HomeMy WebLinkAboutStory Mansion Change Order No. 11, R & R Taylor, 2009 TM =~== Document G701 - 2001 Change Order PROJECT (Name and address): CHANGE ORDER NUMBER: 011 OWNER: City of Bozeman -Story Mansion DATE: April 15, 2009 ARCHITECT: Interior Renovation 811 S. Willson Ave. CONTRACTOR: Bozeman, MT 59715 TO CONTRACTOR (Name and address): ARCHITECT'S PROJECT NUMBER: 08-02 FIELD: ^ R&R Taylor Construction, Inc CONTRACT DATE: January 07, 2009 OTHER: ^ P.O. Box 1234 CONTRACT FOR: General Construction Bozeman, MT 59771-1234 THE CONTRACT IS CHANGED AS FOLLOWS: (Include, where applicable, any undisputed amount attributable to previously executed Construction Change Directives) The following items aze included in this change order - Light fixture W revisions & hide ceiling conduit above main stair, see PR #013 (deduct $613.20) - Add Trim at 111&112 crown, infill basement window at mech demo, see PR #016 & 017 (add #279.84) The original Contract Sum was $ 1,071,242.00 The net change by previously authorized Change Orders $ 36,546.60 The Contract Sum prior to this Change Order was $ 1,107,788.60 The Contract Sum will be decreased by this Change Order in the amount of $ 333.36 The new Contract Sum including this Change Order will be $ 1,107,455.24 The Contract Time will be increased by Zero (0) days. The date of Substantial Completion as of the date of this Change Order therefore is June 30, 2009 NOTE: This Change Order does not include changes in the Contract Sum, Contract Time or Guaranteed Maximum Price which have been authorized by Construction Change Directive until the cost and time have been agreed upon by both the Owner and Contractor, in which case a Change Order is executed to supersede the Construction Change Directive. NOT VALID UNTIL SIGNED BY THE ARCHITECT, CONTRACTOR AND OWNER. Comma-Q Architecture, Inc. R&R Taylor Construction, Inc City of Bozeman ARCHITECT (Firm name) CONTRACTOR (Firm name) OWNER (Firm name) 109 N Rouse Ave, #1, Bozeman, MT P.O. Box 1234, Bozeman, MT 59771- P.O. Box 1230, Bozeman, MT 59771 59715 1234 ADDRESS __ A S AD.BRESS _ ~ 1\ n n , BY (Signature) '` ~Y~S(gnature) BY (Signature) Ben Lloyd (Typed name) ~~~ ~~~~ DATE Russell L. Olsen (Typed nar re) ~~ DAT James Goehrung (Typed name) S- r3 -© ~ DATE AIA Document G701 T"" - 2001. Copyright ©1979, 1987, 2000 and 2001 by The American Institute of Architects. All rights reserved. WARNING: This AIA® Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This document was produced by AIA software at 11:05:59 on 04/15/2009 under Order No.1000388712_1 which expires on 2/17/2010, and is not for resale. User Notes: (3182293344) Change O~de~ Request Proposal Request #1 SA Revised ~~~~~ R&R TAYLOR ~(~NSTRU~TIf~N INS, To: Date: 04/13/09 Job Number: 2008-O15 COMMA-Q ARCHITECTURE, INC. 109 N ROUSE AVE. #1 Job Name: STORY MANSION BOZEMAN, MT 59715 Date Accepted By: 04/20/09 We hereby agree to make the change(s) specified below: DEDUCT: Matzinger change in W tiYture specification $ -1,42.00 ADD: Matzinger change in W fixttu•e and hide conduit about main stair $ 774.00 OH&P 20% 154.80 Subtotal $-613.20 Note: Per Proposal Request Number: 015 Please sign and return one copy to our office immediately. Sub Total of Above 6% Contact Management Fee Total Change Order Request The Contract Time will be increased $ -613.20 $0.00 $ -613.20 0 days R & R•T~vlor Construction Inc. Russ Olsen From: Kim Everts [kim@commaq.com] Sent: Monday, April 13, 2009 11:50 AM To: Russ Olsen Cc: 'laura landon' Subject: Story Mansion electrical items Russ, Can you revise COR 15 to the following items only and resend to us? 1. The $774.00 cost from Matzinger for the Change in the W fixture and hide conduit about th.e main stair. 2. The $1,542.00 credit from Matzinger for the change in the W fixture specification. The other electrical items of the conduits to the upper floor for future phase F. Alarm and phone is still in James lap to decide what to do, I don't know what he will decide with that item or the Telephone work costs. I have sent them onto him 'for his review and decision. However, the 2 items above need to move forward. Thanks. Call with questions. Kim Kim Everts Comma-;~Archi#ertur~, ~+~~ 109 N Rouse Ave, #1 Bozeman, MT {dOB) 58b-1112 klm~lcommaa.com Change O~de~ Request P~o~osal Request #18 R~rR TAY~O-R CQNSTRUCTI4N 1NC. To: Date: 04/ 13/09 Job Number: 2008-015 COMMA-Q ARCHITECTURE, INC. 109 N ROUSE AVE. #1 Job Name: STORY MANSION BOZEMAN, MT 59715 Date Accepted By: 04/20/09 We hereby agree to make the change(s) specified below: Provide and install additional trim, per SKA 25 at N, W, S walls in Toilet 1 12 and Entry Corridor 1 1 1 at new addition $ 220.00 Provide and install infill at basement level window at north wall of room located below Library er SKA 26 No Charge OH&P 20% 44.00 Subtotal $264.00 Note: Per Proposal Request Number: 016 & 17 Please sign and return one copy to our office immediately. Sub Total of Above 6% Contact Management Fee Total Change Order Request The Contract Time will be increased $ 264.00 $15.84 $ 279.84 0 days Inc. s ~ ® TM =~= Document G709 - 2001 Work Changes Proposal Request PROJECT (Name and address): PROPOSAL REQUEST NUMBER: 016 OWNER: City of Bozeman -Story Mansion ARCHITECT: Interior Renovation 811 S. Willson Ave. DATE OF ISSUANCE: Apri103, 2009 CONSULTANT: ^ Bozeman, MT 59715 CONTRACTOR: OWNER (Name and address): CONTRACT FOR: General Construction FIELD: ^ City of Bozeman OTHER: ^ P.O. Box 1230 CONTRACT DATE: January 07, 2009 Bozeman, MT 59771 FROM ARCHITECT (Name and address): Comma-Q Architecture, Inc. 109 N Rouse Ave, #1 Bozeman, MT 59715 TO CONTRACTOR (Name and address): R&R Taylor Construction, Inc P.O. Box 1234 Bozeman, MT 59771-1234 ARCHITECT'S PROJECT NUMBER: 08-02 Please submit an itemized proposal.for changes in the Contract Sum and Contract Time for proposed modifications to the Contract Documents described herein. Within Ten (10) days, the Contractor must submit this proposal or notify the Architect, in writing, of the date on which proposal submission is anticipated. THIS IS NOT A CHANGE ORDER, A CONSTRUCTION CHANGE DIRECTIVE OR A DIRECTION TO PROCEED WITH THE WORK DESCRIBED IN THE PROPOSED MODIFICATIONS. DESCRIPTION (Insert a written description of the Work): Provide and install additional trim, per SKA 25, at north, west, & south walls in Toilet 112 and Entry Corridor 111 (at new addition). ATTACHMENTS (List attached documents that support description): SKA 25 (one page) REQUE BY THE ARCHITECT: ~1 ~~ . --- - -.~ (Signatur ) Pat Larum, Architect (Printed name and title) AIA Document G709T"" - 2001. Copyright m 1993 and 2001 by The American Institute of Architects. All rights reserved. WARNING: This AIA° Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This document was produced by AIA software at 10:17:54 on 04/03/20D9 under Order No.1000388712_1 which expires on 2/17/2010, and is not for resale. User Notes: (1807476073) l„ ~' ~' if '{' ,~' f , t ~' ' ,jl ~' ~" - is i ' 1, '~ ~~ WD BEAD BOARD CLG 1 i:. r t ~ ADDITIONAL WOOD TRIM, PAINTED. PROVIDE (N) I' ~, `, r } WD TRIM AT NORTH, WEST, AND SOUTH WALLS - ~. '~ ~ " ' OF ROOMS 111 & 112. (E) TRIM ON EAST WALLS -- TO REMAIN ,r i G, ' ~~'~ - ~~ ,~ _ ~. ~% i' _ r ,, ~. ~~ - . r '~ ~ - 1 ~: 1 WOOD TRIM DETAIL The Historic z 04102!09 PR #016 DRAWING NUMBER: ~J Mansion T ~ Stor . . y ~ Interior Renovation DRAWING TITLE S KA 2 5 811 South Willson Ave., Bozeman, MT 59715 : Comma-Q ADDITIONAL TRIM AT TOILET 111 & Architecture, inc. DATE: scALE: PRO~ECTa: ENTRYICORRIDQR 112 04102109 1 112" = 0802 WOOD TRIM, PAINTED, TO MATCH (E) WOOD TRIM AT EAST WALL OF ROOMS 111 & 112. TM =.~== Document G709 - 2001 Work Changes Proposal Request PROJECT (Name and address): PROPOSAL REQUEST NUMBER: 017 City of Bozeman -Story Mansion Interior Renovation 811 S. Willson Ave. DATE OF ISSUANCE: Apri103, 2009 Bozeman, MT 59715 OWNER (Name and address): City of Bozeman P.O. Box 1230 Bozeman, MT 59771 CONTRACT FOR: General Construction CONTRACT DATE: January 07, 2009 FROM ARCHITECT (Name and address): Comma-Q Architecture, Inc. 109 N Rouse Ave, #1 Bozeman, MT 59715 70 CONTRACTOR ("Name and address): R&R Taylor Construction, Inc P.O. Box 1234 Bozeman, MT 59771-1234 ARCHITECT'S PROJECT NUMBER: 08-02 OWNER: ARCHITECT: CONSULTANT: ^ CONTRACTOR: FIELD: ^ OTHER: ^ Please submit an itemized proposal for changes in the Contract Sum and Contract Time for proposed modifications to the Contract Documents described herein. Within Ten (10) days, the Contractor must submit this proposal or notify the Architect, in writing, of the date on which proposal submission is anticipated. THIS IS NOT A CHANGE ORDER, A CONSTRUCTION CHANGE DIRECTIVE OR A DIRECTION TO PROCEED WITH THE WORK DESCRIBED IN THE PROPOSED MODIFICATIONS. DESCRIPTION (Insert a written description of the Work): Provide and install infill at basement level window at north wall of room located below Library, per SKA 26. ATTACHMENTS (List attached documents that support description): SKA 26 (one page) REQUE~ BY THE ARCHITECT: --°~, (Signatur Ben Lloyd, Architect/President (Printed name and title) AIA Document G709TP^ - 2001. Copyright ©1993 and 2001 by The American Institute of Architects. All rights reserved. WARNING: This AIA® Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, -) may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This document was produced by AIA software at 10:18:15 on 04/03/2009 under Order No.1000386712_i which expires on 2117/2010, and is not for resale. User Notes: (548602029) REMOVE (E) WINDOW FRAME, SCREEN & ABANDONED DUCT. (E) BRICK MOLDING TO REMAIN, TOUCH-UP PAINT (N) 314" PLYWOOD, PAINT TO MATCH (E) WINDOW FRAMES. CAULK & SEAL FOR WEATHERTIGHTNESS R19 GATT INSULATION (N) 314" PLYWOOD (2) P.T. 2X6 WOOD FRAME EXISTING WALL DETAIL AT WINDOW iNFILL t' The Historic nsion M St T B o DRAWING NUMBER: ~ a ory . . ~ ~ Interior Renovation 811 South Willson Ave., Bozeman, MT 59715 DRAWING TITLE: MENT WINDOW S KA 26 COmma~Q Architecture, Inc. DATE• SCALE: PRaECTr: 04102109 314" =1'-0" 0802 INFILL AT BASE