HomeMy WebLinkAboutResolution 4210 Modification with BN Builders, Change Orders for Landfill AdditionCOMMISSION RESOLUTION N0.4210 A RESOLUTION OF THE CITY COMMISSION OF THE CITY OF BOZEMAN, MONTANA, APPROVING ALTERATION/MODIFICATION OF CONTRACT WITH BN BUILDERS, INC., BOZEMAN, MONTANA. WHEREAS, the City Commission did, on the 27th day of May 2009, authorize award of the bid for the Construction of the Bozeman Landfill Addition to BN Builders, Inc., Bozeman, Montana; and WHEREAS, Section 7-5-4308, Montana Code Annotated, provides that any such alterations or modifications of the specifications and/or plans of the contract be made by resolution; and WHEREAS, it has become necessary in the prosecution of the work to make alterations or modifications to the specifications and/or plans of the contract. NOW, THEREFORE, BE IT RESOLVED by the City Commission of the City of Bozeman, Montana, that the proposed modifications and/or alterations to the contract between the City of Bozeman, a municipal corporation, and BN Builders, Inc., Bozeman, Montana, as contained in Change Order #3 and Change Order #4, attached hereto, be and the same are hereby approved; and the City Manager is hereby authorized and directed to execute the contract change order for and on behalf of the City; and the City Clerk is authorized and directed to attest such signature. PASSED AND ADOPTED by the City Commission of the City of Bozeman, Montana, at a regular session thereof held on the 5th day of October, 2009. ~ ~'-~'~ KAAREN JACO N Mayor Page 1 of 2 ~` YO/J .~y~ ~ - ~ n ~ ~~ ~ .`~ „ t ~ =~ ~, .9. ~~ ~~. !., ..,, City'~TIN co ~1~~ . APPROVED AS TO FORM: ~~ ~ ~' ,- G~SLTLLIVAN City Attorney Page 2 of 2 ~( _ ~ i Bowling I sandholm I architects CFlANC;E OR®E~ Project: Bozeman Landfill Addition Great Northern Town Center Helena, MT 59601 To Contractor: BN Builders, Inc 2066 Stadium Dr., Ste 102 Bozeman, MT 59715 C.O. #3 Date: September 11, 2009 Owner ^ Architect ^ Architect's Project No: 08-263 Contractor ^ Field ^ Contract Date: June 1, 2009 Other ^ Contract For: General Construction i'he Contract is changed as follows: Increase Contract Sum. Reason for change: Direction from building department to upgrade mechanical penetrations to fire rated damper (CP# 5002) Owner directed change to re-configure locker room (CP# 5008 and CP#5012) Owner and Architect request for snow stops at roof, and Owner request for heat tape outlet at eave (CP#5011) Attachment(s): CP# 5002 CP# 5008 CP# 5011 CP# 5012 Contract Sum Adiustment~ The original Contract Sum was $ 2 The net change by previously authorized Change Orders $ 71 648.00 The Contract S i 29,612.97 um pr or to this Change Order was The Contract S ill b $ 301,260.97 um w e increased by this Change Order by the amount of $ 3 919 12 The new Contract Sum including this Change Order will be $ , . 305 180 09 Contract Time Adiustment~ The Contract Time will be increased by zero 0 days. The date of Substantial Completion as of the date of this Change Order therefore is: September 28 2009 Not valid until signed by Architect, Contractor, and Owner. Signatures: Architect: Dowling sandholm Architects 15 West 14'h Street -Suite 103 Helena, Mt 59601 Contractor: BN Builders, Inc 2066 Stadium Dr., Ste 102 Bozeman, MT 59715 Owner: City of Bozeman P.O. Box 1230 Bozeman, MT 59771 By:~~ Date: rl ~ Mike Wiseman By: Date: - ((- Oq Scott Jay ~.-1y~ By Date: 6 ~ s ~ Chris Kukulski BINIB BNBuilders, Inc. Tuesday, August 4, 2009 Mike Wiseman Dawling Sandholm Architects 55 West 14th Street Helena, MT 59601 RE: Change Proposal - CP# 5002 City of Bozeman Landfill Add. - 509004 Dear Mike Wiseman, This letter is to request authorization to proceed with the following extra work: CP Number: 5002 Description: Add (2) Smoke/Fire Dampers Proposed Amt: $ 1,611.20 Days Requested: 0 days Scope of Work (see attached for detailed cost summary); Per comments made by the City of Bozeman during plan review, provide labor, equipment & materials to install . (2) additional smoke/fire dampers between existing offices and new garage. Please sign below and return a copy of this letter to indicate your acceptance of this extra work and approve the price for this work. Additional costs may apply if authorization is received after . BNBuilders has proceeded with this work per previous ROM approval (attached). This change proposal represents the final price for this work. [~ BNBuilders has proceeded with this work based on owner approval via email (see attached) or verbal direction. This change proposal represents the final price for this work. Submitted by: 8-Y o9 ScoitJay BNBuilders, Inc Accepted by: Date: _~ ~ ~ o Mike Wiseman Dowling Sandholm Architects CHANGE PROPOSAL ®ETAIL BACKUP Project #: 509004 CP # 5002 Clty of Bozeman Landfill Add. 2143 Story Milt Road Bozeman, MT 59715 BNBuilders, Inc, phone: 206-382-3443 Fax: 206-382-3440 Contractor Description Amount HVAC 1 520.00 BNBuilders Inc. Overhead & Profit $0.00 BNBuilders, Inc. OH & Profit on Subcontractors $91.20 Totat: $1,611.20 ~' 05/25/2009 08:35 4063880735 SUMMIT MECHANICAL Summit Mechanical, Irr~, 77 Elk Bugle Court Belgrade, MT 59714 (406) 38$-2064 (406) 388-p735 All Generals Re: Bozeman City Landfill Shop Addition We are pleased to quota the above mentioned project as Ilsted below. b~VISI(aN 22 - ~''~UMSZ1tiTG 220000 General Provisions fpr Plumbing Work 220200 Common Pipe Requirements and ripe Fiftings 220517 Piping Specialties 22D$23 Valves 220629 Supports, Anchors, and Bases 220700 Pipe Insulation 221176 DamestiG Water System 221316 Waste, Vent and Drain Piping Systems x24000 Plumbing Fixtures and Trim Permit Test & 8afance ALL OI' THE A,)BC>VE HE,A,'~'11VG f+OR ";i;FiE SLTt+v~ OF: AL'~>rJl~,iVATE ~~: O~~'zotV: Add (2) SmokelFire Dampers >PBrcE a~~G~,uDES: Outside Utilities Electrical Bond 1% TaX CiIESPEC')';FULLY SU~MITT'ED BI': Job #: 2906$ ~~ 23_-~ HVAC PAGE 02/02 230000 General Provisions for HVAC Work 2307710' Duct Insulation 233113 Ductwork End Accessories 2337xp~Fans 2345Up Furnaces and Condensing Units 235513 Gas Fired Unit Heaters 268239 Terminal Units . ..$ 29,520.00 ADD $ 7',J$2.00 ADD ~ $ 1,520:00 0~'TE' June 25, 2009 B~NiB BNBuilders, Inc. Wednesday, August 12, 2009 Mike Wiseman Dowling Sandholm Architects 55 West 14th Street Helena, MT 59601 RE: Change Proposal - CP# 5008 City of Bozeman Landfill Add. - 509004 Dear Mike Wiseman, This letter is to request authorization to proceed with the following extra work: CP Nurnber: 5008 Description; Locker Room Wall Revisions per SKi-1 Proposed Amt: $ 677.60 Days Requested: 0 days Scope of Work (see attached for detailed cost summary): Provide labor, equipment & materials to make locker room wall revisions per SK1-1. Please sign below and return a copy of this letter to Indicate your acceptance of this extra work and approve the price for this work. Additional costs may apply if authorization is received after . ^ BNBuilders has proceeded with this work per previous ROM approval (attached). This change proposal represents the final price for this work. ^ BNBuilders has proceeded with this work based on owner approval via email (see attached) or verbal direction. This change proposal represents the final price for this work. Sub ed by: Accepted by: Date: 5c >ay Mike Wiseman BNBui/ders, Inc Dow/ing Sandholm Architects CHANGE PROPOSAL DE7'ATL BACKUP Project #: 509004 CP # 5008 .City of Bozeman Landfill Add. 2143 Story Mill Road Bozeman, MT 59715 BNBuilders, Inc. phone: 206-382-3443 Fax; 206-362-3440 Contractor Description Amount Superintendent $450.00 All Materials 155.00 BNBuilders Inc. Overhead & Profit 72.60 BNBuilders, Inc. OH & Profit on Subcontractors ~ $0.00 Total: $677.60 BINIB BNBuildersy Inc. Wednesday, September 2, 2009 Mike Wiseman Dowling Sandl~olm Architects 55 West 14th Street Helena, MT 59601 RE; Change Proposal - CP# 501]. City of Bozeman Landfill Add. - 509004 Dear Mike Wiseman, This letter is to request authorization to proceed with the following extra work: CP Number: 5011 Description: Additional Snow cleats & Outlet for heat tape Proposed Amt: $ 1,370.62 Days Requested: 0 days Scope of Work (see attached for detailed cost summary): Provide labor, equipment & material to install snow cleats along with weatherproof outlet for Feat tape as . indicated on RFP #2. ^ Please sign below and return a copy of this letter to indicate your acceptance of this extra work and approve the price for this work. Additional costs may apply if authorization is received after . ^ BNBuilders has proceeded with this work per previous ROM approval (attached). This change proposal represents the final price for this work. ^ BNBuilders has proceeded with this work based on owner approval via email (see attached) or verbal direction. This change proposal represents the final price for this work. Su nl ed by: Accepted by: Date: ~'•Z aR _ ~I G cottJay l~9ike Wiseman BNBuilders, Inc Dow/ing Sandholm Architects MATZINGER ELECTRIC, INC. 907 Bridger Drive Bozeman, MT 59715 Phone: (406) 587-7290 Fax: (406) 587-7298 P!'©~'JOSaI 9/2/2009 TO: BNBuflders Gaines Hall Bldy. on 11 tl~ and Grant St Room #108 Bozeman, MT 59715 JOB: City Landfill Shops Project: Heat Tape Outlet. Change Order Number: 1000014418 WORFC DESCRIPTION: Add a new duplex receptacle to the City Landfill Shops for the addition of heat tape. The total amount of this Proposal is: $247.00 Sincerely, Jeff Matzinger Matzinger Electric ~~~ Bowling I sandhntm 1 architects REQUEST FOR PROPOSAL Date: August 26, 2009 Job Number: #08-263 RFP #02 Project: City of Bozeman Landfill Shop Addition Bozeman, MT 59715 Issued To: .Scott Jay BN Builders 2066 Stadium Dr., Ste 102 Bozeman, MT 59715 The Contractor shall submit an itemized proposal for changes in the Contract Sum and Contract Time for the proposed modifications to the Contract Documents as described herein. The Contractor shall submit itemized and detailed information within ten ('10) days, or notify the Architect, in writing, of the anticipated submission date. This is not a Change Order, a Construction Change Directive, nor a Notice to Proceed. Description of Work: Item 02.1: Please provide a cast to supply and install snow fencing or snow cleats at the areas indicated on sheet SK2- 1 Item 02.2: Please provide a cost to supply and install a weatherproof outlet for heat tape at the location indicated on sheet SIt2-1. Please notify if an alternate location would be more appropriate. Attachments: Drawing SK2-1 Requested By: Dowling Sandliolm Architects By: Date: 8/26/09 Michael Wiseman End of Request for Proposal CF~AIVGE PROPOSAL DETAIL BACKUP Project #: 509004 CP # 5011 City of Bozeman Landfill Add. 2143 Story Mifl Road Bozeman, MT 59715 BNBuilders, Inc. phone: 206-38Z-3443 Fax: 206-382-3440 C011traCtOr Description Amount Furnish/Install weatherproof outlet $247.00 Snow Cleats $15/Each $300.00 Snow Cleat Install 690.D0 BNBuilders Inc. Overhead & Profit 118.80 BNBuilders, Inc. OH & Profit on Subcontractors $14.82 Total: $1,370.62 dwnno andnaun nr~neaas P.c. ccPv ~_ ~ w O II O ""I nQ D r~- Q o `\ IT v I aM ~i 2 mT Z A rn 0 A N BID DOCUMENTS m ~^ B REV 7 V, S~ A o N ~ B co ~ S o C N N A G _.._._.._..~.._ D OQ ~ r" 4 v~ o m OE6C OgTE CITY LANDFILL SHOPS L~_,-L Bowling I sandholm I architects e~ozEnn~NYjvIMI98RD 2Ud1 Siadinm Dr. Suim 2 Oounw. hTf 39715 PROJECT N. 0.9g0B~10] ~IUG 5360111 ~~ JUG SS6d111J fu<+~+~~n~'.don1inesand~wln~.co~n BiNB BNBuilders, Inc. Wednesday, September 2, 2009 Mike Wiseman Dowling Sandholm Architects 55 West 14th Street Helena, MT 59601 RE: Change Proposal - CP# 5012 City of Bozeman Landfill Add. - 509004 Rear Mike Wiseman, This letter is to request authorization to proceed with the following extra work: CP Number: 5012 Description: Electrical Changes Due to Locker Room Revision Proposed Amt: ~$~9~:56-" Z~jq.1i Days Requested: 0 days Scope of Work (see attached for detailed cost summary): Provide labor, equipment & materials to add (1) type.H fixture along with wiring fan in IT closet due to revisions made to locker room space. ^ Please sign below and return a copy of this letter to indicate your acceptance of this extra work and approve the price for this work. Additional costs may apply if authorization is received after . ^ BNBuilders has proceeded with this work per previous ROM app'rovai (attached). This change proposal represents the final price for this work. ^ BNBuilders has proceeded with this work based on owner approval via email (see attached) or verbal direction. This change proposal represents the final price for this work. Su ~tted by: -O°t ott Jay BNBuilders, Inc Accepted by: Date: Mike Wiseman Dowling Sandholm Architects CHANGE PROPOSAL DETAIL BACKUP Project #: 509004 CP # 5012 g N g 2143 Story Mill Road ~'i Add. Bozeman, MT 59715 BNBuilders, Inc. phone: 206-382-3443 Fax: 206-382-3440 Contractor Description Amount Electrical p BNBuilders Inc. Overhead & Profit $0.00 BNBuilders, Inc. OH & Profit on Subcontractors ~' Z.HS °o t"~•~~ Total: ~~~93;50 R~~~~ MATZINGER ELECTRIC, INC. 907 Bridger Drive Bozeman, MT 59715 Phone: (406) 587-7290 Fax: (406) 587-7298 Pd'4~JJ©Sa~ 9/2/2009 TO: BN Builders Gaines Hall Bldg. on 11th and Grant St Room #108 Bozeman, MT 59715 JOB: City Landfill Shops Project: Expanded Locker Room Chan es Change Order Number: 1000014419 WORK DESCRIPTION: Add one Type "H" fixture as-weFl-es-a~-ie-P~vr~/@at~i~setr--- o~ The total amount of this Proposal is: ~~ 2 Sincerely, Jeff Matzinger Matzinger Electric 0 BNBuilders, Inc. Friday, September 11, 2009 Mike Wiseman Dowling Sandholrn Architects 55 West 14th Street Helena, MT 59601 RE: Change Proposal - CP# 5013 City of Bozeman Landfill Add. - 509004 Dear Mike Wiseman, This letter is to request authorization to proceed with the following extra work: CP Number: 50f3 Description: Paint Sheet Rock at Westside of Existing Shop Proposed Amt: $ 2,236.60 Days Requested: 0 days Scope of Wo-•k (see attached for detailed cost summary): Provide labor, equipment & material to prime/paint 2,125 square feet of sheetrock on west side of the existing shop wall. ^ Please sign below and return a copy of this letter to indicate your acceptance of this extra work and approve the price for this work. Additional costs may apply if authorization is received after . ^ BNBuilders has proceeded with this work per previous ROM approval (attached). This change proposal represents the final price for this work. ^ BNBuilders has proceeded with this work based on owner approval via email (see attached) or verbal direction. This change proposal represents the final price for this work. Submitted by: Accepted by: Date: ScoitJay Mike Wiseman BNBuilders, fnc Dowling Sandhoim A~chifects L ~ C ~-~ M a-h A9~.r 10- S`~q C&iANGE PROPOSAL OE~'AYL BACKUP Project #: 509004 CP # 501.3 City of Bozeman Landfill Add. 2143 Story Mill Road EBozeman, MT 59715 BNBuilders, Inc. phone: 206-382-3443 Fax: 206-382-3440 contractor Description Amount Palntin & Coatin 2 110.00 BNBuilders Inc. Overhead & Profit $0.00 BNBuilders, Inc. OH & Profit on Subcontractors $126.60 Total: $2,236.60 F.O. BOX 1 1028 BOZEMAN~ MT 58719 P H oN E/FAX: 586-8484 CELL: 580-5271 WWW.PEAKPAI NTl NGMT.COM JAMES@PEAKPAINTINGMT.COM ~~tl B~'ic~~@ Page I of 1