Loading...
HomeMy WebLinkAboutResolution 4200 Alteration with Trapper Peak Co. (C.O. 2) COMMISSION RESOLUTION N0.4200 A RESOLUTION OF THE CITY COMMISSION OF THE CITY OF BOZEMAN, MONTANA, APPROVING ALTERATION/MODIFICATION OF CONTRACT WITH TRAPPER PEAK CONSTRUCTION INC., WILLOW CREEK, MONTANA. WHEREAS, the City Commission did, on the 11th day of November 2008, authorize award of the bid for the Landfill Final Closure project, to Trapper Peak Construction, Inc., Willow Creek, Montana; and WHEREAS, Section 7-5-4308, Montana Code Annotated, provides that any such alterations or modifications of the specifications andlor plans of the contract be made by resolution; and WHEREAS, it has become necessary in the prosecution of the work to make alterations or modifications to the specifications and/or plans of the contract. NOW, THEREFORE, BE IT RESOLVED by the City Commission of the City of Bozeman, • Montana, that the proposed modifications andlor alterations to the contract between the City of Bozeman, a municipal corporation, and, Trapper Peak Construction Inc., as contained in Change Order No. 2, attached hereto, be and the same are hereby approved; and the City Manager is hereby authorized and directed to execute the contract change order for and on behalf of the City; and the City Clerk is authorized and directed to attest such signature. PASSED AND ADOPTED by the City Commission of the City of Bozeman, Montana, at a regular • session thereof held on the 31st day of August 2009. nn,nn~ G~/~- Kaaren Jacobson, yor ATTEST: S acy~ en City C rk APPROVED AS TO FORM: Gr Sullivan Ci Attorney CHANGE ORDER No. 2 DATE OF ISSUANCE August 10, 2009 EFFECTIVE DATE OWNER City of Bozeman CONTRACTOR Trapper Peak Construction, Inc. Contract: City of Bozeman Landfill Phase 2 Closure Project Project: City of Bozeman Landfill Phase 2 Closure Project OWNER's Contract No. ENGINEER Great West En ing Bering ENGINEER's Contract No. 2-85-00069 You are directed to make the following changes in the Contract Documents: Description: Hand picking the litter from the compost provided by the City. Payment will be made based on personnel hours and use of a recovery cart and ATV. The cost for this item is $1,500 and requires 2 additional contract days. Placement of additional soil along the east side of the landfill to eliminate the old access road as requested by City. The cost for this item is $3,500 and required an additional 2 contract days. Reclamation of the City's borrow area including 6" of topsoil, seeding, fertilizing, and erosion control. Also included in this item is the aesthetic landscaping features including softening the slope face on the south boundary of the current borrow area as requested by the City. The cost for this item is $47,600 with an additional 30 contract days required. Fill of the rill on the Class IV area as requested by the City. The cost for this item is $1,500 with one day of additional contract time required. Reason for Change Order: Additional soil placed along the east side of the landfill, the reclamation of the City's borrow area, and the fill of the Class IV rill are all additional work items requested by the City. The hand picking of the waste from the compost provided by the City is required to meet closure certifications. Attachments: (List documents supporting change) Project Update letter to Dustin Johnson CHANGE IN CONTRACT PRICE: Original Contract Price $ 304,600 Net Increase FBec~eftse3 from previous Change Orders No. 1 to 1 $ 57,130 Contract Price prior to this Change Order: $ 361,730 Net increase (~ee~ease~ of this Change Order: $ 54,100 Contract Price with all approved Change Orders: $ 415,830 CHANGE IN CONTRACT TIMES: Original Contract Times: Substantial Completion: 105 calendar days Ready for final payment: da s or dates Net change from previous Change Orders No. 1 to No. 1 Substantial Completion: 30 calendar days Ready for final payment: da s Contract Times prior to this Change Order: Substantial Completion: 135 calendar days Ready for final payment: da s or dates Net increase ({lesrease3 this Change Order: Substantial Completion: 35 calendar days Ready for final payment: (days) Contract Times with all approved Change Orders: Substantial Completion: 170 calendar dam Ready for final payment: (days or dates) Page 1 of 3 Contractor certifies and agrees that there are no additional costs or claims for extra work, additional time, delays or omitted items, of any nature whatsoever, associated with the subject change order items, except as identified and set forth herein and nless expressly stated otherwise in the Change Order. And further, that the price agreed-upon herein represent e 11 cost and value for the subject work performed and the materials supplied under the terms of the contract th t the work quantities and value were properly d termined and are correct. CONT O Authorized Signature) Date RECOMMENDED BY: AP ROVE B ~L~,`d~ ~ ~ ~ t~-o~ ~ (ENG EER -Signature) Date WNER (Authorized Signature) Date EJCDC 1910-8-B (1996 Edition Prepared by the Engineers Joint Contract Documents Committee and endorsed by The Associated General Contractors of America and the Construction Specifications Institute. Page 2 of 3 CHANGE ORDER INSTRUCTIONS A. GENERAL INFORMATION This document was developed to provide a uniform format for handling contract changes that affect Contract Price or Contract Times. Changes that have been initiated by a Work Change Directive must be incorporated into a subsequent Change Order if they affect Price or Times. Changes that affect Contract Price or Contract Times should be promptly covered by a Change Order. The practice of accumulating Change Orders to reduce the administrative burden may lead to unnecessary disputes. If Milestones have been listed in the Agreement, any effect of a Change Order thereon should be addressed. For supplemental instructions and minor changes not involving a change in the Contract Price or Contract Times, a Field Order should be used. B. COMPLETING THE CHANGE ORDER FORM Engineer normally initiates the form, including a description of the changes involved and attachments based upon documents and proposals submitted by Contractor, or requests from Owner, or both. Once Engineer has completed and signed the form, all copies should be sent to Owner or Contractor for approval, depending on whether the Change Order is a true order to the Contractor or the formalization of a negotiated agreement for a previously performed change. After approval by one contracting party, all copies should be sent to the other party for approval. Engineer should make distribution of executed copies after approval by both parties. If a change only applies to price or to times, cross out the part of the tabulation that does not apply. Page 3 of 3 HELENA {{{tYYY r j ' ~„~ , PO Box 4817 ^ 2501 Belt View Drive ~ `~ r,:r+l ~ ' ~ ~~~~'~ _~ ~, Helena, MT 59604 ~ `~ 406.449.8627 ^ Fax 406.449.8631 ~. s..{ ~,~~.~.~+~ ` _______.~_y~.,. _._w».~~.~. rat est, engineering August 7, 2009 Dustin Johnson City of Bozeman Engineering Department PO Box 1230 Bozeman, MT 59771 RE: City of Bozeman Landfill Closure- Project Status Update Dear Dustin: I conducted a inspection of the landfill closure project on August 3, 2009 and met on-site with Riley and Sheila Malone of Trapper Peak Construction as well as Steve Johnson and Shad Bare of the City. This letter summarizes my findings and recommendations. Main Landfill Area The ET layer has been placed over the entire closure area, tested and accepted by Great West. Trapper Peak has placed the topsoil and compost on most of the closure area except a small area west of the topdeck access road. Trapper Peak will blade the landfill closure area one more time in preparation for seeding, fertilizing and placement of the straw wattles. The seeding and straw wattles will not be completed until this fall so that the site can be seeded dormantly. The specifications call for fall seeding not to be conducted until after October 15th. We will monitor weather conditions and give Trapper Peak authorization to proceed with the seeding once conditions are appropriate. The compost provided by the City has a significant amount of waste in it. Trapper Peak has provided an estimate for hand picking the litter from the compost prior to seeding for $1,500. This has been enclosed in the attached ~u-~~~ change order. 115 N Broadway Suite 5()0 eiiur~gs, MT 5s~o1 Great West and the City previously approved the placement of additional soil 406.652.5000 Faxaos.2aa.1363 along the east side of the landfill to eliminate an old access road. The estimate of $3,500 was approved by Great West and the City and the work has been ~+~+ completed. This item is included in Change Order #2. 602 Ferguson Suite 1 Bozeman, MT5971$ 406.587.0504 Fax 40&.587.0541 F:\BOZEMAN-LF Consulting-99104\Correspondence\D_JohnsonProject update.doc G/ reatW~C engineering Other punchlist items for the main landfill area include extension of the well casings and leachate collection cleanouts and construction of the lysimeter. Soil Borrow Areas Reclamation of the borrow area utilized by Trapper Peak for this project and by Shumaker under the previous closure project is part of the contract and the City would like to have Trapper Peak proceed with this work. An additional soil borrow area utilized by the City during their landfill operations is located immediately west of the contractor's borrow area. Trapper Peak has provided an estimate of $47,600 for the reclamation of the borrow area. We are recommending approval of this change order request and it is enclosed in the attached Change Order #2. Class IV Rill The City requested that Trapper Peak fill a rill on the existing Class IV area. The estimate of $1,500 was approved by Great West Engineering and the City and work has been completed. This item is included in Change Order #2. Asbestos Pit The City requested that Trapper Peak fill the remainder of the space in the asbestos pit with soil stockpiled from the pit excavation. Trapper Peak provided a unit price estimate and a quantity for this work which has been completed. The estimate provided by Trapper Peak included not only placement of the fill but reclamation of the stockpile area and the borrow area used by Envirocon during the placement of asbestos waste. Reclamation of the stockpile and borrow area includes approximately 2 acres of regarding, topsoil placement and seeding. Placement of the fill in the asbestos pit required Trapper Peak to handle the material several times to complete the work which also increased the cost of this work. Trapper Peak has agreed to submit a detailed justification for the $11.75/cubic yard amount provided in their estimate. The City has also requested that the quantity of 12,480 cubic yards estimated by Trapper Peak be verified. This will be accomplished by potholing down to the waste to determine the depth of cover. Trapper Peak has agreed to provide their 330 excavator to excavate these test pits at $225/hour. It is estimate that the test pits can be excavated in 4 -6 hours. Great West will log the pits and estimate the final quantity from this information. If Great West and the City accept the final justification for the unit price and the final quantity, this work will be rolled into a change order. F:\BOZEMAN-LF Consulting-99104\Correspondence\D_JohnsonProject update.doc