HomeMy WebLinkAboutChange Orders 3, 5, 6, 8, 10, 14 and 19, Intermodal Facility i� Commission Memorandum REPORT TO: Honorable Mayor and City Commission FROM: James Goehrung, Director of Facility Services Chuck Winn, Assistant City Manager SUBJECT: Change Orders numbers 3, 5, 6, 8, 10, 14, and 19 for the Bozeman Interinodal Facility MEETING DATE: November 16, 2009 AGENDA ITEM TYPE: Consent RECOMMENDATION: Authorize the City Manager to sign Change Orders for the Downtown Bozeman Intermodal Facility in the amount of $80,768.69. BACKGROUND: After the opening of the garage there were multiple change orders submitted by the construction manager that were under discussion with administrative staff. Staff has since had a number of meetings with the contractor and design professionals to determine which components of the change orders might be attributed to the contractor, the architect and which were the responsibility of the City. The total for the changes amounted to $91,841.25. The construction manager has agreed to cover a portion of the cost of these changes so the city's billing is for $80,768.69 Change Order #003 A portion of this change order was addressed back in April. The balance on this change addresses site related work. Cost of this change is $44,151.25. Change Order #005 Is for additional structural steel associated with brick ledgers, and stair towers. The original request for this change was $15,825.62. The construction manager has agreed to cover $5,275.28 of the change, leaving a balance of $10,550.72. Change Order #006 Is for the cost of the truncated cones and color change material required by the Americans With Disabilities act on all transitional points in the garage. The areas include all ramps leading from the entrances and elevators. The ramps were not shown on the original plan and were not called out during plan review. Staff caught the omission prior to the ramps being poured so the cost covers the panels and installation. Cost for the change is $9,072.00. The construction manger has agreed to cover $3,023.97, leaving a balance of $6,048.03. 23 Change Order #008 is for a modification of the rebar associated with the shear walls. These are the partial wall areas that surround the various deck levels. The added rebar and tie in costs were $8,320.00. The construction manager has agreed to cover $2,773.31, leaving a balance of $5,546.69. Change Order #010 This change was for the installation of all the directional signage at the entrances to the garage and within the garage. The signage was purchased by the city and the contractor installed all the signage. The decision was made to have the contract install the signage because all of the post tension cables that run throughout the garage. Cost of the installation was $8,293.00. Change Order #014 The original lights that were specified for the canopy entrances to the building on Black and Mendenhall were too tall 1'or the application. If installed the original lights would have been within inch of the canopy roof. The heat from the lamps would have compromised the rubber membrane material on the roof. The cost covers four light fixtures and includes a credit for the four fixtures that were not installed. Cost for the fixtures is $1,928.00. Change Order #019 The items for this change include some life safety issues that were called out by the Building Department during the final walk through and inspection. The change includes adding additional exit lights and stroke seals on some storage room doors inside the garage. This change amounted to $4,251.00. FISCAL EFFECTS: The Parking Garage Construction Fund paid $37,069.66 of these change order amounts. The nature of the some of the site work in Change Order #003 was unanticipated street repairs surrounding the Garage that were paid from the Gas Tax Fund, in the amount of $37,651. The ADA repairs detailed in Change Order #006, in the amount of $6,048.03 were paid from the ADA Special Revenue Fund. ALTERNATIVES: As suggested by the City Commission. Attachments: Change Order Requests Change Order- Resolution Report compiled on November 10, 2009 24 MARTEL CONSTRUCTION, INC. �y MAIN OFFICE BIGFORK OFFICE 1203 South Church Avenue 305 Highway 83 RECIPIENT OF 1990 NATIONAL BUILD AMERICA AWARD Bozeman, MT 59715 -5801 Bigtork, MT 59911 1999 SBA ENTREPRENEURIAL SUCCESS AWARD (406) 586 -8585 Fax (406) 586 -8646 (406) 837 -1063 Fax (406) 837 -1068 11 999 MONT s MCA CONCRETE MEOENCE ARD January 21, 2009 Prugh Lenon Architects, P.C. 27 Fast Main Street Bozeman, Montana 59715 Attention: Dick Prugh Re: Bozeman Intermodal Facility Bozeman, Montana 59715 Subject: COR 003 Reference: Sitework Scope Issues Dear Dick, As requested, we propose to provide all labor, materials, and equipment required to perform the above mentioned work. Our breakdown of the work is attached. Our quotation is based on our interpretations of of the instructions and scope of work identified in the request, specifications and /or drawings. If we have misinterpreted the request in any way (omissions, etc.), please advise us prior to processing this quotation into a formal Change Order. Otherwise, our interpretation shall stand as correct. We have been directed to proceed with the work per the instructions in the Change Order Request. We are requesting an additive Change Order for the amount of Markel Construction, Inc. reserves the right to submit a request for any additional time and or cost for disruption, impacts, acceleration, delay, or suspension which cannot be determined at this time. If you have any questions, please call me at (406) 922 -5504. Sincerely, MAR NSTRU r Li -k" ark Brown Enclosure(s) cc. File James Goehrung COB James Nickleson Morrison Maierle COMMERCIAL RESIDENTIAL INSTITUTIONAL INDUSTRIAL 944ZOa 1 Prugh Lenon Architects, P.C. January 21, 2009 Page 2 RE: Bozeman Intermodal Facility Bozeman, Montana 59715 SUBJECT: COR 003 REFERENCE: Sitework Scope Issues CHANGE REQUEST BREAKDOWN: Labor Material Subcontract Other 103,395.33 Subtotal 103,395.33 Construction Managers Fee 6.0% 6,203.72 Subtotal 109, 599.05 Insurance Bonds 1.5% 1,643.99 Subtotal 111,243.04 Gross Receipts Tax 1.0% 1,112.43 Calculated Proposal Request 112,355.47 TOTAL CHANGE ORDER REQUESTED: 1 1 $112,355 REMARKS AND QUALIFICATIONS: Martel Construction, Inc. Bozeman Intermodal Facility Sitework Issues Change Order Request #003 January 20, 2009 Item Description Reference Amount #1 Site Grading Bid Scope Issue Walker Excavating $31,350.00 #2 Deduct Sand Oil Separator Access ($925.00) #3 Rimrock Engineering Engineering for Recycled Material $450.00 #4 Revised Asphalt Grading Walker Excavating Morrison Maierle Grade Revisions Requested by COB I M -M for Slope Grading on Mendenhall $6,301.58 #5 Alley Grading Bid Scope Issue Add For Sawcut, Demolition, Haul -Off Grading Revised Section $39,835.00 #6 Asphalt Paving Scope Issues Gallatin Asphalt Deduct Alley Asphalt Paving 6200 SF +I ($11,914.00) Add For Increased Asphalt Paving Scope Attached Gallatin Asphalt Directive $30,861.75 #7 Grade Alley for Winter Use 200 CY +I- 1 Minus Road Mix. Material f Delivered) $2,900.00 200 CY +I- I"" Minus Road Mix -Labor $1,200.00 #8 Lawson's Greenhouse Bid for Package 2D June 6, 2008 Includes Revisions Per COB $17,336.00 Bid Package 2D Allowance Trees, Tree Guards Irrigation System Contract Allowance ($15,000.00) #9 Topsoil for Tree Grate Planting Areas Per City Arborist Furnish 25 CY +I- Screened Topsoil $600.00 Place 25 CY +I- Screened Topsoil $400.00 SubTotal $103,395.33 Construction Managers Fee 6.0% $6,20172 SubTotal $109,599.05 Insurance Bonds 1.5% $1,643.99 SubTotal $111,243.04 Gross Receipts Tax 1.0% $1,112.43 Total $112,355.47 Page I of 1 NOY- 10- 2008(MON) 16:29 P. 002 1002 Walker Excavation Inc. 27o Floss Fiat Rd. Unit B Belgrade, MT 597 Order#: 5 Order Date: 11/10/2008 Change Order Invoice To! Martel Construction Project: 718 1203 S. Church Bozeman Intermodal Facility Bozeman MT 69715 The contractor agrees to perform and the owner agrees to plans Attached pay for the following changes to this contract, Ordered By: Customer Order: Specltloations Attached Description of Work Amount DEMO OF OFF SITE ITEMS Mobllizatlon 960.00 Remove existing'curb haul off 4,060,00 Remove asphalt Tracy, pulverize asphalt Mend 15,485.00 ad Black and excavate new pave areas (28" section 5" minus pltrun and existing materials Streets, 10,237.50 In place 18" section Sidewalk removal and Disposal 607,50 Negative changes will lower tno overall contract price requiring no sdditlonal payment by owner. Requested Amount of Change 31,350.00 Owner: Date: Contractor: pate: NOV- 03- 2008(MON) II:52 P. 002/002 Walker Excavation Inc, .27 Floss Flat Rd, Unit B Belgrade, MT 59714 Invoice* 1357 Contract Invoice Date: 11/03/2008 Billed To: Martel Construction Frolect: Bozeman Intermodal Facility 1203 Church Bozeman MT $9715 Due bate: 12/03/ Terms 3ODY order# Description Quantity Price Amount Credit Deletion 1 Storm Drain MH with Pipe Sand Oil Access Lid Rise Credlt $1925.80 (Note $1000.00 Credlt will follow once Anderson Precast sells MH.) $925.00 Credlt at this time 1.0000 925.000000 925.00 Mai A service charge of 18.00 per annum will be charged on al! amounts Sales Tax: 0.00 overdue on regular statement dates. Invoice Tot81: 925.00 Thank you for your prompt paymentl Retention: 0.00 Amount Paid: 0.00 Amount Due 926.00 INVOICE RIMROCK ENGINEERING' INC. Phone 406.294.8400 5440 Holiday Avenue Billings, MT 59101 Fax 406.294.8405 Bill To bate Invoice Martel Construction, Inc. 11/4/2008 03 -10587 1203 South Church REI Project No. Bozeman, MT 59715 B- 08- 104 -01 Project Name P.O No. Terms Bozeman Intermodal Facility Net 30 Description Quantity Rate Amount'' Sample Test Pits and Provide Alternative Pavement 1 450.00 450.00 Section Analysis o� RECEIVED 140 €I Martel Construction inc Total $450 RiIMROCK ENGINEERING, INC. 5440 r;olid3yAvenue Billings. MT 59 10 1 rsix 406 294.6 405 October 31, 2008 RECEIVED Martel Construction, Inc. OCT 3 1 2006 1203 South Church Martel Construction, lec, Bozeman, MT 50715 Attention: Mr. Tony Martel Subject: Pavement Section for Bozeman Intermodal Facility Black Tracy Avenues, Mendenhall Street Bozeman, Montana Dear Mr, Martel: Rirnrock Engineering, Inc. was requested to observe four test pits located on Tracy Avenue, Black Avenue and Mendenhall Street which surround the Bozernan Intermodal Facility_ The purpose of the test pits was to measure the thickness of the asphalt and base course in the existing structural pavement section and observe the subgrade soils. Information provided by Walker Excavation, Inc. stated that the proposed structural pavement section shown an the project plans requires 4" of asphalt, a" of crrlshed base course and 18" of subbase gravels, Rinirock Engineering Was requested to review the test pits and existing section to determine it the in -place asphalt and base aggregates could be pulverized and used in `►ae pavement section. The test pits had 3.5 inches of asphalt that was underlain by 9 inches of aggregate that had bitumen oil spread on the aggregate at sometime in the past. The AASHTO Design Procedure for flexible pavements utilizes a structural number for each of the components in the pavement section. Rimrock Engineering has completed research on recycled asphalt and base aggregates and concluded that the structural number for recycled material compares to the number used for subbase aggregates. This number is less than the number assigned to virgin crushed base course. It is 0Ur opinion that the asphalt and base aggregate coated with bitumen can be ptiverized and used as subbase for this project. The subgrade soils on this project consisted of lean /fat clay nirnrock E iiuimeenrlg, Inc:. 1 Or iober 31. 2008 which was generally soft to medium stiff. We recommend that the pavement section is constructed by placing virgin 6 inch minus subbase on the clay subgrade and then placing the pulverized recycled material immediately below the 6 inches of crushed base course. If we can be of any further assistance, please don't hesitate to call. Sincerely, RIMROCK ENGINEERING, INC. Robert W. Kokes, P. E, Principal Rum.rock Engirfee ng, Inc_ 2 October 31, 2003 Wa .Excavatian Ine. Mo Floss .Flat Rd. U1li.t S .Belgrade, MT 59714 Time Materials Invoice Invoice 1200 Invoice Late: 12109/2008 To: Martel Construction Project: Bozeman Intermodal Facility 1203 S. Church Bozeman MT 59715 Terms: 30QY Record# Trans,# Date Description Cast Amount 718 Bozeman Intermodal Facility Mendenhall regradel 20.000 Demolition 65762 152259 11/13/2008 Knife River 644.75 65781 120108 12/01/2008 McOwen, Ron 552.50 Cost Code Total: 1,197.25 70.000 Roadway Excay. /Grading /Gravel 65082 EC1606 Volvo Exc 11/13/2008 6.50 115.00 747.50 65083 EC1608 Volvo Exc 11/14/2008 4.00 115.00 460.00 65084 John Deere 650J D 11/14/2008 2.00 95.00 190.00 65171 Case 95XT Skidste 11/13/2008 5.00 a@ 80.00 400.00 65172 Case 95XT Skidste 11/1412008 3.00 80.00 240.00 65173 Case 95XT Skidste 11/1412008 4.00 80.00 320.00 65221 Cat CS563 Vibr. Ro 1111312008 6.00 95.00 570.00 65223 International Water 11/13/2008 1.00 88.00 88.00 65224 Cat CS563 Vibr. Ro 11/13/2008 0.50 95.00 47.50 65305 Shane J L.aughery 11/13/2008 1.50 hrs 40.00 60.00 65422 Steven M Murphy 11113/2008 1.50 hrs 40.00 60.00 65424 Steven M Murphy 11/13/2008 1.50 hrs 40.00 60.00 65497 Steven D Devers 11/14/2008 4.00 hrs 40.00 160.00 65564 2001 Case 590M B 1111812008 1.00 85.00 85;00 65606 2001Case 590M B 11118 12008 2.00 85.00 170.00 65633 William B Cole IV 11/18/2008 4.50 hrs 55.00 247.50 65700 Steven M Murphy 11/18/2008 3.00 hrs 40,00 120.00 65710 Ryan Howard 11118/2008 2.50 hrs 40.00 100.00 65751 152909 11/18/2008 Knife River 694.99 A service charge of 18.00 per anum will be computed on all amounts overdue RECEI "V -ED on regular statement dates. DEC Thank You for your prompt payment! Maw Coostradan, I "c. Time Materials Invoice Invoice 1200 Continued... Date: 12 -22 -2008 Record# Trans# Date Description Cost Am ount Cost Code Total: 4,824.49 Phase Total: Mendenhall regradel 6,017.74 Job Cost Total: 6,017.74 Markup Q 4.72 283.84 Total Charges: 6,301.58 Invoice Total: 6,301.58 I J4& Page 2 of 2 Proposal From: Walker Excavation Inc. Project: 0900 <4 270 Floss Flat Road, Suite B Description: BIF- Alley Belgrade, MT 59714 Bid Date: 1 -20 -09 Phone: 406- 388 -5834 CP Fax: 406 388 -5837 ITEM D ESCRIPTION BID QTY U/M UNIT BID AMOU 010 Mobilization 1.000 LS 1,525.00 $1,525.00 020 Sawcut, Remove, Dispose existing concrete and 1,400.000 S.F 9.95 $13,930.00 asphalt in R.O.W. (incl. vac truck for utility locate) 070 Cut remainder of alley to SG, haul dispose (area 300.000 BCY 41.00 $12,300.00 outside of existing wall backfill) 072 Cut North side of alley to top of pitrun, place and 100.000 BCY 33.00 $3,300.00 compact exist. pitrun within South side 075 6" minus pitrun added to south side to make an 18" 135.000 CCY 56.00 $7,560.00 section 145 Sewer cleanout monument boxes 4.000 EA 305.00 $1,220.00 TOTAL BID: $39,835.00 Proposal notes: 1. Numbers good for spring 2009 construction season. 2. Martel Construction will provide finished edge of asphalt grade control along the parking garage. 3. We have included 14 hrs of vac truck for the high pressure gas line. We will request a construction meeting for the excavation next to the gas line due to the lack of cover over the main and services at subgrade elevation. Special construction methods and materials maybe required by N W Energy and will be added to this proposal. 4. All road mix cushion and paving by others. 5. Special vaults or covers for existing phone, cable or anyother utility will be by others. RECEIVED JAN 20 2009 Martel Construction, Inc. Walker Excavation Inc. Page 1 of 1 Mark Brown From: Jeff Baker Gallatin Asphalt, Inc. Ubaker @gallatinasphaltinc.com] Sent: Wednesday, November 05, 2008 12:25 PM To: Mark Brown Subject: Alley Way Deduct for Intermodel /lark, I've gone over the numbers for the alleyway for the parking garage. The alleyway was bid at originally bid with a 3 inch section f AC and a 4 inch section of road mix. The price was based on 6,440 square feet at a price of $1.85 per square foot including the base gravel for a total of $11,914.00. The pricing structure we had for the rest of the work was substantially higher due to a hickey sections. It also took into account a substantial amount of hand patching along the new curb and gutter on Mendenhall. Please give me a call if you have any further questions. I espectfully, eff U I lat" 3allatin Asphalt Inc. 106- 388 -7044 baker gallatinasp =rom: Mark Brown [mailto:mbrown @martelconst.com] sent: Monday, November 03, 2008 9:46 AM ro: Jeff Baker; Josh Walter; Trevor Livesay; James Nickelson; Ty Giffin 'c: Pat Bjorndal iubject: BIF Sitework Schedule fo All, 'lease see attachment for November Sitework at the Parking Garage. (hanks, Mark Brown Vlartel Construction, Inc. 1203 South Church Avenue 3ozeman, Montana 59715 Direct 406 -922 -5504 =ax 406 -586 -8646 ,ell 406- 539 -9450 11/25/2008 r w P.O. BOX 69 BELGRADE, MONTANA 59714 SAND, GRAVEL EXCAVATION WORK 406 -388 -6844 FAX 406 -388 -6091 MINE ACCOUNTING INFORMATION 406 -388 -6844 FAX 406 388 -6091 MINING CONSTRUCTION Dear Customers: Due to the rising cost of fuel and labor costs, TMC Inc. is forced to make the following price changes. All prices are picked -up at our pits. Price change is effective January I' 2008 D Material Weight /CY Price /CY 0 PIT RUN 3291.3 $6.00 6" PIT RUN 2900 $6.50 (STOREY PIT) 3" RD MIX 3113.1 $7.00 .11/2 "RD MIX 2743.2 $7.75 2824.2 $8.00 y SCR.3 14" ROCK 2400 $11.25 11/2" SEWER ROCK 2500 $11.00 CONCRETE ROCK 2500 $12.00 IPA WASHED SAND 2800 $6.50 FILTER SAND 2800 $13.00 f F CONCRETE MIX 2800 $15.00 /!/f�o GV 3/8" CHIPS 2300 $23.00 RIP RAP 2800 $30.00 NATURAL FINES 2800 $6.00 SCR. TOPSOIL 2000 $16.00 MASON SAND 2400 $18.00 MICRO CHIPS 2300 $26.00 CRUSHED ASPHALT 2600 $7.50 8" COBBLE 2500 $10.50 (STOREY PIT) 4" 6" COBBLE 2500 $12.50 (STOREY PIT) 2" 3" COBBLE 2500 $14.50 (STOREY PTT) PICK UP LOADS AT THE PITS $25.00 LOAD TRUCKING Single Truck S85.00/hour Trucks/Pup $90.00/hour Transfer $95.001hour Dump Fees: Clean Fill Material 2.00 /ton RECEIVED Asphalt/Concrete Rubble $25.00 /ton DEC 2 7 2007 Mat ►eE u0ns0'UCb00, Inn. l ;;�e D'ec 02 08 10:29a Jeff Baker 406 -388 -0778 P,1 RECED'E'D DEC 02 2000 WORK DIRECTIVE CHANGE Martel Construction, Inc. Job No PLP -5 -08 Change No 1 Approval Date Project: Martel Construction, Inc. Date of issuance: 1112012008 Owner Co: Mark Brown Owners Project Na: 1203 South Church Engineers Project No: Bozeman MT 59715 Engineer: Contract F Bozeman Intermodal Facility Contractor: Gallatin Asphalt, Inc. 6465 River Rd Bozeman, MT 59718 (D Change Title NO Description Price Civil Engineering Changes 1 Change From a 4" Section of vase Gravel to a 6' Section in the 1,617.00 Alleyway. 77 additional tons of Road mix $21.00 Per ton in place. Civil Engineering Changes 2 Change From a 4" Section of base Gravel to a 6" Section on Black 735.00 and Mendenhall Streets. 35 additional tons of Road mix $21.00 Per ton Civil Engineering Changes "3� Change From 3" section of asphalt placed in 1 lift to a 4" section of 3,510.00 asphalt placed in 2 lifts in the Alleyway, 39 additional tons of AC $90.00 Includes Paving Area Twice) Civil Engineering Changes 4 Change From 3" section of AC placed in 1 lift to a 4" section of AC 1,620.00 placed in 2 Iifts on Mendenhall and Slack. 18 additional tons of AC $90.00 Includes Paving Area Twice) Contractor Ordered Changes i I Saw Cut Perimeter Area of New Asphalt Section on Black and 98835 Mendenhall. 565 Lineal Feet 1.75 Contractor Ordered Changes 2 Excavate, Haul Off and dispose of asphalt section on Slack and 375 "00 Mendenhall. 15 tons $25.00 Contractor Ordered Changes 3� Pave Additional Square Footage on Black and Mendenhall. 22,016 "00 Planned SF Quantity was 2,850. Actual for Mendenhall Tracy is 5454 sf. Actual For Black is 2,900. 5,504 Ad $4.00 Total Changes $30,861.75 'Dec 02 08 10:30a Jeff Baker 406- 388 -0778 p.2 Method of determining change in Contract Price: Method of determining change in Contract Time: Time Materials Contractor Records Unit Price Engineer Records ❑.Cost plus Fixed Fee Other Records Other Estimated Increase in Contract Price Estimated increase (decrease) in Contract $30,861.75 Time: 0 days. If the change involves an increase, the estimated amount is not to It the change involves an inorease the maimate time is not to be exeeded without further authorization. be exceeded without further authorization. RECOMMENDED: AUTHORIZED: Date Date 1408 Yiillaire Lane (406) 58-5171 Baseman, Montam 89715 March 17, 2008 Martel Construction 1203 So. Church Bozeman, Mt. 59715 U Att. Mark Brown Re; Parking Garage landscape& Irrigation Landscape; Provide and install 3 Maple, 6 Prairie Spire Ash AND 4 Boulevard Linden trees 1 3 /4 containered. Provide and install 13 4' type c tree guards. Provide and install fabric and bark mulch in tree pits. Warrant trees for 1 growing season. Provide and install sod. All clean up necessary. Irrigation: Provide one Rain Bird 4 station lockable clock. Provide and install water hookup in meter pit using galvanized pipe. Also provide antisyphon valve, pressure regulator and filter. Provide and install 2" pvc sleeves for new trees. Two zones (1 north and east and 1 west). New trees to have 4 2gph emitters per tree and existing to have 10 2 gph emitters per tree. Provide and install 6 1804 spray pop up heads for sod area. System is designed for winterizing by compressed air. RECEIVED $5050.00 Trees, labor, fabric and mulch. MAR 18 2.00 $4253.00 Tree guards, freight and labor. $350.00 Sod and topsoil. MW Constudon, Inc, $370.00 Miscellaneous and clean up. $5162.00 Irrigation system. $15,005.00 Total. Respectfully, Jim Lawson C p. ww. Western Plumbing RECEIVED Estimated Proposal Date: May 21, 2008 in 6 Project: Bozeman Parking Garage Martel Construction, inc. Contractor: Lawson's Greenhouse Attention: Jim Lawson Scope: Install Piping and Backflow Preventer from Meter in Meter Pit to Landscape Area 30' away. 1. Labor Materials $830.00 Total $830.00 2" PVC Sleeves provided and installed by others. Change Orders: 1. Only performed with "an approved change order and signed by Owner /Agent 2. Will be billed at: Extra $65.00 per hour 3. Materials will be billed at cost -plus 30% Fixtures and equipment: A 50% prepay will be billed prior to ordering all fixturds and equipment. This es ate is valid for 30 days. est Plumbing Date MARTEL CONSTRUCTION, INC. m MAIN OFFICE BIGFORK OFFICE 1203 South Church Avenue 305 Highway 83 RECIPIENT OF 1990 NATIONAL BUILD AMERICA AWARD Bozeman, MT 59715 -5801 Bigfork, MT 59911 1999 SBA ENTREPRENEURIAL SUCCESS AWARD 1999 MONTANA FAMILY BUSINESS OF THE YEAR AWARD (406) 586 -8585 Fax (406) 586 -8646 (406) 837 -1063 Fax (406) 837 -1068 2001 MCACONCRETE EXCELLENCE AWARD January 19, 2009 Prugh Lenon Architects, P.C. 27 East Main Street Bozeman, Montana 59715 Attention: Dick Prugh Re: Bozeman Intermodal Facility Bozeman, Montana 59715 Subject: COR 005 Reference: Structural Steel Issues Dear Dick, As requested, we propose to provide all labor, materials, and equipment required to perform the above mentioned work. Our breakdown of the work is attached. Our quotation is based on our interpretations of of the instructions and scope of work identified in the request, specifications and /or drawings. If we have misinterpreted the request in any way (omissions, etc.), please advise us prior to processing this quotation into a formal Change Order. Otherwise, our interpretation shall stand as correct. We have been directed to proceed with the work per the instructions in the Change Order Request. At this time, we are hereby requesting 10 calendar days time extension to the scheduled completion date of August 4, 2008. Z We are requesting an additive Change Order for the amount of. $a Martel Construction, Inc. reserves the right to submit a request for any additional time and or cost for disruption, impacts, acceleration, delay, or suspension which cannot be determined at this time. If you have any questions, please call me at (406) 922 -5504. Sincerely, MARTEL INC. Mark Brown Enclosure(s) CC. File James Goehrung COB COMMERCIAL RESIDENTIAL INSTITUTIONAL INDUSTRIAL 9:w�e 5760 Prugh Lenon Architects, P.C. January 19, 2009 Page 2 RE: Bozeman Intermodal Facility Bozeman, Montana 59715 SUBJECT: COR 005 REFERENCE: Structural Steel Issues CHANGE REQUEST BREAKDOWN: Labor Material Subcontract Other 44,803.56 Subtotal 44,803.56 Construction Managers Fee 6.0% 2,688.21 Subtotal 47,491.77 Insurance Bonds 1.5% 712.38 Subtotal 48,204.15 Gross Receipts Tax 1.0% 482.04 Calculated Proposal Request 48,686.19 TOTAL CHANGE ORDER REQUESTED: $48,686 REMARKS AND QUALIFICATIONS: I i I Martel Construction, Inc. Bozeman Intermodal Facility Structural Steel Issues Change Order Request #005 January 19, 2009 Item Description Reference Amount #1 Additional Fabricated Steel 2.5 Ton Steel West $5,540.00 Added Brick Ledger Angles per DCI 2 TS Columns on R3 #2 Erection Placement For Item #1 $6,000.00 2.5 Ton $24001 Ton #3 Additional Detailing Hours Steelhead Drafting #4 Price Increase Steel Joists Metal Deck Steel West #5 Additional Ironworker Man Hours to Field Modify Structural Steel $2,170.35 (Steel was fabricated per approval drawings) Structural Systems 32.5 Hours $66.781HR #6 Fabricate Additional Tube Steel Column Stair 2 Custom II $278.21 #7 Fabricate Additional Tube Steel Columns Stair 1 3 Bear Mountain $575.00 �r Construction Managers Fee 6.0% $873.81 SubTotal $15,437.37 Insurance Bonds 1.5% $231.56 SubTotal $15,668.93 Gross Receipts Tax 1.0% $156.69 Total $15,825.62 Page 1 of 1 Martel Construction, Inc. Bozeman Intermodal Facility Structural Steel Issues Change Order Request #005 January 19, 2009 Item Description Reference Amount #1 Additional Fabricated Steel 2.5 Ton Steel West $5,540.00 Added Brick Ledger Angles per DCI 2 TS Columns on R3 #2 Erection Placement For Item #1 $6,000.00 2.5 Ton $2400 Ton #3 Additional Detailing Hours Steelhead Drafting $10,000.00 #4 Price Increase Steel Joists Metal Deck Steel West $20,240.00 #5 Additional Ironworker Man Hours to Field Modify Structural Steel $2,170.35 (Steel was fabricated per approval drawings) Structural Systems 32.5 Hours $66.78IHR #6 Fabricate Additional Tube Steel Column Stair 2 Custom II $278,21 #7 Fabricate Additional Tube Steel Columns Stair 1 3 Bear Mountain $575.00 SubTotal $44,803.56 Construction Managers Fee 6.0% $2,688.21 SubTotal $47,491.77 Insurance Bonds 1.5% $712.38 SubTotal $48,204.15 Gross Receipts Tax 1.0% $482.04 Total $48,686.19 Page 1 of 1 JAN -19 -2009 07:OOAM FROM -STEEL WEST 208 237 1582 T-855 P- 002/002 F -352 Mike Hoehner From_ Mike Hoehner [hoehnen@steelwest.net] Sent. Monday, December 01, 2008 3:19 PM To: Mark Brown cc: Tony Martel Subject: Bozeman lntermodal Facility Mark: Per our discussions last week I have visited with 5teelhead concerning the additional ledger angles and columns which were added to this project, Our total cost for this additional work is $5540.00. We would also like an update on the status of the price change for the escalation costs in joist and deck and the detailing by 5teelhead Drafting. 1 anticipate finishing the balance of the handrails for Stair #1 and sending them to the powder coater late this week and then picking up the balance of the galvanized frames for delivery to you_ Any questions please call me. Thanks, Mike RECEIVE[ JAN 19 2009 Martel Construction, Inc. STEEL WEST, INC. �w.► 5690 Industry Way P.O. Box 5427 Pocatello, Idaho 83202 -000; (208) 237 -1580 Fax (208) 237 -1582 FEDERAL lD# 82- 0294656 July 9, 2008 RECEIVE[) Mr. Mark Brown Martel Construction JUL 09 2008 1203 S. Church Street Martel Construction, i nc. Bozeman, Montana 59715 Reference: Bozeman Intermodal Facility, Bozeman, Montana Subject: Price Increase on Steel Joist and Metal Deck Dear Mark: Due to the extremely lengthy time it has taken to approve the steel joist and metal deck on this project there has been a large increase in the pricing from our supplier. Our total add price for this delay in delivery is $20,240.00. 1 need to get this change approved or I may face another cost change. Please advise. Any questions please call me Sincerely, Mike G. Hoehner Estimator /Project Manager Steel West Inc. Structural Steel Detailing, Rebar and Plate Detailing ELHEUD 280 Laurel Lane Chubbuck, ID 83202 (208) 232 -6010 N Drafting FAX: (208) 232 -6010 E -Mail: steelheaddraft @gwestoffice.net Oct. 22, 2008 Mike, SW07 -36 Bozeman intermodel Facility Request for payment for extra time in detailing: We have used an extra 250 hours in detailing on this job due to the lack of information contained within the design drawings. 1) Design of stairs fell directly upon us, we had to design and detail stairs for review, then design and detail again with review comments and send in for approval, then detail one more time with approval comments, this all caused extra time involved that was not in our original bid. (85 hrs $3400) 2) Design of both entry canopies fell upon us to design the canopies to fit and to detail them for review, then redesign with comments per review and re- detail for approval, then add approval comments and re- detail for fabrication, again this added time that was not in our bid. (55 hrs $2200) 3) Design of security frames and detailing for review and then redesign to fit existing conditions and to re- detail this frames to field dimensions, again this added time that was not in our bid. (40 hrs $1600) 4) Design of the stair handrail and detailing of the rail to fit conditions that we were not aware of during our bid process has added extra time in this area. (30 hrs $1200) 5) Extra time involved in changing items to work with field conditions and changes requested from jobsite, again this added time that was not in our bid. (40 hrs $1600) Total cost: $10,000.00 RECEIVED OCT 2 LJ 2008 Martel constaction, Inc, A am not trying to lay blame on anyone involved with this project, everyone has worked together to get this building built, but it has been a long drawn out process that has taken more time than originally thought. I feel that we have worked with Martel Construction hand -in -hand and done everything possible to help them get this put together. We have just spent more time on working this job than was original bid. Please accept this as a request for additional time associated with job. Thank you, Troy Gardner Steelhead Drafting Any questions please call. STRUCTURAL SYSTEMS, INC. Serving Montana Since 1 969 P.O. Box 2069 Missoula, MT 59806 734 South First West Missoula, MT 59801 Phone (406) 728 -5597 Fax (406) 549 -2661 RECEIVED CUSTOMER'S ORDER NO. PHONE ��T 09 2009 NAME Martel construction, Inc. ADDRESS SOLD BY CASH C.O.D. CHARGE ON ACCT MDSE, REM PAID OUT CITY. DESCRIPTION PRICE AMOUNT JOAO mmI::: &1 14 0 "'d 1 1 I 1 1 1 1 1 574 _�t- 1 1 I 1 1 1 TAX RECEIVED a TAL 1 Check Us Out on the Web! www.structsys.com 2205 800 225 -6380 or neb$.com STRUCTURAL SYSTEMS, INC. Serving Montana Since 1969 P.O. Box 2069 Missoula, MT 59806 734 South First West Missoula, MT 59801 Phone (406) 728 -5597 Fax ON) 549 -2661 RECEIVED CUSTOMER'S ORDf_R NO. PHONE OgTE NAME DDRESS SOLD BY. CASH C.O.D. CHARGE J ONACCT. IMDSE.RETD. PAID OUT QTY. DESCRIPTION PRICE AMOUNT I 1 1 i 1 1 1 1 i 1 i 1 1 Jn 1 1 _r__.___ 1 1 1 1 1 1 1 __...__..i..- TAX 1 RECEIVED 8Y 1 TOTAL Check Us Out on the Web! www.structsys.com 2207 To Reorder: c �jf FW $04225 -6360 or nobs.com STRUCTURAL SYSTEMS, INC. Serving Montana Since 1969 P.O. Box 2069 Missoula, MT 59806 734 South First West Missoula, MT 59801 Phone (446) 728 -5597 Fax (406) 549.2661 RECEIVED CUSTOMER'S ORDER NO. PMONE I'= 0}9 2}009 NAME Mp1 l�� �Jo7fs uCton Inc. ADDRESS SOLD BY CASH C.O.D: CHARGE J_ ON ACOT I MDSE. REM. PAID OUT QTY. DESCRIPTION PRICE AMOUNT I I TAX RECEIVED 13Y —TOf Check Us Out on the Web! 2208 www.structsys.com T Reorder: 800- 225 -6380 or nebaxom STRUCTURAL SYSTEMS, INC. Serving Montana Since 1969 P.O. Box 2069 Missoula, MT 59806 734 South First West Missoula, MT 59801 Phone (406) 728 -5597 Fax (406) 549 -2661 RECEIVED CUSTOMER'S ORDER NO. PHONE wo 9 200 NAME Martel Construction, lnc. ADDRESS SOLD BY CASH C.O.DL CHARGE ON ACCT. MDSE. RETD. PAID OUT QTY. DESCRIPTION PRICE AMOUNT RECEIVED BY i Check Us Out on the Web! 22 www.structsys.com 10 To Reorder: 800 225 -6380 or nebs.com STRUCTURAL SYSTEMS, INC. Serving Montana Since 1969 P.O. Box 2069 Missoula, MT 59806 734 South First West Missoula, MT 59801 Phone (405) 728.5597 Fax (406) 549 -2661 RECEIVED CUSTOMER'S ORDER NO. PHONE FIB 9 200 NAME Martel tel Co tL`7Jtructlion, Inc. ADDRESS r SOLD BY CASH C.O.D. CHARGE ON ACCT. MDSE..RETD. PAID OUT QTY. DESCRIPTION PRICE AMOUNT 1 1 1 1 t I 1 t 1 1 1 1 1 1 1 1 1 1 1 t 0 7 I 1 TAX RECEIVeD sv TOTAL t Check Us Out on the Web! www.structsys.com 2 211 1� To Reorder 800- 225-6380 or nebs.com Martel Construction, Inc. Job Cost Summary 01 -17 -2009 Page 5 System Time: 4:04 pm 07-016 Bozeman Intermodal Facility Bozeman, MT Original JTD Budget Estimate Costs Variance MECHANICAL 15 -999 Plmbg /HVAC +Fr Sprnk -Willm 461,000.00 420,657.00 40,343.00 MECHANICAL 461,000.00* 420,657.00* 40,343.00* ELECTRICAL 16 -999 Electricl -Vally Elc Cntrt 573,000.00 580,930.00 7,930.00 ELECTRICAL 573,000.00* 580,930.00* 7,930.00 FIELD WORK ORDERS FWO -001 Rotate Col Grd C.6 12 600.20 600.20 FWO -002 ADA Ramps 2,048.85 2,048.85 FWO -003 24 x 24 Access Doors 1,289.99 1,289.99 FWO --004 Slab Step Retail 325.42 325-42- FWO -005 Add Rebar Shearwalls 7,056.00 7,056.00 FWO -006 Beam Penetrations 48.00 48.00 FWO -007 Black Ave SS Repair 838.57 838.57 F'WO -009 Door M -1 Revisions 1,443.00 1,443.00 FWO -010 MACON- Issues 13,738.12 13,738.12 FWO -011 Fab. $#4 Stirrups 238.01 238.01 FWO -013 Add TS Col. Stairs 278.21 278.21- PWO -014 Move Mendenhall Fence 939.97 939,97_ FWO -015 Site Grading 450.00 450.00 FWO --016 Parapet Wall 0 -1 886.72 886.72 FIELD WORK ORDERS .00* 30,181.06* 30,181.06 07 -016 Totals 8,113,500.80* 8,573,932.55* 460,431.75-* r 003330 CUSTOMER'S ORDER NO. DEPARTMENT ATE I NAME G ADDRESS Z 4x• CITY, STATE, ZIP SOLD BY CASH C.D.D. CHARGE ON ACCT. MDSE RETD I PAIDOUT QUANTITY DESCRIPTION PRICE AMOUNT. i Lv 3 4 eg 5 6 7 8 9 10 Q 11 12 13 U h• Lr 14 C 44 dry t 15 y 71S 16 17 18 19 1 1 20 RECEIVED B edemg KEEP THIS SLIP FOR RE EREI E 5805 MARTELCONSTRUCTION, INC. MAIN OFFICE BIGFORK OFFICE 1203 South Church Avenue 305 Highway 83 RECIPIENT OF 1990 NATIONAL BUILD AMERICA AWARD Bozeman, MT 59715 -5801 Bigfork, MT 59911 1999 SBA ENTREPRENEURIAL SUCCESS AWARD 1999 MONTANA FAMILY BUSINESS OF THE YEAR AWARD (406) 586 -8585 Fax (406) 586 -8646 (406) 837 -1063 Fax (406) 837 -1068 2001 MCA CONCRETE EXCELLENCE AWARD January 18, 2009 Prugh Lenon Architects, P.C. 27 East Main Street Bozeman, Montana 59715 Attention: Dick Prugh Re: Bozeman Intermodal Facility Bozeman, Montana 59715 Subject: COR 006 Reference: ADA Ramps Dear Dick, As requested, we propose to provide all labor, materials, and equipment required to perform the above mentioned work. Our breakdown of the work is attached. Our quotation is based on our interpretations of of the instructions and scope of work identified in the request, specifications and /or drawings. If we have misinterpreted the request in any way (omissions, etc.), please advise us prior to processing this quotation into a formal Change Order. Otherwise, our interpretation shall stand as correct. We have been directed to proceed with the work per the instructions in the Change Order Request. At this time, we are hereby requesting NA calendar days time extension to the scheduled completion date of August 4, 2008. We are requesting an additive Change Order for the amount of. $9,072 Martel Construction, Inc. reserves the right to submit a request for any additional time and or cost for disruption, impacts, acceleration, delay, or suspension which cannot be determined at this time. If you have any questions, please call me at (406) 922 -5504. Sincerely, MARTS CONSTRUCTION, INC. ark Brown G Enclosure(s) CC. File James Goehrung COB COMMERCIAL RESIDENTIAL INSTITUTIONAL INDUSTRIAL 'FdAd&Jr >960 Prugh Lenon Architects, P.C. January 18, 2009 Page 2 RE: Bozeman Intermodal Facility Bozeman, Montana 59715 SUBJECT: COR 006 REFERENCE: ADA Ramps CHANGE REQUEST BREAKDOWN: Labor 2,048.45 Material Subcontract 6,300.00 Other Subtotal 8,348.45 Construction Managers Fee 6.0% 500.91 Subtotal 8,849.36 Insurance Bonds 1.5% 132.74 Subtotal 8,982.10 Gross Receipts Tax 1.0% 89.82 Calculated Proposal Request 9,071.92 TOTAL CHANGE ORDER REQUESTED: $9,072 REMARKS AND QUALIFICATIONS: Martel Construction, Inc. Bozeman intermodal Facility ADA Ramps Change Order Request #006 January 17, 2009 Item Description Reference Amount #1 Add Truncated Dome Panel ADA Ramps Castle Rock Concrete $6,300.00 #2 Additional Labor Material For ADA Ramp Formwork Martel $2,048.45 SubTotal $8,348.45 Construction Managers Fee 6.0% $500.91 SubTotal $8,849.36 Insurance Bonds 1.5% $132,74 SubTotal $8,982.10 Gross Receipts Tax 1.0% $89.82 Total $9,071.92 I Page 1 of 1 Page 1,of 1 Mark Brown From: Jonathan Skillman U s kill man @castlerockconcrete.com] Sent: Thursday, October 23, 2008 2:06 PM To: Mark Brown Subject: Change order proposal for 14 truncated domes. Vlark: ro furnish and install 14 truncated dome panels I agree to $6300. this comes to $450 per panel. The average bid price for the panels for MDT in 2007 was $477 per panel. ks agreed, I will hold off on billing these out this month if you will get me a change order before next months billing. thanks. Jonathan Skillman 'roject Manager 1;astleRock Concrete Inc. V 1/18/2009 04/24/2008 15:18 4653888069 PAGE 02 70 Rock Road Belgrade, MT 59714 Phone: (406) 388 -8090 Fax: (406) 388 -8089 C871VrCFtETE, NC�IC,. Email: castlerock *castierockconcrete.com DATE: April 24, 2008 LOCATI Baxeman PROJECT: B ozeman Parking Garage CONTMCTW; Martel Construction Proposed Change ADA Detectable Warning Surface Bid Items ITEM ITEM UNIT UNIT TOTAL NUMBER DESCRIPTION MEASURE QUANTITY PRICE PRICE 1 ADA D CTAB WARN G SP 200.0 45.00 9000.00 TOTAL BID PRICE ,000.00 CONDITIONS: -Prize includes furnish and installation of 20 pieces of 24" by EW Blade colored ADA panels as ou#lined and marked on the plan sheet ICR by Mark Brown dated Q24MODB. -Price based on ADA solutions product submidW to Martel on March 12, 2008. -Some trlming may be necessary W make product fit correctly. Respectfully Sub 1 nathan SkIllman CastleRock to Inc. PAGE 01 04/24/2008 15:18 4068888089 CASTLEROCK CONCRETE INC. 70 Rack Rd. r• Belgrade, MT 59714 r• �f �f` PHONE; 406 1388402 0 FAX: 4061388 -8089 C d i11 iR T c, A r C.. Fax TO: COMPANY: an r FAX NO.: �1ffX� S .t^ PHONE NO. FROM: t �,►tCI,GG is OF PAGES INCLUDING COVER: 2 BATE: t SUBJECT: D, DA gwerx p0qrcf.&;j�' MESSAGE: Martel Construction, Inc. Job Cast Summary 01 -17 -2009 Page 5 System Time: 4:04 pm 07 -016 Bozeman Tntermodal Facility Bozeman, MT Original JTD Budget Estimate Costs Variance MECHANICAL 15 -999 Plmbg /HVAC +Fr Sprnk -Willm 461,000.00 .420,657.00 40,343.00 MECHANICAL 461,000.00* 420,657.00* 40,343.00* ELECTRICAL 16 -999 Electricl -Vally Elc Cntrt 573,000 -00 580,930.00 7,930.00 ELECTRICAL 573,000.00* 580,930.00* 7,930.00 FIELD WORK ORDERS FWO -001 Rotate Col Grd C.6 12 600.20 600.20 FWO-002 ADA Ramps 2,048.85 2,048.85 FWO -003 24 x 24 Access Doors 1,289.99 1,289.99 FWO -004 Slab Step Retail 325.42 325.42 FWO -005 Add Rebar Shearwalls 7,056.00 7,056.00 FWO -006 Beam Penetrations 48.00 48.00 FWO -007 Black Ave SS Repair 838.57 838.57 FWO -009 Door M -1 Revisions 1,443.00 1,443.00 FWO -010 MACON- Tssues 13,738.12 13,738.12 FWO -011 Fab. #4 Stirrups 238.01 238.01 FW6-013 Add TS Col. Stairs 278.21 278.21 FWO -014 Move Mendenhall Fence 939.97 939,97 FWO -015 Site Grading 450.00 450.00 FWO -016 Parapet Wall 0-1 886.72 886.72 FIELD WORK ORDERS .00* 30,181.06* 30,181.06 07 -016 Totals 8,113,500.80* 8,573,932.55* 460,431.75 i i MARTEL CONSTRUCTION, INC. MAIN OFFICE BIGFORK OFFICE 1203 South Church Avenue 305 Highway 83 RECIPIENT OF 1990 NATIONAL BUILD AMERICAAWARD Bozeman, MT 59715 -5801 Bigfork, MT 59911 1999MONTANA FAMILY 2 INE590F THE YEAR AWARD (406) 586 -8585 Fax (406) 586 -8646 (406) 837 -1063 Fax(406)837-1068 2001 MCA CONCRETE EXCELLENCE AWARD January 19, 2009 Prugh Lenon Architects, P.C. 27 East Main Street Bozeman, Montana 59715 Attention: Dick Prugh Re: Bozeman Intermodal Facility Bozeman, Montana 59715 Subject: COR 008 Reference: Add Rebar Shear Walls Rotate Col. C/6 Re- profile Tendons Dear Dick, As requested, we propose to provide all labor, materials, and equipment required to perform the above mentioned work. Our breakdown of the work is attached. Our quotation is based on our interpretations of of the instructions and scope of work identified in the request, specifications and /or drawings. If we have misinterpreted the request in any way (omissions, etc.), please advise us prior to processing this quotation into a formal Change Order. Otherwise, our interpretation shall stand as correct. We have been directed to proceed with the work per the instructions in the Change Order Request. At this time, we are hereby requesting 5 calendar days time extension to the scheduled completion date of August 4, 2008. We are requesting an additive Change Order for the amount of. $8,320 Martel Construction, Inc. reserves the right to submit a request for any additional time and or cost for disruption, impacts, acceleration, delay, or suspension which cannot be determined at this time. If you have any questions, please call me at (406) 922 -5504. c c Sincerely, 0 0 MARTEL CONSTRUCTION, INC. o CqAJ�4 C c' Mark Brown Enclosure(s) C 4� uo 01 06 cc. File 06 James Goehrung COB 0.3 COMMERCIAL RESIDENTIAL INSTITUTIONAL INDUSTRIAL I S 157M i R Mountain Kebab, Inc. P.D. B ox 67l Bigfork, MT 59911-0671 WORK AUTHORIZATION FORM CONTRACTOR'S NAME OUR JOB NAME NO. ATE D THIS IS TO AUTHORIZE WORK TO BE PERFORMED AS: (CHECK ONE) EXTRA WORK TO OUR CONTRACT: TIME AND MATERIALS STRAIGHT TIME RATE OVERTIME RATE CONTRACTOR'S P.O. NO. PREMIUM TIME ONLY r' DESCRIPTION OF WORK: i ROCKY MOUNTAIN RESAn, INC. IS HEREBY AUTHORIZED TO PROCEED WITH THE WORK AS DESCRIBED: AUTHORIZED BY: CONTRACTOR EMPLOYEES NAME HOURS DATE INITIAL THE DESCRIBED WORK HAS SEEN PERFORMED AS AUTHORIZED AND THE ABOVE HOURS ARE CORK s d SIGNED SIGNED CONTRACTOR f;'!�C KY MOUNTAIN!?EE+AFt, INC. WIHITF COPY Main Office CANARY COPY Fabricator PINK COPY Contractor GOLDENROD COPY w=ield MARTEL CONSTRUCTION, INC. MAIN OFFICE BIGFOpK OFFICE 1203 South Church Avenue 305 Highway 83 RECIPIENT OF 19W NATIONAL SUILOAMERICAAWARD Bozeman, MT 59715.5801 ftfork, MT 59911 1998 SBA ENTREPRENEURIAL 3000E38 AWARD 1998 MONTANA FAMILY BUSINESS OF THE YEAR AWARD (406) 586 -8585 Fax (406) 686 -8646 (406) 837 -1063 Fax (406) 837 -1068 7001 MCA CONCRETE EXCELLENCE AWARD May 4, 2009 Prugh Lenon Architects, P.C. 27 East Main Street Bozeman, Montana 59715 Attention: Dick Prugh Re: Bozeman Intermodal Facility Bozeman, Montana 59715 Subject: COR 010 Reference: Install Owner Furnished Parking Signage Dear Dick, As requested, we propose to provide all labor, materials, and equipment required to perform the above mentioned work. Our breakdown of the work is attached. Our quotation is based on our interpretations of of the instructions and scope of work identified in the request, specifications and /or drawings. If we have misinterpreted the request in any way (omissions, etc.), please advise us prior to processing this quotation into a formal Change Order. Otherwise, our interpretation shall stand as correct. We have been directed to proceed with the work per the instructions in the Change Order Request. We are requesting an additive Change Order for the amount of. Martel Construction, Inc. reserves the right to submit a request for any additional time and or cost for disruption, impacts, acceleration, delay, or suspension which cannot be determined at this time. If you have any questions, please call me at (406) 922 -5504. Sincerely, VEL NSTRUCTI y r To Martel Enclosure(s) CC. File James Goehrung COB COMMERCIAL RESIDENTIAL INSTITUTIONAL INDUSTRIAL �ata�� l X60 MARTEL CONSTRUCTION, INC. MAIN OFFICE BIGFORK OFFICE 1203 South Church Avenue 305 Highway 83 RECIPIENT OF 1990 NATIONAL BUILD AMERICA AWARD Bozeman, MT 59715-5801 8igfork, MT 59911 1999 SBACNTREPRENEURIAL SUCCESS AWARD 1999 MONTANA FAMILY BUSINESS OF THE YEAR AWARD (406) 586 -8585 Fax (406) 586 -8646 (406) 837 -1063 Fax (406) 837 -1068 2001 MCA CONCRETE EXCELLENCE AWARD February 4, 2009 Prugh Lenon Architects, P.C. 27 East Main Street Bozeman, Montana 59715 Attention: Dick Prugh Re: Bozeman Intermodal Facility Bozeman, Montana 59715 Subject: COR 014 Reference: Type L Fixtures Black Ave. Mendenhall St. Canopies Dear Dick, As requested, we propose to provide all labor, materials, and equipment required to perform the above mentioned work. Our breakdown of the work is attached. Our quotation is based on our interpretations of of the instructions and scope of work identified in the request, specifications and /or drawings. If we have misinterpreted the request in any way (omissions, etc.), please advise us prior to processing this quotation into a formal Change Order. Otherwise, our interpretation shall stand as correct. We have been directed to proceed with the work per the instructions in the Change Order Request. We are requesting an additive Change Order for the amount of. 111 $1,928 Martel Construction, Inc. reserves the right to submit a request for any additional time and or cost for disruption, impacts, acceleration, delay, or suspension which cannot be determined at this time. If you have any questions, please call me at (406) 922 -5504. Sincerely, MARTE.4 CONSTRUCTION, INC. Z&� ark Brown C I& Enclosure(s) I' l CC. File James Goehrung COB COMMERCIAL RESIDENTIAL INSTITUTIONAL INDUSTRIAL 1 960 Prugh Lenon Architects, P.C. February 4, 2009 Page 2 RE: Bozeman Intermodal Facility Bozeman, Montana 59715 SUBJECT: COR 014 REFERENCE: Type L Fixtures Black Ave. Mendenhall St. Canopies CHANGE REQUEST BREAKDOWN: Labor Material Subcontract 1,774.00 Other Subtotal 1,774.00 Construction Managers Fee 6.0% 106.44 Subtotal 1,880.44 Insurance Bonds 1.5% 28.21 Subtotal 1,908.65 Gross Receipts Tax 1.0% 19.09 Calculated Proposal Request 1,927.73 TOTAL CHANGE ORDER REQUESTED: $1,928 REMARKS AND QUALIFICATIONS: Typ L Recessed Fixtures would not fit in canopies as drawn and specified. See attached Will Van Dyken fax dated 1/23109 for substitute Type L Surface Mount Fixture. Jan-23-09 03408P Van Dyken Engineering 406- 586 -2205 P.01 4„ VAN NOWYMIN FAX (4061 5&5--22DS PRC F=ONAL fiONSLILI NG ENGNSM 37 Sp.NGH PILV Do BOMMAN, t i 57 i Sc Dates k0. 09 papo �Ina1• To: PAr) J�j 0 A/- RZI I h4 &P BAR A 6 "Utioxg.. .nth2 r L C }l /-IAf7 70 7 7/ t 4 I T-1- A'j r it 411 paps am Aot reaeivedo Jan -211 -09 03_08P Van loykan EngIneer;ng 406 —See -2205 P_02 Surface Squares (TS'I.S, TS24) Sur'f1riR5¢WMSprC(frCftfarr C'�;�;Y33��� *�s� Surtac Sgwre Ilanil� ins are deargr+ed ier eotlatkFdat a�plr�arl�ens, AvalBble In 70 •;F.��; !41160 watt mogi+l hfgh ptessurn 5adfurl+ Iamp end t7S M 400 watt mend base vMW hdllde tamp. Avaliable with tsp jfO 120. AS. 24% I77, 480 Wntt or 41UT (129, 208, 240, 27TA 66!12 baltest. IJATOUIFO� shall ba COMP*tefy v*­-.wed em of y lns�fla4ort, A 20 gauge C.R. stni houOrg, one pleoe smeal doer end vim frntshed h haktd yyhlta lamp Trot kvll; d eMantr!l. Stu* 5tW frwo sappertnd with concealed tMlon spring !antic" (751 5) o; hn:90 fM4) is easily remand for dear iO5 and eelarnping. Avelfabla with a di dic e of ddfkwrb, Corning #73 "C" 0111! PO T515 only), drop teaOMR ;L�, lrfurrrph t ON, T524 trig). t4Lrnp ti If M4.1. 7515 otdy Poreel'ain lamp qui so&et wkh 1,5�IGHT 2b59 ft prated st�M 0*11 and spring Inackti tenter mmtKt t*mlvwtes lamp Wosening. a4010e 0r�ks Surface Squaws 5hall4MMOn a 1w9 lasting U_L recognlxsd Hipb P was Factor (HPF) av *iraretf Clt W type Wait. "If stag m[! la! tt -20f ft metal l Nilde and 7n� 40f 4.4tt tot gih hi prmute sodlurn. Memo rY ap arrgos mry ba lnipd in 175 -aq6 v rrr I wort tr V* tuilde fttum. Far vigAblltty of 22W4 W, So t baR4st e�it+stdt &coy, spinnrm�tu:tAo- rOts+ce4r prauldest urtiffanrY rfmrrrrMud wide hear 6strt6unnn. Y\ D 1 t'►LN 1{it����l'�L� Corwitle�fnbl 5 banks. sh[�vla[+vrrrs, F�o+tfgwa roams, arrd aMlIcaft s where AL CMUL III temng dots net perm!# rccewd lighting. MDNTANA mrtorpl d o�clrt�iti �tt�tat�tNp ►7d+4d �ta WNrwl�+t�fq {m� dlxur»rttlr WON ��I lo= tJ ts",'� TYPE EE; T815.1- 5- 8- H4MT -CO -DP -SLACK 1S' SURFACE SQUARE 1Nf C.ORNINU #7;l CaLAS r F9N�t11Mj4• :PAd6irlGp �iMi�'3�Iy1{ ti�ravr a.loe tlptan. sra*'rc+ s�.et T51S/YSlf d.711 5•1NId■Seem 6 SurfMtMGVM H- Mfit +Iit+IrWr !74 M•tivgh4'MW CO• CPT" R7 1 100 ri Mlgh P+esva 208 Flnar tx Omp Le *e i -ISO 54dlran 240 IC51•t Tft* I e- 737 S737a Ow I 1-20 25t! 4 (T 74,10P• KSM I {f515 tl 6.1100 A1k�rWOerM- 700 T90PS M,, 2"v) i 3I4.370PS 31F 5Ind1a wMa area 350.3M DIX• PautleMbe*ru* aan 4t17PS EM xma "My Guard Raley and 6ack*t (4ffau l feuart T 4M6t! Emrrgerxy t7uem Daly Rela7 and Saeket kanso laCtery) �'S quart 3cv�r1 Linty leitr. pawar ocgrdrad, consult lactary! DP vamp 1000W 7P lame runt swans CSA Certffcanon can factory, PM- Fft%Dn Orw*sd Sodrel 1 ntdulevt fASvsls 601554:039 1 OA 581 X330 6eoc 70881 4{qa 71FD Pxloas 13" FO, 9mr 6kalr 9 lJtrtl 44r 1*" 7 wrAanligt'd.eem D c� OPOSED CHANGE ORDER CCN# 1016 Valley Electrical Contracting Date: Bozeman 009 2820 Latimer Suite A Project Name: Bozeman Intermodal Facility Missoula, Latimer 59$08 Project Number: 3552 Page Number: 1 Client Address: Martel Construction Contact: Mark Brown 1203 South Church Avenue Bozeman, MT 59715 Work Description Credit for 4) Type L fixtures to be replaced with Surface Mounted Fixtures. Replacement fixtures= Northstar TS 15- 1- 5- 8- H- 4MT -CO -DP -BLACK We reserve the right to correct this quote for errors and omissions. This quote covers direct costs only and we reserve the right to claim for impact and consequential costs. This price is good for acceptance within 10 days from the date of receipt. We request a time extension of 3 days. Wewill supply and install all materials, labor, and equipment as per your instructions on CCN #1016. Itemized Breakdown Description Qty Net Price Unit Total Mat($) LaborUni Total Hours FIXTURE L -4 150.00 E 600.00 1.13 E -4.52 FIXTURE L- REPLACEMENT 4 490.00E 1,960.00 1.00E 4.00 B1 -1 YELLOW WIRE CONN -8 D.DDC -0.00 0.00C -0.00 #10x2 WOODSCREW -16 0.000 -0.00 0.000 -0.00 LU100 HPS LAMP -4 0.00E -0.00 0.08E -0.32 MXR100 /U /MED /OMHLAMP 4 0.00E 0.00 0.08E 0.32 Return Frt Handling 1 50.00 E 50.00 0.00 E 0.00 Fn for Replacements 1 50.00 E 50.00 0.00 E 0.00 Totals 1,460.00 -0.52 ORIGINAL PROPOSED CHANGE ORDER Client Address: CCN# 1016 Valley Electrical Contracting Martel Construction Date: 1/2812009 2820 Latimer Suite A 1203 South Church Avenue Project Name: Bozeman Intermodal Facility Missoula, MT 59808 Bozeman, MT 59715 Project Number: 3552 Page Number: 2 Summary General Materials 1,460.00 Material Markup (Q 15.000 219.00 Material Total 1,679.00 JOURNEYMAN -0.52 Hrs $52.00) -27.04 r &d (2.00 Hrs Q $55.00) 110.00 Labor Markup 15.000 12.44 Final Adjustment -0.40 Final Amount $1,774.00 CONTRACTOR CERTIFICATION Name: Date: Signature: I hereby certify that this quotaton is complete ern accurete based m the inFwrretion provided. CLIENTACCEPTANCE CCN #:1016 Final Amount :$1,774.00 Name: Date: Signature: Change Order t needy accept this quotaWn and autWIM Ule Wntractor tD coffoete the above tleacrlbed mOL ORIGINAL VAN MKRH (INSOMMEMO S FAX (941 QS.lLL17'4N N. fYil Sf� I. P A C k a VA A AR A-6 7 JQ 1 l a 9e Kam P Az /V 5 P1eaao apl3 At a.0 X222 oxa =u received. Sup*e Squares (TSI5, TS24) 5urtno Square kmtna m are dn;ned far rarta mraal a ka*m, Avaldbld In 7a f� :rg�Ms- to aoo watt ul lose hr h pressur4 7&lum lam and 175 t4 4 00 watt base ►+�9 P mogul molar halide lamp. Ararlable with f5p�% p) 120.,M. 240, 277,490 vdt a 41AT (120, 2011, 240, 27M. 60H2 ballast. LoT*1mlre shall Era caftsplc#eiy sr*AvWL'd far ease of x. lnsiallatian. 4 Aark Piaducr DmmAtiam tamp rrdi h�elireLad A 20 gauge CA st4b1 hrm Wq, one plem sWvl Omar amd tdm finished Er1 b l od w" enaarter. SW* skeel fragile suppodRtj with CgleeeKed t=1011 spring tatdies (1515) EwhgjpS (T524) is easily rer CMdl for rlmning and relamping. A,velfalsla wt#h a ctolre of diffr m, Cartring #73 (C% drop opal (d4 TSi S omly), drop lmmrrre (M, Triumph I WSH, M4 Dilly ar Tdomph If MR TS15 m4y► PbreArMri lamp gHp sadtat with WEIGHT m 2659 ftrs rl�kel plet4d screw Omll andspring I�dKd eerr�r Knntaet eNmkates lamp Wosenin¢, BnPlaxk ChiilriflAdstks surface Sgvarc:s shall wntnln a king lacvng U.L. rerognlxad Nigh P1mw Factor (HPF) n,ua° rrstss au�tra foil w type Wait. Wfll start lamas at -201 C VC1 fOr rrKO hrallde and 1 a.• M2 4{1f "K) fnr higis pressure sodium. Mal�ury vapor lamps may by used In MAC* vmtt i "Ida i6rb7res. For alailahlltry of 72W4W., MHz b4Wst rat Imay. 7� Ra'MWforr4s3ansW 2s TuAl Spun alumlrhmt ST=CG raflretar pr&AE6&a ursifC r tynursotrlcal wide tmmrn dl&i lhrrfiarl. y'/fyA k' s, N E NGLNEE RI NG SCFWu edA p�cdum VAN ONALO W�r WO EWW CarTkkm, rablbiss. 5tom banks, shavwaim, wnfareme roorrd, and appllcalbrxr where 8OZEWN MONTANA cefnng does net prm+tt rccrRCd llgh #ir`g- `om*jd do GtArip�inCR vriTh fit! me fT1 410aal0Iidd onoWoobf l tIlFlll� 4 Y 13 E3 CmAhAlkamm 15' SURFACr SQUARE W 1 CORNING �#73 PEA T5;15,.. Mi t30 R isege/ 5yuw nisnug 0-m S iMd■ Diem a- Surfx+ Mmmt 4. haft +I 1-IAIrer i70 H Nigh Pa*w CCs -CmW4 F7� 1 104 I s High Nemm WS Fancr Lx Drop Lemite 2 -ISO Stdhorm 240 m r&xrph I j 3 17S Z77 mu ow 4 4B4 Ks" 1A40 II 6 i0U M +IM7: Kt 14, 24q, {rS15 rx'Jy} 1 740. 207$ 744, 27M r 320.3m SIF %I" In11no Free 350.3FW, DIF pnuh18M%%&FUW 4W _40M EM. EIr1omOit7/quelh lhdnpr Ind Soawt (wrnsal fadary) EMsb Emeigeh othVrY tof Relaf end Swkd Kmnsldr IX700 OS 4'>a*d Sc,� Only K vm+w regrArrrd, eansuk leerery} Dp Damp maven TP 7W"F Rewmt scoms CSA CMI(maaon eansuh ffit4r}4 P% Fmhbn bdmud So*d 7brth Syr LWiing 2150 p+rl� PIS F,Ci, IRA 503A IernKh& MM 64155 -4319 703 681 -030 Fax 70MI -61546 vnmfxlighta.eam Surface Squares (TSIS, TS24) Surface Square Specification Surface Square luminaires are designed for commercial applications. Available in 70 to 400 watt mogul base high pressure sodium lamp and 175 to 400 watt mogul base metal halide lamp. Available with (specify) 120, 208, 240, 277, 480 volt or 4MT (120, 208, 240, 277V), 50Hz ballast. Luminaire shall be completely pre -wired for ease of installation. Basic Product Description A 20 gauge C.R. steel housing, one piece steel door and trim finished in baked white Lamp not included enamel. Sturdy steel frame supported with concealed torsion spring latches (TS15) or hinges (TS24) is easily removed for cleaning and relamping. Available with a choice of diffusers, Corning #73 (CO), drop opal (DO TS15 only), drop lexalite (LX), Triumph I (KSH, TS24 only), or Triumph II (KSH -2, TS15 only). Porcelain lamp grip socket with WEIGHT 26 -59 Ibs nickel plated screw shell and spring loaded center contact eliminates lamp loosening. Ballast Characteristics Surface Squares shall contain a long lasting U.L. recognized High Power Factor (HPF) e -1 /q" (rsls) Li auto transformer type ballast. Will start lamps at 20 °F 30 °C) for metal halide and 12" (TS24) -40 °F -40 °C) for high pressure sodium. Mercury vapor lamps may be used in 175 -400 watt metal halide fixtures- For availability of 220/240V, 5CHz ballast consult factory. 15" (TS15) Y Reflector Assembly 24" (TS24) Spun aluminum stucco reflector provides a uniform symmetrical wide beam distribution. Suggested Applicatons Corridors, lobbies, Stores, banks, showrooms, conference rooms, and applications where ceiling does not permit recessed lighting. Unit Wattage Photometrics Mounting Lamp Style Voltage Ballast Style Options TS -15 2 5 8 H 120 H co Surface Square TS15/TS24 0-70 5 wide Beam 8- Surface Mount H Metal Halide 120 H High Power CO Corning #73 1 100 LS High Pressure 208 Factor LX Drop Lexalite 2 150 Sodium 240 KSH Triumph 1 3 175 277 (TS24 only) 4-250 480 KSH -2 Triumph II 6-400 Accessories 4MT (120, 208, (TS 15 only) 200 20OPS SIF 240,277V) 320 320PS SIF Single Inline Fuse 350 350P5 DIF Double Inline Fuse 400 40OPS EM Emergency Quartz Relay and Socket (consult factory) EM60 Emergency Quartz Delay Relay and Socket (consult factory) QS Quartz Socket Only (aux. power required, consult factory) DP Damp Location TP Tamper Resistant Screws CSA Certification consult factory. POS Position Oriented Socket North Star Lighting 21 50 Parkes Drive RO. Box 6038 Broadview, Illinois 60155 -6038 708 681 -4330 Fax 708-681-4006 www- nslights.com Surface Squares (TS15, TS24) Photometrics aas ZONAL LUMEN SUP-MARY Number: TS24- 658H -CO ZONE LUMENS °6LAMP %FIXT Lamp. Phosphor Coated Metal Halide k� l 0 -W 280.9 26.1 41.2 0 A0 404.4 40'4 &3'9 Reflector: Pyramidal patterned surface Cho 5726 57a 90.4 090 6332 63.3 1000 9 -Iso 0.6 0.0 0.0 reflector; flat prismatic door glass G So 633.3 63.3 100-0 Efficiency: 63.3% CIE Type: Direct deg. 90'• COEFFICIENTS OF UTILIZATION- ZONAL CAVITY METHOD Luminaire Spacing Criteria. 1.1 0 Deg, y ih 80 70 _50 30 _10 0 1.2 90 Deg. 70 50 39 10 70 50 30 10 50 30 10 50 30 10 50 30 10 0 90 deg. v Candela Lumen values are based on 1,000 0 75 75 78 75 74 74 7a Y4 70 70 ]a 6] 57 67 65 65 65 p 1 71 ,6 65 65 69 87 656 63 64 63 62 82 61 60 60 59 58 57 lamp lumens. For other lamp lumen ratings, 2 6, 82 59 56 65 61 58 50 59 57 55 57 55 53 55 54 52 51 f_ 3 62 57 53 50 61 66 52 49 54 51 49 63 50 45 61 49 47 46 multiply candela and lumen values by the 4 58 52 48 45 57 51 47 44 50 46 44 49 46 43 47 45 43 42 5 54 46 43 40 53 47 43 40 46 42 39 45 41 39 44 41 39 37 number: Lumens divided by 1,000, 6 51 44 39 36 50 43 39 36 42 38 35 41 38 35 40 37 35 34 00 7 47 40 35 32 cB 4o 35 32 39 35 52 38 34 32 37 34 31 30 8 44 37 32 29 43 36 32 29 33 02 29 35 31 29 34 31 28 27 Per 1,000 Lamp Lumens 9 41 34 29 26 40 51 29 26 03 29 26 32 28 26 31 28 26 25 10 38 31 27 24 38 31 26 24 30 26 23 30 26 23 29 26 23 22 Mr........ GANaQIA.._,...LU.ME..N$ 0.0 9o,0 0 326.0 3R6.o 5 3250 328.0 31.0 15 313.0 335.0 92.0 25 277.0 310.0 137.0 35 201.0 232,0 144.0 45 117,0 133,0 106.0 55 59.0 67.0 6210 65 33.0 30.0 34.0 75 19.0 IB,o 20.0 05 6.0 5,0 7.0 90 0,0 0.0 J-333 ZONAL WHEN SUMMARY Lamp: Number: T515- 158H -CO Lamp: Phosphor Coated Metal Halide ZONE LUMENS %LAMP %FIXT 0.30 262.0 25.2 38.4 ,•40 400.0 4DO 6D9 Reflector: Specular hammertone interior 0.60 586.0 58.6 89.3 o•90 6570 65.7 10o,D reflector with truncated pyramid 9D-16o 0.0 0.0 00 0 -Itl0 657.0 65.7 100.0 shape, clear flat prismatic cover .`es glass in metal door frame, COEFFICIENTS OF UTILIZATION ZONALCAVITV METHOD prisms out 0 deg, 901 80 70 5o 30 10 0 p 70 SO 30 10 7o 5D 30 10 50 30 10 50 30 10 60 30 10 0 Efficiency: 65.7% 90 deg. CIE Type. Direct 0 76 70 78 76 76 76 76 76 73 73 73 70 70 70 87 61 67 68 73 70 68 66 71 69 66 64 86 54 62 83 62 61 61 60 59 57 Luminaire Spacing Criteria. 1.2 0 Deg. 2 67 63 69 55 66 61 58 55 59 56 54 67 55 53 55 53 51 50 1.2 90 De 3 62 s6 52 48 61 55 51 47 53 50 47 52 49 46 50 47 45 44 4 58 51 46 42 56 50 45 4P 46 44 41 47 43 41 46 42 40 39 53 46 41 37 52 45 40 37 44 40 38 43 39 36 42 39 36 34 6 50 42 37 33 49 41 38 33 40 36 33 39 35 32 38 35 32 31 Candela Lumen values are based on 1,000 7 46 38 33 30 45 35 33 30 37 33 29 3e 32 29 35 32 29 26 6 43 35 30 27 43 35 30 Z7 34 30 27 33 29 26 33 29 26 25 lamp lumens, For other lamp lumen ratings, 9 41 33 20 24 40 32 75 24 32 27 24 31 27 24 30 27 24 23 10 38 30 26 22 30 30 25 22 29 25 22 29 25 22 26 25 22 21 multiply candela and lumen values by the number: Lumens divided by 1,000. Per 1,000 Lamp Lumens RErI S ...,,.._cANML&.....- LUMEN 0.0 90.0 0 333.0 333.0 5 331.0 330.0 31.0 15 314,0 $13.0 89.0 25 286.0 287.0 132.0 3s 237.0 240.0 147.0 45 147,0 157,0 116.0 55 60.0 80.0 71.0 65 37.0 41.0 40.0 75 21.0 21,0 23.0 H 85 B.0 6,0 8.0 9D 0.0 0.0 North Star Lighting a 2150 Parkes Drive R0. Box 6038 Broadview, Illinois 60155 -6038 708-681-4330 Fax 708-681-4006 www n5lights.com MGM Surface Squares (TS15, TS24) fay, ZONAL, lOMENSNMMAAY Catalog Number: TS24- 65SH -KSH l ZONE L0M5Ng %L4MP °.:Fl%T p' p Lam Phosphor Coated Metal Halide y 263 0_30 259.0 216.9 41.3 Y `y I 0 0 364.0 30.4 58.0 Reflector: Pyramidal patterned surface 0.60 47x.0 47.8 76.2 175 0_90 608.0 60.6 96.9 reflector; pyramidal shaped \1`�` I 90 -130 19.0 1.9 3.1 o-,ao 647.0 62.7 100.0 prismatic drop lens X 87 Efficiency: 62.7% 0deg, 99- CIE Type: Direct COEFFICIENTS OF UTILIZATION- ZONAL CAVITY METHOD Luminaire Spacing Criteria: 1.0 0 Deg. f 80 70 50 30 10 0 11 90 Deg. 70 50 30 10 70 50 30 10 50 30 10 50 30 10 60 30 10 0 90 deg. \60" 0 ]4 74 14 74 72 72 72 72 09 59 e9 65 65 65 62 62 62 01 Candela Lumen values are based on 1,000 1 as 65 63 Sd 88 84 81 59 81 59 57 58 56 55 55 54 53 51 2 63 50 55 51 61 57 54 51 55 52 59 57 50 48 5o 48 46 45 lamp lumens. For other lamp lumen ratings, 3 59 53 48 45 57 52 48 44 50 46 43 48 45 42 46 44 41 40 4 55 49 44 40 53 48 43 40 40 42 39 44 41 38 43 40 38 38 multiply candela and lumen values by the 5 51 44 40 36 50 44 39 36 42 35 35 41 37 35 40 37 34 33 number: Lumens divided b 1,000. 6 4 9 41 38 33 47 40 35 33 39 35 32 38 35 32 37 34 31 30 y 0. 7 45 38 33 30 44 37 33 30 35 32 29 35 32 29 34 3, 29 26 3 43 35 51 27 42 35 30 27 34 30 27 33 29 27 32 29 27 25 Per 1,000 Lamp Lumens 9 40 33 2 25 39 32 28 25 31 2B 25 31 27 25 30 27 24 23 10 38 31 26 23 37 30 28 23 29 26 23 29 25 23 28 25 23 22 a,o so.o 0 339.0 339.0 S 340.0 343.0 33.0 ,5 327.0 35010 96.0 25 245.0 2820 130.0 35 142.0 183.0 105.0 45 7$.0 100.0 65.0 55 a0 .a 63.0 49.0 65 49,0 57.0 50.0 75 46.0 5010 47,0 85 35.0 25.0 33.0 90 24.0 15.0 95 14.0 4.0 14.0 105 4.0 2.0 3.0 115 210 OA 2.0 125 0.0 0.0 1.0 135 0.0 0.0 0.0 North Star Lighting 2150 Parkes Drive P.O. Box 6038 Broadview, Illinois 60155 -6038 708- 681 -4330 Fax 708 -681 -4006 www,nslights.com i` Y MARTEL C O NSTRUCTIO N, INC. NINA OFFICE BWOBII OFFICE 1203 South Church Avenue 305 Highway 83 RECIPIENT OF 17909A71ONAL SUILOAMERICAAWARO Bozeman, MT 59715 -5801 Bigtork, MT 59911 1 N2ERAENTREPRENEURIAL SUCCESS AWARD (406) 586.8585 Fax (406) 586 -8646 (406) 837 -1063 Fax (406) 837 -1068 1996 2001 MCA COO RETEEXCELLE CE AWARO May 2, 2009 Prugh Lenon Architects, P.C, 27 East Main Street Bozeman, Montana $9715 Attention; Dick Prugh Re; Bozeman Intermodal Facility Bozeman, Montana 59715 Subject. COR 4 019 Reference; Add Exit Lighting, Closures Smoke Seal for Storage Dear Dick, As directed, we propose to provide all labor, materials, and equipment required to perform the above mentioned work. Our breakdown of the work is attached. Our quotation is based on our interpretations of of the instructions and scope of work identified in the request, specifications and /or drawings. If we have misinterpreted the request in any way (omissions, etc.), please advise us prior to processing this quotation into a formal Change Order. Otherwise, our interpretation shall stand as correct. We have been directed to proceed with the work per the instructions in the Change Order Request. We are requesting an Additive Change Order for the amount of Sa,251 Martel Construction, Inc. reserves the right to submit a request for any additional time and or cost for disruption, impacts, acceleration, delay, or suspension which cannot be determined at this time. If you have any questions, please call me at (406) 922 -5504. Sincerely, M L NSTRUCTION, I Ton artel It Q� G Enclosure(s) CC. File James Goehrung COB COMMERCIAL RESIDENTIAL INSTITUTIONAL INDUSTRIAL 54 9&1� 1 dD Tot1 Martel From: Don Stueck Sent: Tuesday, April 14,2009 11:11 AM To: 'jgoehrung @bozeman. net' Cc: Tony Martel Subject: Added Lights r James, the emergency lights will be shipped out of Atlanta tomorrow so we should have them on Thurs. Matzinger will start installing the nine added lights on Thursday and have everything complete by Friday evening. Matzinger will do this on a time and material basis with a guaranteed max of $5000. The lights are $240 each plus $260 freight. Adding conduit, wire and labor the total will not exceed $5,000 plus our fees. Don Stueck Commercial Project Manager Martel Construction, Inc. Phone: (406) 922 -5603 Fax: (406) 586 -8102 dstueck0mar,j loon t,com I i I I X MARTEL CONSTRUCTION, INC. MAIN OFFICE BIGFDRK OFFICE Vie_? 1203 South Church Avenue 305 Highway 3 RECIPIENT OF 1 NATIONAL BUILDAMERICAAWARD j y 9G0 042 SBA ENTREPRENEURIAL SUCCESS AWARO r7- w�. Bozeman, MT 59715 5$01 Biplork, M759911 1999 MONTANA FAMILY SUgINES50FTNEYEwRAWARO (406) 586 -8585 Fax (406) 586.8646 (406) 837.1063 Fax(406)837-1068 2001 MCA CONCRETE E%CELLENCEAWARD April 10, 2009 Mr. Bob Risk Chief Building Official Bozeman Building Dept. Re: Emergency lighting for Intermodal Facility Dear Bob, Per our agreement today, Martel Construction will guarantee that by Friday, April 17 at 4:30p.m. there will be temporary emergency lights on the 2 nd and 3rd levels of the Bozeman Intermodal Facility. We will work with your department and the fire department to identify where the code requires these lights and will at least get these temporary light in place. The emergency lights for this project are special order lights that are guaranteed to minus 40 below zero so it may take us some time to get the permanent lights ordered and here for installation but we will proceed timely to do so. We will require help from the fire department and you to locate the lights on the top level a� there aren't any walls to place them on. I'm sure we will find spots to make sure we are meeting your requirements even if they have to be hung off the light poles. Thank you for help in resolving this matter to allow the facility use on Mor)day for their grand opening. r Respectfully, q Don 5tueck Commercial Project Manager Martel Construction, Inc. to r Ig U J: COMMERCIAL RESIDENTIAL INSTITUTIONAL 4� INDUSTRIAL ied 1960 `e pS 4 l yp� x 4 vv J'+. Y'.i Yy N !e L t i h p i A` .V t �'t YJ� T !Vt,Gd r SJ �i'��•' h as e �7'Nti �Saa ��WT�'z�y r 1 6524 b� XF ary y/ ts4s a a s �2����` A�� "3'�r'��Y s Z g a` "�3�� 9 a.' v �A x> A• p� �c« t z s� r f�a.t'� 3 y I i tyk r v c r a<.. �Pa 7� Y v a r. i x ri7 �1 y,'t �=�y�. 1 t4W t�$ a t p R C r S'1� RfI.FT• ..i r h 1 s2' NBC I w •y'�t� 'r' a.< Y i+t'�y •!,F 7 Rq i. :r 5. r sz x e tr"' IN`'*"§Fy4a kS�:Mw�x' y�«yJ ,_nt .c a �ttr7ae xs z 1 W E ti�•t 1 f� y w B 'W" P SC�ti 1 gtC �r ckw'iE' R4aa a F k r 7 7jER r ��j y r�.,. t t^A Y rc, k"�;a•. c �fiL"s 6 @t' Lt 7 �r�x ro ;a `Sa ,ri'« •w �p age r r 'ya w okr^"� ���a of BRIMS ,.S d� R q r� .i., Pg� rZx y .?w�u`' 4� i°'"�G�r;..': �.f G' a �r a.f Ft" ���R�'* ,f r r t ;W3i" ='e T A ON Au, 5 0a g w a g 5 a'� pr �y'.`+' 'F� �`s i G I i t.,:.. ,4�e «.�y 1. n i'Ap F a �n 7 �t"�• s 't a F 0 p $1 F�'r S Pw4 x fi r s yn s "k v r w Trt.,. ^'^r""`t liT a dyx ,r A% •c. a 1� G�y'.�� t ti t a y 1 1 f M m a C it +•BF >,9rt p�'Cn��i.y. °'k4 5,"R'� •i'C S �T Xf B P h ta F) G 4; '�Zi' c r S:k�ffi0.'1a• 1� Y' 'i �M oCho' f�pPx'ir cFV� "*�F •�xz -~r �2 SaY� r W iY� �1������"w tae a rc ;�s p8¢1(y �y��+' rG� �.q p'Fg �u (y a �*'���n'"��'°��� pi ...y....y..L..w•�L.. ��t ���G}•i.A �S e r, .�.iC.i:?iY`/��H0.. b� 'dB.R �Sd. ,J is �.�...l �lt� A..G....i... a 4Je z .y ^F� i. rSr