HomeMy WebLinkAbout09- Change Order No. 1, 2008 Sewer Rehabilitation Project, Great West EngineeringCHANGE ORDER
N
DATE OF ISSUANCE January 6, 2008 EFFECTNE DATE
OWNER City of Bozeman CONTRACTOR Planned and Engineered
Construction, Inc.
Contract: 2008 Sewer Rehabilitation Project
Project: Schedule A - 2008 Sewer Rehabilitation OWNER's Contract No.
ENGINEER Great West Engineering Inc. ENGINEER's Contract No. 1-08121
You are directed to make the following changes in the Contract Documents:
Description: Increase of 4" sewer service connections from 5 connections to 49 connections and the addition of 4"
PVC SDR 35 sewer service pipe to run to the properly line.
Reason for Change Order: Additional sewer service connections with structural or root issues.
Attachments: (List documents supporting change) N/A
CHANGE IN CONTRACT PRICE:
Original Contract Price
$ 440,790.00
Net Increase (Decrease) from previous Change
Orders No. N/A to N/S
0.00
Contract Price prior to this Change Order:
$ 440,790.00
Net increase of this Change Order:
$ 0.00
Contract Price with all approved Change Orders:
$ 440,790.00
Contractor certifies and agrees that there are no additional costs or claims for extra work, additional time, delays or
omitted items, of any nature whatsoever, associated with the subject change order items, except as identified and set
forth herein and unless expressly stated otherwise in the Change Order. And further, that the price agreed-upon herein
represents the full cost and value for the subject work performed and the materials supplied under the terms of the
contract and that the work quantities and value were properly determined and are correct.
CONTRACTOR (Authorized Signature)
RECD ENDE Y:
~ ~
(ENGINEER - ature) at
EJCDC 1910-8-B (1996 Edition)
Date
CHANGE IN CONTRACT TIMES:
Original Contract Times:
Substantial Completion: 60 Davs
Ready for final payment:
Net change from previous Change Orders No. N/A
to No. N/A
Substantial Completion: 60 Davs
Ready for final payment:
Contract Times prior to this Change Order:
Substantial Completion: 60 Davs
Ready for final payment:
Net increase this Change Order:
Substantial Completion: 15 Davs
Ready for final payment:
Contract Times with all approved Change Orders:
Substantial Completion: 75 Davs
Ready for final payment:
PROVED BY:
I ~--o
O ER (Authorized Signature) Date