HomeMy WebLinkAboutBuilding Inspection 4th Quarter Fiscal YearPage | 1 ` Commission Memorandum REPORT TO: Honorable Mayor and City Commission FROM: Bob Risk, Chief Building Official Jason Shrauger, Fire Chief Chuck Winn, Assistant City Manager SUBJECT: Building Inspection 4th Quarter FY09 Update April 1 – June 30, 2009 MEETING DATE: August 3, 2009 RECOMMENDATION: Accept this report detailing the financial and workload position of the Building Inspection Division for the quarter ending June 30, 2009. DISCUSSION: Because of the difficulties estimating Building Inspection revenues and workloads (plans reviews & inspections), we committed to make quarterly reports regarding staffing levels and operating costs in the department. The FY09 Budget was balanced with the following assumptions: A. REVENUES: Without an increase in current fees, we estimated receiving approximately $70,000/month. This estimate was based on building permit activity during the last quarter (April-June) of FY08. How much revenue we collect is a function of the number of permits sold and the type of project being constructed. For the first quarter of FY09, actual revenues collected averaged 285 Page | 2 $95,000/month, or 35% above our estimated amount. For the second quarter of FY09, actual revenues collected averaged $52,000/month or 26% below the estimated amount. For the third quarter of FY09, actual revenues averaged $70,000/month which equals the estimated amount. The fourth quarter of FY09 actual revenues averaged $73,000/month which exceeds the estimated amount. Basis for FY09 Budget Estimates – Actual Revenues 4th QTR FY08 April 2008 $68,000 May 2008 $63,000 June 2008 $88,500 Average Per Month: $73,000 Actual Revenues 1st QTR FY09 July 2008 $108,000 August 2008 $81,000 September 2008 $96,000 Average Per Month: $95,000 Actual Revenues 2nd QTR FY09 October 2008 $96,000 November 2008 $28,000 December 2008 $30,000 Average Per Month $52,000 Actual Revenues 3rd QTR FY09 January 2009 $83,500 February 2009 $24,000 March 2009 $103,000 Average Per Month $70,000 286 Page | 3 Actual Revenues 4th QTR FY09 April 2009 $40,000 May 2009 $74,000 June 2009 $103,000 Average Per Month $73,000 The average monthly revenue for FY09 is approximately $73,000 month which exceeds our estimated amount. B. CASH RESERVE: The Building Inspection Fund Cash Reserve was $629,232 at the end of June, which equates to 53% of the FY09 expenditure levels. The cash reserve balance is up $998 from the cash reserve balance of $628,234 at the end of the third quarter. · After the spending adjustments made in the 2nd Quarter, the Department’s budget was reduced to an estimated $91,000/month for the remainder of the fiscal year. Actual spending for the third quarter was $260,300, or an $86,766 per month. The lower expenditure levels are attributed to in house reductions of our line item budget spending. · During the 3rd quarter, in response to existing workloads, building division staff was reduced by an additional 2 FTE’s: 1 permit technician, and 1 building inspector. After payouts for accrued leave time, these staffing changes will reduce department expenditures by an estimated $19,200 through the end of this fiscal year. · During the 4th Quarter, we accepted a voluntary layoff from a staff member causing the building division staff to be reduced by 1 FTE. (1 permit technician) · The Building Division FY09 staff reduction total is now 5 FTEs which will reduce department expenditures from the FY09 budget by an estimated $322,706 for the 2010 fiscal year. C. BUILDING PERMIT NUMBERS: While the total number of new permits for the third quarter FY09 decreased 22% from second quarter FY2009 levels, the new permit levels for the fourth quarter FY09 increased 44% over the Third Quarter FY09. 287 Page | 4 Permit Type 4Qtr FY08 1Qtr FY09 2Qtr FY09 3Qtr FY09 4 Qtr FY09 Building 192 358 298 184 419 Plan Check 200 205 141 101 183 Electrical 174 181 141 99 125 Plumb/Mech 228 259 148 146 158 Fire Systems 24 19 21 17 17 Moving 1 2 0 0 1 Demolition 6 8 3 7 10 Total Permits 825 1033 752 582 913 WORKLOADS: As of today, the building inspection division staff includes: ¼ Fire Chief, ½ Deputy Chief Inspections, 1 Chief Building Official, 2 Plans Examiners, 3 Building Inspectors, 1 Fire Inspector, 1 Code Compliance Officer, and 1 Permit Coordinator. D. “Inspections per Inspector Day” has historically been used to measure the workload of building inspectors. The accepted level of inspections per inspector day is 15. We reviewed the actual inspections per inspector day averages for FY05 through FY09 and the results are in the table below. Fiscal Year Inspections/Inspector Day Standard 15 2009 14.59 2008 15.45 2007 2006 2005 5 year average inspections per day- 12.56 13.01 14.27 13.97 During the last half of FY09, inspection numbers have showed a gradual but steady increase to an average 13.50 inspections per inspector day for the last month of the 4th Quarter FY09. See table below. 288 Page | 5 Fiscal Year 2009 Inspections/Inspector Day Standard 15 January 10.92 February 11.58 March April May June FY 09 average inspections per day - 11.11 11.79 13.25 13.50 14.59 In addition to the historical inspector workload, the field inspection staff is performing inspection related computer entries that were previously completed by the permit technician. Also, to help compensate for the recent permit technician staff reduction and the increased volume of building permit applications we are receiving, the building division code enforcement officer has been trained to accept permit applications, issue building permits, and to provide general office coverage as needed. STAFFING PLAN: With our current and projected workload, the Building Division is currently at the minimum staffing level needed to provide the minimum services mandated by the Administrative Code of Montana, City of Bozeman Ordinances, the International Building Code and Current Building Division Policies. Currently, the building division staffing level includes: ¼ Fire Chief, ½ Deputy Chief Inspections, 1 Chief Building Official, 2 Plans Examiners, 3 Building Inspectors, 1 Fire Inspector, 1 Code Compliance Officer, and 1 Permit Coordinator. FISCAL EFFECTS: During the 2009 Fiscal year, the building division staff worked hard to streamline our operations and conserve funds. We reviewed our budget line items and were able to cut $28,000. We revised our CIP vehicle policy and we were able to save $31,200 in vehicle costs. 289 Page | 6 During FY09, while trying to anticipate our FY09 Quarterly workloads and project our staffing requirements for the upcoming 2010 fiscal year, we reduced the building division staffing levels by 5 FTEs which results in additional expenditure reductions of $300,000. There will be a 2-3 month delay in any financial savings that might come from the above described staff reductions due to leave accrual payouts. This means that staff reductions made in April, May, and June won’t decrease total expenditures until FY10. Our 4th Quarter estimated monthly expenditures for the department stand at $84,600/month. Our revenues for the 4th Quarter FY09 averaged $73,000/month and our monthly expenditure levels were approximately $84,600/month which left us with a reserve fund balance at the end of the 4th Quarter of $629,232 which represents 53% of the FY09 Approved Budget and represents 63% of the Recommended FY10 budget. ALTERNATIVES: As suggested by the City Commission. 290