HomeMy WebLinkAboutChange Order 3 & 4, Landfill Addition, BN Builders1,
dowling I sandholm I architects
CHANGE ORDER
Project: Bozeman Landfill Addition
Great Northern Town Center
Helena, MT 59601
To Contractor: BN Builders, Inc
2066 Stadium Dr., Ste 102
Bozeman, MT 59715
The Contract is changed as follows:
Increase Contract Sum.
C.O. #3
Date: September 11, 2009
Owner
■
Architect
■
Architect's Project No: 08-263
Contractor ■
Field
❑
Contract Date: June 1, 2009
Other
❑
Contract For: General Construction
Reason for change:
Direction from building department to upgrade mechanical penetrations to fire rated damper (CP# 5002)
Owner directed change to re -configure locker room (CP# 5008 and CP#5012)
Owner and Architect request for snow stops at roof, and Owner request for heat tape outlet at eave (CP#5011)
Attachment(s):
CP# 5002
CP# 5008
CP# 5011
CP# 5012
Contract Sum Adiustment:
The original Contract Sum was $ 271,648.00
The net change by previously authorized Change Orders $ 29,612.97
The Contract Sum prior to this Change Order was $ 301,260.97
The Contract Sum will be increased by this Change Order by the amount of $ 3,919.12
The new Contract Sum including this Change Order will be $ 305,180.09
Contract Time Adiustment:
The Contract Time will be increased by zero 0 days.
The date of Substantial Completion as of the date of this Change Order therefore is: September 28, 2009
Not valid until signed by Architect, Contractor, and Owner.
Signatures:
Architect: Dowling Sandholm Architects
15 West 14'h Street —Suite 103
Helena, Mt 59601
Contractor: BN Builders, Inc
2066 Stadium Dr., Ste 102
Bozeman, MT 59715
Owner: City of Bozeman
P.O. Box 1230
Bozeman, MT 59771
By: Date: r�
Mike Wiseman
By: Date:
Scott Jay
B .OM'� Date• 6 s -05
Chris Kukulski
BNBuilders, Inc.
Tuesday, August 4, 2009
Mike Wiseman
Dowling Sandholm Architects
55 West 14th Street
Helena, MT 59601
RE: Change Proposal - CP# 5002
City of Bozeman Landfill Add. - 509004
Dear Mike Wiseman,
This letter is to request authorization to proceed with the following extra work:
CP Number: 5002
Description: Add (2) Smoke/Fire Dampers
Proposed Amt: $ 1,611.20
Days Requested: 0 days
Scope of Work (see attached for detailed cost summary):
Per comments made by the City of Bozeman during plan review, provide labor, equipment & materials to install .
(2) additional smoke/fire dampers between existing offices and new garage.
[please sign below and return a copy of this letter to indicate your acceptance of this extra work and approve the
price for this work. Additional costs may apply if authorization is received after.
BNBuilders has proceeded with this work per previous ROM approval (attached). This change proposal
represents the final price for this work.
BNBuilders has proceeded with this work based on owner approval via email (see attached) or verbal direction.
This change proposal represents the final price for this work.
Submitted by: Accepted by:. Date:
8_ -0 J_7 _:: 0
Scott Jay Mike Wiseman
BNBuilders, Inc Dowling Sandholm Architects
CHANGE PROPOSAL DETAIL BACKUP
Project #: 509004 CP # 5002
City of Bozeman Land
B N B 2143 Story Mill Road fill Add.
Bozeman, MT 59715
BNBuilders, Inc. Phone: 206-382-3443
Fax:206-382-3440
Contractor
Description
Amount
HVAC
1 520.00
BNBuilders Inc.
Overhead & Profit
$0.00
BNBuilders, Inc.
OH & Profit on Subcontractors
$91.20
Total. $1,611.20
I. 06/25/2009 08:35
4063880735
SUMMIT MECHANICAL
PAGE 02/02
All Generals
Summit Mechanical, ln6.
77 Elk Bugle Court
Belgrade, MT 59714
(406) 388-2064
(406) 388-0735
Re: Bozeman City Landfill Shop Addition ,Job #: 2905$
We are pleased to quote the above mentioned project as listed below.
bIVISION 22 - PLUMBING
220000 General Provisions fpr Plumbing Work
220200 Common Pipe Requirements and Pipe Fittings
220517 Piping Specialties
220523 Valves
220629 Supports, Anchors, end Bases
220700 Pipe Insulation
221116 Domestic Water System
221316 Waste, Vent and Drain Piping Systems
224000 Plumbing Fixtures and Trim
PRICE INCLUDES: .
Permit
Test & Balance
ALL OF THE A,BOYt, HEATING FOR THE SUM OF:
ALTERNATE #I:
OPTION: Add (2) Smoke/Fire Dampers
)PRICE EXCLUDES:
Outside Utillties
Electrical
Bond
1% Tax
RESPECTFULLY SURMITT)ID BIr:
DATE: June 25, 2009
DMSION 23 HVAC
230000 General Provisions for HVAC Work
230770' Duct Insulation
233113 Ductwork and Accessories
23372p•Fans
234500 Furnaces and Condensing Units
236613 Gas Fired Unit Heaters
2382$8 Terminal Units
ADD $ 7,D62.00
ADD �1,520.00
BNBuilders, Inc.
Wednesday, August 12, 2009
Mike Wiseman
Dowling Sandholm Architects
55 West 14th Street
Helena, MT 59601
RE: Change Proposal - CP# 5008
City of Bozeman Landfill Add. - 509004
Dear Mike Wiseman,
This letter is to request authorization to proceed with the following extra work:
CP Number:
5008
Description:
Locker Room Wall Revisions per SKI-1
Proposed Amt:
$ 677.60
Days Requested:
0 days
Scope of Work (see attached for detailed cost summary):
Provide labor, equipment & materials to make locker room wall revisions per SKI-1.
Please sign below and return a copy of this letter to Indicate your acceptance of this extra work and approve the
price for this work. Additional costs may apply if authorization is received after .
(] BNBuilders has proceeded with this work per previous ROM approval (attached). This change proposal
represents the final price for this work.
BNBuilders has proceeded with this work based on owner approval via email (see attached) or verbal direction.
This change proposal represents the final price for this work.
Sub ed by: Accepted, by: Date:
7
g- / Z t—� `T �—
Sco >ay Mike Wiseman
BNBuilders, Inc Dowling Sandholm Architects
CHANGE PROPOSAL DETAIL BACKUP
Project #: 509004 CP # 5008
.City of Bozeman Landfill Add. N B
2143 Story Mill Road
Bozeman, MT 59715
BNBuilders, Inc. Phone: 206-382-3443
Fax: 206-382-3440
Contractor
Description
Amount
Superintendent
$450.00
All Materials
1155.00
BNBuilders Inc.
Overhead & Profit
$72.60
BNBuilders, Inc.
OH & Profit on Subcontractors
$0.00
Total: $677.60
ink rk
BNBuilders, Inc.
Wednesday, September 2, 2009
Mike Wiseman
Dowling Sandholm Architects
55 West 14th Street
Helena, MT 59601
RE: Change Proposal - CP# 5011
City of Bozeman Landfill Add. - 509004
Dear Mike Wiseman,
This letter is to request authorization to proceed with the following extra work:
CP Number: 5011
Description: Additional Snow cleats & Outlet for heat tape
Proposed Amt: $ 1,370.62
Days Requested: 0 days
Scope of Work (see attached for detailed cost summary):
Provide labor, equipment & material to install snow cleats along with weatherproof outlet for heat tape as .
indicated on RFP #2.
❑ Please sign below and return a copy of this letter to indicate your acceptance of this extra work and approve the
price for this work. Additional costs may apply If authorization is received after.
[� BNBuilders has proceeded with this work per previous ROM approval (attached). This change proposal
represents the final price for this work.
[] BNBuilders has proceeded with this work based on owner approval via email (see attached) or verbal direction.
This change proposal represents the final price for this work.
;Sup,,d by: Accepted by: Date:
cottJy Mike Wiseman
BNBuilders, Inc Dowling Sandholm Architects
MATZINGER ELECTRIC, INC.
907 Bridger Drive
Bozeman, MT 59715
Phone: (406) 587-7290
Fax: (406) 587-7298
Proposal
9/2/2009
TO:
BNBullders
Gaines Hall Bldg, on 11 th and Grant St
Room #108
Bozeman, MT 59715
JOB: City Landfill Shops
Project: Heat Tape Outlet.
Change Order Number: 1000014418
WORK DESCRIPTION: Add a new duplex receptacle to the City Landfill Shops for the addition of heat
tape.
The total amount of this Proposal is: $247.00
Sincerely,
Jeff Matzinger
Matzinger Electric
H7,
L
dowling I sandhotm I architects
REQUEST FOR PROPOSAL
Date: August 26, 2009
Project: City of Bozeman
Landfill Shop Addition
Bozeman, MT 59715
RFP #02
Job Number: #08-263
Issued To: Scott Jay
BN Builders
2066 Stadium Dr., Ste 102
Bozeman, MT 59715
The Contractor shall submit an itemized proposal for changes in the Contract Sum and Contract Time for the
proposed modifications to the Contract Documents as described herein. The Contractor shall submit
Itemized and detailed information within ten (10) days, or notify the Architect, in writing, of the anticipated
submission date.
This is not a Change Order, a Construction Change Directive, nor a Notice to Proceed.
Description of Work:
Item 02.1:
Please provide a cost to supply and install snow fencing or snow cleats at the areas indicated on sheet SK2-
1
Item 02.2:
Please provide a cost to supply and install a weatherproof outlet for heat tape at the location indicated on
sheet SK2-1. Please notify if an alternate location would be more appropriate.
Attachments:
Drawing SK2-1
Requested By:
Dowling Sandholm Architects
End of Request for Proposal
By: Date: 8/26/09
Michael Wiseman
CHANGE PROPOSAL DETAIL BACKUP
Project #: 509004 CP # 5011
City of Bozeman landfill Add.
B N B 2143 Story Mill Road
Bozeman, MT 59715
BNBuilders, Inc. Prone: 206-382-3443
Fax: 206-382-3440
Contractor
Description
Amount
Furnish/Install weatherproof outlet
$247.00
Snow Cleats $15/Each
$300.00
Snow Cleat Install
$690.00
BNBuilders Inc.
Overhead & Profit
$118.80
BNBuilders, Inc.
OH & Profit on Subcontractors
$14.82
Total: $1,370.62
dwfto Wndhulm wohlW3, P.C. CCPYRjGHTWW
I...
�w
7.
I
z
wp
m...
0.
L..
I
10
$ : .... .... l
a -I
I
z .. i ...
p
I
,...
-i
-...,...._........_................ ......................._,...., ....._.....,.........._...,._..... ............,........_....._._.._..._.......L_...
p.._
... ....
. ...........__......._._......__.....__.._._......................_....-........._....._............_............._...L........
Z
_._...... ._
_ ...--... .. ._.. :::C:".
-
i
1
I
:.
m
....r__ ... ...... _ ..:..
_..
.. __:.. ..._.._ . ._ _. .......... .._._ ....._... ...... ._.. .. .._...
0
p
_ ..
0
I
0
y
........... _...._._....._..............._....__._..__............_..._......_....... ... ....... ..............__........_......._ ..._. ...
_- I_...:.
`
m
I .-
z
.
_.. m
0
.............-......._......:_................. _..........----.:............. _..__...._..__......._........ _.._...... _... _. __...__: �......._ .....1:.........
0
....__..__._ .. _
i..
... _.. _..
...
I'..'.
.... _......... _. -- ...----._ ..-MATCH EXIST
-
h
IIII III4II�IIII II itl i �I'I i �Il'o �I I �l�IIIIlI II��� J���+
...:.:.::::......._[:........_:.....:..::......:.:.::.-..:..::.::.::..:.:.._._:.:..:::..::::::_:...._....:.:.:..........::.:__e_::.:..........::::...-.[:..::c:......
[.....::1.:.:.....
. __.._..._._......_._..-- .....
>..
_ ... .
I
i
�........
::........ _..._....__..._.__..__........._.........._.._........._._
.............................._...........
...........
Z
CT
mz
'_
n
D
9
N
N -�
O z
CJ
_
.l1
�I_1 o
I
4
In
BID DOCUMENTS
`^
4o V+
3
_
Q REV CE6C
S A
B -
C
GATE
-
dowling I sandhoim I architects
2Ud2Si�dinm Dr. ' 2Dv7cnuin Mf57715
•IM i36a113+J06536.114 fuC+o'inr.dv�rtlngrandlivhn.cam
CITY LANDFILL SHOPS
2143 STORY MILL RO
BOZE:MAN. MT SMS
PROAECTM OSA•08-203
B N B
ON Builders, Inc.
Wednesday, September 2, 2009
Mike Wiseman
Dowling Sandholm Architects
55 West 14th Street
Helena, MT 59601
RE: Change Proposal - CP# 5012
City of Bozeman Landfill Add. - 509004
Dear Mike Wiseman,
This letter is to request authorization to proceed with the following extra work:
CP Number: 5012
Description: Electrical Changes Due to Locker Room Revision
Proposed Amt: ..$-�93.5
Days Requested: 0 days
Scope of Work (see attached for detailed cost summary):
Provide labor, equipment & materials to add (1) type.H fixture along with wiring fan in IT closet due to
revisions made to locker room space.
❑ Please sign below and return a copy of this letter to indicate your acceptance of this extra work and approve the
price for this work. Additional costs may apply if authorization is received after .
❑ BNBuilders has proceeded with this work per previous ROM approval (attached). This change proposal
represents the final price for this work.
❑ BNBuilders has proceeded with this work based on owner approval via email (see attached) or verbal direction.
This change proposal represents the final price for this work.
Su 'tted by:
,A--:��- L-1, q-;z-o-,
ott Jay
BNBuilders, Inc
Accepted by:
Mike Wiseman
Dowling Sandholm Architects
Date:
CHANGE PROPOSAL DETAIL BACKUP
Project #: 509004 CP # 5012
City of Bozeman Landfill Add.
B N B 2143 Story Mill Road
Bozeman, MT 59715
BNBuilders, Inc. Phone: 206-382-3443
Fax: 206-382-3440
Contractor
Description
Amount
Electrical
. 0
BNBuilders Inc.
Overhead & Profit
$0.00
BNBuilders, Inc.
OH & Profit on Subcontractors
sd
vA50
14-15-`
Total:
� `' 4 ��
MATZINGER ELECTRIC, INC.
907 Bridger Drive
Bozeman, MT 59715
Phone: (406) 587-7290
Fax: (406) 587-7298
Proposal
9/2/2009
TO:
BN Builders
Gaines Hall Bldg. on 11th and Grant St
Room ##108
Bozeman, MT 59715
JOB: City Landfill Shops
Project: Expanded Locker Room Changes
Change Order Number: 1000014419
WORK DESCRIPTION: Add one Type "H" fixture as-vrreFl-es-a�'
f
The total amount of this Proposal is: � `' '"''r "f �fi��;o/
Sincerely,
Jeff Matzinger
Matzinger Electric
i NW. :.
0" oar Ko.4
l�!
BNBuiiders, Inc.
Friday, September 11, 2009
Mike Wiseman
Dowling Sandholm Architects
55 West 14th Street
Helena, MT 59601
RE: Change Proposal - CP# 5013
City of Bozeman Landfill Add. - 509004
Dear Mike Wiseman,
This letter is to request authorization to proceed with the following extra work:
CP Number: 5013
Description: Paint Sheet Rock at Westside of Existing Shop
Proposed Amt: $ 2,236.60
Days Requested: 0 days
Scope of Work (see attached for detailed cost summary):
Provide labor, equipment & material to prime/paint 2,125 square feet of sheetrock on west side of the existing
shop wall.
[� Please sign below and return a copy of this letter to indicate your acceptance of this extra work and approve the
price for this work. Additional costs may apply if authorization Is received after .
F1 BNBullders has proceeded with this work per previous ROM approval (attached). This change proposal
represents the final price for this work.
(] BNBuilders has proceeded with this work based on owner approval via email (see attached) or verbal direction.
This change proposal represents the final price for this work.
Submitted by: Accepted by: Date:
S��' p (- Q A'42' I '1 0 �—
ScottJay Mike Wiseman
BNBuilders, Inc Dowling Sandholm Architects
.i o, s- 0 q
CHANGE PROPOSAL DETAIL BACKUP
Project #: 509004 CP # 5013
City of Bozeman Landfill Add.
B N B 2143 Story Mill Road
Bozeman, MT 59715
BNBuilders, Inc. Phone: 206-382-3443
Fax: 206-382-3440
Contractor
Description
Amount
Painting & Coating
2 110.00
BNBuilders Inc.
Overhead & Profit
$0.00
BNBuilders, Inc.
OH & Profit on Subcontractors
$126.60
Total: $2,236.60
COMMISSION RESOLUTION NO.4210
A RESOLUTION OF THE CITY COMMISSION OF THE CITY OF BOZEMAN,
MONTANA, APPROVING ALTERATION/MODIFICATION OF CONTRACT
WITH BN BUILDERS, INC., BOZEMAN, MONTANA.
WHEREAS, the City Commission did, on the 27th day of May 2009, authorize award of the bid for
the Construction of the Bozeman Landfill Addition to BN Builders, Inc., Bozeman, Montana; and
WHEREAS, Section 7-5-4308, Montana Code Annotated, provides that any such alterations or
modifications of the specifications and/or plans of the contract be made by resolution; and
WHEREAS, it has become necessary in the prosecution of the work to make alterations or
modifications to the specifications and/or plans of the contract.
NOW, THEREFORE, BE IT RESOLVED by the City Commission of the City of Bozeman,
Montana, that the proposed modifications and/or alterations to the contract between the City of Bozeman, a
municipal corporation, and BN Builders, Inc., Bozeman, Montana, as contained in Change Order #3 and
Change Order #4, attached hereto, be and the same are hereby approved; and the City Manager is hereby
authorized and directed to execute the contract change order for and on behalf of the City; and the City Clerk
is authorized and directed to attest such signature.
PASSED AND ADOPTED by the City Commission of the City of Bozeman, Montana, at a regular
session thereof held on the 5th day of October, 2009. \
KAAREN JACOMbN
Mayor
Page 1 of 2
S
Clty'�rgllN CO •�ti0
APPROVED AS TO FORM:
GUVSMLIVAN
City Attorney
Page 2 of 2