HomeMy WebLinkAboutResolution 4197 Knife River Change Order, 2009 Street ImprovementCOMMISSION RESOLUTION N0.4197
A RESOLUTION OF THE CITY COMMISSION OF THE CITY OF BOZEMAN,
MONTANA, APPROVING ALTERATION/MODIFICATION OF CONTRACT
WITH KNIFE RIVER, BELGRADE, MONTANA.
WHEREAS, the City Commission did, on the 15th day of June 2009, authorize award of the bid for
the 2009 Street Improvements project, to Knife River, Belgrade, Montana; and
WHEREAS, Section 7-5-4308, Montana Code Annotated, provides that any such alterations or
modifications of the specifications and/or plans of the contract be made by resolution; and
WHEREAS, it has become necessary in the prosecution of the work to make alterations or
modifications to the specifications and/or plans of the contract.
NOW, THEREFORE, BE IT RESOLVED by the City Commission of the City of Bozeman,
Montana, that the proposed modifications and/or alterations to the contract between the City of Bozeman, a
municipal corporation, and Knife River, Belgrade, Montana, as contained in Change Order No. 1, attached
hereto, be and the same are hereby approved; and the City Manager is hereby authorized and directed to
execute the contract change order for and on behalf of the City; and the City Clerk is authorized and directed
to attest such signature.
PASSED AND ADOPTED by the City Commission of the City of Bozeman, Montana, at a regular
session thereof held on the 27t" day of July 2009.
~~
Gam'"' ,
KAAREN JACOBSO ayor
Page 1 of 2
i
STACY LME , CM
City Clerk
APPROVED AS TO FORM:
G~G SULLIVAN
City Attorney
Page 2 of 2
CHANGE ORDER
No. 1
DATE OF ISSUANCE EFFECTIVE DATE ~t,.l~ a~7, oZ00~
OWNER City of Bozeman CONTRACTOR Knife River
Contract: 2009 Street Improvements
Proiect: OWNER's Contract No.
ENGINEER City Engineer ENGINEER's Contract No.
You are directed to make the following changes in the Contract Documents:
Description: Substitute new unit prices for Bid Items 107, 108, 109, 110, and 111 as per Knife River letter dated
July 14, 2009
Reason for Change Order: Original striping subcontractor proposed does not meet Contract Specifications.
Attachments: (List documents supporting changepwner letters to Contractor dated July 7, 2009 and July 15,
2009; Contractor letter to Owner dated July 14, 2009
CHANGE IN CONTRACT PRICE:
Original Contract Price
$ 368,370.95
Net Increase (Decrease) from previous Change
Orders No. to None
Contract Price prior to this Change Order:
$ 368,370.95
Net increase H~ee-rease) of this Change Order:
$ 27,857.00
Contract Price with all approved Change Orders:
$ 396,227.95
CHANGE IN CONTRACT TIMES: NONE
Original Contract Times:
Substantial Completion:
Ready for final payment:
da s or dates
Net change from previous Change Orders No._ to
No. _
Substantial Completion:
Ready for final payment:
da s
Contract Times prior to this Change Order:
Substantial Completion:
Ready for final payment:
da s or dates
Net increase (decrease) this Change Order:
Substantial Completion:
Ready for final payment:
(days)
Contract Times with all approved Change Orders:
Substantial Completion:
Ready for final payment:
(days or dates)
Contractor certifies and agrees that there are no additional costs or claims for extra work, additional time, delays or
omitted items, of any nature whatsoever~ssociated with the subject change order items, except as identified and set
forth herein and unless expressly stated otherwise in the Change Order. And further, that the price agreed-upon herein
represents the full cost and value for the subject work performed and the materials supplied under the terms of the
contract and that the wyrk quantitiesand value were properly determined and are correct
~_/~/~_--~/C~- 1 4
01 RACTOR (Authorized Signature) Da e
RECD N D B'~
~21~
( INEER -Signature) ate
APP OVED BY: e
'~ 3c~~
ER (Authorized Signature) Date
EJCDC 1910-8-B (1996 Edition
Prepared by the Engineers Joint Contract Documents Committee and endorsed by The Associated General Contractors of America aryl the
Construction Specifications Institute.
Page 1 of 2
Y:\WORDDOCS\2009 Street Improvements1C06 Change Order No 1.doc
THE CITY OF BOZEMAN
20 E. OLIVE • P.O. BOX 1230
BOZEMAN, MONTANA 59771.1230
ENGINEERING DEPARTMENT
PHONE: (406) 582-2280 FAX: (406) 582-2263
July 7, 2009
Knife River -Belgrade
P.O. Box 9
Belgrade, MT 59714
Attn: Jackie Flikkema
Re: 2009 Street Improvements
Dear Jackie:
In accordance with Section 6.06 of the Standard General Conditions of the Construction
Contract, the City of Bozeman is objecting to the use of Arrow Striping as a subcontractor on the
above referenced project for thermoplastic striping, as their striping does not meet our
specifications. Please select and submit for approval an alternate subcontractor, with new unit
prices if necessary, for Bid Items 107 through 111. A Change Order will be processed if the
alternate subcontractor is deemed acceptable.
Please contact me if you have any questions.
Sincerely,
~'
//7
Andrew Kerr
Engineering Assistant
Cc: Debbie Arkell, Director of Public Service
HOME OF MONTANA STATE UNIVERSITY
GATEWAY TO YELLOWSTONE PARK
.~ K fZIVEft
AN MDU RESOURCES COMPANY
www.kniferiver.com
Mountain Region-Belgrade Division
PO Box 9
Belgrade, MT 59714
(406) 388-6832
(406) 388-8347 FAX
July 14, 2009
City of Bozeman
Attn: Andy Kerr
PO Box 1230
Bozeman, MT 59771
Re: City of Bozeman Street Improvement 2009
Dear Andy:
:~E ;.'~
41£R; 1 r Rf~fllzf~ ~.
tit
~~~. _ E~i
I have included the pavement marking unit prices for the above referenced project as you
requested. These prices came from Montana Lines who was the 2°d Bidder for this project.
Please respond as needed.
UNIT TOTAL
NO ITEM UNIT PRICES QUANTITY PRICES
4" YELLOW
107 STRIPING LF $6.50 940 $6,110.00
8" WHITE
108 STRIPING LF $14.00 354 $4,956.00
24" WHITE
109 STRIPING LF $38.00 667 $25,346.00
4" WHITE
110 STRIPING LF $6.50 1725 $11,212.50
WORDS &
111 SYMBOLS SF $38.00 138 $5,244.00
* * * * *MOBLIZATION INCLUDED IN THIS PRICE*
If you have any questions, please call me at 388-6x31 ext.29
Sincerely,
___-~ ~_~
acqueline Flikkema
Knife River -Belgrade
$52,868.50 ~
Equal Opportunity Employer
THE CITY OF BOZEMAN
20 E. OLIVE • P.O. BOX 1230
BOZEMAN, MONTANA 5977 1-1 230
ENGINEERING DEPARTMENT
PHONE: (406) 5$2-2280 FAX: (406) 582.2263
July 15, 2009
Knife River -Belgrade
P.O. Box 9
Belgrade, MT 59714
Attn: Jacqueline Flikkema
Re: 2009 Street Improvements
VIA FAX: 388-8347 No hard copy will follow
Your selection of Montana Lines as the replacement subcontractor for thermoplastic striping on
the above project is approved. I will begin processing a Change Order for the new Unit Prices.
Sincerely,
Andrew Kerr
Engineering Assistant
Cc: John VanDelinder, Street Superintendent