REPORT TO: Honorable Mayor and City Commission
FROM: Lanette Windemaker, AICP, Contract Planner
SUBJECT: Preliminary Plat Approval Extension; Cattail Lake Major Subdivision Phase
3; #P-06022
MEETING DATE: Monday, June 16, 2008
ACTION ITEM
RECOMMENDATION: The City Commission grants the preliminary plat approval extension for
one year, or until July 17, 2010.
BACKGROUND: Scott Hacker has requested a one-year extension on the preliminary plat
approval for the above-reference major subdivision on behalf of Crestview Lake LLC. This major
subdivision received preliminary plat approval on July 17, 2006. The Findings of Fact and Order
were signed on August 21, 2006. Because it was a multi-phase major subdivision, the subdivider
had three years, or until July 17, 2009, to submit a final plat application. On September 4, 2007,
the City Commission authorized the Director of Public Service to execute the Cattail Lake Major
Subdivision Phases 1 & 2 Final Plat. The subdivider is requesting the first one-year extension on
the Phase 3, the final phase, of their preliminary plat approval.
UNRESOLVED ISSUES: There are no unresolved issues at this time.
FISCAL EFFECTS: There should be no fiscal impacts from this request.
ALTERNATIVES: As suggested by the City Commission.
CONTACT: Please email Lanette Windemaker at lwindemaker@bozeman.net if you have any
questions prior to the public hearing.
APPROVED BY: Andrew Epple, Planning Director
Chris Kukulski, City Manager
144
May 22, 2008
Lanette Windemaker
Contract Planner
City of Bozeman
20 East Olive
PO Box 1230
Bozeman, MT 59771-1230
RE: Cattail Lake Subdivision
Preliminary Plat Extension
Dear Lanette:
Crestview Lake LLC, the developer of Cattail Lake Subdivision, requests a one-year
extension of the preliminary plat granted on August 28, 2006. Such an extension
would change the expiration date of the preliminary plat from August 28, 2009 to
August 28, 2010.
As we discussed, Phases I & II of the subdivision received final plat in 2007 and we
are currently in the process of constructing apartment units in Phase I. Phase III, the
balance of the subdivision, has not yet been commenced. Our plans for Phase III
remain consistent with the requirements of the preliminary plat.
Please call me at the number above with any questions.
Sincerely,
R. Scott Hacker
Managing Member
Crestview Lake LLC