution of the work to make alterations or
modifications to the specifications and /or plans of the contract.
NOW, THEREFORE, BE IT RESOLVED by the City Commission of the City of Bozeman,
Montana, that the proposed modifications and /or alterations to the contract between the City of Bozeman, a
municipal corporation, and BN Builders, Bozeman, Montana, as contained in Change Order #3, attached
hereto, be and the same are hereby approved; and the City Manager is hereby authorized and directed to
execute the contract change order for and on behalf of the City; and the City Clerk is authorized and directed
to attest such signature.
1 of 2
Resolution No. 4239, Change Order 3
PASSED AND ADOPTED by the City Commission of the City of Bozeman, Montana, at a regular
session thereof held on the 1st day of February, 2010.
lik KRAUSS
"it r
ATTFT`
�F B2
e s ep t ic
T IN Co. 0
APPROVED AS TO FORM:
TR
G SULLIVA
City Attorney