TO DO List:
Everyone a) attend July 14 City Commission meeting, 7pm, Courthouse;
b) mark calendars for first Thursday of each month for NSURB
meetings (official publicly posted meeting schedule) at 6pm in the
Stiff Building, Olive @ Black, upstairs conference room
Keri a) work with engineering department to find a day convenient to
them on which we could order in lunch and meet them -start
building a great working relationship; their offices
b) post Winter Plan to NSURB's website (meeting minutes, agenda
too?)
Mike a) draft letter to downtown association about salary-sharing staff
Scott a) will walk sidewalks again, finding linear footage that is good
Ron a) find Big Box fund vote in commission minutes
b) talk with Ron Dingman about CTEP funds
In attendance: Ron Brey, Susan Kozub, Scott Hedglin, Carl Solvie, Susan Fraser,
Michelle Wolfe, Mike Hope
Call to Order Ron Brey called meeting to order
Public Comment none
Election of Officers
Chair Motion by S.Fraser to nominate Michelle Wolfe
Seconded by S.Kozub
Vote: all in favor of Michelle Wolfe as Chair of NSURB
Vice Chair Motion by S.Fraser to nominate Carl Solvie
Seconded by M.Hope
Vote: all in favor of Carl Solvie as Vice-Chair of NSURB
Recorder Motion by M.Wolfe to nominate Susan Fraser
Seconded by S.Kozub
Action Vote: all in favor of Susan Fraser as Recorder of NSURB
In January 2009 discuss/re-elect officers
Presentation -Chris Thompson, Aggrandized Creative Services (attachment)
Presented Bozeman Passage signage concept; banner size proposed 3' wide x 5' tall;
discussion followed -downtown banner example, do we have to put project out to bid
(yes if using TIF monies) or we can be middlemen to business owners, Chris asked for
NSURB backing, Chris' projected cost = $50K per year, includes changing banners
every 6 months, cart before horse -need lightposts before banners; Michelle to Chris -
do not represent yourself to business owners as supported by this board.
Page 1 of 4
N7URB htt°://www.bozeman.net/commission/north seventh urban renewal board (nsurbl2.asgx
Discussion Items
a. Set regular meeting date, time, place -all agreed good with lst Thursday of the
month in the upstairs conference room of the Alfred M Stiff Professional Building,
20 E Olive, 6pm. Will be posted inside City Hall.
b. Sidewalk improvements -Michelle reported she'd walked up and down 7th several
times, finding less than 6 sections are a horror to walk, the top worst being UHaul
and Cats Paw sections. Winter weather is another picture - a `real bear' to traverse.
Looked at 1988 drawings, when medians were installed. Ron and Carl recalled the
sidewalk improvements were brought to a halt by the furniture company. It was a
question of digging up mature landscaping and signage -drainage problem was
also mentioned.
Discussion continued, focusing on getting engineers to draw up a true work plan
for sidewalk, lights, landscaping based on the Winter Plan. Question: need to get
right-of--ways before plan can be implemented?
Scott worked up the following costs -
Budgetary Unit Costs -Street Improvements
Description Cost Unit Multiplier Cost per LF
Demo Existing Sidewalk $7.00 sf 5 ft wide $ 35.00
Disposal Existing Sidewalk $1.00 sf 5 ft wide $ 5.00
4" Concrete Sidewalk w/ base $6.00 sf 5 ft wide $ 30.00
Sod $0.40 sf 5 ft wide $ 2.00
Irrigation (no meter/tap fee) $1.50 sf 5 ft wide $ 7.50
Street Lights w/concrete base $4,000.00 ea 1 per 40 LF $ 100.00
Street Trees $400.00 ea 1 per 40 LF $ 10.00
Allowances
per
Pedestrian Curb Cut $500.00 ea 1 occurance $ 500.00
per
Relocate Existing Tree $350.00 ea 1 occurance $ 350.00
per
Relocate Existing Shrub $100.00 ea 1 occurance $ 100.00
Scott will walk sidewalks again, finding linear footage that is good, possibly 50%
good, thus reducing the project cost to ~750K-$lmillion.
c. Lighting - Susan K handed out her research into lightposts options. Solar is not
financially viable. Do we want pedestrian lighting only or something to replace the
existing cobra lighting? Discussion followed, including MDOT regulations that
would have to be met, etc.
Page 2 of 4
N7tJRB http://www.bozeman.net/commission/north seventh urban renewal board (nsurb)2.aspx
d. MDOT feedback -Carl reported they have no money for us, only CTEP funds
available. Bozeman committee decides how monies spent, says we can put name in
the hat. Ron Dingman is the administrator of these funds. 1:1 matching grant.
e. Grants/Climate Protection staff -Ron reported on new position, thinking could
work with them especially in respects to solar-fired lighting. Job description not set
yet, still new, but would be good to get foot in door.
Work Plan and Budget preparation
Ron announced that Monday's, July 14, 2008, City Commission meeting includes
several groups, mainly Prospera, presenting economic plans using the Big Box funds.
Ron strongly encouraged NSURB to be present and remind Commissioner Krauss and
all commissioners that $225,000 of those funds were promised to North 7th four+
years ago, namely to Mike Hope as he was presenting on the fairgrounds ice rink plan.
Mike agreed to speak for NSURB during the public comment period of the July 14
meeting, reclaiming the promised monies. He will explain that:
• the board has just been established,
• an engineering plan is our first cost (est. $60-$75K),
• if all linear footage of 7th, from Main St to Oak St, is replaced, the project
cost will be $1.5 million (Scott has worked up the cost figures).
All board members were encouraged to attend.
Ron will look thru the commission minutes to find that vote in which the monies were
promised.
There are currently $30K in TIF monies, the next increment will be available in
November 2008.
Final Notes from Ron (retiring August 1)
• July 15 Planning Board meeting -updating 2020 Plan -might want to attend
• Keri Thorpe will support board - as get busier, will probably need to hire staff.
Discussed hooking in with downtown groups, sharing salary costs and time of
their current staff person, Chris. Carl agreed with Mike on this and Mike is to
draft a letter to the downtown association, just something to get the ball rolling.
Michelle will need to sign letter. Discussed $ l OK as being a good starting figure.
NSURB has more work to do than downtown. Chris is presenting to city on July
21 -might want to get letter to the association PDQ so can be included in this
budget presentation to the commission.
• Might want/need to adopt bylaws in the future
• Remember Winter Plan has already been approved so use it
Page 3 of 4
N7URB http://www.bozeman.net/commission/north seventh urban renewal board (nsurbl2.aspx
• Need to build good relationships with city departments, i.e. engineering going to
need to know by January of each year what our plans are, etc. he has been
working on `selling NSURB' to the departments and is feeling like he's making
some progress.
Must give consistent message, no necessarily same person each time, just
consistent language.
Scott asked how best to achieve this? Ron said keep it informal. Scott suggested
we ask Keri to contact engineering, set up a lunch time in their office at their
convenience, order pizzas, etc, and just meet. All agreed great idea.
Planning staff is getting cut next year due to drop in development rate; engineering
staff OK because of large waste water projects; no one should be warding off work
these days so hopefully engineering will be able to do the work plan for us.
For nest meeting, August 7, 6pm in the Stiff Building, Olive @ Black
a. Followup on July 14 city commission meeting
b. Discuss engineering plan, getting city office help, potential RFP
c. Need to finish work plan and budget
d. Ask Keri to set up convenient lunch meeting with MDOT -relationship
building
Adjournment - 8:17pm