PROFESSIONAL SERVICES AGREEMENT
FOR
BOZEMAN WASTEWATER TREATMENT PLANT PHASE I
IMPROVEMENTS
THIS IS AN AGREEMENT made as of ~ 2008 between THE CITY OF
BOZEMAN, a Municipal Corporation, P.O. Box 1230, Bozeman, Montana, 59771-1230
(OWNER) and HDR Engineering Inc, 8404 Indian Hills Drive, Omaha, NE 68114-4098,
(ENGINEER).
WHEREAS the parties previously entered into a Professional Services Agreement dated
Anri1T 9 2007, herein referred to as the Original Agreement, for professional engineering services for
the Bozeman Wastewater Treatment Plant Improvements; and
WHEREAS, the scope of the Original Agreement included preliminary design and design
engineering services; and
WHEREAS, the parties desire to amend provisions of the Original Agreement to add
bidding, construction, startup and software programming services for the project.
NOW, THEREFORE, IN CONSIDERATION OF THE MUTUAL COVENANTS
CONTAINED HEREIN, the parties agree as follows:
The conditions and provisions set forth in the attached EXHIBIT F (AMENDMEN PHASE) I
CITY OF BOZEMAN, MONTANA WATER RECLAMATION FACILITY (WRF)
EXPANSION CONSTRUCTION SCOPE OF SERVICES; EXHIBIT G (AMENDMENT NO. l) -
CITY OF BOZEMAN, MONTANA WATER RECLAMATION FACILITY (WRF) PHASE I
EXPANSION ENGINEERING FEE ESTIMATE, are hereby incorporated in and made part ofthis
Agreement.
ARTICLE 4 -Basic Engineering Services
The Title of Section 4.4 of the Original Agreement is replaced with the following:
"4.4 BIDDING OR NEGOTIATING PHASE"
Section 4.4.7 is added to the Original Agreement as follows:
"4.4.7 Provide additional Bidding Services as described in Task 1100 -BID SERVICES of the attached
Exhibit F."
~~
The Title of Section 4.5 of the Original Agreement is replaced with the following:
"4.5 CONSTRUCTION PHASE"
Section 4.5.4 is added to the Original Agreement as follows:
"4.5.4 Additional Construction Contract Services. In addition to the services provided under Article 10
(Exhibit A) and Section 4.5.1 of the Original Agreement, the ENGINEER shall provide the Additional
Construction Contract Services during construction as described in Task 1200 -Construction Administration,
Task 1300 - Proj ect Startup & Commissioning, Task 1400 -Application Software Programming Services and
Task 1500 -Project Closeout of the attached Exhibit F."
Article 6 -Compensation For Engineering Service
Article 6.2 of the Original Agreement is replaced with the following:
"6.2 DIRECT LABOR COST PAYMENT FOR BASIC SERVICES AND EXPENSES OF ENGINEER.
Construction and project documentation services performed as Basic Engineering Services under
Sections 4.4 through 4.7 (Tasks 700, 800 & 900 in Exhibit C, and Tasks 1100, 1200, 1300, 1400 &
1500 in Exhibit F), including General Administration of Construction Contract, Resident Project
Representation, Project Documentation, Construction Testing, Bidding, Project Startup &
Commissioning, Application Software Programming and Project Closeout services shall be
compensated in accordance with the following:
6.2.1 The OWNER shall pay for Bidding Phase, Construction Phase and Project Documentation
Services an amount not to exceed $4 767 571 ($129 9571 SubTasks 700, 800 and 900 Exhibit
C }+$4 637 614 1 SubTasks 1100, 1200, 1300, 1400 and 1500 Exhibit F 1) except as provided under
6.2.1.2 and 6.2.4.
6.2.1.1 Costs Compensation. Compensation for these services shall be based on the ENGINEER's
Direct Labor Cost times a factor of 3.15 for services rendered which shall cover Direct Labor, Direct
Labor Overhead, General & Administrative Overhead and Profit, plus reimbursable expenses as
provided in 6.2.2.
6.2.1.2 Notification. At any time during the construction that it becomes apparent that the Bidding
Phase, Construction Phase and Project Documentation Services rendered under this Agreement will
exceed the negotiated compensation for these services, and prior to performing services in excess of
the contract ceiling, the ENGINEER shall give OWNER written notice thereof. Promptly thereafter
OWNER and ENGINEER shall review the scope and progress of the project work. ENGINEER shall
obtain written authorization from OWNER, prior to any additional costs being incurred under
paragraph 6.2.1.3. If it is determined that due to a change in project scope under paragraph 5.2.1, the
ENGINEER is entitled to additional compensation, OWNER and ENGINEER may negotiate terms as
provided under 6.2.1.1. The amount and terms of any additional compensation under 6.2.1.1 or
6.2.1.3 shall be negotiated and agreed in writing pursuant to 9.16.
6.2.1.3 Costs Exceeding Estimated Compensation. Except as allowed under 5.2.1, when the total cost
of the original scope Construction Phase and Project Documentation Services exceeds the negotiated
compensation for these services, the OWNER shall pay only for the direct costs incur-ed in excess of
the estimated compensation. These costs consist of an amount equal to the ENGINEER'S Direct
Labor Cost times a factor of 2.80 for services rendered which shall include Direct Labor, the
federally audited payroll Direct Labor Overhead, and General & Administrative Overhead costs, but
shall not include any allowance for profit.
2
6.2.2. Failed Test Expenses. The ENGINEER shall maintain and provide to the OWNER, a record
of the costs associated with failing quality control tests performed for the OWNER during the course
of the construction of the project and recommend an amount the OWNER deduct from the
contractor(s) payments.
6.2.3 The OWNER shall pay an amount for Additional Services rendered by the ENGINEER and
approved in writing by the OWNER on the basis of the ENGINEER'S Direct Labor Costs times a
factor of 3.15, or an amount otherwise negotiated at the time such services are requested and approved
by the OWNER. Additional Services also include those services defined in SubTask 1000 of Exhibit
C, in an amount not to exceed 100 000."
Article 7 - Meaning of Terms
Article 7.3 of the Original Agreement is replaced with the following:
"7.3 DIRECT LABOR COSTS
Direct Labor Costs used as a basis for payment mean the actual salaries and wages paid to all
ENGINEER'S personnel engaged directly on the Project, including, but not limited to, engineers,
architects, surveyors, designers, drafters, specification writers, estimators, other technical and business
personnel; but does not include indirect payroll related costs or fringe benefits. For the purposes of
this Agreement the principals and employees of the ENGINEER maximum billable Direct Labor
Costs are:
HDR En ineerin ,Inc.
Princi als $63
Project Desi n/Mana er $63
Su ervisin En ineer III $63
Su ervisin En ineer II $60
Su eroisin En ineer I $53
En ineer III $49
En ineer II $47
En ineer I $30
Desi n En ineer II $36
Desi n En ineer I $30
Staff En ineer $27
Senior Environmental Professional $60
Environmental Professional II $53
Environmental Professional I $27
Project Architect $54
Senior Environmental Technician $29
En ineerin Technician $37
En ineerin Technician II $28
En ineerin Technician I $24
CADD Drafter $24
Accountin /Admin $24
Clerical $24
Morrison - Maierle, Inc.
Princi als $64
Su ervisin En ineer III $53
Su ervisin En ineer II $47
Su ervisin En ineer I $47
Senior En ineer II $44
Senior En ineer I $40
Desi n En ineer II $36
Desi n En ineer I $30
Staff En ineer $25
Senior Environmental Professional $33
Environmental Professional $30
En ineer Intern $25
Senior Surve Mana er $42
Surve Part Chief $35
Land Surve or I $24
Surve Technician $24
Senior En ineerin Technician $37
En ineerin Technician II $28
En ineerin Technician I $24
CADD Drafter $21
Technicians $20
Clerical $19
Printer $21
Except as specifically amended herein, the Original Agreement shall remain in full force and
effect and the parties shall be bound by all terms and conditions therein.
In witness whereof, the Parties hereto do make and execute this Agreement.
CITY OF BOZEMAN, MONTANA
~~
~~(City Manager)
DATE: ~ ~ -1 ~ ' dg
HDR ENGINEERING, INC.
BY:
(Amanda McInnis, P. .Department Manager)
DATE: /~/~~/0200~
ATTEST:
BY: ~ J
(Cit Cler c)
EXHIBIT F -CITY OF BOZEMAN, MONTANA
WATER RECLAMATION FACILITY (WRF)
PHASE 1 EXPANSION
CONSTRUCTION SCOPE OF SERVICES
1 1 00 bid Services
1200 Construction Administration
1300 Project Startup Assistance & Commissioning
1400 Application Software Programming Services
1 S04 Project Close-Out
Task 1 100 -Bid Services
Objective:
Provide assistance to the City in project bidding, bid evaluation and assistance to the City in
award of a construction contract. The scope of services for project bidding assumes that a single
construction contract will be bid and executed. The bidding services provided by
HDR/MMI/IAC shall meet the requirements presented in Section 4.4. of the Professional
Services Agreement (PSA).
HDR/MM/ Subtasks:
Subtask 1101- Printing/Plotting P/ans and Specifications
HDR/MMI will provide for printing of contract documents for use in bidding the construction
contract(s). Half-sized documents will be used exclusively during project review and bidding to
save costs. Full size will be made available after the project bid. Actual number of document
sets may vary dependent upon project requirements. HDR/MMI will invoice the City for actual
charges incurred for printing.
It is assumed that ninety 90 sets of plans and specifications (printed in installments of 30, 20, 20,
10 and 10 sets) will be produced for the final bid and permit acquisition point. HDR/MMI will
provide the City with the camera-ready originals of the project specifications and drawings
following the project bid, and will supply the Contractor with four (4) sets of executed contract
Scope of Services 1 of 20 11/14/2008
documents as required by Section 4.4.6. of the PSA. HDR/MMI will develop a separate
document fee account during the bidding phase for fees collected from the sale of document sets
(non-refundable). HDR/MMI will utilize the document fee collected to address direct costs
associated with document distribution and administration of the project. Any difference in the
cost for document printing and disposition, from what is collected in document fees assessed to
the perspective bidders and what is included as charges presented in the engineering services
budget, will be treated as an additional scope item and billed as additional services. If the
revenue received from the sale of documents exceeds costs for document printing and
distribution, the additional funds will be returned to the City.
Subtask 1102 -Bid Advertisement
HDR/MMI will assist the City in advertising for and obtaining bids for materials, equipment and
services to be performed by a contractor for the construction contract. It is envisioned that the
Project will be bid as a single construction contract, in accordance with Section 4.4.1. of the
PSA.
Subtask 1103 -Prospective Bidder Notification
HDR/MMI will contact up to ten (10) general contractors who have bid similar projects in both
Montana and surrounding states approximately four (4) weeks prior to the first bid advertisement
to alert them to the project, general bidding requirements, etc.
Subtask 1104 -Pre-Bid Conference
HDR/MMI will prepare an agenda and conduct apre-construction conference, in accordance
with Section 4.4.1.of the PSA, to be attended by the City, interested Contractors, and HDR/MMI.
The meeting will include a presentation given by the HDR/MMI Project Manager, and a tour of
the work site.
Subtask 1105 -Addenda and Bid Assistance
HDR/MMI shall receive and respond to prospective contractor questions in accordance with
Section 4.4.2. of the PSA. HDR/MMI shall assist the City in determining acceptability of
substitutes in accordance with Section 4.4.4. of the PSA.
Subtask 1106 -Bid Opening, Tabulation and ContractAward
HDR/MMI will attend the bid opening, prepare bid tabulation sheets, assist the City in evaluating
bids, and help the City determine contractor responsiveness and responsibility. This subtask will
also include assistance to the City for awarding the construction contract in accordance with
Sections 4.4.5. and 4.4.6. of the PSA.
De/iverab/es:
^ Recommended bid advertisement.
^ Camera-ready specifications and reproducible drawings.
^ Pre-qualification review recommendations.
^ Addenda.
Scope of Services 2 of 20 11/14/2008
^ Bid tabulation.
^ Recommendation of award.
^ Pre-bid conference meeting minutes.
^ Drawings (camera-ready copies, eighty (80) half-size copies of bid and permit acquisition
documents, ten (10) copies of full-size after bidding).
^ Specifications (camera-ready copies, eighty (80) copies of bid documents).
^ Final Contract Documents in digital .pdf and ACAD format.
Task 1200 -Construction Administration
Ob, jective.•
Assist the City of Bozeman in administering the construction of the Wastewater Reclamation
Facility Phase 1 Upgrade Project in accordance with Section 4.5 -Construction Phase of the
PSA. The scope of services for project construction services assumes that a single construction
contract would be completed and executed. HDR;/MMI/IAC will manage and control its
professional services contract to provide efficient completion of the project.
HDR/MM///AC Subtasks:
Subtask 1201 -Project Administration
The HDR/MMUTAC project manager will conduct periodic meetings with City staff, in
conjunction with construction review meetings, to review project progress, schedule and budget;
identify information needs, and make decisions regarding changes in the scope of the
construction management efforts.
A progress summary will be prepared with each monthly invoice. The progress summary will
describe the work progress to date, the budget expenditures to date, and identify information
requirements or decisions that need to be made by the City. These memos will help maintain
frequent communications with the City.
Subtask 1 ZOZ -Pre-construction Conference
HDR/MMI will schedule, prepare an agenda and administer apre-construction conference to be
attended by the City, Contractors, appropriate subcontractors, and HDR/MMI's Project and
Construction Services Managers in accordance with Section 4.5.1.1. of the PSA.
Subtask 1 Z03 -Construction Engineering
HDR/MMUTAC will consult with and advise the City of Bozeman as set forth in the engineering
services contract. The City of Bozeman's instructions to the contractor will be issued through
HDR/MMUTAC, who will have limited authority to act on behalf of the City of Bozeman to the
extent provided in the PSA. HDR/MMUTAC will consult with and advise the City of Bozeman
as set forth in Section 4.5 and Article 10, Exhibit A of the PSA.
Scope of Services 3 of 20 11/14/2008
Subtask 1204 - On-site Construction Observation
The City of Bozeman and HDR/MMI agree that HDR/MMI will provide resident representation
at the site. HDR/MMI will provide the City of Bozeman Resident Project Representative(s) to
assist in carrying out such responsibilities at the site, in accordance with Section 4.5.2. and
Article 11, Exhibit B of the PSA.
Subtask 1205 -Record Drawings
HDR/MMI/IAC will prepare final record drawings and maintain communication, data architecture
and control system configuration drawings and data, which conform to construction records and will
furnish the City with an electronic copy of the final product in accordance with Section 4.6. of the
PSA. HDR/MMI will provide the City one set of record drawings on 22 IN x 34 IN reproducible
sheets, two sheets hard copy, as well as one set of record drawings in electronic format for use with
AutoCAD Version 2008. One complete set of .pdf format drawings will also be developed for use at
the treatment plant site and City Engineering office. These drawings will be based on construction
records provided by the Contractor, City and on-site resident project representatives. HDR/MMI will
complete the record drawings within three months of the date of receipt of all of the marked-up prints
and other necessary data from the Contractor.
Subtask 1206- Fie/d Surveying/Staking
HDR/MMI will provide required field surveying and staking for facility construction. Field
survey information will be developed and stakes provided for project components to provide the
Contractor with reasonable information to complete the work.
HDR/MMI has established a horizontal and vertical survey control network around the project
site. Existing facilities are located with respect to this control. Using the existing control,
HDR/MMI will establish one set of stakes for the Contractor to use in performance of the work.
Generally, staking will include pipelines, utility corridors, buildings, structures, access roads,
parking areas, site grading, and fencing. Further, elevation control will be established at multiple
points on the job site. HDR/NIMI will provide the following stakes:
^ Water Main Improvements (Fittings, hydrants, 50' stations)
^ WRF Process Yard Piping Improvements (Fittings, manholes, vaults, 100' stations)
^ Utilidor Improvements (Vaults and 100' stations)
^ New Building Improvements (Building corners)
^ New Structure Improvements (Structure corners and midpoints for circular structures)
^ Access Road Improvements (100' stations, grade changes, fillets)
^ Parking Areas Improvements (100' stations, grade changes, fillets)
^ Curb and Gutter, Paving Improvements (Top back of curb)
^ Storm Drain Improvements (Ditch alignment or pipe at 100' stations, manholes/vaults)
^ Detention Basin Improvements (Basin Bottom with slope stakes)
^ East Gallatin Rip Rap Improvements (100' stations)
^ Fencing Improvements (100' stations, bends, gates)
^ Elevation Control Improvements (20 points across job site)
Scope of Services 4 Of 20 11/25/2008
HDR/MMI will provide the above-described staking one time only. Re-staking or additional
staking needed by the Contractor to complete the work shall be done solely at the Contractor's
Expense.
Subtask 1207- Geotechnica/and Material Testing Services
HDR/MMI will coordinate testing of the construction materials to be incorporated into the
project as part of the construction contract. The Contractor will be required to provide testing
from an independent testing agency for all materials imported for incorporation into the project.
HDR/MMI will provide testing of in-situ materials to be used during construction or materials
control verification using the services of the MMI Bozeman testing lab and local engineering
staff, including provision of the following services:
^ Concrete strength, air content and slump
^ Embankment (backfill), trench backfill, and gravel and pavement densities
^ Aggregate gradations
^ Asphalt concrete plant mix strength, flow and asphalt content and core samples
HDR/MMI will conduct the required on-site testing using the Contractor provided initial
materials control tests for all imported materials, or coordinate the Contractor provided
compaction testing throughout the project, utilizing the materials testing data provided as noted
above. The type and frequency of tests will be specific to the construction and will be
conducted in a manner to develop a good verification that the compaction requirements are being
met. HDR/MMI will coordinate the provision of testing reports and will make recommendation
to the City as to the acceptability of the work in accordance with Section 4.7 of the PSA.
SK Geotechnical will provide observation services on and as needed basis to confirm the
findings of the Geotechnical Evaluation Report.
Subtask 1208- Special /nspection Services
HDR/MMI will provide on-site special inspection of the buildings in accordance with Sections
1704-1709 of the 2006 International Building Code as required by the City of Bozeman Building
Department. HDR/MMI will coordinate the provision of testing reports and will make
recommendation to the City as to the acceptability of the work in accordance with Section 4.7 of
the PSA.
Deliverab/es.•
^ Progress reports and invoices (3 copies and digital .pdf file).
^ Workshop/Meeting agendas and notes in bullet item format (3 copies and digital .pdf
copy of each agenda and meeting notes).
^ Submittal review comment letters responding to contractor submittals.
^ Pre-construction conference meeting summary notes.
^ Construction meeting summary notes and action items list.
^ Field logs including daily reports for all days when HDR/MMUTAC are on-site.
^ Geotechnical and compaction testing reports.
Scope of Services 5 of 20 11/14/2008
^ Responses to requests for information.
^ Response to contract change proposals.
^ Contract change orders.
^ Deficiency punch lists.
^ Record drawings (one set of full-size copies, camera-ready reproducible documents,
digital files).
^ Project observation reports.
^ Shop drawing submittal log.
^ Contractor pay estimate reviews.
^ Compiled monthly reports.
^ Field copy of Shop Drawings.
Task 1300 -Project Startup Assistance and Commissioning
Objectives:
In addition to the startup requirements of the construction contractor, HDR/MMUTAC will
provide startup assistance to the City in final project commissioning of the newly constructed
facilities. The services will include:
HDR/MM///AC Subtasks.~
Subtask 1301 -Operations and Maintenance Manua/
HDR/MMI will prepare an electronic Operations and Maintenance (e0&M) Manual addressing
the improvements incorporated in this project. The manual content and format will be developed
in consultation with City staff and in accordance with Montana Department of Environmental
Quality requirements. It is anticipated that the manual will be provided in electronic form to
meet the minimum O&M requirements of MDEQ. MDEQ can, if preferred, be provided with
one (1) electronic copy for their records and Two (2) hard copy printouts of electronic files to
supplement their existing hard copy O&M Manual records. The Operations and Maintenance
Manual development will include the following general elements:
^ Prepare electronic text and graphics files to reflect the changes in the plant.
^ Text files will be produced in the latest version of Microsoft Word. Graphic files will be
produced in latest version of AutoCAD and converted to .pdf format.
^ The preparation of unit process operating procedures will be provided. General standard
operating procedures will be provided for all key process systems included in the Phase 1
project, and software links will be provided from the e0&M links to provide operator
access to selected e0&M materials.
^ Prepare and deliver a draft electronic copy of the revised text and graphics for review by
the City approximately one month prior to startup.
^ The City will forward a compilation of all comments to the draft electronic copy to HDR
within two weeks of receipt.
^ Revise the text and graphic files and deploy one (1) final electronic version on a City
server and final paper copy (if required) to MDEQ within two weeks of receipt of
comments. HDR will also provide MDEQ with a CD-ROM containing the associated
electronic text and graphics files.
Scope of Services 6 of 20 11/14/2008
Subtask 1302- E/ectronic O&M Manua/
HDR/MMI will develop an e0&M Manual for the City of Bozeman's WRF Phase 1 Project,
which will provide the City staff the necessary information to operate and maintain its facilities
in an efficient and reliable manner. The e0&M Manual will contain a variety of information,
including facility and equipment descriptions, design criteria, process control narratives, design
drawings, and vendor manuals. Using the e0&M Manual, City staff will be able to access this
information in an electronic format with an easy-to-use graphical user interface.
The e0&M Manual will be developed as a web application in the Microsoft ASP.net web
environment and will function on a City provided Windows-based server. The e0&M Manual
will be internally accessible via Internet Explorer and will not be accessible by the general
public. An on-line HTML text editor (Cute Editor) will be embedded in the e0&M Manual web
pages to enable easy text editing by City staff without having to know HTML. HDR owns a
Cute Editor Enterprise License that allows for free distribution as long as the software is used on
HDR's e0&M application. Static data will be retrieved from the City's OP532 5QL database for
digital presentation in the e0&M. Equipment numbering and equipment Data Sheets will be
coordinated with the City's existing JobCal computerized maintenance management system
(CMM5) to the greatest extent possible.
The Operations Manual electronic development would include the following steps:
1. Web Site Map Development. A project kick-off meeting/workshop will be held to
discuss general O&M content, system configuration and customizations, system
installation and training, coordination with the design team, and the overall time schedule
for development and implementation of the e0&M Manual system. The purpose of this
task is to prepare a web site map to illustrate the comprehensive e0&M Manual for the
wastewater treatment facilities. The draft e0&M Manual web site map will:
^ Illustrate the e0&M Manual structure, organization and level of detail for each unit
process.
^ Explain how navigation (hyperlinks) between each section will be implemented.
^ Show what reference information to be included in the e0&M Manual.
The web site map will be developed in coordination with City staff, and will be
specifically tailored to meet requirements and needs of the facility staff. The site map
will be customized as necessary to provide the specific sub-sections desired by the plant
staff. HDR/MMI will initially concentrate on developing the high level architecture of the
e0&M Manual structure to define the structure and organization. HDR/MMI will prepare
a draft web site map for review and comment. HDR/MMI and City staff will then hold a
four-hour workshop focusing on defining the content format and level of detail within
each unit process, including:
^ e0&M Manual guidelines and maintenance help guide.
^ Plant reference information.
^ Equipment O&M manuals provided by equipment vendors via hyperlinks to PDF files.
^ Unit process content details.
Scope of Services 7 of 20 11/14/2008
2. Manual Content Preparation. HDR/MMI will prepare the O&M manual content for each
unit process shown in the web site map. Example content definitions are shown in the
following table. Note that content definitions for this project will be specific and
customized to those sub-sections agreed upon and defined by the web site map developed
with plant staff.
Example e0&M Content Definitions
.
Overview
A short description of each unit process.
A short description of the theory behind each unit process illustrating
Theory the design intent. Strategies for evaluating data and making process
adjustments.
Figures Hyperlinks to 2D and 3D figures illustrating each unit process.
Design Criteria Tabular listing of unit process sizes, loadings, and other design
criteria.
Components Hyperlinks to equipment manuals provided by equipment vendors in
PDF file format.
Controls A description of manual and automatic controls.
System A list of duties to be performed by operators when making daily
Procedures process checks. General procedures for starting up and shutting
down the process.
Troubleshooting A list of process alarms showing possible causes and suggested
responses.
Safety General safety considerations for the unit process.
Existing equipment O&M manuals that are only available in hard copy may be scanned
into PDF files and hyperlinked within the e0&M manual, but will not be included in this
scope of services initially. City personnel will be trained on procedures for completing
this effort following project completion. Equipment record sheets will be stored as .pdf
files.
Graphic Content Definition. HDR/MMI will develop 2D and 3D figures for
communicating to plant O&M staff the design intent, and how to operate the unit process.
The figures will be developed from the conformed contract drawings but will be modified
by deleting extraneous construction related information that is not pertinent to O&M
personnel. The figures will be prepared in AutoCAD and converted to PDF file format
for inclusion in the e0&M Manual. The graphics will be sized for the monitor size the
City intends to use to access the e0&M Manual. A total of fifty (50) 2D and twenty five
(25) 3D figures are anticipated. In addition, HDR/MMI will incorporate the plant as-built
drawings into the e0&M Manual in .pdf file format and provide hyperlinks to each
drawing.
Scope of Services 8 of 20 11/1.4/2008
4. Svstem Conf~uration and Customization. HDR/MMI will develop specific system
customizations, including screen layouts, file formats, administration and integration
needs. Technology issues related to installation on a City web server will be identified.
5. Svstem Installation. HDR/MMI will develop the draft and final e0&M Manuals on an
HDR/MMI server. The draft and final versions will be available to City staff via the
Internet for review. HDR/MMI will coordinate installation of the final e0&M Manual on
the City's server with the City's information technology (IT') staff at the end of the
project. The final e0&M Manual will be downloaded to the City's network server via an
HDR FTP site.
6. Svstem Training. HDR/MMI will schedule a meeting with the plant staff, and facilitate
two (4) four-hour training sessions for the plant staff on how to use and maintain the
e0&M. The four-hour training sessions will provide general instruction and use of the
e0&M Manual and will provide instruction on how the plant staff can edit and revise the
e0&M Manual. Training will also be provided to the City's IT staff on e0&M Manual
system administration, maintenance, and security. One four-hour training session has
been budgeted for this effort. The computers and servers necessary to view the electronic
Operations Manual are not included with the production of the electronic Operations
Manual.
City Requirements:
^ Provide necessary software on City WRF computers to enable the electronic Operations
Manual to function The e0&M Manual hardware and software will be supplied by the
City meeting the minimum requirements as follows:
- Path to and the necessary space on a City provided server at the WRF facilities for
the electronic Operations Manual. The server shall be a Microsoft Windows
machine (running Microsoft Windows Server 2003).
- At least a 2.0 GHz processor or better and 512 of RAM and at least 2 gigabytes of
hard drive space.
- IIS (Internet Information Services 5.0 or higher).
- Microsoft.NET (pronounced dot net), Framework 1.1.
- SQL Server 2000 or later.
- AutoCAD viewer.
^ Frovide ancillary software on the City's computers necessary to run the e0&M Manual,
including Microsoft Internet Explorer, M5 Windows, or Vista and the 5QL database.
^ Existing equipment manuals (hard copy) for.scanning and conversion to Adobe. PDF
files at kickoff meeting.
^ Review comments on draft e0&M Manual.
^ Availability of District IT staff for e0&M Manual installation.
^ Meeting space for e0&M Manual training sessions on the City computer.
^ Participation in training sessions.
^ Participate in teleconferences and meetings.
Scope of Services 9 of 20 11/14/2008
^ Review and approve modifications to approach, schedule and deliverables as
appropriate.
Deliverables:
^ Meeting agenda and minutes for kickoff/web site map workshop.
^ DRAFT and Final e0&M Manual web site maps.
^ New equipment manuals from vendors in .pdf file format as they become available from
the construction contractor.
^ Project as-built drawings in .pdf file format on CD-ROM or via transfer to HDR/MMI
FTP site for hyperlinking in final e0&M manual
^ Draft and final e0&M Manual web site maps.
^ Draft e0&M Manual in electronic format accessible by plant staff via the Internet.
^ Attend meeting at the City WRF site. to demonstrate draft e0&M Manual to plant staff.
^ Final e0&M Manual in electronic format downloadable to the City network server via
an HDR FTP site.
^ Coordination with City's IT staff to download and install final e0&M Manual.
^ Two four-hour training sessions at the WRF to City O&M staff.
^ One four-hour training session to City IT staff.
^ Memoranda and meeting notes, as required.
Subtask 1303 -Plant Faci/ity Start-up and Operator Training
HDR/MMI will review operating data for submission to the funding agencies and will assess
overall performance of the new equipment and facilities. HDR/MMUTAC will provide
operational assistance to the City of Bozeman after the System is started, and train the City of
Bozeman's personnel.
Pre-startup Training will be provided to communicate to the plant operators the following:
1. The ability to operate the equipment in each unit process.
2. An understanding of both the field and SCADA equipment controls and the ability to
operate both.
The pre-startup training will be presented in a classroom setting using a lecture format
supplemented with figures and graphics delivered via an overhead projector or using Microsoft
PowerPoint on an LCD projector. The training material for each specific session will consist of
draft copies of the Operations Manual sections or HDR developed process presentations. Pre-
startup training will be presented in the following modules:
1. Biological Nutrient Removal (BNR) Theory of Operation (To be provided in two (2)
separate and similar sessions by HDR's JB Neethling and Bob Bower -utilizing an HDR
presentation format customized for the Bozeman WRF Facility)
2. Headworks, including influent flow measurement, screening and grit removal
3. Unified Fermentation and Thickening (UFAT) system
4. Primary effluent pumping and flow control systems
5. Bioreactors and aeration blowers system
Scope of Services 10 of 20 11/14/2008
6. Secondary clarification
7. RAS/WAS flow control systems
8. UV disinfection system
9. Anaerobic digestion facilities
10. High strength waste receiving system
11. Utilities and support facilities including standby engine generator and electric service
entrance switchboard
12. HMI and SCADA server system
Coordination with individual HDR/IAC PLC/SCADA programmer(s) will be provided. The
portion of each module pertaining to SCADA controls will be presented by the HDR/IAC
SCADA programmers who programmed that system. The HDR/IAC SCADA programmer will
use an LCD projector to show the actual SCADA screens for each equipment item discussed in
the module. The SCADA presentation will cover manual starting, stopping and speed control of
equipment, set-point adjustment, operating mode changes, alarms, data collection and trending,.
Startup Coordination will also be provided to the City of Bozeman to provide coordination
between the contractor, the construction administration team and the plant staff during startup of
the new equipment. The startup coordinator will allow the startup of new equipment to occur if,
and only if, the equipment and ancillary subsystems are ready to be placed into service and the
manufacturer's O&M manuals are on-site and available for use by plant staff. The secondary
purpose of this effort is to provide informal training to the plant operators during the actual
process startup.
HDR/MMI/IAC will coordinate clean water testing with the contractor. The clean water test
occurs prior to startup and uses non-potable water to demonstrate the functionality of new
equipment and controls. The following process units will have a clean water test:
1. Headworks, including influent flow measurement, screening and grit removal.
2. Unified Fermentation and Thickening (UFAT) system
3. Primary effluent pumping.
4. Bioreactor and aeration blowers.
5. Secondary clarification and RAS/WAS systems.
6. UV disinfection.
7. Anaerobic digestion.
8. High strength waste receiving.
HDR/MMI/IAC will conduct startup service for each project element or unit process in
conjunction with the training services provided by the City's supervisor. Startup means placing
the equipment into operation for its intended purpose and using the intended process material,
i.e. primary effluent, primary sludge, filtrate, etc. Startup assistance will be provided as follows
for the project components listed above.
Startup services will include the following work products:
Scope of Services 11 of 20 11/14/2008
1. Review and approve equipment supplier training agendas and training material outlines
as provided by the Contractor. Use discretion, based on experience with vendor training,
to enforce contract provisions for vendor training duration.
2. Coordinate vendor training schedule with Contractor and plant staff to ensure that vendor
training occurs on Wednesdays as a first choice, Tuesdays and Thursdays as second
choice and avoids Mondays and Fridays.
3. Prepare a startup plan that lists specific responsibilities for the contractor, construction
administration staff, PLC/SCADA programmer(s) and plant staff.
4. Provide the written startup plan to the contractor, the construction administration staff,
PLC/SCADA programmer(s) and the plant staff approximately one month before startup.
5. Schedule and conduct startup review meetings (as required) between the contractor, the
construction management staff, PLC/SCADA programmer(s) and the plant staff
approximately two weeks before startup.
6. Revise and reissue the startup plan and schedule as needed based on the review meeting.
7. Verify the equipment is ready for the clean water test:
8. Verify the manufacturer's field service forms have been completed for each piece of
equipment.
9. Verify pipe pressure tests and concrete water tightness tests have been conducted.
10. Verify rotating equipment has been bumped to check for proper operation and rotation.
11. Verify instrument calibration and loop testing is complete.
The following activities will be performed during startup:
1. Coordinate with the contractor, the construction administration staff, the PLC/SCADA
programmer and the plant staff to ensure that process material is introduced to the process
in such a way as to not adversely impact the rest of the plant.
2. Verify and document that the controls and alarms are working in conformance with the
software pre-design report.
3. Verify and document the results of testing that was deferred from the clean water test.
4. Identify and document equipment or control deficiencies (i.e. punch list).
5. Provide discipline-specific deficiency lists.
Operator training during the clean water test and startup will be conducted by HDR/MMUTAC on
an informal basis in the field. The purpose of this training is to provide an opportunity to answer
operator questions, to demonstrate (when requested) the transition from manual control to
automatic control, and to demonstrate alternate modes of operation (when requested).
Deliverab/es:
^ Startup checklists and training materials including the HDR developed BNR Theory of
Operation session customized for the Bozeman WRF facility.
^ Two separate training sessions (may be consecutive or combined with other systems and
held on the same day) for each of the separate unit project element or process.
^ Written unit process operation procedures for each project element or unit process.
^ Startup plans coordinated with the construction schedule.
Scope of Services 12 of 20 11/14/2008
Task 1400 -Application Software Programming Services
Ob, jectives.•
Implement the programming for the Plant SCADA system including PLC (Programmable Logic
Controller) ladder logic and their associated OI (Local Operator Interface) and HMI (Human-
Machine Interface) configurations. The new PLC ladder logic will be installed on the Plant
PLC's (new and existing, as required). The new HMI interface will be configured using the
Plant's modified Wonderware InTouch 10.0 system, as specified and shown in the Contract
Documents. The PLC ladder logic, OI and Wonderware HMI process displays will be
developed in collaboration with WRF plant personnel to provide the controls as described in the
City of Bozeman Water Reclamation Facility (WRF) Phase 1 Improvements Project Contract
Documents (Project Manual).
The existing Plant SCADA system and PLC ladder logic will be reviewed to identify old control
logic that should be removed. The existing PLCs and PLC applications will also be updated to
the newest version of manufacturer firmware that is available for the hardware and the existing
PLC program(s) and HMI configurations will be edited to conform existing programming to the
new programming configuration where possible. Application and 3rd party module compatibility
will also be verified for firmware upgrades.
The existing process alarm management system will be modified to incorporate the new alarm
points created as part of the Phase 1 Improvements project. The existing process alarm system
includes an alarm dialing software (SCADA!arm) program. The OI and HMI displays (both
existing and new displays) will be modified to conform to the developed project software
standards and provide an improved alarm generation and archive system.
It is intended to demonstrate the functionality of the modified and/or new Wonderware and
Panelview process displays and SCADA alarms in conjunction with the new or modified PLC
ladder logic. City of Bozeman Operations will perform hands-on activities necessary to run the
simulated processes as identified in the Final Software Pre-design Report.
HDR/MM///AC Subtasks:
Subtask 1401-System /ntegration Project Management
HDR/MMUTAC will provide systems integration project management support for the project for
the following work activities:
^ Hold monthly onsite meetings with City of Bozeman Staff, Contractor and design staff to
discuss the mechanics of implementing the Software changes and to define standards to
be followed. The project schedule will be discussed and coordinated with the
construction schedule to define milestones and resource allocations. It is expected the
software development and system integration will occur through approximately twelve
(12) months of the construction period.
^ Document meeting decisions and action items; assign the activities to team members, and
follow-up to ensure timely resolution.
Scope of Services 13 of 20 11/14/2008
^ Review Contractor provided equipment, electrical and instrumentation and control
system submittals, and provide coordination input for electrical and instrumentation
systems.
^ Monitor project progress including work completed, work remaining, budget expended,
schedule, estimated cost of work remaining, and estimated cost at completion.
^ The project schedule will be developed by HDR/IAC following receipt of the
Contractor's project schedule to show the required programming to be completed one
month before the associated construction start-up date.
^ Manage the work provided to verify compliance with the current WRF HMI software
standards, quality of documentation, and scheduling.
^ Monitor project activities for potential changes, anticipate changes whenever possible,
and with City of Bozeman approval, modify project subtasks, subtask budgets, and
approach.
^ Assist the City of Bozeman with the selection of computer workstations, software
packages, and networking components required for the process control and monitoring
equipment for the Phase 1 Improvements project. This includes the recommendation of
computer hardware and software for the SCADA Workstations, SCADA Servers, and
Office Workstations. This contract does not include the costs for the procurement of
these components, and assumes these hardware and software items will be delivered to
HDR/MMI/IAC by the City as needed by the project schedule.
^ To enable work sharing and collaboration between HDR/MMI/IAC and the City, a
project FTP site within HDR's FTP system will be developed to enable "common" access
to available information applicable to system integration.
Deliverables.•
^ Agendas for meetings.
^ Meeting notes for meetings.
^ Monthly invoice with Software project progress summary report.
^ Project software development FTP site.
subtask 1402 -Software Pre-Design Report
HDR/MMUTAC will provide software development preliminary design and develop a software
design summary for the project. The following work activities are planned:
^ Prepare a Software Pre-Design Report for the project which will include the following
information:
1. Understanding of the existing WRF HMI and OI software standards.
2. Updated Control Loop Descriptions (using Contract Document Specification Section
13442).
3. Existing Wonderware HMI and Panelview OI Process Display Printouts marked up to
show planned modifications. Sketches and descriptions of new OI and HMI displays
will be provided.
4. Interface Definition Specifications (ID5), i.e. PLC/OI/I-IMI tag databases, based on
information in the Contract Document).
5. Process Field Database Interface and Report Generation.
Scope of Services 14 of 20 1 ]./14/2008
a. Provide system programming and interface coordination for integration with
the City's existing OPS32 SQL® database and Wonderware's Muni-Suite
software using OPS32 SCADA Interface software provided by the City
through separate procurement.
b. Each report saved with report date-based file naming convention (or as
requested by the City).
6. Conduct review of existing PLC programming and SCADA software and define
recommendations for software programming revisions and cleanup of existing
software code. A minimum of one hundred twenty (120) programming man-hours
are assumed for the review of the existing programs and PLC code.
7. Alarm generation and alarm management will be as shown in the Contract
Documents and will be based on the Wonderware and SCADA!arm handling
functions. As a minimum, alarms will be stored in an alarm database to enable data
access and/or report generation and printing from the SCADA report printer.
8. Real-time and historical data management will be consistent with current WRF
Software standards. Reports will be printed from the historical database files, in
spreadsheet format as desired by the City.
9. Define e0&M interface requirements and coordinate with e0&M development team.
^ Conduct up to three (3) Software Pre-Design Report review meetings with City of
Bozeman staff and HDR/NIlVIUTAC to discuss the following:
1. The modified and new HMI and OI process displays and their functionality for the
major process areas.
2. Identify which OI and Wonderware HMI process screens (and tags) are to be
removed or updated.
a. Report content, format and printing.
b. Alarm management.
c. Data management.
3. Finalize the plan for cleaning up existing OI, HMI and PLC programs.
Document meeting decisions and action items; assign the activities to team members, and
follow-up to ensure timely resolution.
^ Issue the Final Software Pre-design Report, including summary comments and revisions
discussed in the meeting.
Delive~ab/es:
^ Agendas for review meetings.
^ Meeting notes of review meetings.
^ Final Software Pre-design Report -Five (5) copies.
^ Existing PLC program clean-up report.
^ HMI Hardware and Software report.
Scope of Services 15 of 20 11/14/2008
Subtask 1403 -Software Programming & Testing
The PLC logic (Allen-Bradley ControlLogix) program and OI and. HMI process screens and
database configuration will be designed from the information provided by the Final 5ofiware
Pre-Design Report. This subtask includes the following work activities:
^ Obtain the most current existing PLC programs, OI and HMI process screens,
configuration files, tag database(s), data files, and other required files from City of
Bozeman's SCADA system just prior to beginning the programming effort.
^ Develop a PLC, OI and HMI program modification Plan.
^ Before loading the new or modified programming into the various PLC's and the OI and
HMI systems, coordinate with the City of Bozeman staff and IAC to confirm if additional
modifications have been made to the PLC, OI or HMI software.
^ Develop the programming for the new equipment to meet the requirements identified in
the updated Final Software Pre-Design Report.
^ Merge the new or modified PLC, OI and HMI programming with the existing PLC ladder
logic and OI and HMI graphic displays where required.
^ Provide for cleanup programming of the existing PLC and SCADA system programming
identified in the Final Software Pre-design Report. A maximum of one hundred twenty
(120) programming man-hours is assumed for completion of the existing software re-
programming for the purposes of this budget. Actual man-hours will be provided as a
deliverable to the Final Software Fre-design Report.
^ Remove existing PLC programming when it is replaced with new PLC programming.
^ Obtain the latest Panelview and Wonderware process screens and configuration files and
databases (i.e., process database, alarm area database, picture files) for the WRF from the
City and IAC.
^ Wonderware process screens will be designed to meet the requirements identified in the
Final Software Pre-design Report. The types of Wonderware HMI and Panelview OI
process graphics or pictures to be generated include process screens, overview screens,
controller pop-ups, real time and historical trending screens, and report screens. It is
assumed that the existing Wonderware HMI process screens will remain unchanged,
unless any of them need to be modified to include or remove process equipment
pertaining to the Phase 1 project.
^ The new Wonderware HMI and Panelview OI process tag databases, tag-groups, process
screens and the picture files for the new equipment being added will be merged or
replaced with existing screens and files on the SCADA Server. Screen navigation,
consistent with existing, will be modified to integrate these changes into the system.
^ Coordinate with City of Bozeman for required modifications to existing HMI and OI
screens.
The Software will be tested and debugged. HDR/MMUTAC may use a software
simulation package (where possible and practical) to thoroughly test the PLC, HMI and
OI Software process interface. The UO simulator software program will be used to
simulate the real UO to be connected for this project. Only the pertinent Wonderware and
Panelview process databases and the new and modified Wonderware and Panelview
process screens will be active in the simulator for testing to limit confusion and expedite
testing.
Scope of Services 16 of 20 11/14/2008
HDR/MMUTAC will provide a 90% software submittal for City review. A meeting will
be conducted with the City to review City comments and finalize software design.
The City wi//.•
^ Provide the PLC and HMI system software and hardware, specified by HDR/MMUTAC,
to be used for the programming, testing and commissioning efforts. The Hardware and
software will be returned to the City when required to be put into service or at the end of
the project.
^ Review and provide comment on the 90% software submittal.
Deliverab/es:
^ Latest PLC ladder logic disk (CD-ROM) and hardcopy (print-outs).
^ Latest Wonderware and Panelview process electronic files for screens, pictures, pop-ups,
alarms, and data handling. It is assumed the City will continue to utilize their current
OPS32 SQL database program for reporting. HDR/MMUTAC will provide needed
interface programming to enable the City to retrieve data from their SCADA system into
the OPS32 program to continue their current reporting. This scope of services does not
include any additional report development.
^ 90% complete Wonderware and Panelview process displays for City of Bozeman
Operations staff review (color print-out hardcopy, and where applicable marked up color
print-outs of existing graphic displays).
^ As-built documentation of non-modified PLCs, OI or HMI components is not included.
Subtask 1404 - Functiona/Demonstrations
This Subtask includes the following work activities:
During the software development and testing period, HDR/MMI/IAC will perform up to
two (2) periodic QA/QC reviews. This will involve verification that the program strategy
is correct, adequately documented, and in accordance with WRF HMI software standards
developed under Subtask 1402.
Software Demonstration meetings will be held at the 90°10 design completion. It is
anticipated that up to five of these meetings will be required as indicated below. These
meetings will be held in the Water Reclamation Facility. It is intended to demonstrate the
functionality of the modified and/or new Wonderware and Panelview process displays
and SCADA alarms in conjunction with the new or modified PLC ladder logic. City of
Bozeman Operations will perform hands-on activities necessary to run the simulated
processes as identified in the Final Software Fre-design Report.
Software Demonstration 90% Duration
meeting (days +
travel)
Headworks, Primary Effluent 1 2
Pumping systems
Scope of Services 17 of 20 11/14/2008
Software Demonstration 90°Io Duration
meeting (days +
travel)
Blower Room and UFAT I 1
systems 2
Bioreactors, RA5, UV 2
Disinfection, and Digester
Building systems 1
Lift Station No.2 and 1
Miscellaneous systems 6
Totals 5
Deliverables:
^ Agendas for Software Demonstration Meetings.
^ Meeting minutes from the Software Demonstration Meetings.
^ Hardcopy printout of the PLC ladder logic programs.
^ Hardcopy printout of the HMI and OI process displays, databases and reports.
^ SCADA! arm configurations.
Subtask 1405 -Field Commissioning and Software Startup
This subtask includes the following work activities:
~R/MMI/IAC will verify that the interconnections for ~ ~,ed in SectioOn 3440~These
correctly by witnessing the Contractor s loop testa g ( p
tests are referred to as the Operati est~s are ompl te, HDR/MMI/Ip'C ~'~'cill upload the new
^ After the Operational Readiness T
PLC ladder logic. Also, at this time we will transs scre ns and thIe a sociat d d tabased
OI's the new Wonderware and Panelview proc
files. The new Remote I/O Bases will then b erator alarm notification func ons wl be
Functional Testing period will begin. All op
tested for proper operation.
^ Functional Testing is the process of putting b e erforerned. Minor corrections lw ll be
operation. Loop tuning of the controls wi p
made to the new PLC logic and Wonderware and Panelview process interfaces and
SCADA alarms if found necessary.
Deliverables: re-startup and startup
Field commissioning and software startup plan identifying p
^ activities and responsibilities. This plan will be issued prior to startup.
Deliver new or modified PLC program files to be installed prior to the Functional Testing
period.
18 of 20 i v14i2oos
Scope of Services
HDR/MMI will provide their consultation on contract close-out in accordance with the PSA
Subarticle 4.5.1.12 and 4.5.1.13.
Subtask 1 S02 -Certification
C will rovide the City with the necessary certification documentation as required
HDR/MMI/IA p y with the one-
by the Montana Department of Environmental Qualm theirrta lcrov°al f the project design and
year certification requirements provided by MDBQ pp
will include the evaluation of one year of treatment plant performance data and individual
process unit performance testing.
Deliverables:
^ Final recommendation for payment.
^ Final deficiency list check-off.
^ Notice of project acceptance and final project completion.
End Scope of Services
20 of 20
11 /14/2008
Scope of Services
Key personnel
HDR
DM -Design Manager
QA1 -Quality Assurance
QA3 -Quality Assurance
DT1 -Design Team
DT2 -Design Team
DT3 -Design Team
DT5 -Design Team
OPS -Operations Specialist
TS1 -Technical Support
TS2 -Technical Support
TS3 -Technical Support
TS6 -Technical Support
TS7 -Technical Support
TS8 -Technical Support
CAD - CAD Technidan
ADM1 -Project Controller
ADM2 -Project Assistant
MMI
DT -Design Team
CMSt - CM Specalists
PDT2 -Preliminary Design Team
DT7-StrocWal Design
DT7 -Design Team
DT8 -Design Team
CMS3 - CM Specialists
TS17 -Technical Support
TS12 -Technical Support
CS1 -Construction Team
CS2 -Construction Team
ADM2 -Clerical
IAC SI-1 - Prtncpal
SI-2 -Project Manager
SI3 -Senior Engineer
SI4 -Project Engineer
SI-5 - ConWls Engineer
Slfi -Senior Programmer
Labor Cateaorv Nar
Design Manager Dar
Principal g~
Principal Jot
Supervising Engines Cr
Engineer II Ma
Engineer I Co
Engineering Technic Tc
Supervising Engines Ct
Project Architect Dc
Supervising Engines Tr
Engineer III gi
Supervising Engines D
Engineer III q
Princpal E
CADD Drafter h
Accounfing/Admin. M
Clerical t
Supervising Engines
Supervising Engines
Supervising Engines
Senior Engineer I
Senior Engineer I
Senior Engineer II
Engineering Technh
Land Surveyw/CAC
Design Engineer II
Construction Engin
Constriction Engin
Clerical
Principal
Project Manager
Senior Engineer
Project Engineer
Controls Engineer
Senior Programm
DRAFTBOZeman Phase 1 Construction Budget (11)rev.xls
11/21/2ppg
Task 1100 Bidding Services
HDR Staff
Dan Harmon, Design Manager
Bud Benjes, QA
John Koch, QA
Craig Caprara, RASIWAS Pumping
Matt Gough, Aeration BasinIBNR
Coralynn Jones, Blower Building
Tom Hanou, Constructibilty
Chris Sheridan, Operations Specialist
Donn Hogan, Architectural
Paul Cockrell, HVAC
Brad Miller, Structural Design
Don Best, Instrumentation Design
Adam Serock, Project Financing/3D
Emie Swanson/Randy Geist, Electrical
Allyson Gillespie, CAD Technician
Katie Ward, Project Controller
Chris Kelly, Project Assistant
HDR Totals
Morrison Maierie Staff
Nancy Cormier, Hydraulic Profile
James Nickelson, Site Planning
Mike Kaczmarek, Groundwater Study
Nate Menuez, Structural Design
Craig Brawner, Design Team
Travis Meyer, Ultraviolet Disinfection
Bill Farrell, Field Inspection
Steve Rude, Surveyor
Mike Brandt, Standby Power
Roger Sommerville, Construction Team
Steve Malmberg, Construction Team
Sue DugaNPaula Madden, Clerical
Morrison Maierie Totals
IAC Staff
Chuck Wambeke, Principal
Gary Johnson, Project Manager
Mark Jenko, Senior Engineer
Kyle Cram/Mike Roche, Project Engineer
Matt Wolfe, Controls Engineer
Sean Rumelhart, Senior Programmer
IAC Totals
Exhlbn G
City of Bozeman Water Reclamation Faclllty
Phase 1 Expansion
Total
1101 1102 1103 1104 1106 1106 Hours Rate Total
0 4 0 12 104 44 164 $ 60.00 $ 9840.00
0 0 0 0 0 0 0 $ 65.00 $ -
0 0 0 0 4 0 4 $ 65.00 $ 260.00
0 0 0 0 0 0 0 $ 60.00 $ -
0 0 8 0 80 0 88 $ 44.00 $ 3 872.00
0 0 0 16 100 0 116 $ 26.00 $ 3 016.00
0 0 0 0 0 0 0 $ 38.00 $ -
0 0 0 0 0 0 0 $ 55.00 $ -
0 0 0 0 24 0 24 $ 52.00 $ 1248.00
0 0 0 0 8 0 8 $ 58.00 $ 464.00
0 0 0 0 8 0 8 $ 47.00 $ 376.00
0 0 0 0 60 0 60 $ 57.00 $ 3,420.00
0 0 0 0 0 0 0 $ 25.00 $ -
0 0 0 0 0 0 0 $ 59.00 $ -
8 0 0 0 0 0 8 $ 23.00 $ 184.00
32 0 0 0 32 0 64 $ 19.00 $ 1216.00
32 0 0 0 0 0 32 $ 2.00 S 736.00
.
'?2 4 8 29 420 44 576 3 24.63200.
0 20 0 0 20 0 40 $ 45.00 $ 1800.00
0 60 0 132 8 40 240 $ 51.00 $ 12 240.00
0 0 0 0 0 0 0 $ 45.00 $ -
0 0 0 0 0 0 0 $ 38.00 $ -
0 20 0 8 20 44 92 $ 36.00 $ 3 312.00
D 0 0 0 0 0 0 $ 43.00 $ -
0 0 0 0 0 0 0 $ 29.00 $ -
0 0 0 0 0 0 0 $ 33.00 $ -
0 0 0 0 0 0 0 $ 34.00 $ -
0 0 0 8 0 0 8 $ 35.00 $ 280.00
0 0 0 0 0 0 0 $ 31.00 $ -
0 60 n n 20 0 An S 18.00 $ 1,440.00
0 160 0 148 68 &4 d60 S 19072A0
0 0 0 0 0 0 0 $ 51.00 $ -
0 0 0 0 0 0 0 $ 44.00 $ -
0 0 0 0 0 0 0 $ 41.00 $ -
0 0 0 0 0 0 0 $ 33.00 $ -
0 0 0 0 0 0 0 $ 31.00 $ -
0 0 0 0 0 0 0 $ 32.00 $ -
TOTAL HOURS 72 164 x. 8 - 176 48A 12[3 1036
Total Labor S 43,704.00
1101' Printing/Plotting Plans and Specifications OH/Profit Multiplier x3.16
1102' Bid Advertisement Total Direct Labor _ S 137,667.60
1103` Prospective Bidder Notification
1104' Pre-bid Conference Direct Expenses:
1105` Addenda and Bid Assistance
Miscellaneous $ 7,000.00
1106* Bid Opening, Tabulation and Contract Award Travel Expenses $ 1,100.00
MappirxyPhotos/Surveys $ 2,000.00
Printing and Photocopying $ 11,000.00
Technology $ 5,949.60
Total Direct Expenses $ 27,049.60
S 164,717.20
DRAFTBozeman Phase 1 Construction Budget_(11)rev.xls Page 3 of B
11 /21 /2008
~ }~ T
`y
Exhibit G
City of Bozeman Water Reclamation Facility
Phase 1 Expansion
Task 1300 Project Startup Assistance & Commissioning
HDR Staff
Dan Harmon, Design Manager
Bud Benjes, QA
John Koch, QA
Craig Caprara, RAS/WAS Pumping
Matt Gough, Aeration Basin/BNR
Coralynn Jones, Blower Building
Tom Hanou, Constructibilty
Chris Sheridan, Operations Specialist
Donn Hogan, Architectural
Paul Cockrell, HVAC
Brad Miller, Structural Design
Don Best, Instrumentation Design
Adam Serock, Project Financing/3D
Ernie Swanson/Randy Geist, Electrical
Allyson Gillespie, CAD Technician
Katie Ward, Project Controller
Chris Kelly, Project Assistant
HDR Totals
Morrison Maierle Staff
Nancy Cormier, Hydraulic Profile
James Nickelson, Site Planning
Mike Kaczmarek, Groundwater Study
Nate Menuez, Structural Design
Craig Brawner, Design Team
Travis Meyer, Ultraviolet Disinfection
Bill Farrell, Field Inspection
Steve Rude, Surveyor
Mike Brandt, Standby Power
Roger Sommerville, Construction Team
Steve Malmberg, Construction Team
Sue Dugan/Paula Madden, Clerical
Morrison Maierle Totals
Subtasks Total
1301 1302 1303 Hours Rate Total
4 16 16 36 $ 60.00 $ 2,160.00
0 0 0 0 $ 65.00 $ -
0 0 16 16 $ 65.00 $ 1,040.00
0 0 0 0 $ 60.00 $ -
0 0 0 0 $ 44.00 $ -
0 24 24 48 $ 26.00 $ 1,248.00
0 0 0 0 $ 38.00 $ -
40 1160 460 1660 $ 55.00 $ 91,300.00
0 0 0 0 $ 52.00 $ -
0 0 0 0 $ 58.00 $ -
0 0 0 0 $ 47.00 $ -
0 0 0 0 $ 57.00 $ -
0 100 0 100 $ 25.00 $ 2,500.00
0 0 0 0 $ 59.00 $ -
8 290 0 298 $ 23.00 $ 6,854.00
0 0 0 0 $ 19.00 $ -
0 0 40 40 $ 23.00 $ 920.00
',S2 .1:590 556 2198 $ 106 022.00
0 16 24 40 $ 45.00 $ 1,800.00
8 16 40 64 $ 51.00 $ 3,264.00
0 0 0 0 $ 45.00 $ -
0 0 0 0 $ 38.00 $ -
0 0 180 180 $ 36.00 $ 6,480.00
8 16 24 48 $ 43.00 $ 2,064.00
0 0 0 0 $ 29.00 $ -
0 0 0 0 $ 33.00 $ -
0 0 0 0 $ 34.00 $ -
0 0 80 80 $ 35.00 $ 2,800.00
0 0 0 0 $ 31.00 $ -
8 0 0 8 $ 18.00 $ 144.00
24 48 348 420 S 16,552.00
0 0 5 5 $ 51.00 $ 255.00
0 0 8 8 $ 44.00 $ 352.00
0 0 16 16 $ 41.00 $ 656.00
0 0 100 100 $ 33.00 $ 3,300.00
0 0 0 0 $ 31.00 $ -
0 0 0 0 $ 32.00 $ -
0 ' ' 0 129 129 $ 4,563.00
IAC Staff
Chuck Wambeke, Principal
Gary Johnson, Project Manager
Mark Jenko, Senior Engineer
Kyle Cram/Mike Roche, Project Engineer
Matt Wolfe, Controls Engineer
Sean Rumelhart, Senior Programmer
IAC Totals
TOTAL HOURS 76 1638 1033 2747
1301 Operations and Maintenance Manual Total Labor $ 127,137.00
1302 Electronic O & M Manual OH/Profit Multiplier x3.15
1303 Plant Facility Start-up and Operator Training Total Direct Labor $ 400,481.55
Direct Expenses:
Miscellaneous $ 10,000.00
Travel Expenses $ 5,000.00
Mapping/Photos/Surveys $ -
Printing and Photocopying $ 1,000.00
Technology $ 10,383.50
Total Direct Expenses $ 28,383.50
TASK TOTAL $ 426,865.05
DRAFTBozeman Phase 1 Construction Budget_(11)rev.xls Page 5 of 8 11/21/2008
c 't
Exhibit G
City of Bozeman Water Reclamation Facility
Phase 1 Expansion
Task 1400 Application Software Programming Services
Dan Harmon, Design Manager
Bud Benjes, QA
John Koch, QA
Craig Caprara, RAS/WAS Pumping
Matt Gough, Aeration Basin/BNR
Coralynn Jones, Blower Building
Tom Hanou, Consterat!olns Specialist
Chris Sheridan, Op
Donn Hogan, Architectural
Paul Cockrell, HVAC
Brad Miller, Structural Design
Don Best, Instrumentation Design
Adam Serock, Project Financingl3D
Emie SwansoNRandy Geist, Electrical
Allyson Gillespie, CAD Technician
Katie Ward, Project Controller
Chris Kelly, Project HDR1Totals
Morrison Maierle Staff
Nancy Cormier, Hydraulic Profile
James Nickelson, Site Planning
Mike Kaczmarek, Groundwater Study
Nate Menuez, Structural Design
Craig Brawner, Design Team
Travis Meyer, Ultraviolet Disinfection
Bill Farrell, Field Inspection
Steve Rude, Surveyor
Mike Brandt, Standby Power
Roger Sommerville, Construction Team
Steve Malmberg, Construction Team
Sue Dugan/P~orr godrdMaierle Toltals
IAC Staff
Chuck Wambeke, Principal
Gary Johnson, Project Manager
Mark Jenko, Senior Engineer
Kyle CramlMike Roche, Project Engineer
Matt Wolfe, Controls Engineer
Sean Rumelhart, Se lAC Totalsmmer
TOTAL
1401' System Integration
1402` Software Pre-Design Report
1403` Software Programming and Testing
1404` Functional Demonstrations
1405' Field Commissioning and Software Startup
1406` Post Startup Support
DRAFTBozeman Phase 1 Construction Budget_(11)rev.xls
0
134
TASK TOTAL
Page 6 of 8
Total
0
0.0
15.(
71.1
0 $ 45.00 5
0 $ 51.00 $ "
p $ 45.00 $
0 $ 38.00 $
0 $ 36.00 $
0 $ 43.00 $
0 $ 29.00 $
0 $ 33.00 $ "
0 $ 34.00 $ -
p $ 35.00 $
0 $ 31.00 $
0 $ 1'3.00 $
0 $
$
114 $
51 •~ $ 5,814.
112 $
44.00 $ 4 928,
18 $ 41.00 $ 656
1536 $ 33.00 $ 50,688
40 $ 31.00 $ 1,240
73fi $ 32 00 $ 23,552
~- $ 142,384.00
Total Labor x3.15
OH7Profit Multi Ifer $ 448 509.60
Total Direct Labor
Direct Expenses: $ 30,000.00
Miscellaneous $ 5,000.00
Travel Expenses $ _
Mapping/PhotoslSurveys $ 1,800.00
Printing and Photocopying $ 14,053.00
Technol $ 50 853.00
Total Direct Ex nses
$ 499,362.60
11/21/2008
Commission Memorandum
REPORT TO:
FROM:
SUBJECT:
MEETING DATE:
Honorable Mayor and City Commission
Bob Murray, Project Engineer
Chris Kukulski, City Manager
2007 WWTP Upgrade - Phase I Expansion Project
12/1/08
RECOMMENDATION: Authorize City Manager to sign.
BACKGROUND: Attached is a copy of the partially executed Amendment Number 1 with HDR
Engineering, Inc. for Professional Engineering Services for the Wastewater Treatment Plant Upgrade -
Phase I Expansion Project. The original agreement only covered the design phase services. This
amendment is to add the bidding and construction phase services.
The document is in the City's standard format. The proposed fee of $4,767,571 appears to be
commensurate with the project complexity and anticipated total project cost. This is part of the total
project costs that were presented to the Commission at the time of the construction contract award.
FISCAL EFFECTS: The project has multiple funding sources which have been the subject of previous
Commission presentations.
ALTERNATIVES: As suggested by the City Commission.
Respectfully submitted,
Robert J. urray Jr., Project ngineer
Chris A. Kukulski, City Manager
Attachments: Amendment No. 1
Report compiled on 11/25/2008