HomeMy WebLinkAbout09- Change Order 1, Sewer Rehabilitation Project, Planned and Engineered ConstructionCHANGE ORDER
No
DATE OF ISSUANCE January 6, 200q_ EFFECTIVE DATE
OWNER City of Bozeman CONTRACTOR Planned and Engineered
Construction, Inc.
Contract: 2008 Sewer Rehabilitation Project
Project: Schedule A - 2008 Sewer Rehabilitation OWNER's Contract No.
ENGINEER Great West En ing eerin~?, Inc. ENGINEER'S Contract No. 1-08121
You are directed to make the following changes in the Contract Documents:
Description: Increase of 4" sewer service connections from 5 connections to 49 connections and the addition of 4"
PVC SDR 35 sewer service pipe to run to the property line.
Reason for Change Order: Additional sewer service connections with structural or root issues.
Attachments: (List documents supporting change) N/A
CHANGE IN CONTRACT PRICE:
Original Contract Price
$ 440,790.00
Net Increase (Decrease) from previous Change
Orders No. N/A to N/S
$ 0.00
Contract Price prior to this Change Order:
$ 440,790.00
Net increase of this Change Order:
$ 0.00
Contract Price with all approved Change Orders:
$ 44II,790.90 - -- -- --
CHANGE IN CONTRACT TIMES:
Original Contract Times:
Substantial Completion: 60 Days
Ready for final payment:
Net change ftom previous Change Orders No. N/A
to No. N/A
Substantial Completion: 60 Dais
Ready for final payment:
Contract Times prior to this Change Order:
Substantial Completion: 60 Days
Ready for final payment:
Net increase this Change Order:
Substantial Completion: 15 Days
Ready for final payment:
Contract Times with all approved Change Orders:
Substantial Completion: 75 Days
-- Ready f~r~nal pa-ymentc -
Contractor certifies and agrees that there are no additional costs or claims for extra work, additional time, delays or
omitted items, of any nature whatsoever, associated with the subject change order items, except as identified and set
forth herei unless expressly stated otherwise in the Change Order. And further, that the price agreed-upon herein
repres the ull cost and value for the subject work performed and the materials supplied under the terms of the
con ct hat th~ork quantities and value were properly determined and are correct.
;~ Z ~o o~
fcON RACTOR (Authorized Signature) at
~~ENDE Y: AP OVED BY:
GINEER - ature) at WNER (Authorized Signature) Date
EJCDC 1910-8-B (1996 Edition)
Page 1 of 3