Commission Memorandum
REPORT TO: Honorable Mayor and City Commission
FROM: Anna Rosenberry, Finance Director
Chris Kukulski, City Manager
SUBJECT: Capital Improvements Criteria for General Fund Items
MEETING DATE: September 15, 2008
RECOMMENDATION: Approve attached General Fund Capital Improvements Plan
Critiera, with any modifications.
BACKGROUND: We are beginning our update of the City’s Capital Improvements Plan
(CIP) for FY2010-2014. According to the Charter, this plan must be presented to the
Commission by the City Manager no later than December 15, 2008.
We have prepared a proposed list of criteria and scoring system for all General Fund Items. The
City Manager will have ultimate responsibility for scoring CIP items, and the scoring sheets will
be included in the CIP document. These scores will be considered when scheduling purchases
and projects in the recommended CIP.
FISCAL EFFECTS: None.
ALTERNATIVES: As suggested by the City Commission.
Respectfully submitted,
Anna Rosenberry, Finance Director Chris Kukulski, City Manager Report compiled on: September 10, 2008
Attachment: Proposed General Fund CIP Criteria
23
Bozeman Capital Improvements Plan Rating Criteria for General Fund Items
Criteria Rating Notes This
Project’s
Score
1. Level of Service Up to 20 pts 20 - Corrects a health or safety hazard or
prevents a critical breakdown of an existing
city facility or equipment.
15 - Repairs, rehabilitates, or replaces
physically deteriorated or functionally
obsolete existing city facility or equipment.
10 - Brings an area up to the basic level of
service as identified in an adopted city wide
plan.
5 – Expands an approved City service.
0 – Other.
2. Operating Budget
Impact
Up to 10 pts 10 - Provides a significant decrease in city
operating and/or maintenance expenses.
5 – Has a neutral or small impact on
operating and/or maintenance expenses.
0 – Provides a significant increase in city
operating requirements.
3. Service Area Up to 10 pts 10 – Direct Benefit to entire city.
5 – Direct benefit to roughly half city or
indirect benefit to entire city.
2 – Direct benefit to small area of the city
or indirect benefit to several areas.
4. Departmental
Priority
Up to 10 pts 10 – Critical to Department’s Mission
7 – High
3 – Moderate
0 – Questionable/Very Difficult to Complete
5. Commission Work
Plan
Up to 10 pts 10 – Identified project in Adopted
Commission Work Plan
5 – Contributes to an indentified project in
the Adopted Commission Work Plan.
0 – Not identified in Adopted Commission
Work Plan.
6. Municipal Climate
Protection (Municipal
Climate Action Plan –
MCAP)
Up to 5 pts 5 – Is recommended by MCAP and will
accomplish a stated MCAP goal.
3 – Will assist in meeting MCAP goal.
0 – No relation to MCAP.
7. Seasonal Use Up to 5 pts 5 – Year Round.
3 – Six to Eleven months per year.
1 – Five or fewer months per year.
TOTAL Up to 70 pts.
24