COMMISSION RESOLUTION NO. 4232
A RESOLUTION OF THE CITY COMMISSION OF THE CITY OF BOZEMAN,
MONTANA, APPROVING ALTERATION /MODIFICATION OF CONTRACT
WITH BN BUILDERS, BOZEMAN, MONTANA.
WHEREAS, the City Commission did, on the 27th day of May, 2009, authorize award of the bid for
the Construction of the Landfill Addition to BN Builders, Bozeman, Montana; and
WHEREAS, Section 7 -5 -4308, Montana Code Annotated, provides that any such alterations or
modifications of the specifications and /or plans of the contract be made by resolution; and
WHEREAS, it has become necessary in the prosecution of the work to make alterations or
modifications to the specifications and /or plans of the contract.
NOW, THEREFORE, BE IT RESOLVED by the City Commission of the City of Bozeman,
Montana, that the proposed modifications and /or alterations to the contract between the City of Bozeman, a
municipal corporation, and BN Builders, Bozeman, Montana, as contained in Change Order #5, attached
hereto, be and the same are hereby approved; and the City Manager is hereby authorized and directed to
execute the contract change order for and on behalf of the City; and the City Clerk is authorized and directed
to attest such signature.
Page 1 of 2
PASSED AND ADOPTED by the City Commission of the City of Bozeman, Montana, at a regular
session thereof held on the 19"' day of January, 2010.
ra K. KRAUSS
or
(ter
.1
AI1VI KISAf •ate
r
Acting .Cfto�lt ~l0`
APPROVED AS TO RM:
E LIVAN
Ci Attorney
Page 2 of 2
dowling I sandholm I architects
CHANGE ORDER C.O. SqZ,�
Project: Bozeman Landfill Addition Date: January 4, 2010 Owner
2143 Story Mill Rd Architect
Bozeman, MT 59715 Architect's Project No: 08 -263 Contractor
Field
To Contractor: BN Builders, Inc Contract Date: June 1, 2009 Other
2066 Stadium Dr., Ste 102
Bozeman, MT 59715 Contract For: General Construction
The Contract is changed as follows:
Increase Contract Sum.
Reason for change:
Owner and Architect discussed need for heat tape at eave/ gutter. An electrical outlet had initially been installed
for heat tape, and it was agreed to wait until winter conditions to asses the extent of heat tape that would be
necessary. After viewing ice damming, heat tape at the gutter was considered necessary, but not on the eave
itself.
French drains at the downspouts were discussed by Owner and Architect as insurance that the heated runoff
coming from the downspout would not immediately freeze in the shallow gravel and create an ice patch that
extended to the sidewalk. CP #5014 is the contractor's bid for work.
Attachment(s):
CP# 5014
Contract Sum Adjustment:
The original Contract Sum was 271,648.00
The net change by previously authorized Change Orders 33,532.09
The Contract Sum prior to this Change Order was 305,180.09
The Contract Sum will be increased by this Change Order by the amount of 2,332.00
The new Contract Sum including this Change Order will be 307,512.09
Contract Time Adjustment:
The Contract Time will be increased by zero 0 days.
The date of Substantial Completion as of the date of this Change Order therefore is: September 28, 2009
Not valid until signed by Architect, Contractor, and Owner.
Signatures:
Architect: Dowling Sandholm Architects By: l,t"`- Date:
2042 Stadium Dr, #2 Mike Wiseman
Bozeman. MT, 59715
Contractor: BN Builders, Inc By: Date:
2066 Stadium Dr., Ste 102 Scott Jay
Bozeman, MT 59715
Owner: City of Bozeman By Date: O 1-- 19- (O
P.O. Box 1230 ris Kukulski
Bozeman, MT 59771
.B N B
BNBuilders, Inc.
Thursday, December 17, 2009
Mike Wiseman
Dowling Sandholm Architects
55 West 14th Street
Helena, MT 59601
RE: Change (Proposal CP# 5014
City of Bozeman Landfill Add. 509004
Dear Mike Wiseman,
This letter is to request authorization to proceed with the following extra work:
CP Number: 5014
Description: Heat Tape French Drain Installation
Proposed Amt: 2,332.00
Days Requested: 0 days 11�
Scope of Work (see attached for detailed cost summary):
Heat Tape: Install 120' of 120V 6 w /ft heat tape in gutter and downspouts only. Includes heat cable 20A
120V circuit with ground fault protections and installation.
French Drains: Dig (2) 4'dia x 4' deep pits and fill w/ 1" washed rock topping off w/ 3/4" rock to match
existing.
F1 Please sign below and return a copy of this letter to indicate your acceptance of this extra work and approve the
price for this work. Additional costs may apply if authorization is received after
BNBuilders has proceeded with this work per previous ROM approval (attached). This change proposal
represents the final price for this work.
n BNBuilders has proceeded with this work based on owner approval via email (see attached) or verbal direction.
This change proposal represents the final price for this work.
Submitted by: Accepted by: Date:
12/17/09
Scott Jay Mike Wiseman
BNBuilders, Inc Dowling Sandho /m Architects
'f
CHANGE PROPOSAL DETAIL BACKUP
Project 509004 CP 5014
B N B City of Baseman Landf111 Add.
2143 Story Mill Road
Bozeman, MT 59715
BNBuilders, Inc. Phone: 206- 382 -3443
Fax: 206 -382 -3440
Contractor Description Amount
Heat Tape Installation $1,500.00
French Drain Installation $700.00
BNBuilders Inc. Overhead Profit $0.00
BNBuilders, Inc. OH Profit on Subcontractors 1 $132.00
Total: $2,332.00
I
Gallatin Electric, Inc. Phone: 406 388 -2126
101 Bartz Lane Fax: 406.388 -2186
Belgrade MT 59714 •ry 3SS� gallatinelectricservice.com
Proposal
TO: BN Builders Proposal 1554
293 Rodeo Drive Suite 2 Date: 11/12/2009
Florence MT 59833 Phone: 406 375 -6920
Fax: 406- 375 -6921
Project: Specifications: Electrical
City Landfill Heat Tape
Scope Of Work:
PLANS AND SPECIFICATIONS,
Option1: Install 120' of 120V 6 w /ft heat tape in gutter and t downspouts only.
Includes heat cable 20A 120V circuit with ground fault protections, and installation.
*125' max length per circuit O Fahrenheit start -up.
Option 2: Install 400' of 240V 6 w /ft heat tape in gutters, downspouts, $6,000.00
and 2' on roof. Includes heat cable, 2 -20A 240V circuits with ground fault
protection, and installation.
250' max length per circuit 0 Fahrenheit start up.
Option #1 recommended by MFG for metal roofs.
Does not include connection of existing tape if needed.
Proposal See Above
CONDITIONS
It Is understood and agreed that we shall not be liable for any loss, damage, or delays occasioned by tire, strikes, or material stolen after delivery
upon premises, lockouts, acts of (god, public enemy, accidents, boycotts, material shortage, disturbed labor conditions, delayed delivery of
material from seller's suppliers, force majeure, inclement weather, floods, trelght embargoes, causes incidental to national emergencies, war,
or other causes beyond the reasonable control of the seller, whether of like or different character, or other causes beyond his control. Prices
quoted in this contract are based upon present prices and upon the condition of the proposal being accepted within thirty days. Also general
conditions which are standard for specialty contractors in the constructlun Industry,
In the event of significant delay or price Increase of material occurring during the performance of the contract through no tault of the contractor,
the contract sum, time of performance, or contract requirements shall be equitably adjusted by change order in accordance with the procedures
of the contract documents. A change in price of an item of material shall be considered significant when the price of an item is between
the date of this contract and the date of installation.
TERMS
Due upon Completion
THIS PROPOSAL IS SUBMITTED IN DUPLICATE ORELECTRONICALLY, RETURN TO US OP ONE COPY WITH
SIGNATURE VIAMA L OR ELECTRONICALLY WILL CONSTITUTE A CONTRACT.
ACCEPTED
BY