HomeMy WebLinkAboutCommission Memo for Story Mansion Change Orders 3-7Commission Memorandum REPORT TO: Honorable Mayor and City Commission FROM: ~ James Goehrung, Director of Facility Services Chris Kukulski, City Manager SUBJECT: Change Orders for the Story Mansion Renovation MEETING DATE: March 9, 2009 RECOMMENDATION: Authorize the City Manager to sign Change Orders numbers 3 through 7 for the renovation of the Story Mansion in the amount of $23,343.44. Change Order #003 in the amount of $5,049; Change Order #004 in the amount of $4,168.98; Change Order #005 in the amount of $5,542.79; Change Order #006 in the amount of $4,834.19; Change Order #7 in the amount of $3,748.48. BACKGROUND: Work began on the renovation of the Story Mansion on January 5, 2009. Work is progressing well on the project with the basement and main floor demolition complete. The basement renovation and conversion is well under way. Plumbing and electrical rough in is 30 % complete. Mechanical ducting is being installed. The addition excavation, foundation and footing walls are installed. The fire sprinkler system installation has started in the basement and main floor. Installation on the second and third floors has been curtailed due to the identification of additional asbestos containing materials. Change Order #003 is for the conversion of the 2 inch fire line to a 1 '/2 inch domestic water line. City Code requires that the line be sized down on the outside of the building. This work will expose the line; neck it down to the appropriate size; connect the new 1 '/z inch line into the building and the water meter; and reclaim the lawn area. This approach was chosen because the impact fee fora 1 %2 water line, over a 2 inch line, is $12,000.00 less. This could be a net savings of approximately $7,000. Change Order #004 is for the cost of replacing the wood floor that was damaged by the asbestos abatement contractor during the removal of the flooring materials in the kitchen and dining room. This work is being charged to the project, but the cost has already been recovered from the abatement contactor. Safetech, the abatement contractor charged $11,250.50 for the removal of the asbestos flooring. The cost for the flooring repair was deducted from their bill and they were only paid $7,081.52. Change Order #005 items include a number of code required items that are required for the proposed assembly uses. The plan review was done concurrent with bidding the project in order to address the tight time line for the project. The revisions include a 60 minute fire rated door; the installation of fire blocking at a number of ceiling and wall areas; and the replacement of two glass units in windows south wall that abut the solarium. Floor levels were raised at this location to address Americans With Disabilities Act requirements and the raised floors put the window height closer to floor grade requiring that the glass be changed out to tempered glass for safety purposes. Change Order #006 addresses framing issues that were uncovered during the demolition phase of the project. Past modifications to the building resulted in framing and flooring members being cut away and not braced properly. The structural engineer evaluated the framing once it was exposed and specified the proper method of attachment. These costs are for the hangers, fasteners, and materials needed to properly brace the structural elements of the building. Change Order #007 is for addition material changes to the kitchen prep area. There were many modifications to this area of the building over the years. The solid wall board material was installed using a heavy glued up over older wall materials. Upon removal of the solid wall material, the older wall material could not be salvaged. Covering it with another layer of sheet rock would have required changing the window and door j ams and have resulted in a good deal of extra mud and tape work because of the uneven surfaces. Direction was given to remove the wall finishes down to bare studs, insulate the wall cavities, (because there was no insulation in the walls), and re-sheet rock the walls. FISCAL EFFECTS: These five items will be assessed against the contingency fund for the project. The contingency for the project is $83,210. The three changes approved on February 23 were for $9,088.38. This left a balance of $74,121.62 in the contingency budget. These five changes are for $23,343.44, leaving a contingency balance of $50,778.18. ALTERNATIVES: As suggested by the City Commission. Respectfully submitted, James Goehrung Chris A. Kukulski, City Manager Director of Facility Services Attachments: Change order documents #003 through #007 Report compiled on March 4, 2009 RECEIVEQ ~' /I%~o4m TRANSMITTAL ~ ~ ~~~~; February 24~, 2009 ~r~titi'it~11'~Q Architectur's, Inc. To: City of Bozeman Attention: James Goehrung 109 N r?ause Avenue, pi Bozeman, MT 59715 From: Laura Landon 406.585.1112 Project: Story Mansion Interior Renovation Location: Bozeman, MT Job Number: 08-02 Copy to: File we are sending you Attached Under separate cover ^ the following: Shop drawings: ^ these are transmitted as checked below: Submittal: ^ Approved: ^ Specification: ^ Approved as corrected: ^ Prints: ^ Revise and resubmit: ^ Samples: ® Rejected: ^ Drawings: ^ For your use: ^ p~~; ^ For approval: For review & comment: ^ date qry description 02120109 3 Change Order 003 02/20109 3 Change Order 004 02/20/09 3 Change Order 005 02120/09 3 Change Order 006 02120/09 3 Change Order 007 Comments: James, Please review the attached change orders, sign all copies, keep one copy for your records and return the remaining copies to our office. Thank you, Laura Landon