Loading...
HomeMy WebLinkAboutFinal Change Orders No.'s 3, 5, 6, 8, 10, 14, 19 for Intermodal Facility.pdf Commission Memorandum REPORT TO: Honorable Mayor and City Commission FROM: James Goehrung, Director of Facility Services Chuck Winn, Assistant City Manager SUBJECT: Change Orders numbers – 3, 5, 6, 8, 10, 14, and 19 for the Bozeman Intermodal Facility MEETING DATE: November 16, 2009 AGENDA ITEM TYPE: Consent RECOMMENDATION: Authorize the City Manager to sign Change Orders for the Downtown Bozeman Intermodal Facility in the amount of $80,768.69. BACKGROUND: After the opening of the garage there were multiple change orders submitted by the construction manager that were under discussion with administrative staff. Staff has since had a number of meetings with the contractor and design professionals to determine which components of the change orders might be attributed to the contractor, the architect and which were the responsibility of the City. The total for the changes amounted to $91,841.25. The construction manager has agreed to cover a portion of the cost of these changes so the city’s billing is for $80,768.69 Change Order #003 – A portion of this change order was addressed back in April. The balance on this change addresses site related work. Cost of this change is $44,151.25. Change Order #005 – Is for additional structural steel associated with brick ledgers, and stair towers. The original request for this change was $15,825.62. The construction manager has agreed to cover $5,275.28 of the change, leaving a balance of $10,550.72. Change Order #006 – Is for the cost of the truncated cones and color change material required by the Americans With Disabilities act on all transitional points in the garage. The areas include all ramps leading from the entrances and elevators. The ramps were not shown on the original plan and were not called out during plan review. Staff caught the omission prior to the ramps being poured so the cost covers the panels and installation. Cost for the change is $9,072.00. The construction manger has agreed to cover $3,023.97, leaving a balance of $6,048.03. 23 Change Order #008 – Is for a modification of the rebar associated with the shear walls. These are the partial wall areas that surround the various deck levels. The added rebar and tie in costs were $8,320.00. The construction manager has agreed to cover $2,773.31, leaving a balance of $5,546.69. Change Order #010 – This change was for the installation of all the directional signage at the entrances to the garage and within the garage. The signage was purchased by the city and the contractor installed all the signage. The decision was made to have the contract install the signage because all of the post tension cables that run throughout the garage. Cost of the installation was $8,293.00. Change Order #014 – The original lights that were specified for the canopy entrances to the building on Black and Mendenhall were too tall for the application. If installed the original lights would have been within ½ inch of the canopy roof. The heat from the lamps would have compromised the rubber membrane material on the roof. The cost covers four light fixtures and includes a credit for the four fixtures that were not installed. Cost for the fixtures is $1,928.00. Change Order #019 – The items for this change include some life safety issues that were called out by the Building Department during the final walk through and inspection. The change includes adding additional exit lights and smoke seals on some storage room doors inside the garage. This change amounted to $4,251.00. FISCAL EFFECTS: The Parking Garage Construction Fund paid $37,069.66 of these change order amounts. The nature of the some of the site work in Change Order #003 was unanticipated street repairs surrounding the Garage that were paid from the Gas Tax Fund, in the amount of $37,651. The ADA repairs detailed in Change Order #006, in the amount of $6,048.03 were paid from the ADA Special Revenue Fund. ALTERNATIVES: As suggested by the City Commission. Attachments: Change Order Requests Change Order Resolution Report compiled on November 10, 2009 24 Page 1 of 2 COMMISSION RESOLUTION NO. 4215 A RESOLUTION OF THE CITY COMMISSION OF THE CITY OF BOZEMAN, MONTANA, APPROVING ALTERATION/MODIFICATION OF CONTRACT WITH MARTEL CONSTRUCTION, INC. , BOZEMAN, MONTANA. WHEREAS, the City Commission did, on the 16th day July of 2007, authorize award of the bid for the Construction of the Bozeman Intermodal Facility to Martel Construction, Inc., Bozeman, Montana; and WHEREAS, Section 7-5-4308, Montana Code Annotated, provides that any such alterations or modifications of the specifications and/or plans of the contract be made by resolution; and WHEREAS, it has become necessary in the prosecution of the work to make alterations or modifications to the specifications and/or plans of the contract. NOW, THEREFORE, BE IT RESOLVED by the City Commission of the City of Bozeman, Montana, that the proposed modifications and/or alterations to the contract between the City of Bozeman, a municipal corporation, and Martel Construction Inc., Bozeman, Montana, as contained in Change Orders: #003, #005, #006, #008, #010, #014 and #019, attached hereto, be and the same are hereby approved; and the City Manager is hereby authorized and directed to execute the contract change order for and on behalf of the City; and the City Clerk is authorized and directed to attest such signature. 25 Page 2 of 2 PASSED AND ADOPTED by the City Commission of the City of Bozeman, Montana, at a regular session thereof held on the th day of November, 2009. ___________________________________________ KAAREN JACOBSON Mayor ________________________________________ STACY ULMEN, CMC City Clerk APPROVED AS TO FORM: ____________________________________________ GREG SULLIVAN City Attorney 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 61 62 63 64 65 66 67 69 70 71 72 73 74 75 76 77 79 80 81 82 83 84 85 86 87 88 89 91 92 93 94 95 96