HomeMy WebLinkAboutGreater Bozeman Area Transportation Plan (2007 Update)
Commission Memorandum
REPORT TO: Honorable Mayor and City Commission
FROM: Bob Murray, Project Engineer
Chris Kukulski, City Manager
SUBJECT: Greater Bozeman Area Transportation Plan (2007 Update) – Project
Presentation and Discussion
MEETING DATE: January 22, 2008
RECOMMENDATION: Listen to presentation; ask questions for clarification, discussion.
Motion and vote to direct staff to bring back a UDO amendment to 18.44.060.D Level of Service
Standards.
BACKGROUND: Jeff Key from Robert Peccia & Associates will be present to discuss the
“Greater Bozeman Area Transportation Plan (2007 Update)” project. The purpose of the
presentation is twofold. First, it will serve as the second of four scheduled meetings before the
commission to provide and update on the overall project. Progress to date will be discussed as
well as the future activities that are planned. The second issue to be discussed is the current and
proposed level of service standards to be used in the plan, as well as for future developments.
Currently the City and State have different standards for acceptable level of service at
intersections. This has created conflicts between the two agencies when looking at new
development proposals. This issue was discussed at the December meeting of the TCC, and
although there was not a quarum present, the recommendation was for the Plan to utilize the
MDT standard. If the commission decides to change the City standard to match that of MDT,
then a UDO amendment will be necessary.
FISCAL EFFECTS: N/A
ALTERNATIVES: None
110339
Respectfully submitted,
_________________________________ ____________________________
Robert J. Murray Jr., Project Engineer Chris A. Kukulski, City Manager
Attachments: Presentation Materials
Report compiled on 1/15/2008
110440
1/15/2008 1
Greater Bozeman Area
Transportation Plan
(2007 Update)
Bozeman City Commission
Project Update
January 22nd, 2008
Bozeman City Commission
Project Update
January 22nd, 2008
110541
1/15/2008 2
Today’s Meeting Goal
Give the City Commission a general project update
Review some of the items that are
being discussed at the TCC level
Discuss level of service definitions and criteria currently in effect in the planning area
Discuss next steps
110642
1/15/2008 3
General Project Update
Project is going well and is on
schedule
Presently a little over half way
through the contract.
{First third –data collection & outreach
{Second third –analysis & traffic modeling
{Remaining third –recommendations
development & additional outreach
Have held 10 TCC meetings
(monthly) with 8 remaining
Have held two formal public meetings
{Meeting 1 (06/27/07) –65 citizens
{Meeting 2 (11/28/07) –70 citizens
Have held over twenty (20) “other”
outreach activities to date
110743
1/15/2008 4
Some Issues Brought about at
TCC Level
Complete Street Policy
Context Sensitive Design
A true “multi-modal”Transportation
Plan
Desire for a mix of Transportation System Management (TSM) and Major Street Network (MSN) projects that can be implemented going forward
Identify and incorporate roundabouts, at select intersections, as a form of intersection traffic control
Desire to identify alternate and/or parallel routes to some congested facilities
Further review and/or definition of
“level of service”standards
110844
1/15/2008 5
Level of Service -Defined
Level of service (LOS) is a qualitative measure developed by the transportation profession to quantify driver perception for such elements as travel time, number of stops, total amount of stopped delay, and impediments caused by other vehicles.
It provides a scale that is intended to match the perception by motorists of the operation of the intersection.
Level of service provides a means for identifying intersections that are experiencing operational difficulties, as well as providing a scale to compare intersections with each other.
The level of service scale represents the full range of operating conditions. The scale is based on the ability of an intersection or street segment to accommodate the amount of traffic using it.
The scale ranges from “A”which indicates little, if any, vehicle delay, to “F”which indicates significant vehicle delay and traffic congestion.
110945
1/15/2008 6
Level of Service
(Signalized Intersections)
111046
1/15/2008 7
Level of Service
(Unsignalized Intersections)
111147
1/15/2008 8
Level of Service
(Graphic Portrayal)
111248
1/15/2008 9
Level of Service
(Graphic Portrayal)
111349
1/15/2008 10
MDT LOS Criteria
MDT Traffic Engineering Manual (Figure 30.2B)
111450
1/15/2008 11
Gallatin County LOS Criteria
Gallatin County does not have a formal LOS standard as part of their Subdivision Regulations and/or adopted Growth Policy
Gallatin County uses its discretion on a
case-by-case basis to decide what an
acceptable level of service would be.
111551
1/15/2008 12
City of Bozeman LOS Criteria
Defined by the Unified Development
Ordinance
“Streets and intersection level of service “C”shall be
the design and operational objective, and under no conditions will less than level of service “D”be accepted. All arterial and collector streets, and movements on intersection approach legs designated as arterial or collector streets, shall operate at a minimum level of service “C”. The design year for necessary improvements shall be a minimum of fifteen years following construction of said improvements.”
111652
1/15/2008 13
City of Bozeman LOS Criteria
Current application of the UDO
Scenario 1
Existing intersection operation is a LOS D and
development traffic impact continues the LOS at a D
then------no mitigation is being required.
Scenario 2
Post-development analysis shows intersection
operations to fall below LOS D, then------intersection
mitigation (i.e. improvements) must achieve a LOS
of C over the next fifteen years.
So what is the issue?
111753
1/15/2008 14
LOS Needed Discussion
Different jurisdictions have different approaches to
level of service
Can the Transportation Plan provide a consistent
approach to level of service that can accommodate
every jurisdictions operational objectives?
Apply level of service criteria to the intersections as
a whole? Or apply to individual turning
movements?
What is acceptable should be defined in the
Transportation Plan.
Should the LOS criteria be a LOS C or better for the
intersection as a whole, with the allowance that some
individual turning movements can be worse than a
LOS C?
111854
1/15/2008 15
Conclusion/Next Steps
We are just now defining different modeling
scenarios to assess their value
Will begin the “typical section”discussion over the next two months
Start developing the Transportation Plan recommendations
{Policy level
{Facilities (Road, intersections, non-motorized)
{Programs
{Etc.
Will start outreach activities again
Will be working towards a preliminary
recommendations “technical
memorandum”for review by the TCC and
in anticipation of the third public meeting
{Shooting for late March/early April
Questions?
111955
GREATER BOZEMAN AREA TRANSPORTATION PLAN
(2007 UPDATE)
Public Informational Meeting Number 2
November 28, 2007
Meeting Summary
The second public open house informational meeting for the Greater Bozeman Area Transportation
Plan (2007 Update) was held on Wednesday, November 28, 2007 in the Bozeman High School
Cafeteria at 205 North 11th Avenue. The meeting took place between 6:30 and 9:00 p.m. and
included a PowerPoint presentation beginning at approximately 6:40 p.m.
The meeting was attended by the following agency and Consultant Team members:
Debbie Arkell City of Bozeman
J.P. Pomnichowski Bozeman Transportation Coordinating Committee
Chris Scott Gallatin County
Rob Bukvich MDT Bozeman
Carol Strizich MDT Helena
Al Vander Wey MDT Helena
Jeff Key Robert Peccia & Associates (RPA - Helena)
Scott Randall Robert Peccia & Associates (RPA - Helena)
An estimated 70 people attended the meeting. Forty-six (46) people signed the attendance sheets for
the meeting, although others joined the meeting as it progressed. Copies of the sign-in sheets from
the meeting are on file with RPA.
Meeting Purposes
The purposes of the public meeting were to:
• Review the project status and schedule for the Greater Bozeman Area Transportation Plan
(2007 Update).
• Review the transportation system “existing conditions”.
• Review the non-motorized survey highlights.
• Review land use forecasting and socioeconomics.
• Have a general discussion about the project with those in attendance.
Meeting Presentation
Jeff Key of RPA began the meeting at 6:40 p.m. Mr. Key used a PowerPoint presentation to present
project information. The presentation began with a review of the project status and schedule. A
graphic of the project schedule was shown and discussed. A review of the transportation system
“existing conditions” followed with separate discussions for the motorized and non-motorized
portions. Graphics from the existing conditions memo were presented and discussed. Graphics for
Greater Bozeman Area Transportation Plan (2007 Update) 1 of 6
Summary of Public Meeting No. 2 – November 28, 2007
112056
Greater Bozeman Area Transportation Plan (2007 Update) 2 of 6
Summary of Public Meeting No. 2 – November 28, 2007
motorized transportation were shown for traffic volumes, corridor size, intersection operation and
crash statistics. The non-motorized system was discussed with graphics shown for the bicycle
network, bicycle collisions, pedestrian facilities, and pedestrian crashes. A very brief review of the
non-motorized survey was given, including a discussion about the results of the survey and specific
comments stemming from the survey. Finally, a review of the land use forecasting and
socioeconomics results and processes were discussed. The presentation lasted about 45 minutes.
Public Comments/Questions
Following the PowerPoint presentation, Mr. Key opened up the meeting for general comments and
questions from the audience. The following comments and/or questions were heard during this part
of the meeting:
Does this plan consider the use of impact fees and how they affect where future
businesses locate? Jeff Key explained that it is difficult to analyze how impact fees will
affect business locations because we don’t have the tools necessary to directly asses this issue
via the transportation plan. It was also mentioned that impact fee studies look at the
transportation plan for guidance on future transportation system needs, and as such the plan
serves as the basis/justification for the impact fee assessments.
Does the transportation plan guide development? Mr. Key stated that the plan should
provide the blueprint for transportation in the area, but that it is not a land use plan. It was
explained that the plan should be in general compliance with accepted documents, including
adopted plans such as Growth Policies, Neighborhood Plans, and zoning densities.
Does the study address unnecessary trips or distances due to the lack of development
diversity and options? Mr. Key explained that while mixed land uses are desirable, it is
difficult to analyze the “cause and effect’ relationship of providing complementary land uses
through a regional transportation plan. He also explained that some of the newer and future
developments on the horizon are trying to accomplish the mixed land use development goal.
Does the plan use tools to discourage traffic on certain routes? Mr. Key explained that
there is traffic calming guidance in the plan which can be used to help deter or provide safer
travel on roadways. He also explained that roadways can be designed to discourage traffic if
there is a safe alternative elsewhere.
What is the objective of the plan and how is it used? Mr. Key explained that the
transportation plan is intended to be used on a daily basis by city staff, planners, elected
officials, development community and the public at large. He mentioned that the plan
shows where needed work should happen and when to implement certain actions contained
in the plan in accordance with land use changes. The future roadway classifications and
typical sections defined in the transportation plan are also important. It was also mentioned
that conflicts within the plan should be limited to help ensure a quick adoption process and
to encourage use.
112157
Greater Bozeman Area Transportation Plan (2007 Update) 3 of 6
Summary of Public Meeting No. 2 – November 28, 2007
Does the plan address site specific or broad recommendations for non-motorized
improvements? Mr. Key explained that Alta Planning and Design will be making both
policy and specific recommendations for the area under study. He also mentioned that
guidance on how to implement and fund the recommendations will also be within the plan.
What can you do to help city and county cooperate? Mr. Key explained that RPA’s role
with regards to the transportation plan is to develop the plan under guidance of the TCC
and public and to make the plan easy to implement for city and county officials.
Does the plan address interaction concerns between various planning agencies
during construction phases? Simultaneous construction projects can cause
additional traffic congestion during construction. Mr. Key stated that during the
development of the plan, RPA works with the TCC which encourages coordination of
projects and provides opportunities for coordination during the development of the plan.
He also explained that due to the nature of construction in the Bozeman area (i.e. high
growth, short construction season) it is often times difficult to limit the affect that
construction has on traffic. He also said that other communities will be looked at to see if
there is a better way to coordinate construction projects amongst the various jurisdictions
and will try to implement guidance into the plan.
Does the plan address non-motorized funding issues? Mr. Key talked about how the
funding source discussion is the last part of the plan, but that funding historically has always
fallen short. He mentioned that Alta brings a national perspective on non-motorized
funding to the project and may have ideas with regards to innovative funding sources.
How does the plan address maintenance issues on bike lanes? Mr. Key explained that
Alta is addressing this concern and that the standard maintenance guidelines/solutions can
be addressed in the plan.
Is there a list of current planned projects for the Bozeman area? Mr. Key explained
that a preliminary list was provided by the City, County and the MDT, but that changes need
to be made to that list. The revised list may be available at the next TCC meeting.
What is the website for information on the transportation plan? Mr. Key gave
www.rpa-hln.com as the main website for information. It was also mentioned that links
from the city and county websites exist for the project website.
A comment was made with regards to how street sweeping causes unsafe conditions
along bike lanes, especially at choke points, and that the county and city don’t have a
good communication on priority for maintaining bike lanes.
Will the new plan make new recommendation for typical sections or will there be
carried over from the previous plan? Mr. Key stated that the city and county would like
RPA to have fewer typical sections in this plan, and that they need to be revisited. He said
that this issue has not been addressed yet, but it will be visited over the coming months.
112258
Greater Bozeman Area Transportation Plan (2007 Update) 4 of 6
Summary of Public Meeting No. 2 – November 28, 2007
There is a state law that says local areas can enact a 2 cent gas tax that has not been
used; could the law be changed so that this could be applied to help with the non-
motorized network? Mr. Key stated that while it is feasible, it would require an advocate to
push a bill through the state.
Are there any alternatives to chip sealing with regards to the unsafe conditions it
causes on bike lanes? Mr. Key said that he would research this issue through Alta, and
that he knows that in Wyoming only the driving lanes are chip sealed (i.e. not the shoulders).
Will overhead lighting recommendation be part of this plan? Mr. Key stated that
lighting on NHS routes must be done in accordance with the national standard set in place.
He also stated that urban areas can have lower impact type lighting and that the city just
passed a “dark skies” ordinance to help reduce lighting in the city, but that the county does
not have guidance. He mentioned that more research needs to be done to help address this
concern, but that the city development ordinance has requirements within the city area.
Has the study area in this plan grown since the last plan? Mr. Key state that the study
area boundary has changed and the current study area boundary is located on the website.
How can more comments be made to RPA? Mr. Key said that the website provided has
a 1-800 number, as well as a link to his e-mail and the city’s e-mail. He also said that
questions concerning bicycles, pedestrians, and transit can be sent to Alta.
Does the plan include more information for motorists about cyclists? Mr. Key stated
that the existing conditions memo that Alta provided does address this, and has suggestions
for additional signage. He also mentioned that the safe routes to schools program addresses
this concern.
Will Alta address the number of people using non-motorized facilities for tax
purposes? Mr. Key said that if Alta has good ideas about how to implement taxes to pay
for non-motorized facilities, that it will be put into the plan. He said that funding sources
will be addressed in the plan.
A comment was made that as a bicyclist, he would be happy to pay a license for his
bike, and that bike licensing is not a new idea and was previously implemented in
the 60’s.
Is there a value to having fewer cars on the road? Mr. Key stated that reductions in
vehicle miles of travel due to recommended network improvement is looked at and is a
criterion for identifying network improvements. He also mentioned that different changes
to the system are tested to see how they affect the system and overall vehicle miles of travel.
A citizen comment was made about how encouraged he was on how much energy
has been put into non-motorized transportation to help reduce vehicle traffic. Mr.
Key stated that while it is important to look at non-motorized transportation, there are still
traffic issues that need to be addressed and that will still exist. He also mentioned that it was
112359
Greater Bozeman Area Transportation Plan (2007 Update) 5 of 6
Summary of Public Meeting No. 2 – November 28, 2007
a requirement set forth by the city, county and MDT to have an expert on board with this
project to assist with the non-motorized aspects of the transportation system.
How does mass transit figure into the transportation plan? Mr. Key said that he has
spoken with the board of directors for Stream Line Transit, and that they do a yearly
coordination plan for the transit system. He said that RPA has a good handle on the routes
and timing of the transit system and that the route system will not be revisited. Stream Line
contracts with an engineer with specialty in transit systems (Current Transportation
Solutions) and that dialogue with that entity has been occurring on this transportation plan
development.
A comment was made about needing a coordination plan for Streamline for people
who have equipment like bikes, and/or ski equipment. Mr. Key stated that Bridger
Bowl does have a shuttle service that accommodates people going skiing or working at
Bridger Bowl and that it coordinates with employees hours, vacation times for kids, and with
Streamline.
A comment was made about how if people are afraid to bike, and bike sales are
increasing (which indicates more people want to bike), then the plan isn’t working.
Mr. Key said that people not biking isn’t only about being scared, but that it is about safety,
timing, distance, and other factors. He also mentioned that Missoula is often looked at as
having a great bike/ped system, but that the “being scared” comment is still heard there as
well.
A comment was made by Jeff Key that the third public meeting will include Alta
Planning and Design, and will include workstations to promote continued
interaction between the public and the Consultant team.
The meeting concluded at about 9:00 p.m.
Other Comments Made After the Meeting
Gooch Hill Road / US 191: This is a “tee” intersection. There are grade issues on Gooch
Hill Road as it ties into US 191. Also, a southbound left-turn is needed, but it may create
issues with the northbound lane.
There should be some language in the plan that discusses the health benefits of non-
motorized travel, and the dire conditions of our nations youths regarding obesity and
inactivity. Maybe tie it into the Safe Routes to School (SRST) work that ALTA is doing?
The Gallatin Gateway community has brainstormed on very modest, though realistic traffic
concerns and needs as part of their community planning forum. They will summarize and
mail to Jeff and/or Warren Vaughn.
112460
Greater Bozeman Area Transportation Plan (2007 Update) 6 of 6
Summary of Public Meeting No. 2 – November 28, 2007
The downtown “one-ways” are not needed. This is a golden opportunity to revitalize the
downtown with aggressive land use visioning and changes. This can start with the roadways.
Why not remove one of the lanes on the two-lane one-way and install a protected diagonal
parking area. There is more than enough capacity with one single one-way lane. Then,
redevelopment can occur with friendlier streetscape, good parking, and appropriate scale to
the downtown.
Meeting summary prepared by Robert Peccia & Associates, Inc.
F:\TRANS\BOZEMAN\Minutes\Public_mtg_2_minutes.doc
112561