HomeMy WebLinkAboutBozeman WRF Phase 1 Early Out Improvements for Contract Manual
.~
~
.......!)... '.:
^"
"
DOCUMENT NO: '2 2
Water Reclamation Facility (WRF)
City of Bozeman, Montana
Project No. 00. ..52713
Contract Manual
For Construction of:
Bozeman WRF Phase 1 Early Out Improvements
June 2001
ID~
HDR Engineering, Inc.
11'/ MORRISON .
II. MAIERLE, INC.
.
July 12, 2007
Ci~ of Bozeman WRF Early Out ImpI'Ovements Prqject
LETTER OF TRANSMITTAL
SUBJECT:
Addendum No" 1
Dear Bidding Document Holders and Prospective Bidders:
Please find enclosed Addendum No, 1 for thc City of Bozeman WRF Early Out
Improvements Project Please acknowledge leceipt ofthis addendum by signing and
dating the space provided in the Bid FOlm
.
Please contact ow office if you have any questions,
Sincerely,
~~~~G,mc
Daniel T, Harmon, PE
Project Engineet
c" Bob Mmray, City of Bozeman
T om Adams, City of Bozeman
James Nickelson, Morrison Maierle
.
HDR Engineering.lne
1715 South Reserve
SuitaC
Missoula MT 5980H708
PhOlle:(4061537..2200
Fax: (4061541..8131
Wlw/,hdrinC.com
.
ADDENDUM NO.1
City of Bozeman WRF Early Out Improvements Pro,ject
HDR EngineeJing, Inc.
1715 South Reserve, Suite C
Missoula, MT 59801
Phone: (406) 532-2200
Monison Maiede
9011echnology Boulevard
Bozeman, Mf 59771
Phone: (406) 587-0721
PART 1 - GENERAL
1.01 SCOPE
A This addendum forms a paIt of the Bidding and Contract Documents and modifies the
Project Manual and Drawings as described below
B. This Addendum consists of2 pages and the following attachments:
L Updated Planholders List, Dated 7/11/08,
2 Pre-Bid Conference Agenda & Attendance List
1 02 ACKNOWLEDGEMENT
A Bidders acknowledge receipt of this Addendum by signing and dating in the space
provided in the Bid Form
. PAR T 2 - PROJECT MANUAL
2,01 BIDDING REQUIREMENTS, CONTRACT FORMS, AND CONDITIONS OF THE
CONTRACT
A Section 00500 ~ Agreement
1.. To Atticles 00500A.02..A.1.. through 4., modify the days to achieve Substantial
Completion and Final Payment to read as follows:
"1, The work associated with Bid Items No 1 and No" 2 that requires removal
of the aeration basin cells from se1vice for completion will be completed
and ready for basin partial utilization on or before August 31, 2007. It is
assumed that the aeration basin mixers may be lowered into the basins
while the basins are back in se1vice without the need fOt removal of the
basins horn service once again..
2 The remaining work associated with Bid Items No, 1, No, 2, No, 3 and No,.
4, including Owner~provided basin mixers installation and Owner-provided
electtical, instIUmentation and controls, will be substantially completed and
ready for aeration basin service on or before September 30,2007. The
mounting, hoist and rail equipment shall be delivered to the pr~ject early,
as identified in Section 01011 - Owner' Furnished Equipment, for
installation by the Contractor
.
07/12/07
Page I
City ofBozeffillll WRF Early Out Improvements Project
Addendum No 1
.
.
.
"
.J.
The wOIk associated with Bid Item No.4 will be substantially completed
on or bef01e September 3D, 2007
All work will be completed and ready for fmal payment in accordance with
Paragraph 14.07..B. of the General Conditions within 145 calendar days
after the date when the Contract time commences to run, as provided in
Par'agraph 2.03 of the General Conditions"
4..
B. Section 01011 - Owner Fumished Equipment
1 To Article 0 I 0 II.IolA.Ia., change the aeration basin mixer delivery dates to read
as follows:
"a.. Aeration Basin Mixers
Event
Deliver mixer guide mils and
in-basin supports
Deliver mixers and associated
hoists to site
Perform ManufactW'er's Field
Services
No Earlier Than:
July 28, 2007
No Later Than:
August 22, 2007
July 28, 2007
September 14. 2007
September 6, 2007
September 29,2007"
2..02 DIVISION 9 - FINISHES
A. Section 09905 - Painting and Protection Coatings
1.. To Article 09905,3, lA" delete the following in its entirety: "1.. Cast iron (sluice
gate) "
2..03 DIVISION 15 - MECHANICAL
A. Section 15116 - Sluice Gate Repair and Rehabilitation
1 . 10 Article 15116.. L LA.1 C, delete the word "repair" fiom the sentence,
2 Delete AItic1e 15116..1..1 Al.,d in its entirety..
3.. To Article 15116..1..3 A2. and 4, delete the word "repair" and replace with
"rehabilitation."
4. To Atticle 15116 J ..3 A.., add Article L3AS, to read:
"5 . Rehabilitation shall be considered to mean modification of existing gate
seats and operating mechanism to enable operation ohhe gates through
their full range of open-close operation.."
5.. I 0 Article 15116.2..1..E., delete the word "repair" from the article title..
6.. To Article 15116..2..LE..2, delete the word "repair" from the article
END OF ADDENDUM
07/12/07
Page 2
City of Bozeman WRF Early Out Improvements Project
Addendum No 1
.
.
.
CITY OF BOZEMAN
BOZEMAN EARl Y OUI PRo./EO
PLAN HOLDERS LIST
Planholder/
Contact Person
UPDATE: July 11,2007
Planholder
Category
] City of Bozeman 6/28/07 Ovvner
Bob MUIIay
20 East Olive Street
Bozeman, MT
2 HDR Engineering 6/28/07 Engineer
1715 South Reserve Street
Missoula, MT 5980 I
406-532-2200
406-541-813] - fax
3 HDR Engineering 6/28/07 Engineer
2913 Millennium Circle
Billings, MT
4 Morrison Maier'le 6/28/07 Engineer
910 Helena A venue
Helena, MT
5 Morrison Maierle 6/28/07 Engineer
2020 Grand Avenue
Billings, MI
ri Morrison Maier'le 6/28/07 Engineer
901 Technology Blvd
Bozeman, MT
7 Morrison Maierlc 6/28/07 Engineer
1228 Whitefish Stage. Unit 3A
Kalispell, MT
8 Morrison Maierlc 6/28/07 Engineer
30 II Palme!
Missoula M T
9 Gr'eat Falls Builders Exchange 6/28/07 Plan Center
1625 3rd Avenue North
Great Falls MI 59401
406-453-2513
406-72 7-5997 - fax
10 Billings Builders Exchange 6/28/07 Plan Center
2050 Broadwater Ave, Ste A
Billings, MI 59102
406-652-131 ]
406-652-1391 ( fax)
11 McGraw-Hili 6/28/07 Plan Center
Constr'uction/Dodge Plan
Center
4082 Chinden Blvd
Boise, Idaho 83714
12 Missoula Plans Exchange 6/28/07 Plan Center
Jennifer Fox
201 North Russell
Missoula, MI 5980 J
(406) 549~SOO2
(406) 721-2l)41 (fax)
P:\Water\11206 Bozeman\527 1 3 Boz Early Out\8 0 Construction_Equipment Contracts\Early Out Plan Holders
ListDOC
.
.
.
CITY OF BOZEMAN
BOZEMAN EARL.Y OUI PROJECT
PLAN HOLDERS LISI
Planholder/
Contact Person
UPDA TE: July iI, 2007
Planholder
Category
13 NW Montana Plans Exchange 6/28/07 Plan Center
Gail Nickerson
2303 Highway 2 East
Kalispell, MT 59901
(406) 755.5888
(406) 755.5896 (fax)
14 Montana Contractor's 6/28/07 P Ian Center
Association
DeDee Johnson
1717 11\1. Avenue
Helena, MT 59601
(406) 442.4162
(406)449-3199 (fax)
15 Montana DEQ 6/28/07 Agency
Paul LaVigne
16 Montana DEQ 6/28/07 Agency
Paul LaVigne
17 DLM Contf'8cting
40 Spanish Peak D! # 1 02
Bozeman, MT 59718
(406) 586.2881
(406) 586.2868 (fax)
18 Williams PlumbinglHeating General
213 I Industrial Dr
POBox 10
Bozeman, MI 59771
(406) 587-0969
(406) 587-0519 (fax)
19 Bozeman Builders Exchange Plan Center
1105 Reeves Rd W Ste 800
Bozeman, MT 59718
(406)586-7653
(406) 586-4062 (fax)
20 Dick Anderson General
705 Bridge!
Bozeman, MT 59715
(406) 579-4006
(406) 522~5429 (fax)
21 T &L Painting, lne Sub
509 Colorado Ave NW
Great f<alls, MT 59404
(406) 771~7919
(406) 454-0567 (fax)
22
23
24
25
26
27
28
29
P:\Water\11206 Bozeman\52713 Boz. Early Out\S 0 Construction_Equipment Connacts\Early Out Plan Holders 2
List DOC
.
.
.
UPDATE; lu(y 11,2007
CITY OF BOZEMAN
BOZEMAN EARLY OUT PRO/Eel
PLANHOLDERS LIST
Plan holder/
Contact Per-son
Document Planholder
Sent Category
30
31
32
33
P:\Water\11206 Bozeman\52713 Boz Eroly Out\8,0 Construction_Equipment Contl'acts\Early Out Plan Holders 3
listDOC
.
.
.
,
CITY OF BOZEMAN, MONTANA
WRF EARLY OU IMPROVEMENTS PROJECT
JULY 9, 2007 1 :00 PM
PRE-BID CONFERENCE
AGENDA
1. INTRODUCTIONS:
2.. BID OPENING DATE AND TIME:
. Bids Received no later than 2:00 P.M, MST, July '18, 2007.
. Bids Opened 2:00 P,M (or shortly thereafter), July 18,2007, and read aloud at the
City Clerk's Office, 411 E Main Street, Bozeman, Montana.
3" PROJECT OVERVIEW:
. OWNER
. F!Jnding Sources (City Cash Reserves)
. Contract documents available from MMI Bozeman office - Contact James Nickelson,
901 Technology Blvd" Bozeman, MT 59771, #(406)-587-0721, $60 non-refundable
fee per set
. Contract sets available for review at City, MMI, HDR and identified Plan Centers..
4. BID PROPOSAL: (See specification sections 00020, 00100 for instructions.)
. Use forms in Contract Manual"
)- Bid Form - Additional forms available from MMI.. See specification section 00301,
)> General Bidder Information - Montana State License and Registration Required,
)- Bid Bond (Security),
)- Turn in entire bound Contract Manual.. See Section 00100, Article 13
. Subcontractor/Supplier Listing- See Section 00480 - Information Required of Biddrs
on Bid Forms"
. Wage Rates - See specification section 00830.
. Gross Receipts Tax - 1 % to be withheld from contract for payment to Montana Board
of Equalization.. (On Bid Form)"
. Four (4) Bid Items, Basis of Contract Award is total of all Bid Items (Items 1 through
4)
5. LABOR STANDARDS- This project has State rules, laws, etc., that apply. (Refer to
Section 00100, Article 23 and Secti<?n 00830),.
6, PAY REQUESTS
8" Takes time, allow approximately 21.30 days See Section 00810, Articles SC-
14..02 and SC-14,07.
b, Need five (5) signed originals-2 for engineer and 2 for City (file & field), one (1)
for Contractor
7. KEY CONTRACT DOCUMENTS:
. General Conditions, EJCDC 2002 version - See Section 00700
City of Bozeman WRF Early-out Improvements Project
Pre-bid Meeting 1 of 2
7/9/2007
.
.
.
· Supplementary Conditions - See specification section 00810
8 SUBSURFACE INVESTIGATION AND PHYSICAL CONDIT-IONS:
· No soils investigation needed,
· As~built drawings available
g, SCOPE OF WORK/DESCRIPTION OF FACILITIES:
. See specification section 01010 - Work elements, sequencing and time constraints,
· Four (4) separate Bid Items,
· Sluice Gate rehabilitation
. Basin Mixer Installation
· Secondary Clarifier inlet diffusion well modifications
· General Conditions bid Item No 4,
· Aeration cell dewatering and cleanup"
. Owner Furnished Equipment - See Section 01011,
10_ PERMITS & FEES:
. Permits contactor's responsibility
11 UTILITY COORDINATION:
. No initial coordination with Utilities required City contractor to perform electrical
installation
12 TIME OF COMPLETION:
· See specification Section 00500 - Agreement, Article 4.
. Bid Items 1 & 2 in~basin work, requiring basin removal from service ~ completion:
August 22, 2007 - based upon August 1, 2007 notice to proceed
. Remaining work associated with Bid Items 1,2 & 3 - completion: August 27\ 2007 -
based upon August 1, 2007 notice to proceed
. Bid Item 4 substantial completion: September 30, 2007 - based upon August 1, 2007
notice to proceed,
. Liquidated Damages: $200/day.
13" STAGING AND STORAGE AREAS:
. Parking..
· Access/egress
. Storage
14 MISCELLANEOUS ITEMS:
. 7.
15., TOUR OF PROJECT SITE:
City of Bozeman WRF Early-out Improvements Project
Pre-bid Meeting 2 of 2
7/9/2007
.
.
.
CITY OF BOZEMAN, MONTANA
WRF EARLY OUT iMPROVEMENTS PROJECT
JULY 9, 2007 1 :00 PM
PRE-BID CONFERENCE
ATTENDANCE LIST
Name Representing Phone and/or emaH
HDR Engineering 406-532-2207
Dan Harmon Dan.harmon(ci:!hdrinc.com
406-586-2881
Dan Hyer DLM Contracting dlm(ci:!montanadsl.net
406-586-0889
Tim Tholt Dick Anderson Timt@daconstruction.com
_..~--" ..
406-586-9159
T om Adams City of Bozeman tadams@bozeman.net
.
.
.
CONTRACT MANUAL
BOZEMAN WRF PHASE 1 EARLY OUT IMPROVEMENTS
CITY OF BOZEMAN, MONTANA
t hereby certify that the Project Plans and Specifications in the Contract Documents were
prepared by me or under my direct supervision and that I am a duly registered Engineer
under the laws of the State of Montana.
.:t --,
HDR ENGINEERING, INC.
1715 S. Reserve St., Suite C
Missoula, MT 59801
(406) 532-2200 Phone
(406) 541-8131 Fax
.
.
.
CITY OF BOZEMAN, MT
WATER RECLAMATION FACILITY PHASE 1 EARLY OUT IMPROVEMENTS
LIST OF SPECIFICATIONS
DIVISION 0 - BIDDING REQUIREMENTS, CONTRACT FORMS, AND CONDITIONS OF THE
CONTRACT
INVITATION TO BID
INSTRUCTIONS TO BIDDERS
NOTICE OF AWARD
NOTICE TO PROCEED
BID FORM
BID BOND
NON-COLLUSION AFFIDAVIT
INFORMATION REQUIRED OF BIDDERS
CONSTUCTION AGREEMENT
PERFORMANCE BOND
PAYMENT BOND
GENERAL CONDITIONS
SUPPLEMENTARY CONDITIONS TO THE GENERAL CONDITIONS
DUTIES, RESPONSIBILITIES, AND LIMITATIONS OF THE RESIDENT PROJECT
REPRESENTATIVE
FEDERAL PREVAILING WAGE RATE DETERMINATION (DAVIS BACON RATES FOR
PUBLIC WORKS CONTRACTS IN MONTANA)
00020
00100
00130
00140
00301
00410
00460
00480
00500
00610
00620
00700
00810
00821
00830
MISCELLANEOUS FORMS
REQUEST FOR INFORMATION
CHANGE PROPOSAL REQUEST
CHANGE ORDER
FIELD ORDER
WORK CHANGE DIRECTIVE
ORDER TO CONTRACTOR TO SUSPEND WORK
ORDER TO CONTRACTOR TO RESUME WORK
APPLICATION AND CERTIFICATION FOR PAYMENT
CERTIFICATE OF SUBSTANTIAL COMPLETION
CONTRACTORS CERTIFICATE AND RELEASE
SHOP DRAWING TRANSMITTAL
O&M MANUAL TRANSMITTAL
DEACTIVATION REQUEST
EQUIPMENT RECORD SHEET
ADDITIONAL TECHNICAL SPECIFICATIONS
DIVISION 1 - GENERAL REQUIREMENTS
01010 SUMMARY OF WORK
01011 OWNER FURNISHED EQUIPMENT
01035 ENVIRONMENTAL HAZARD INFORMATION
01060 SPECIAL CONDITIONS
01150 MEASUREMENT AND PAYMENT
01340 SUBMITTALS
01370 SCHEDULE OF VALUES
01400 QUALITY CONTROL
01600 PRODUCT DELIVERY STORAGE AND HANDLING
00...52713-00123
Bozeman WRF Phase 1 Early Out Priority Improvements
TQC- 1
6/6/2007
01640
01700
01710
PRODUCT SUBSTITUTIONS
CONTRACT CLOSEOUT
CLEANING
.
DIVISION 2 - SITE WORK
02072 DEMOLITION, CUTTING AND PATCHING
DIVISION 3 - CONCRETE (NOT USED)
DIVISION 4 - MASONRY (NOT USED)
DIVISION 5 - METALS
05505 METAL FABRICATIONS
DIVISION 6 - WOOD AND PLASTIC (NOT USED)
DIVISION 7 - THERMAL AND MOISTURE PROTECTION
07900 JOINT SEALANTS
DIVISION 8 - DOORS AND WINDOWS (NOT USED)
DIVISION 9 - FINISHES
09905 PAINTING AND PROTECTIVE COATING
DIVISION 10 - SPECIALTIES (NOT USED)
DIVISION 11 - EQUIPMENT (NOT USED)
.
DIVISION 12 - FURNISHINGS (NOT USED)
DIVISION 13 - SPECIAL CONSTRUCTION
13342 SECONDARY CLARIFIER MECHANISM IMPROVEMENTS
DIVISION 14 - CONVEYING SYSTEMS (NOT USED
DIVISION 15 - MECHANICAL
15116 SLUICE GATE REPAIR AND REHABILITATION
DIVISION 16 - ELECTRICAL (NOT USED)
DRAWINGS (ATTACHED)
GENERAL
1 TITLE, LOCATION MAP AND DRAWING INDEX
2 STANDARD SYMBOLS AND ABBREVIATIONS
3 SITE LOCATION AND STAGING PLAN
AERATION BASIN MODIFICATIONS
101 PLAN AND SECTIONS
102 SECTIONS AND DETAILS
END OF SECTION
.
00...52713-00123
Bozeman WRF Phase 1 Early Out Priority Improvements
TOC.2
6/6f2007
.
DIVISION 0
.
BIDDING REQUIREMENTS, CONTRACT FORMS, AND
CONDITIONS OF THE CONTACT
.
.
SECTION 00020
INVITATION TO BID
Separate sealed bids for construction of the Bozeman Wastewater Treatment Plant Improvements will be
received by City of Bozeman, Montana at the office of the City Clerk, 411 East Main Street, Bozeman,
Montana 59715 until 2:00 PM local time on July 18, 2007, and then publicly opened and read aloud.
The project generally consists of, but is not necessarily limited to, the following major items: Removal and
rehabilitation of three (3) existing 3 FT x 4 FT manually operated sluice gates within the existing aeration
basins; installation of four (4) new owner furnished submersible mixers (two each in Basin Cells NO.1 and
No.2); and rehabilitation and modification of the existing clarifier center diffusion well direction baffles in
Secondary Clarifier NO.4. This work includes the furnishing and installation of equipment, materials, and
related appurtenances in the following general trade areas of work: demolition, piping, plumbing, roofing
concrete, equipment installation, and other related trades to complete the work. The work will be
completed under a single contract with OWNER'S Engineer completing all required electrical,
instrumentation and controls modifications to the WRF SCADA system for implementing control strategy
changes for the aeration blowers, basin aeration system and new owner provided basin mixers.
The Contract Documents consisting of half size Drawings and Project Manual may be examined or
obtained at the office of Morrison-Maierle, Inc., 901 Technology Blvd., P.O. Box 1113, Bozeman, MT
59771. Phone (406) 587-0721.Required deposit is $60.00 per set, which is non refundable, by regular
mail or United Parcel Service (UPS). Payment of an additional $20.00 is required for express mail. Full
size drawings may be purchased for an additional $60.00, non~refundable.
In addition, the Drawings and Project Manual may also be examined at the following locations:
.
The City Engineer's Office at the City Office Building, 20 East Olive, Bozeman, Montana and the offices of
the consulting engineer, HDR Engineering Inc., 1715 S. Reserve St., Suite C, Missoula, Montana; and
2913 Millennium Circle, Billings, Montana; Morrison-Maierle, Inc., at 910 Helena Avenue, Helena,
Montana; 2020 Grand Avenue, Billings, Montana; 901 Technology Boulevard, Bozeman, Montana; 1228
Whitefish Stage Road, Unit 3A, Kalispell, Montana; 3011 Palmer, Missoula, Montana; or 1321 8th Avenue
North, Suite 104, Great Falls, Montana; or at plan exchanges in Great Falls, Billings, Dodge-Sean-Boise,
Kalispell, Missoula, Montana Contractors-Helena.
There will be a Pre~Bid Conference at the Wastewater Treatment Plant at 255 Moss Bridge Road (near
the North 19th Street interchange) at 1 :00 PM local time on July 9, 2007. Interested CONTRACTORS are
encouraged to attend. A tour of the project site(s) will be conducted after the meeting.
CONTRACTOR(s) and any of the CONTRACTOR's subcontractors bidding on this project will be required
to obtain registration with the Montana Department of Labor and Industry (DLI). Forms for registration are
available from the Department of Labor and Industry, P.O. Box 8011, 1805 Prospect, Helena, Montana
59604-8011. Information on registration can be obtained by calling 1-406-444-7734. CONTRACTOR's
are required to have registered with the DLI prior to bidding on this project.
All laborers and mechanics employed by CONTRACTOR(s) or subcontractors in performance of the
construction work shall be paid wages at rates as may be required by the laws of the United States and
the state of Montana in accordance with the schedule of Davis-Bacon prevailing wage rates established '
by the United States Department of Labor and/or the schedule of Montana Prevailing Wage Rates
established by the Montana Department of Labor and Industry included in the Project Manual.
The CONTRACTOR must ensure that employees and applicants for employment are not discriminated
against because of their race, color, religion, sex or national origin.
.
Each bid or proposal must be accompanied by a Certified Check, Cashier's Check, or Bid Bond payable
to The City of Bozeman Montana, in an amount not less than ten percent (10%) of the total amount of the
bid. Successful BIDDERS shall furnish an approved Construction Performance Bond and a Construction
(Labor and Materials) Payment Bond, each in the amount of one hundred percent (100%) ofthe contract
00...52713-00123
Bozeman WRF Phase 1 Early Out Priority Improvements
00020 - 1
6/26/2007
amount. Insurance as required shall be provided by the successful BIDDER(s) and a certificate(s) of that
insurance shall be provided.
The applicable goals and timetables for minority and female utilization shall be included in all Federal and
Federally assisted construction contracts and subcontracts in excess of $10,000. The goals are
applicable to the CONTRACTOR'S aggregate on-site construction work force, not merely that part of the
work force that is performing work on a federal or federally assisted contract or subcontract. The
appropriate goal is inserted in the blank in the Federal EPA Supplemental General Conditions. These
goals are applicable to all of the CONTRACTOR'S construction work regardless of Federal participation
performed in the covered area.
No bid may be withdrawn after the scheduled time for the public opening of the Bids specified above.
The right is reserved to reject any or all Proposals received, to waive informalities, to postpone the award
of the contract for a period of not to exceed ninety (90) days, and to accept the lowest responsive and
responsible bid which is in the best interest of the City of Bozeman.
The CONTRACTOR(s) is required to be an Equal Opportunity Employer.
Brit Fontenot
City Clerk
City of Bozeman
411 East Main
Bozeman, MT 59715
Publication Dates:
July 1, 2007
July 8, 2007
00.. .52713-00123
6/26/2007
Bozeman WRF Phase I Early Out Priority Improvements
00020 - 2
.
.
.
.
.
.
SECTION 00100
INSTRUCTIONS TO BIDDERS
,
,"
TABLE OF CONTENTS
ARTICLE 1 - DEFINED TERMS..... ................................................... ............................................. 2
ARTICLE 2 - COPIES OF BIDDING DOCUMENTS...................................................................... 2
ARTICLE 3 - QUALIFICATIONS OF BIDDERS............................................................................. 2
ARTICLE 4 - EXAMINATION OF BIDDING DOCUMENTS, OTHER RELATED DATA, AND
SiTE....................................................................................................................... 3
ARTICLE 5 - PRE-BID CONFERENCE .........................................................................................5
ARTICLE 6 - SITE AND OTHER AREAS....................................................................................... 5
ARTICLE 7 - INTERPRETATIONS AND ADDENDA.................................................................... 5
ARTICLE 9 - CONTRACT TIMES ............................. ......................................... ............................ 6
ARTICLE 10 - UQUIDA TED DAMAGES, ....................................................................................... 6
ARTICLE 11 - SUBSTITUTE AND "OR-EQUAL" ITEMS .........~.................................................... 6
ARTICLE 12 - SUBCONTRACTORS, SUPPLIERS, AND OTHERS ............................................ 6
ARTICLE 13 - PREPARATION OF BID ......................................................................................... 6
ARTICLE 14 - BASIS OF BID; COMPARISON OF BIDS.............................................................. 7
ARTICLE 15 - SUBMITTAL OF BID................................ .......................... ..................................... 8
ARTICLE 16 - MODIFICATION AND WITHDRAWAL OF BID...................................................... 9
ARTICLE 17 - OPENING OF BIDS ................................................................................................ 9
ARTICLE 18 - BIDS TO REMAIN SUBJECT TO ACCEPTANCE:................................................ 9
ARTICLE 19 - AWARD OF CONTRACT ....................................................................................... 9
ARTICLE 20 - CONTRACT SECURITY AND INSURANCE ....................................................... 10
ARTICLE 21 - SIGNING OF AGREEMENT ................................................................................. 10
ARTICLE 22 - MONTANA STATE LAWS AND REGULATIONS ................................................10
ARTICLE 23 - COMPLIANCE WITH LABOR STANDARDS AND WAGE RATE
REQUI REMENTS........... ,.................................................................................... 10
ARTICLE 24 - PAYMENTS AND BIDDER BREAKDOWN OF BIDS .......................................... 11
ARTICLE 25 - NOTICE OF APPROVAL OF PAYMENT REQUEST PROVISION ..................... 11
ARTICLE 26 - NOTICE OF EXTENDED PAYMENT PROViSiON.............................................. 11
ARTICLE 27 - RET AINAGE......................................................................................................... 12
ARTICLE 28 - BOZEMAN BUSINESS LICENSE ....................................................................... 12
00...52713.00123
Bozeman WRF Phase 1 Early Out Priority Improvements
00100. I
6/612007
SECTION 00100
INSTRUCTION TO BIDDERS
ARTICLE 1 - DEFINED TERMS
.
1.01 Terms used in these Instructions to Bidders will have the meanings indicated in the General
Conditions and Supplementary Conditions. Additional terms used in these Instructions to Bidders have the
meanings indicated below which are applicable to both the singular and plural thereof:
A. Bidder-The individual or entity who submits a Bid directly to OWNER.
B. Issuing Office-The office identified in the Invitation to Bid from which the Bidding Documents are
to be issued and where the bidding procedures are to be administered.
C. Successful Bidder-- The lowest responsible Bidder submitting a responsive Bid to whom OWNER
(on the basis of OWNER's evaluation as hereinafter provided) makes an award.
ARTICLE 2 - COPIES OF BIDDING DOCUMENTS
2.01 Complete sets of the Bidding Documents in the number and for the deposit sum, if any, stated in the
Advertisement or Invitation to Bid may be obtained from the Issuing Office. The deposit will not be refunded.
2.02 Complete sets of Bidding Documents must be used in preparing Bids; neither OWNER nor
ENGINEER assume any responsibility for errors or misinterpretations resulting from the use of incomplete
sets of Bidding Documents.
2.03 OWNER and ENGINEER, in making copies of Bidding Documents available on the above terms, do
so only for the purpose of obtaining Bids for the Work and do not confer a license or grant for any other use.
ARTICLE 3 - QUALIFICATIONS OF BIDDERS
.
3.01 To demonstrate Bidder's qualifications to perform the Work, within five (5) days of OWNER's request,
Bidder shall submit written evidence such as financial data, previous experience in performing comparable
work, business and technical organization, present commitments, and such other data as may be called for
below or in the Supplementary Conditions.
A. Each Bid must contain evidence of Bidder's qualification to do business in the state where the
Project is located or covenant to obtain such qualification prior to award of the contract. No Bidder
will be acceptable if he is engaged in any other work which impairs his ability of meeting all
requirements herein stipulated.
B. In determining the lowest responsible bid, the following elements will be considered; whether the
Bidder involved:
1. maintains a permanent place of business;
2. has adequate plant and equipment to do the work properly and expeditiously;
3. has a suitable financial status to meet obligations incident to the work; and
4. has appropriate technical experience with at least 3 comparable projects involving
rehabilitation or modifications of water andlor wastewater mechanical treatment plants in
size ranging from 1 to 10 mgd.
C. Each Bidder may be required to show that former work performed by him has been handled in
such a manner that there are no just or proper claims pending against such work. No Bidder will be
acceptable if he is engaged on any other work which impairs his ability to finance this contract. The
Bidder shall demonstrate his ability by meeting all requirements herein stipulated, if asked for them.
.
00...52713-00123
Bozeman WRF Phase I Early Out Priority Improvements
00100 - 2
6/6/2007
ARTICLE 4 - EXAMINATION OF BIDDING DOCUMENTS, OTHER RELATED DATA, AND SITE
.
4.01 Subsurface and Physical Conditions
A The Supplementary Conditions identify:
1. Those reports of explorations and tests of subsurface conditions at or contiguous to the
Site that ENGINEER has used in preparing the Bidding Documents.
2. Those drawings of physical conditions in or relating to existing surface and subsurface
structures at or contiguous to the Site (except Underground Facilities) that ENGINEER has
used in preparing the Bidding Documents.
B. Copies of reports and drawings referenced in the Supplementary Conditions will be made
available by OWNER for examination by any Bidder at the Issuing Office on request. Those reports
and drawings are not part ofthe Contract Documents, but the "technical data" contained therein upon
which Bidder is entitled to rely as provided in paragraph 4.02 of the General Conditions has been
identified and established in paragraph 4.02 of the Supplementary Conditions (if any). Bidder is
responsible for any interpretation or conclusion Bidder draws from any "technical data" or any other
data, interpretations, opinions or information contained in such reports or shown or indicated in such
drawings.
4.02 Underground Facilities
A Information and data shown or indicated in the Bidding Documents with respect to existing
Underground Facilities at or contiguous to the Site is based upon information and data furnished to
OWNER and ENGINEER by owners of such Underground Facilities, including OWNER, or others.
OWNER and ENGINEER do not assume responsibility for the accuracy or completeness thereof
unless expressly provided otherwise elsewhere.
. 4.03 Responsibility for Adequacy of Data Furnished .
A Provisions concerning responsibilities for the adequacy of data furnished to prospective Bidders
with respect to subsurface conditions, Underground Facilities, and other physical conditions, and
possible changes in the Bidding Documents due to differing or unanticipated conditions appear in
paragraphs 4.02,4.03, and 4.04 ofthe General Conditions. Provisions concerning responsibilities for
the adequacy of data furnished to prospective Bidders with respect to a Hazardous Environmental
Condition at the Site, if any, and possible changes in the Contract Documents due to any Hazardous
Environmental Condition uncovered or revealed at the Site which was not shown or indicated in the
Drawings or Specifications or identified in the Contract Documents to be within the scope of the Work
appear in paragraph 4.06 of the General Conditions.
4.04 Access to the Site
A On request, OWNER will provide Bidder access to the Site to conduct such examinations,
investigations, explorations, tests, and studies as Bidder deems necessary for submission of a Bid.
Bidder shall fill and compact all holes and clean up and restore the Site to its former condition upon
completion of such explorations, investigations, tests, and studies. Bidder shall comply with all
applicable Laws and Regulations relative to excavations and utility locates.
4.05
Other Work at the Site
.
A Reference is made to Article 7 of the Supplementary Conditions or other sections of the Project
Manual for the identification of the general nature of other work that is to be performed at the Site by
OWNER or others (such as utilities and other prime contractors) that relates to the Work for which a
Bid is to be submitted. On request, OWNER will provide to each Bidder for examination access to or
copies of Contract Documents (other than portions thereof related to price) for such other work.
00...52713-00123
Bozeman WRF Phase 1 Earty Out Priority Improvements
00100 - 3
6/6(2007
4.06
It is the responsibility of each Bidder before submitting a Bid to:
A. Examine and carefully study the Bidding Documents, including any Addenda and the other related
data identified in the Bidding Documents;
.
8. Visit the Site and become familiar with and satisfy Bidder as to the general, local, and Site
conditions that may affect cost, progress, and performance of the Work; including but not limited to
those general and local conditions affecting transportation, disposal, handling and storage facilities,
availability of labor, water, power, roads, climactic conditions and seasons, physical conditions at the
work Sites and project area as a whole, job site topography and ground conditions, equipment and
facilities needed preliminary to and during work prosecution;
C. Become familiar with and satisfy Bidder as to all Federal, State, and Local Laws and Regulations
that may affect cost, progress, or performance of the Work;
D. Carefully study all reports of explorations and tests of subsurface conditions at or contiguous to
the Site and all drawings of physical conditions in or relating to existing surface or subsurface
structures at or contiguous to the Site (except Underground Facilities) which have been identified in
the Supplementary Conditions as provided in paragraph 4.02 of the General Conditions.
E. Obtain and carefully study (or accept consequences of not doing so) all additional or
supplementary examinations, investigations, explorations, tests, studies, and data concerning
conditions (surface, subsurface, and Underground Facilities) at or contiguous to the Site, which may
affect cost, progress, or performance of the Work or which relate to any aspect of the means,
methods, techniques, sequences, and procedures of construction to be employed by Bidder,
including applying any specific means, methods, techniques, sequences, and procedures of
construction expressly required by the Bidding Documents, and safety precautions and programs
incident thereto;
.
F. Agree at the time of submitting its Bid that no further examinations, investigations, explorations,
tests, studies, or data are necessary for the determination of its Bid for performance of the Work at
the price(s) bid and within the times and in accordance with the other terms and conditions of the
Bidding Documents;
G. Become aware of the general nature of the work to be performed by OWNER and others at the
Site that relates to the Work as indicated in the Bidding Documents;
H. Correlate the information known to Bidder, information and observations obtained from visits to
the Site, reports and drawings identified in the Bidding Documents, and all additional examinations,
investigations, explorations, tests, studies, and data with the Bidding Documents;
I. Promptly give ENGINEER written notice of all conflicts, errors, ambiguities, or discrepancies that
Bidder discovers in the Bidding Documents and confirm that the written resolution thereof by
ENGINEER is acceptable to Bidder; and
J. Determine that the Bidding Documents are generally sufficient to indicate and convey
understanding of all terms and conditions for the performance of the Work.
4.07 Representation Made by Submitting a Bid
A. The submission of a Bid will constitute an incontrovertible representation by Bidderthat Bidder
has complied with every requirement of this Article 4, that without exception the Bid is premised upon
performing and furnishing the Work required by the Bidding Documents and applying any specific
means, methods, techniques, sequences, and/or procedures of construction that may be shown or
indicated or expressly required by the Bidding Documents, that Bidder has given ENGI NEER written .
notice of all conflicts, errors, ambiguities, and discrepancies that Bidder has discovered in the Bidding
Documents and the written resolutions thereof by ENGINEER are acceptable to Bidder, and that the
Bidding Documents and any written resolutions are generally sufficient to indicate and convey
understanding of all terms and conditions for performing and furnishing the Work.
00...52713-00123 Bozeman WRF Phase 1 Early Out Priority Improvements 6/6/2007
00100 - 4
4.08 A. Reference is made to Division 1 - General Requirements, Section 01010 - Summary of Work,
for the identification of the general nature of Work that is to be performed at the site by OWNER
or others (such as utilities) that relates to the Work for which a Bid is to be submitted. On
request, OWNER will provide to each BIDDER for examination access to or copies of Contract
Documents (other than portions thereof related to price) for such Work.
.
ARTICLE 5 - PRE-BID CONFERENCE
5.01 A pre-Bid conference will be held at the time, date and place specified in the Invitation to Bid.
Representatives of OWNER and ENGINEER will be present to discuss the Project. Bidders are encouraged
to attend and participate in the conference. ENGINEER will transmit to all prospective Bidders of record such
Addenda as ENGINEER considers necessary in response to questions arising at the conference. Oral
statements may not be relied upon and will not be binding or legally effective.
ARTICLE 6 - SITE AND OTHER AREAS
6.01 The Site is identified in the Bidding Documents. All additional lands and access thereto required for
temporary construction facilities, construction equipment, or storage of materials and equipment to be
incorporated in the Work are to be obtained and paid for by CONTRACTOR. 'Easements for permanent
structures or permanent changes in existing facilities are to be obtained and paid for by OWNER unless
otherwise provided in the Bidding Documents.
ARTICLE 7 -INTERPRETATIONS AND ADDENDA
.
7.01 All questions about the meaning or intent of the Bidding Documents are to be submitted to
ENGINEER in writing. Interpretations or clarifications considered necessary by ENGINEER in response to
such questions will be issued by Addenda mailed or delivered to all parties recorded by ENGINEER as having
received the Bidding Documents. Questions received less than ten (10) days prior to the date for opening of
Bids may not be answered. Only questions answered by formal written Addenda will be binding. Oral and
other interpretations or clarifications will be without legal effect.
7.02 Addenda may be issued to clarify, correct, or change the Bidding Documents as deemed advisable
by OWNER or ENGINEER.
7.03 Any addenda issued during the time of bidding, or forming a part of the Contract Documents loaned
to the Bidder for the preparation of his proposal, shall be covered in the Bid and shall be made a part of the
Agreement. Receipt of each addendum shall be acknowledged in the Bid and on the Bid Form. Any Bid in
which all issued addenda are not acknowledged will be considered incomplete and will not be read.
ARTICLE 8 - BID SECURITY
8.01 A Bid must be accompanied by Bid Security made payable to OWNER in an amount of ten percent
(10%) of Bidder's maximum Bid price and in the form of a cashier's check, certified check, bank money order,
or bank draft, in any case drawn and issued by a national banking association located in Montana or by any
banking corporation incorporated under the laws of Montana; or a Bid Bond on the form attached issued by a
surety authorized to do business in Montana meeting the requirements of paragraphs 5.01 and 5.02 of the
General Conditions. Bid Bonds shall be countersigned by a Resident Montana Agent.
8.02 The Bid Security of the Successful Bidder will be retained until such Bidder has executed the Contract
Documents, furnished the required contract security and met the other conditions of the Notice of Award,
whereupon the Bid Security will be returned. If the Successful Bidder fails to execute and deliver the Contract
Documents and furnish the required contract security within fifteen (15) days after the Notice of Award,
OWNER may annul the Notice of Award and the Bid security of that Bidder will be forfeited. The Bid Security
of other Bidders whom OWNER believes to have a reasonable chance of receiving the award may be
retained by OWN ER until the earlier of seven (7) days after the Effective Date of the Agreement or (91 ) days
after the Bid opening, whereupon Bid Security furnished by such Bidders will be returned.
.
8.03 Bid security of other Bidders whom OWNER believes do not have a reasonable chance of receiving
the award may be returned within seven days after the Bid opening.
00...52713-00123 Bozeman WRF Phase 1 Early Out Priority Improvements 6/6f2007
00100 - 5
ARTICLE 9 - CONTRACT TIMES
9.01 The number of days within which, or the dates by which, the Work is to be (a) Substantially .
Completed and (b) also completed and ready for final payment are set forth in Section 00301 Bid Form and
Section 00500 Construction Agreement.
ARTICLE 10 - LIQUIDATED DAMAGES
10.01 Provisions for liquidated damages, if any, are set forth in Section 00301 Bid Form and Section 00500
Construction Agreement.
ARTICLE 11 - SUBSTITUTE AND "OR-EQUAL" ITEMS
11.01 The Contract, if awarded, will be on the basis of materials and equipment specified or described in the
Bidding Documents without consideration of possible substitute or "or-equal" items. Whenever it is indicated
in the Bidding Documents that a substitute or "or-equal" item of material or equipment may be furnished or
used by CONTRACTOR if acceptable to ENGINEER, application for such acceptance will not be considered
by ENGINEER until after the Effective Date of the Agreement. The procedure for submission of any such
application by CONTRACTOR and consideration by ENGINEER is set forth in Paragraph 6.05 ofthe General
Conditions and may be supplemented in the Supplementary Conditions or the General Requirements of the
technical specifications.
ARTICLE 12 - SUBCONTRACTORS, SUPPLIERS, AND OTHERS
. 12.01 If the Supplementary Conditions require the identity of certain Subcontractors, Suppliers, individuals,
or entities to be submitted to OWNER in advance of a specified date prior to the Effective Date of the
Agreement, the apparent Successful Bidder, and any other Bidder so requested, shall within 7 days after Bid
opening, submit to OWNER a list of all such Subcontractors, Suppliers, individuals, or entities proposed for
those portions of the Work for which such identification is required. Such list shall be accompanied by an
experience statement with pertinent information regarding similar projects and other evidence of qualifications .
for each such Subcontractor, Supplier, individual, or entity if requested by OWNER. If OWNER or
ENGINEER, after due investigation, has reasonable objection to any proposed Subcontractor, Supplier,
individual, or entity, OWNER may, before the Notice of Award is given, request apparent Successful Bidder to
submit a substitute, without an increase in the Bid.
12.02 If apparent Successful Bidder declines to make any such substitution, OWNER may award the
Contract to the next lowest Bidder that proposes to use acceptable Subcontractors, Suppliers, individuals, or
entities. Declining to make requested substitutions will not constitute grounds for forfeiture ofthe Bid Security
of any Bidder. Any Subcontractor, Supplier, individual, or entity so listed and against which OWNER or
ENGINEER makes no written objection prior to the giving of the Notice of Award will be deemed acceptable to
OWN ER and ENGI N EER subject to revocation of such acceptance after the Effective Date of the Agreement
as provided in paragraph 6.06 of the General Conditions.
12.03 CONTRACTOR shall not be required to employ any Subcontractor, Supplier, individual, or entity
against whom CONTRACTOR has reasonable objection.
ARTICLE 13 - PREPARATION OF BID
13.01 The Bid Form is included with the Bidding Documents. Additional copies may be obtained from
ENGINEER; however, the Bid must be made on the forms provided in this bound copy of the Project
Manual. Bids shall be strictly in accordance with the prescribed form. Any modifications thereof or deviations
therefrom may be considered as sufficient cause for rejection. Bids carrying riders or qualifications to the Bid
being submitted may be rejected as irregular.
13.02 All blanks on the Bid Form shall be completed by printing in ink or by typewriter and the Bid signed in
ink. A Bid price shall be indicated for each section, Bid item, alternative, adjustment unit price item, and unit
price item listed therein, or the words "No Bid," No Change," or "Not Applicable" entered.
13.03 A Bid by a corporation must be executed in the corporate name by the president or a vice-president
or other corporate officer who is authorized to bind the corporation accompanied by evidence of authority to
00... 52713~00123 Bozeman WRF Phase I Early Out Priority Improvements 6/612007
00100 - 6
.
.
.
.
sign. The corporate seal shall be affixed and attested by the secretary or an assistant secretary. The
corporate address and state of incorporation must be shown below the signature.
13.04 A Bid by a partnership shall be executed in the partnership name and signed by a partner, whose title
must appear under the signature accompanied by evidence of authority to sign. The official address of the
partnership must be shown below the signature.
13.05 A Bid by a limited liability company shall be executed in the name of the firm by a member and
accompanied by evidence of authority to sign. The State of formation of the firm and the official address of
the firm must be shown below the signature.
13.06 A Bid by an individual shall show the Bidder's name and official address.
13.07 A Bid by a Joint Venture shall be executed by each Joint Venturer in the manner indicated on the Bid
Form. The official address of the Joint Venture must be shown below the signature.
13.08 All signatures are to be in ink and names must be typed or printed in ink below the signatures. The
title of the person(s) executing the Bid shall be clearly indicated beneath the signature(s).
13.09 The Bid shall contain an acknowledgment of receipt of all Addenda, the numbers of which must be
filled in on the Bid Form. A copy of all acknowledged Addenda shall be attached to the Bid Form. Bids in
which all issued addenda are not acknowledged will be considered incomplete and will not be read.
13.10 The address and telephone number for communications regarding the Bid must be shown.
13.11 The Bid must contain evidence of Bidder's authority and qualification to do business in Montana.
Bidder's current Montana state contractor registration number, shall be shown on the Bid Form.
13.12 The Bid will not be considered unless accompanied by proper Bid Security in accordance with Article
8 of these I nstruction to Bidders.
13.13 The Bid may not be considered unless all attached forms or certifications in this Project Manual are
completed. Depending on federal assistance regulations, these may include, but are not limited to:
Noncollusion Affidavit
Certification of Nonsegregated Facilities
13.14 Alternate Bids will not be considered unless called for.
13.15 Bids by telephone, telegraph, fax or other telecommunication systems will not be considered.
13.16 No Bidder may submit more than one Bid. Two Bids under different names will not be received from
one firm or association.
ARTICLE 14 - BASIS OF BID; COMPARISON OF BIDS
14.01 Lump Sum
A. Bidders shall submit a Bid on a lump sum basis for each item of Work listed in the Bid Schedule
as provided in the Bid Form. The Bid will not be considered unless the Bid Form contains prices for
all unit price and/or lump sum items, and alternates, as shown on the Bid Form. Bids and totals shall
be shown legibly in their proper locations. The Total Amount of the Bid shall be legibly written and
numerically presented in the proper places and the Bid Form shall be manually signed.
Discrepancies between words and figures will be resolved in favor of the words.
14.02 The Bid price shall include such amounts as the Bidder deems proper for overhead and profit on
account of cash allowances, if any, named in the Contract Documents as provided in paragraph 11.02 of the
General Conditions.
14.03 The low Bidder will be determined on the basis of the sum of the lowest total Lump Sum Bid Price.
00...52713-00123
Bozeman WRF Phase 1 Early Out Priority Improvements
00100 -7
6/6/2007
14.04 If any of the listed items of equipment to be selected by the Owner are obviously unbalanced and, in
the Owner's judgment, not realistic prices for the particular equipment, the Owner may request additional
information to substantiate the prices prior to determination of the low Bidder or may reject the Bid Proposal.
14.05 The right also is reserved for the Owner to negotiate with the responsible Bidder submitting the lowest .
responsive bid in the event such lowest bid exceeds the amount budgeted for this contract. Such
negotiations, if the Owner elects to negotiate rather than to reject all proposals, shall be directly between the
Owner and such Bidder. The Owner and such Bidder shall review the Contract Documents, and the Owner
may provide such additional information as it deems appropriate to provide. Such Bidder then may be invited
by the Owner to submit a revised bid. The Bidder may elect not to submit a revised bid, and the Owner may
reject any such revised bid. Such revised bid, if any, shall be submitted within thirty days from the date of the
initial bid opening.
ARTICLE 15 - SUBMITTAL OF BID
15.01 Each prospective Bidder is furnished one bound copy of the Bidding Documents with one copy ofthe
Bid Form bound therein. The bound copy of the Bid Form is to be completed and submitted with the Bid
Security and the following data. None ofthe Instructions to Bidders, Bid Form, Bond forms, Agreement,
contract stipulations, or other specifications shall be removed from the bound copy of the Project
Manual prior to submission of Bid. Entire bound Project Manual must be submitted with the Bid at the
Bid Opening.
Data to be submitted with the Bid includes:
A. Copies of acknowledged Addendums
B. Other data required by the Instructions to Bidders, Bid Form, Supplementary Conditions or
Bidding Documents.
15.02 A Bid shall be submitted no later than the date and time prescribed and at the place indicated in the .
Invitation to Bid and shall be enclosed in an opaque sealed envelope plainly marked with the Project title,
the name and address of Bidder, and shall be accompanied by the Bid Security and other required
documents. If a Bid is sent by mail or other delivery system, the sealed envelope containing the Bid shall be
enclosed in a separate envelope plainly marked on the outside with the notation "BID ENCLOSED." A mailed
Bid shall be addressed to:
Honorable Mayor and City Commission
Attention: City Clerk
City of Bozeman Montana
411 East Main Street
Bozeman, MT 59715
15.03 Other Bid submittal requirements:
A. The Bid will not be considered unless accompanied by proper Bid Security in accordance with
Article 8 of these Instruction to Bidders.
B. Alternative Bids will not be considered unless called for.
C. Bids by telephone, telegraph, fax or other telecommunication systems will not be considered.
15.04 The following items shall be completed as part of the Bid submittal:
1. Fill in all blanks on Project Manual Book cover.
2.
Complete all required items in the Bid Form.
.
3. Provide a completed Bid Bond form.
4. Provide a completed Noncollusion Affidavit.
00...52713-00123 Bozeman WRF Phase 1 Early Out Priority Improvements
00100 - 8
6/612007
5. Provide a completed Certification of Nonsegregated Facilities.
.
6. Acknowledge and attach all Addendums.
15.05 Information Required of Bidders: The apparent low Bidder shall be required to submit certain
information as requested in the Section 00480 titled "Information Required of Bidders." This information shall
be submitted within five calendar days after the bid opening by the apparent low Bidder. Failure to comply
with this requirement may render the Bid unresponsive and may result in the rejection of the Bid.
Furthermore, failure of the low Bidder to provide this information shall be reason for the OWNER to make a
claim against the bid security.
ARTICLE 16 - MODIFICATION AND WITHDRAWAL OF BID
16.01 A Bid may be modified or withdrawn by an appropriate document duly executed in the manner that a
Bid must be executed and delivered to the place where Bids are to be submitted prior to the date and time for
the opening of Bids, as called for in the Invitation to Bid. Requests for modification or withdrawal must be
written and must be signed in the same manner and by the same person(s) who signed the Bid.
16.02 If, within twenty-four (24) hours after Bids are opened, any Bidder files a duly signed written notice
with OWNER and promptly thereafter demonstrates to the reasonable satisfaction of OWNER that there was
a material and substantial mistake in the preparation of its Bid, that Bidder may withdraw its Bid and the Bid
security will be returned. Thereafter, if the Work is rebid or negotiated, that Bidder will be disqualified from
further bidding on the Work.
ARTICLE 17 - OPENING OF BIDS
17.01 Bids will be opened at the time and place set for the opening as indicated in the Invitation to Bid and,
unless obviously non-responsive, will be read aloud publicly. An abstract of the amounts of the Bids will be
made available to Bidders after the opening of Bids.
. ARTICLE 18 - BIDS TO REMAIN SUBJECT TO ACCEPTANCE
18.01 All Bids will remain subject to acceptance for ninety (90) days after the day of the Bid opening, but
OWNER may, in its sole discretion, release any Bid and return the Bid Security prior to the end of this period.
ARTICLE 19 - AWARD OF CONTRACT
19.01 OWNER reserves the right to reject any and/or all Bids, including without limitation, nonconforming,
nonresponsive, unbalanced, or conditional Bids. OWNER further reserves the right to reject the Bid of any
Bidder whom it finds, after reasonable inquiry and evaluation, to be non-responsible. OWNER also reserves
the right to waive all informalities not involving price, time, or changes in the Work and to negotiate contract
terms with the Successful Bidder. OWNER also reserves the right to reject the Bid of any Bidder if OWNER
believes it would not be in the best interest of the Project to make an award to that Bidder, whether because
Bid is not responsive, or the Bidder is unqualified or of doubtful financial ability, or fails to meet any other
pertinent standard or criteria established by the OWNER.
19.02 More than one Bid for the same Work from an individual or entity under the same or different names
will not be considered. Reasonable grounds for believing that any Bidder has an interest in more than one
Bid for the Work may be cause for disqualification of the Bidder and the rejection of all Bids in which that
Bidder has an interest.
19.03 In evaluating Bids, OWNER will consider whether or not the Bids comply with the prescribed
requirements, and such alternates, unit prices and other data, as may be requested in the Bid Form or prior to
the Notice of Award.
.
19.04 In evaluating Bidders, OWNER will consider the qualifications of Bidders and may consider the
qualifications and experience of Subcontractors, Suppliers, and other individuals or entities proposed for
those portions of the Work for which the identity of Subcontractors, Suppliers, and other individuals or entities
must be submitted as provided in the Supplementary Conditions.
00...52713-00123
Bozeman WRF Phase I Early Out Priority Improvements
00100 - 9
6/6/2007
19.05 OWNER may conduct such investigations as OWNER deems necessary to establish the
responsibility, qualifications, and financial ability of Bidders, proposed Subcontractors, Suppliers, individuals,
or entities to perform the Work in accordance with the Contract Documents.
19.06 If the Contract is to be awarded, OWN ER will award the Contract to the responsible Bidder whose Bid .
is in the best interests of the Project. Consideration factors will include conformance with all material terms
and conditions of the Contract Documents, Bid price, and other appropriate factors.
19.07 If the Contract is to be awarded, OWNER will give the Successful Bidder a Notice of Award within
ninety (90) days after the day of the Bid opening.
19.08 The OWNER reserves the right to accept or reject the Bids, or portions of Bids if denoted in the Bid as
separate schedules, and to award more than one Bid or schedule for the same Bid if any of the
aforementioned combination of Bids or schedules will be in the best interest of the OWNER.
19.09 The OWNER reserves the right to cancel the award of any Agreement at any time before the
complete execution of said Agreement by all parties without any liability against the OWNER.
19.10 If, at the time this Contract is to be awarded, the total of the lowest acceptable Bid Proposal exceeds
the funds then estimated by the Owner as available, the Owner may reject all Bid Proposals or take such
other action as best serves the Owner's interests.
ARTICLE 20 - CONTRACT SECURITY AND INSURANCE
20.01 Article 5 of the General Conditions, as may be modified by the Supplementary Conditions, sets forth
OWNER's requirements as to Performance Bond, Payment Bond, and insurance. When the successful
Bidder delivers the executed Agreement to OWNER, it must be accompanied by such Bonds and insurance
certificates.
ARTICLE 21 - SIGNING OF AGREEMENT
21.01 When OWNER gives a Notice of Award to the successful Bidder, it shall be accompanied by the
required number of unsigned counterparts of the Agreement with the other Contract Documents which are
identified in the Agreement as attached thereto. Within fifteen (15) days thereafter, successful Bidder shall
sign and deliver the required number of counterparts of the Agreement and attached documents to OWNER.
Within fifteen (15) days thereafter, OWNER shall deliver one fully signed counterparts to Successful Bidder
.
ARTICLE 22 ~ MONTANA STATE LAWS AND REGULATIONS
22.01 All applicable laws, ordinances and the rules and regulations of authorities having jurisdiction over
construction of the project shall apply to the Contract throughout. State laws and ordinances which the
CONTRACTOR must comply with, include but are not limited to, those involving workmen's compensation
insurance, contractor registration, and gross receipts tax.
22.02 . MONTANA CONTRACTOR REGISTRATION REQUIREMENT. Title 39, Chapter 9, Part 2, MCAfor
registration of CONTRACTORS with the Montana Department of Labor and Industry. No bids will be
considered that do not carry the Bidder's Montana Contractor's Registration Number on the bid form and also
on the envelope containing the Bid. Information pertaining to this requirement and registration forms may be
obtained from the Montana Department of Labor and Industry, P.O. Box 8011, 1805 Prospect, Helena,
Montana 59604-8011 or by calling 1-406-444-7734.
22.03 ADDITIONAL CONTRACTOR LICENSE FEE (MONTANA CONTRACTORS GROSS RECEIPTS
TAX). In accordance with Title 15, Chapter 50, MCA, the OWNER shall withhold, in addition to other amounts
withheld as provided by law or specified herein, 1 percent (1 %) of all payments due the CONTRACTOR and
shall transmit such moneys to the Montana Department of Revenue.
ARTICLE 23 - COMPLIANCE WITH LABOR STANDARDS AND WAGE RATE REQUIREMENTS
.
23.01 The work under all Schedules of this Contract is to be paid for in part by state and/or federal grant
and/or loan funds; therefore, minimum prevailing wage rates published by the Montana Department of Labor
and Industry are appended. The OWNER does not guarantee that labor can be procured for the minimum
00...52713-00123 Bozeman WRF Phase 1 Early Out Priority Improvements 6/6/2007
00100 - 10
.
.
.
wages shown on the referenced schedules. The rates of wages listed are minimum only, below which the
CONTRACTOR cannot pay, and they do not constitute a representation that labor can be procured for the
minimum listed.
23.02 The minimum wages included in the Project Manual are not controlling except as to the minimum for
the purpose of Montana State Law or the Davis-Bacon Act; therefore, it is incumbent upon each employer to
pay the standard prevailino rate of wages includino frinoe benefits for health and welfare and pension
contributions. and travel allowance provisions in effect and applicable to the county or localitv in which the
work is being performed. Should the prevailing rate of wages change during the life of the contract, the
CONTRACTOR and/or each employer shall adjust the wages paid to conform to said change in the prevailing
rate of wages as prescribed in Section 18-2-401 through 18-2-432 MCA. The CONTRACTOR and all
subcontractors are directed to the Montana Commissioner of Labor for information on the standard prevailing
rate of wages applicable to this contract within this project area.
23.03 "Standard Prevailing Rate of Wages" is defined by Section 18-2-401 MCA, as including wages, fringe
benefits for health and welfare and pension contributions and travel allowance which are paid in the county or
locality by other contractors for work of a similar character performed in that county or locality by each craft,
classification or type of worker needed to complete a contract.
23.04 Any infraction of the Laws of the State of Montana covering Labor, Title 39, Chapters 1 through 73,
MCA will be forwarded to the State of Montana Department of Labor and Industry.
23.05 "Travel Allowance", in effect at the time of contract award, and according to latest information
received by the State of Montana Department of Labor and Industry, Labor Standards Division, shall be
adhered to where applicable.
23.06 Travel allowance if applicable, mayor may not be all inclusive of "travel" and/or subsistence and
travel time due employees. It is incumbent on the employer to determine the amounts due for each craft
employed according to the method of computation outlined for each craft where applicable.
23.07 To comply with Montana Law Section 18-2-401 thru 18-2-432 MCA, the Contractor shall post in a
prominent and accessible site on the project work area, not later than the first day of work, a legible statement
of all wages to be paid to the employees employed on the project.
ARTICLE 24 - PAYMENTS AND BIDDER BREAKDOWN OF BIDS
24.01 Payment for all work performed under this Agreement will be made by the OWNER within the time
period specified in and in accordance with the procedures outlined in the General Conditions. Payments
made after the time limit will be subject to interest at the rate specified in the Agreement. When the work
extends beyond thirty (30) days, progress payments will be made monthly for any work accomplished during
the preceding month, but subject to retainage as specified elsewhere.
24.02 For the sole purpose offacilitating monthly progress payments, a breakdown oftotallump sum bids is
to be submitted in the Bid Form within 3 working days after the Bid Opening as shown on the Bid Sheet
Schedule. The price breakdown shall be fairly apportioned to the various parts of the work and shall meet
with the ENGINEER's approval. If so requested by the ENGINEER, the CONTRACTOR shall substantiate
any price or prices with additional detail price breakdown or other information as requested by the
ENGINEER.
ARTICLE 25 - NOTICE OF APPROVAL OF PAYMENT REQUEST PROVISION
25.01 These Contract Documents and this Contract allows the OWNER to review and approve each
CONTRACTOR's periodic payment request within 30 days after the request is received by the OWNER.
ARTICLE 26 - NOTICE OF EXTENDED PAYMENT PROVISION
26.01 These Contract Documents and this Contract allow the OWNER to make periodic payments within 21
days after the OWNER's approval of each periodic payment request.
00...52713-00123
Bozeman WRF Phase 1 Early Out Priority Improvements
00100-11
6/612007
ARTICLE 27 - RETAINAGE
27.1 Provisions concerning CONTRACTOR's rights to deposit securities in lieu of retainage are set forth in .
the Agreement.
ARTICLE 28 - BOZEMAN BUSINESS LICENSE
28.01 CONTRACTOR and all subcontractors will be required to obtain a current City of Bozeman Business
License prior to award of the Contract. The City Business License is not required for bidding. The license(s)
may be obtained from the City of Bozeman. Information on requirements and cost of the license may be
obtained by calling 406-582-2300. Applications may be obtained at City Hall, 411 East Main Street
END OF SECTION
.
.
00...52713-00123
Bozeman WRF Phase 1 Early Out Priority Improvements
00100 - 12
6/6/2007
.
.
.
NOTICE OF AWARD
Dated~ q. 2007
Project: Bozeman WRF Phase 1 Early Out
1m rovements
Contract: Phase 1 Early Out Improvements
Owne~s Contract No.:
Owner City of Bozeman
Engineer's Project No. 00.. .52713
Bidder: Dick Anderson, Construction, Inc.
Bidde~s Address: (send Certified Mall, Return Receipt Requested)
Dick Anderson Construction, Inc.
705 Bridger Drive, Suite A
Bozeman, MT 59715
You are notified that your Bid dated Julv 18. 2007 for the above Contract has been considered. You are the
Successful Bidder and are awarded a Contract for: Total work. Bid Items NO.1 throuClh No.4.
The Contract Price of your Contract is: Fortv nine thousand seven hundred ninety four and 0.01/100
Dollars ($49.794.01 ).
Ten (10) copies of each of the proposed Contract Documents (including drawings) accompany this Notice of
Award.
You must comply with the following conditions precedent within fifteen days of the date you receive this Notice
of Award.
1. Deliver to the Owner five (5) fully executed counterparts of the Contract Documents.
2. Deliver with the executed Contract Documents the Contract security [Bonds] as specified in Section
00100, Instructions to Bidders (Article 20), [and] General Conditions (Paragraph 2.01 and 5.01) [and
Supplementary Conditions (Paragraph SC-2.01).]
3. Other conditions precedent:
NA
Failure to comply with these conditions within the time specified will entitle Owner to consider you in default,
annul this Notice of Award and declare your Bid security forfeited.
Within fifteen days after you comply with
counterparts of the Contract Documents.
will return to you two fully executed
By:
C hri & "" K.w.Jt-..Itdt:.,'
-
Authorized Signature
L;"'-'- ~o..t1 Lr
Title "\S ~
Copy to Engineer
BOleman WRF Phase I Early Out Improvements
I
7/23/2007
.
.
.
SECTION 00140
NOTICE TO PROCEED
Dated
Project: Bozeman WRF Phase 1 Early Out
Priority Improvements
Contract:
Owner's Contract No.:
OWner: City of Bozeman
Engineer's Project No.: 00...52713
Contractor:
Contractor's Address: [send Certified Mail, Retum Receipt Requested]
You are notified that the Contract Times under the above contract will commence to run on
. On or before that date, you are to start performing your obligations under the
Contract Documents. In accordance with Article 4 of the Agreement, the date of Substantial Completion is~
, and the date of readiness for final payment is [(or) the number of
days to achieve Substantial Completion is I and the number of days
to achieve readiness for final payment is ].
Before you may start any Work at the Site, Paragraph 2.01. B of the General Conditions provides that
you and Owner must each deliver to the other (with copies to Engineer and other identified additional
insureds) certificates of insurance which each is required to purchase and maintain in accordance with the
Contract Documents.
Also, before you may start any Work at the Site, you must [add other requirements]:
(Contractor)
Received by:
Owner
Given by:
Authorized Signature
(Title)
(Date)
Title
Date
Copy to Engineer
00...52713-00123
Bozeman WRF Phase 1 Early Out Priority hnprovements
00140 - 1
5/1412007
.
.
.
SECTION 00301
BID FORM
PROJECT IDENTIFICATION:
BOZEMAN, MONTANA WATER RECLAMATION FACILITY (WRF) PHASE 1 EARLY OUT
IMPROVEMENTS
BOZEMAN, MONTANA
CONTRACT IDENTIFICATION AND NUMBER:
City of Bozeman Project No.' 00 52- -::;-1 ~
THIS BID IS SUBMITTED TO:
HONORABLE MAYOR AND CITY COMMISSION
ATTN: CITY CLERK
CITY OF BOZEMAN, MONTANA
411 E. MAIN ST.
BOZEMAN, MONTANA 59715
ARTICLE 1 - CONTRACT
1.01 The undersigned Bidder proposes and agrees, if this Bid is accepted, to enter into an Agreement
with OWNER in the form included in the Bidding Documents, to perform and furnish all Work as specified
or indicated in the Bidding Documents for the prices and within the times indicated in this Bid and in
accordance with the other terms and conditions of the Bidding Documents. Bidder will sign and submit
the Agreement with the Bonds and other documents required by the Bidding Requirements within fifteen
(15) days after the date of OWNER's Notice of Award.
ARTICLE 2 - BID TO REMAIN OPEN
2.01 Bidder accepts all of the terms and conditions of the Advertisement or Invitation to Bid and
Instructions to Bidders, including without limitations those dealing with the disposition of Bid Security.
The Bid will remain subject to acceptance for ninety (90) days after the Bid opening, or for such longer
period of time that Bidder may agree to in writing upon request of OWNER.
ARTICLE 3 - SUBMITTING THE BID
3.01 In submitting this Bid, Bidder represents, as set forth in the Agreement, that:
A. Bidder has examined and carefully studied the Bidding Documents, other related data
identified in the Bidding Documents, and the following Addenda, receipt of all which is
hereby acknowledged:
Addendum No.
Addendum Date
01/ \ 2../ ZOo"1-
B.
Bidder has visited the Site and become familiar with and is satisfied as to the general,
local and Site conditions that may affect cost, progress, and performance of the Work.
00...52713-00123
Bozeman WRF Phase 1 Early Out Priority Improvements
0030] - 1
6/6/2007
C. Bidder is familiar with and is satisfied as to all federal, state and local Laws and
Regulations that may affect cost, progress and performance of the Work.
D.
Bidder has carefully studied all: (1) reports of explorations and tests of subsurface
conditions at or contiguous to the Site and all drawings of physical conditions in or
relating to existing surface or subsurface structures at or contiguous to the Site (except
Underground Facilities), if any, which have been identified in the Supplementary
Conditions as provided in paragraph 4.02 of the General Conditions, and (2) reports and
drawings of a Hazardous Environmental Condition, if any, which has been identified in
the Supplementary Conditions as provided in paragraph 4.06 of the General Conditions.
E. Bidder has obtained and carefully studied (or assumes responsibility for having done so)
all additional or supplementary examinations, investigations, explorations, tests, studies
and data concerning conditions (surface, subsurface and Underground Facilities) at or
contiguous to the Site which may affect cost, progress, or performance of the Work or
which relate to any aspect of the means, methods, techniques, sequences, and
procedures of construction to be employed by Bidder, or expressly required by the
Bidding Documents to be employed by Bidder, and safety precautions and programs
incident thereto.
F. Bidder does not consider that any further examinations, investigations, explorations,
tests, studies, or data are necessary for the determination of this Bid for performance of
the Work at the price(s) bid and within the times and in accordance with the other terms
and conditions of the Bidding Documents.
G. Bidder is aware of the general nature of work to be performed by OWNER and others at
the Site that relates to the Work as indicated in the Bidding Documents.
H.
Bidder has correlated the information known to Bidder, information and observations
obtained from visits to the Site, reports and drawings identified in the Bidding Documents,
and all additional examinations, investigations, explorations, tests, studies, and data with
the Bidding Documents.
I. Bidder has given ENGINEER written notice of all conflicts, errors, ambiguities, or
discrepancies that Bidder has discovered in the Bidding Documents, and the written
resolution thereof by ENGINEER is acceptable to Bidder.
J. The Bidding Documents are generally sufficient to indicate and convey understanding of
all terms and conditions for the performance of the Work for which this Bid is submitted.
3.02 Bidder further represents that this Bid is genuine and not made in the interest of or on behalf of
any undisclosed individual or entity and is not submitted in conformity with any agreement or rules of any
group, association, organization or corporation; Bidder has not directly or indirectly induced or solicited
any other Bidder to submit a false or sham Bid; Bidder has not solicited or induced any individual, firm, or
entity to refrain from bidding; and Bidder has not sought by collusion to obtain for itself any advantage
over any other Bidder or over OWNER.
3.03 The Bidder certifies that no official of the OWNER, ENGINEER or any member of such official's
immediate family, has direct or indirect interest in the pecuniary profits or Contracts of the Bidder.
A.
ARTICLE 4 - BID ITEM DESCRIPTION
00.. .52713-00123
This section, in general, describes the bid items included in the BID PROPOSAL. The
description of Bid Items is provided for clarity purposes only. It is not intended to replace,
supersede or preclude any information in the plans and specifications. Unless specified
otherwise, all lump sum and unit price bid items will be paid as a percentage of actual
work complete. Percent complete will be based on the schedule of values submitted by
the Contractor and approved by the engineer. The schedule of values will break down
the lump sum and unit price bid items into discrete work activities beyond the breakdown
shown on the Bid Form. The schedule of values must be submitted and approved by the
Bozeman WRF Phase 1 Early Out Priority Improvements 6/6/2007
00301.2
.
.
.
.
.
.
Engineer before the Contractor can request a payment for work under this Contract.
Descriptions of the project Bid Items are provided below:
BID ITEM NO.1: This unit price Bid Item includes removal, rehabilitation and re-
installation of three (3) 4FT x 3FTsluice gates installed within the existing WRF
aeration basins. The Bid. Item also includes protection of the existing aeration
grid during the sluice gate rehabili~ation effort. Work on each sluice gate
assembly will require isolation of the a.eration basin cells, two at a time,
sequentially to enable access to the work area. The Owner shall drain the basin
cells. It is the Contractor's responsibility to remove wash water. The wash water
shall be disposed of properly through coordination with the Owner.
BID ITEM NO.2: This unit price Bid Item includes provision and installation of
four (4) new Owner provided aeration basin mixers in the existing WRF existing
aeration basins. The mixers will be installed in Aeration Basin Cell Nos. 1 and 2,
with two (2) each in each basin cell. The Bid Item includes installation of the
Owner provided mixer assemblies and assorted lifting hoists. The associated
electrical and controls will be installed by the OWner.
BID ITEM NO.3; This unit price Bid Item includes modifications and
improvements to the metal influent diffusion well baffle directional baffles for
Secondary Clarifier No.4, including all required sandblasting, cleaning and re-
coating of metal affected by the improvements.
BID ITEM NO.4: This unit price Bid Item includes Contractor's
mobilization/demobilization, taxes insurance, permits and all other work not
specifically defined in the other Bid Items.
B.
CONTRACTOR TAKE NOTE: Please pay particular attention to the description of the
basis for awarding the Contract. It is the intent of the Owner to award a Contract to the
lowest responsive, responsible bidder on the basis of the combined total of Bid Items No.
1, No.2, No.3, and No.4. Bidders must include lump sum and unit price bid prices for
all Bid Items No. 1 through NO.4. Bids received that do not include pricing for all Bid
Items will be considered non-responsive.
C. All specific cash allowances are included in the Total Bid Item prices set forth below and
have been computed in accordance with paragraph 11.02 of the General Conditions.
D. Unit Prices have been computed in accordance with paragraph 11.03.B of the General
Conditions. The undersigned agrees that the unit prices shall govern in checking the Bid,
and should a discrepancy exist in the Total Estimated Price and Total Amount of Unit
Prices Bid as listed after extensions are checked and corrections made, if any, the Total
Amount of Unit Prices Bid as corrected shall be used in awarding this Contract.
E. The OWNER reserves the right to reject any or all bids.
00...52713-00123
Bozeman WRF Phase I Early Out Priority Improvements
0030] - 3
6/6/2007
BOZEMAN WASTEWATER TREATMENT PLANT IMPROVEMENTS
BID PROPOSAL SHEET
.
The Bid for the following items shall be a lump sum bid for all construction work described in the Contract
Documents. The bid price shall include all temporary or permanent equipment, materials, supplies, and
labor necessary to construct the item in accordance with the Contract Documents. The total lump sum
price shall be broken down into the following items for the purpose of progress payments and for the
information of the OWNER.
Attachment to #1 Bid Form
1. BID ITEMS:
Bid Item No. Description Total Amount
.
1 Sluice Gate Removal, Rehabilitation and Replacement
Item No. Description Units Quantity Unit Cost Total
Aeration Basin
Dewatering
1.1 Coordination with LS 1
Owner, Wash Water
Removal, Protection of $ ~\Ou .0(; $ ZJOG. Oc
Aeration Grids
Sluice Gate Removal,
1.2 Rehabilitation and Re- EA 3
installation $ CjLQl.Jit-.OO $ Z'1IO() \ .OC
Sluice Gate Touch-up ,
1.3 PaintinQ LS 1 $ (]-OO $ C.OC:
Subtotal $ ,?Jl \{j I . OC
Montana Gross Receipts Tax @ 1 % $ .5\\.0 I
TOTAL BID ITEM NO.1 $ 3L Ll \ 2. ' 0 I
.
Bid Item
No.
Description
Total Amount
2
Installation of Owner provided Basin Mixers and Associated Mounting, Rail &
HoistEqui ment
Description
Aeration Basin Mixers and
Associated Mounting, Rail
and Hoist E ui ment
Aeration Basin Mixer
Commissioning, Training, and
Acce tance T estin
Units
Quantity
Unit Cost
Total
Item No.
2.1
EA
4
$ , 750. 00
$
.
2.2
LS
1
$ Lo50 .00
Subtotal
Montana Gross Receipts Tax @ 1 %
TOTAL BID ITEM No.2
00...52713-00123
Bozeman WRF Pha~e .1 Early Out Priority Improvements
00301 - 4
6/6/2007
.
.
.
Bid Item No.
Description
Total Amount
3
Modifications and Improvements to Secondary Clarifier No.4 Mechanism
Influent Diffusion Well Directional Baffles
De~ri~on Un~
Demolition of existing diffusion
well baffles
Installation of new fabricated
diffusion well baffles
Diffusion well touchwup painting
Item No.
Quantity
Unit Cost
Total
3.1
EA
3
$ ltld.o, lJ
3.2
8
EA
$
.60
3.3
LS
$ lJ.Sb.OO
Subtotal
Montana Gross Receipts Tax @ 1 %
TOTAL BID ITEM No.3
Bid Item Description Total Amount
No.
4 General Conditions
Item No. Description Units Quantity Unit Cost Total
4.1 Mobilization/De- LS 1
mobilization $ Dloo .00 $ YOO, 00.
4.2 General Requirements LS 1 $ \Jl 000. CO $ U 600. ()O
4.3 Permits LS 1 $ 0.6D $ 0.00
Subtotal $ La cIOD.OC
Montana Gross Receipts Tax @ 1 % $ {j)Cj. 0 0
TOTAL BID ITEM No.4 $ (nqlQCl. DO
00...52713-00123
Bozeman WRF Phase I Early Out Priority Improvements
0030] - 5
6/612007
2. BID PROPOSAL SUMMARY (Summary of Bid Items)
Bid Item No.
Description
Total Bid Item Price
(Use Figures)
.
1
Sluice Gate removal, rehabilitation and replacement
$3\ [112-.01
(Use ~igureS)
$ ,'J I T OlQ . !Dr.'\,
(Use Figures) .. .
2
Installation of aeration Owner provided basin mixers and
associated mounting, rail and hoist equipment
3
Modifications and improvements to Secondary Clarifier No.
4 mechanism influent diffusion well directional baffles
$ ,Z::; I ~ OLo ' .7512:,
(Use Figures)
4
General Conditions
$ lo, q Loq , ()()
(Use Figures)
Total Contract Bid Price, including Montana Gross Receipts Tax and other
state and local taxes (Items No.1 through No.4)
$L1q\-=r9~.O!
(Use Figures)
Total Contract Bid Price, including Montana Gross Receipts Tax and other state and local taxes (Bid Items NO.1
through No.4) J-odv. n\Yl (, -t'I1{)1 ISClV\cJ SQ \/.11 Y\ v)llY'dl'Jicl \f)'l\1~ -rOtH' dol lars a.Y1C~ Qrll (1..QJt.:t.
J (Use Words)
BASIS OF AWARD The award will be made by the Owner on the basis of that Bid from the lowest
responsive, responsible Bidder which, in the Owner's sole and absolute judgment, will best serve the .
interest of the Owner. The low Bidder will be determined on the basis of the lowest combined Total Bid
Item Bid Prices of Bid Items No.1, No.2, No.3, and NO.4.
ARTICLE 5 - CONTRACT TIME
5.01 The time of completion of the work is a basic consideration of the Contract. It will be necessary that
the Bidder satisfy the Owner of his ability to complete the work within the stipulated time.
5.02 Bidder agrees that the work will be substantially completed and ready for final payment in
accordance with paragraph 14.07.B of the General Conditions on or before the dates or within the'
number of calendar days indicated in the Constructions Agreement.
ARTICLE 6 - LIQUIDATED DAMAGES
6.01 In the event the Bidder is awarded the Contract and shall fail to meet the Substantial and Final
Completion time limits provided by the Contract Documents, liquidated damages shall be paid to the
OWNER by the Bidder at the rate per calendar day stated in the Agreement plus engineering costs for all
work awarded until all work shall be determined to meet the Substantial and Final Completion
requirements of the Contract Documents.
6.02 The Bidder agrees to pay these liquidated damages for failure to complete the work within the
specified contract time both for compensation to the OWNER for non-use of the completed work and for
compensation to the OWNER for expenses incurred by the OWNER for unscheduled employment of the
Engineer and/or Resident Observer during the contract time overrun.
6.03 The Bidder further agrees to pay liquidated damages for the unscheduled employment of the .
Engineer, Resident Observer and supporting staff necessitated by the Bidder furnishing materials or
00.. .52713-00123 Bozeman WRF Phase 1 Early Out Priority Improvements 6/6/2007
00301 - 6
.
.
.
equipment not in conformance with the Contract Documents resulting in any redesign work by the
Engineer; or any reestablishment of survey lines or benchmarks destroyed by the Bidder's actions; or
additional work required by the failure of the Contractor to maintain adequate record documents.
6.04 Construction observation time will be accrued at straight time up to 40 hours per week and 1.5 times
over 40 hours per week or legal holidays. The Contractor shall provide a construction schedule per
Section 01300, SUBMITTALS. If the Contractor intends to work double shifts, then two construction
observers may be required. If two construction observers are on the job, then observation time will be
accrued a~ttrai Ujme up to 40 hours per week per observer. '
V
6.05 Liql{ mages for the unscheduled employment of the Engineer, Resident Observer, and
supporting .,' all be determined based on the following hourly rates:
: :1-":., i...' " Straiqht Time
Eng'iueer. $122.85/Hour
Res'".laE!f1~bserver' , , $85.00/Hour
survAllt:''i.:',, ". ' $122.85/Hour
Ted?Gi ' " $88.00/Hour
Clerical" , $50.00/Hour
Overtime
$150.00/Hour
$127.50/hour
$122.85/Hour
$132.00/Hour
$75.00/Hour
6.06 Out of pocket expenses for materials, equipment, supplies, transportation and subsistence for each
construction inspector shall be billed at cost plus 10 percent.
6.07 Liquidated damages shall be deducted from monthly progress payments and the final payment as
the damages are incurred.
ARTICLE 7 - BID DOCUMENTS
7.01 The following documents are attached to and made a condition of this Bid:
A.
Required Bid security in the amount of 10% of the maximum Bid price including
alternates, if any, and in the form of a Bid Bond Section 00410, or other form of Bid
Security as identified in the Instructions to Bidders.
B. Surety. If the Bidder is awarded a construction Contract on this Bid Form, the Surety who
provides the Performance Bond and Payment Bond will be:
:~~I~:~\~~ A%:~~~[\
Street City State
whose address is
,t:)'1 Lj t6
Zip ,
N\I
C. Non-Collusion Affidavit.
D. Certification of Nonsegregated Facilities.
E. Information Required of Bidders (tabulation of Subcontractors, Suppliers and other
persons and organizations required to be identified in this Bid).
ARTICLE 8 - MEANING OF TERMS
8.01 The terms used in this Bid with initial capital letters have the meanings indicated in the
Instructions to Bidders, the General Conditions, and the Supplementary Conditions.
ARTICLE 9 - BID REJECTION
9,01 The OWNER reserves the right to reject any or all bids.
00...52713-00123 Bozeman WRF Phase 1 Early Out Priority Improvements
00301-7
6/6/2007
ARTICLE 10 - BID SUBMISSION
SUBMITTED on :-\u.. \\..\ \ 1) ,2007
\
Montana Contractor Registration No.~,~g I A
.
If Bidder is:
'''"i~t
,'IN.' fl!:
A Corporation ,'_ ~p \
;- '-J :) ~
1'-.. - /\ I () o-h/ :::- -~ '(.I ...:J:i>c~ ~ ~
Corporation Name: ! )\cL hYlCi('(<..{)n \-. rlYl~) f LACf2n,~c-IU:' ~g ~EAL)
State of Incorporation: f\l\(\rrtOd'1 0,- ~ %'" ./!~ g
Type (General Business, Professional, Service, Limited -:"'~,,;.14~911fI~'J;:'::
/'1 12, "f/'I"II/:r"~
. .. . l--11\fl II i/li i . 1"1)'- Vi ~c"
LI~~hty): \. );, ~0 "-LA ,~_. \ ~L;, \ /) (l'x') )
~- ) /C' ~: /
B1<- L- /'?/r '/-- ~ ~/:' f r-:--~
Y (Signature --attich evidence of authority to sign if not a Corporate officer)
Name (typed or Rrinted): hJL~".-L~ bIt.-\, y'\ VSJ2.n
Title: \1\ () ~(J,_s\("turcf
~. ~
Attest: /~?-z ~-----------~--
,-" (SignatUfe-6rS~~~ry)
{ ~.""
Business address: -=+-ns ~- \ c\ Q 1<. \( ~.' \ \;! J.
:r"X}tJiYYlClY'1 [\10- 50/""-1- IS
Phone No.: LJ6Lt ~ S?{U - o 'is t(9
(Corporate Seal)
.
Date of Qualification to do business in Montana is
FAX No.:L.JllU- 5~tr 045,<';<
1~1-~
An Individual
Name (typed or printed):
By:
(SEAL)
(Individual's signature)
Doing business as:
Business address:
Phone No.:
FAX No.:
A Partnership
Name (typed or printed):
Bozeman WRF Phase 1 Early Out Priority Improvements
00301 - 8
(SEAL)
6/6/2007
.
By:
00...52713-00123
.
.
11.
.
SECTION 00480
INFORMATION REQUIRED OF BIDDERS
The Bidder shall furnish the following information as specified in Section 00100 Instructions To Bidders.
Failure to do so may render the Bid unresponsive and may result in rejection of the Bid. Additional sheets as
required may be attached.
1.
CSI1R~~~{J~i:Ud7~ Tnc.
2.
Contractor's telephone number: 4tJl1-J=~,'i<:lo - ny; 5<'9
3.
"-
IJr( i2SdJ I\~
4.
Name of Contractor=s representative who inspected the site:
l\ YY\ \lr\n,-t-
Date of Inspection: 0,':7! a 9 I 2...06"7
5. Name, address and telephone number of surety company and agent who will provide required bonds
~~i~~7>~~~ A~.~r~ I~: ~:irr0(VI
(-_~~~l& _ _~ ~ 4:~-/~=-Y_'-!
Attach a list of construction contracts completed by the Bidder during the last 10 years involving
similar work and the amount of the Contract. The list shall include projects the Bidder is currently
working on along with the names, addresses, and the telephone numbers of the project owner
representative most familiar with the details of the project. State the approximate cost of each project
along with the total amount of change orders as a percentage of the original bid price.
7. Bank reference. List the Bank name, Contact person, and telephone number:
N\o~+~~~ YiJ..Q..~i ~n..V\ L ContacT : Dou.~,+;' .\~ v
~y\()---,: . _ _ - _ q ~ ~2l.1_ fo..x: LJO /J1- L/l.f1- 4
8. Have you ever failed to complete any work awarded to you? t\.\o
If so, where and why?:
6.
9. Have you ever defaulted on a contract? No
If so, where and why?
I'
10. Have you ever had any project terminated by the Owner? l\.. \ (\
If so, where and why?
Are you involved in any lawsuits or are any lawsuits pending at the present time?
"i1"
If yes, give the details: ~\Q~ ~...e Q.jf-ili.Vl ai
00..52713-00123
Bozeman WRF Phase I Early Out Priority Improvements
00480 - I
5/22/2007
12.
13.
Will you, upon request, fill out a detailed financial statement and furnish any other information that
may be required by the Owner? ljJ>:'->
Na e of the Rropo~ed resident project superintendent:
0,
Attach aresume of the proposed resident project superintendent including a list and description of all
projects on which this individual has acted as project superintendent along with the name, address,
and telephone number of each project owner representative most familiar with the details of the
project and the capabilities of the proposed project superintendent
14. The Bidder shall list below the name, business address, and contractor=s license number, if any, of
each subcontractor who will be working on this project along with the nature and value of work
assigned to each subcontractor. No changes or substitutions will be allowed without written approval
of the Owner.
Name: Value:
Name: Value:
Name: Value:
Name:
Name:
Name:
Name:
00...52713-00123
Value:
Value:
Value:
Value:
Bozeman WRF Phase I Early Out Priority Improvements
00480 - 2
5122/2007
.
.
.
.
.
.
(Individual's signature)
Name (typed or printed):
Business address:
Phone No.:
FAX No.:
A Joint Venture (Each Joint Venture must sign.)
Joint Venturer Name:
(SEAL)
By:
(Signature of joint venture partner)
Name (typed or printed):
Title:
Business address:
Phone No.:
FAX No.:
Joint Venturer Name:
(SEAL)
By:
(Signature of joint venture partner)
Name (typed or printed):
Title:
Business address:
Phone No.:
FAX No.:
Address of Joint Venture for Receipt of Official Communication:
Address:
Phone No.:
FAX No.:
(Each joint venturer must sign. The manner of signing for each individual, partnership, and
corporation that is a party to the joint venture should be in the manner indicated above.)
END OF SECTION
OO...527l3-00123
B07.eman WRF Phase 1 Early Out Priority Improvements
00301 - 9
6/6/2007
.
.
.
SECTION 00460
NONCOLLUSION AFFIDAVIT
(TO BE EXECUTED AND PROVIDED WITH BID FORM)
STATE OF MONTANA
COUNTY OF Q(1 \ \0. --\l Vl
) SS
\/R~ c-l~ ~~~~\ SQ VI ,(~~:~gO:~~~Yp~~~~r: ~:~~:~t~~~:.i~~~~~~ ~f
\)\rL A<<\.~vSN\ ('(')(\'.-;--vu.CTtc'lVl I ---r31r. ,
the party making the foregoing bid; that such bid is not made in the interest of or on behalf of any undisclosed
person, partnership, company, association, organization, or corporation; that such bid is genuine and not
collusive or sham; that said Bidder has not directly or indirectly induced or solicited any other Bidder to put in a
false or sham bid, and has not directly or indirectly colluded, conspired, connived, or agreed with any Bidder or
anyone else to put in a sham bid, nor that anyone shall refrain from bidding; that said Bidder has not in any
manner, directly or indirectly, sought by agreement, communication, or conference with anyone to fix the bid
price of said Bidder or any other Bidder, nor to fix any overhead, profit, or cost element of such bid price, nor
of that of any other Bidder, nor to secure any advantage against the public body awarding the Contract or
anyone interested in the proposed Contract; that all statements contained in such bid are true; and, further,
that said Bidder has not directly or indirectly, submitted his bid price or any breakdown thereof, nor the
contents thereof, nor divulged information or data relative thereto, nor paid and will not pay fee in connection
therewith to any corporation, partnership, company, association, organization, bid depository, nor to any
member or agent thereof, nor to any other individual except to such person or persons as have a partnership
or other financial interest with said Bidder in his 9.,~p.eFaL.busine~". I ./
(." );(, "f /
Signed:t..--€.-..",;.;, L--r-!/~, :~-(
Title: \}\(,.f' 1?L.Qe:;\c\~ \{\"t
Subscribed and sworn to before me this l<A day
of =r\A\..\\ ,2007.
(SEAL)
Notary Public
~/~~~
"- ~ \
' ~~
Comrr(ISICJY1 E1?)\{~ \2-}olfl ~OJO
00,,52713-00123
Bozeman WRF Phase I Early Out Priority Improvements
00460 - J
5/16/2007
.
.
.
The undersigned hereby authorizes and requests any person, firm or corporation to furnish any information
requested by the Owner in verification of the recital comprising this statement of Bidder's qualifications and
other Information Required of Bidders. The undersigned further agrees that they will not bring suit in a court of
law for any information that is furnished to Owner in good faith by said parties or persons responding to
Owner's requests for information concerning Bidder's qualifications.
Dated this
\<61::U-
day of -::-lLA \.~
,2007.
END OF SECTION
00...52713-00123
Bozeman WRF Phase 1 Early Out Priority Improvements
00480 - 3
5/22/2007
SECTION 00500
CONSTRUCTION AGREEMENT
. THIS AGREEMENT is dated as of the ~ day of in the year~
(effective date), by and between the City of Bozeman, Montana
(hereinafter called OWNER) and
Dick Anderson Construction. Inc.
(hereinafter called CONTRACTOR).
OWNER and CONTRACTOR, in consideration of the mutual covenants hereinafter set forth, agree as
follows:
ARTICLE 1 - WORK
1.01 CONTRACTOR shall complete all Work as specified or indicated in the Contract Documents.
The Work is generally described in the Invitation to Bid and is described in detail in the Contract
Documents and the technical construction drawings.
ARTICLE 2 - THE PROJECT
2.01 The Project for which the Work under the Contract Documents may be the whole or only a part is
generally described as the Bozeman Water Reclamation Facility (WRF) Phase 1 Early Out
Improvements.
ARTICLE 3 - ENGINEER
. 3.01 The Project has been designed by:
HDR Engineering Inc.
1715 S. Reserve St., Suite C
Missoula, MT 59801
Morrison-Maierle, Inc.
1 Engineering Place
Helena, MT 59602
Morrison-Maierle, Inc.
901 Technology Blvd.
Bozeman, MT 59771
who is hereinafter called ENGINEER and who is to act as OWNER's representative, assume all duties
and responsibilities, and have the rights and authority assigned to ENGINEER in the Contract Documents
in connection with the completion of the Work in accordance with the Contract Documents.
ARTICLE 4 - CONTRACT TIMES
4.01 Time of the Essence
A. All time limits for Milestones, if any, Substantial Completion, and completion and
readiness for final payment as stated in the Contract Documents are of the essence of the Contract.
B. The CONTRACTOR agrees to complete the work within the time(s) specified herein.
4.02 Days to Achieve Substantial Completion and Final Payment
.
A. It is assumed for all milestone dates noted below, the Contract Notice to Proceed will
occur on or before August 1,2007.
1. The work associated with Bid Items No. 1 and No 2, that requires removal of the
aeration basin cells from service for completion, will be completed and ready for
basin partial utilization on or before August 22, 2007. It is assumed that the aeration
basin mixers may be lowered into the basins while the basins are back in service
without the need for removal of the basins from service once again.
2. The remaining work associated with Bid Items No.1, No.2, No. 3 and No.4,
including Owner provided basin mixers installation, and Owner provided electrical,
instrumentation and control, will be substantially completed and ready for aeration
00...52713-00123 Bozeman WRF Phase I Early Out Priority Improvements 8/8/2007
00500 - I
.
basin service on or before August 27,2007. The mounting, hoist and rail equipment
shall be delivered to the project early, as identified in Section 01011, Owner
Furnished Equipment, for installation by the Contractor.
3. The work associated with Bid Item NO.4 will be substantially completed on or before
September 30,2007.
4. All work will be completed and ready for final payment in accordance with Paragraph
14.07.B of the General Conditions within 145 calendar days after the date when the
Contract time commences to run, as provided In paragraph 2.03 of the General
Conditions.
4.03
Liquidated Damages
A. CONTRACTOR and OWNER recognize that time is of the essence of this Agreement
and that OWNER will suffer financial loss if the Work is not completed within the times specified in
paragraph 4.02 above, plus any extensions thereof allowed in accordance with Article 12 of the General
Conditions. The parties also recognize the delays, expense, and difficulties involved in proving in a legal
or arbitration proceeding the actual loss suffered by OWNER if the Work is not completed on time.
Accordingly, instead of requiring any such proof, OWNER and CONTRACTOR agree that as liquidated
damages for delay (but not as a penalty), CONTRACTOR shall pay OWNER $500 for each day that
expires after the time specified in paragraph 4.02 for Substantia'l Completion until the Work is
substantially complete. After Substantial Completion, if CONTRACTOR shall neglect, refuse, or fail to
complete the remaining Work within the Contract Time or any proper extension thereof granted by
OWNER, CONTRACTOR shall pay OWNER $200 for each day that expires after the time specified in
paragraph 4.02 for completion and readiness for final payment until the Work is completed and ready for
final payment.
B. Liquidated damages for unscheduled employment of the ENGINEER shall be paid by the
CONTRACTOR to the OWNER as specified in the Bid Form.
.
ARTICLE 5 - CONTRACT PRICE
5.01 OWNER shall pay CONTRACTOR for completion of the Work in accordance with the Contract
Documents an amount in current funds equal to the sum of Fortv nine thousand seven hundred ninetv
four dollars and one cent ($49,794.01) based on the prices stipulated in the Bid Form and
subject to adjustment as provided in the Contract Documents.
A. As provided in paragraph 11.01 of the General Conditions, CONTRACTOR agrees that
lump sum amount(s) constitute full payment for the work and that these lump sum amount(s) represent a
true measure of the labor and materials required to perform the work, including all allowances for
overhead, profit, taxes, bonds, insurance, and all other costs for each type and unit of work called for in
these Contract Documents.
B. As provided in paragraph 11.03 of the General Conditions, estimated unit price quantities
used for bidding purposes are not guaranteed, and determinations of actual quantities and classifications
are to be made by ENGINEER as provided in paragraph 9.07 of the General Conditions. Unit prices have
been computed as provided in paragraph 11.03 of the General Conditions.
ARTICLE 6 - PAYMENT PROCEDURES
6.01 Submittal and Processing of Payments
A. CONTRACTOR shall submit Applications for Payment in accordance with Article 14 of
the General Conditions. Applications for Payment will be processed by ENGINEER as provided in the
General Conditions or other portions of the Contract Documents.
.
6.02 Progress Payments; Retainage
A. OWNER shall make progress payments in accordance with Article 14 of the General
Conditions on account of the Contract Price on the basis of CONTRACTOR's Applications for Payment as
00.. .52713-00123
Bozeman WRF Phase I Early Out Priority Improvements
00500 - 2
8/8/2007
.
.
.
recommended by the ENGINEER once each month during performance of the Work as provided in
paragraphs 6.02.A.1 and 6.02.A.2 below. All such progress payments will be measured by the schedule
of values established in paragraph 2.05.A of the General Conditions or in the case of Unit Price Work
based on the number of units of each bid item completed times the bid unit price in the Unit Price
Schedule of the Bid Form for each bid item, or, in the event there is no schedule of values, as provided in
the General Conditions:
1. Prior to Substantial Completion, progress payments will be made in an amount
equal to the percentage of work completed but, in each case, less the aggregate of payments
previously made and less such amounts as ENGINEER may determine or OWNER may withhold,
including but not limited to liquidated damages, in accordance with paragraph 14.02 of the
General Conditions:
a. The OWNER shall retain 5% of the amount of each payment until final
completion and acceptance of all work covered by the Contract Documents.
b. Retainage will be 5% of materials and equipment not incorporated in the
Work (but delivered, suitably stored and accompanied by documentation satisfactory to
OWNER as provided in paragraph 14.02 of the General Conditions).
2. Upon Substantial Completion and at the OWNER's discretion, the amount of retainage
may be further reduced if requested by the CONTRACTOR. Reduction of retainage is at the sole
discretion of the OWNER. OWNER is not obligated to reduce retainage. Amount of substantial
completion payment will be reduced by such amounts as ENGINEER shall determine in
accordance with paragraph 14.02.B.5 of the General Conditions and by 100% of ENGINEER's
estimate of the value of Work to be completed or corrected as shown on the tentative list of items
to be completed or corrected attached to the certificate of Substantial Completion.
6.03 Final Payment
A. Upon final completion and acceptance of the Work in accordance with paragraph 14.07
of the General Conditions, OWNER shall pay the remainder of the Contract Price as recommended by
ENGINEER as provided in said paragraph 14.07.
B. Lien releases shall be required for all project materials and equipment, from
subcontractors and suppliers and any other related vendors and subcontractors before final payment is
made to Contractor.
ARTICLE 7 - INTEREST
7.01 All moneys not paid when due as provided in Article 14 of the General Conditions shall bear
interest at the maximum rate allowed by law at the place of the Project.
ARTICLE 8 - CONTRACTOR'S REPRESENTATIONS
8.01 In order to induce OWNER to enter into this Agreement, CONTRACTOR makes the following
representations:
A. CONTRACTOR has examined and carefully studied the Contract Documents (including
all Addenda listed in Article 9) and the other related data identified in the Bidding Documents.
B. CONTRACTOR has visited the Site and become familiar with and is satisfied as to the
general, local, and Site conditions that may affect cost, progress, and performance or furnishing of the
Work.
C. CONTRACTOR is familiar with and is satisfied as to all federal, state, and local Laws and
Regulations that may affect cost, progress, performance, and furnishing of the Work.
00.. .52713-00123
8/8/2007
Bozeman WRF Phase 1 Early Out Priority Improvements
00500 - 3
.
.
.
D. CONTRACTOR has carefully studied all: (1) reports of explorations and tests of
subsurface conditions at or contiguous to the Site and all drawings of physical conditions in or relating to
existing surface or subsurface structures at or contiguous to the Site (except Underground Facilities), if
any, which have been identified in the Supplementary Conditions as provided in paragraph 4.02 of the
General Conditions and (2) reports and drawings of a Hazardous Environmental Condition, if any, at the
Site which has been identified in the Supplementary Conditions as provided in paragraph 4.06 of the
General Conditions. CONTRACTOR acknowledges that such reports and drawings are not Contract
Documents and may not be complete for CONTRACTOR's purposes. CONTRACTOR acknowledges
that OWNER and ENGINEER do not assume responsibility for the accuracy or completeness of
information and data shown or indicated in the Contract Documents with respect to Underground
Facilities at or contiguous to the site.
E. CONTRACTOR has obtained and carefully studied (or assumes responsibility for having
done so) all additional or supplementary examinations, investigations, explorations, tests, studies, and
data concerning conditions (surface, subsurface, and Underground Facilities) at or contiguous to the Site
which may affect cost, progress, performance, or furnishing of the Work or which relate to any aspect of
the means, methods, techniques, sequences, and procedures of construction to be employed by
CONTRACTOR, including any specific means, methods, techniques, sequences, and procedures of
construction expressly required by the Contract Documents to be employed by the CONTRACTOR, and
safety precautions and programs incident thereto.
F. CONTRACTOR does not consider that any further examinations, investigations,
explorations, tests, studies, or data are necessary for the performance and furnishing of the Work at the
Contract Price, within the Contract Times, and in accordance with the other terms and conditions of the
Contract Documents.
G. CONTRACTOR is aware of the general nature of work to be performed by OWNER and
others at the Site that relates to the Work as indicated in the Contract Documents.
H. CONTRACTOR has correlated the information known to CONTRACTOR, information
and observations obtained from visits to the Site, reports and drawings identified in the Contract
Documents, and all additional examinations, investigations, explorations, tests, studies, and data with the
Contract Documents.
I. CONTRACTOR has given ENGINEER written notice of all conflicts, errors, ambiguities,
or discrepancies that CONTRACTOR has discovered in the Contract Documents, and the written
resolution thereof by ENGINEER is acceptable to CONTRACTOR.
J. The Contract Documents are generally sufficient to indicate and convey understanding of
all terms and conditions for performance and furnishing of the Work.
ARTICLE 9 - CONTRACT DOCUMENTS
9.01 Contents
A. The Contract Documents consist of the following:
1. This Agreement (pages 1 to 8, inclusive);
2. Performance Bond (pages 1 to 2, inclusive);
3. Payment Bond (pages 1 to 2, inclusive);
4. General Conditions (pages 1 to 44, inclusive);
5.
Supplementary Conditions (pages 1 to 15, inclusive);
6.
Specifications as listed in the Table of Contents of the Project Manual;
00" ,52713~00123
8/8/2007
Bozeman WRF Phase 1 Early Out Priority Improvements
00500 - 4
.
7. Drawings consisting of a cover sheet and sheets numbered 1 through 5 inclusive,
with each sheet bearing the following general title: Water Reclamation Facility Phase 1 Early Out
Improvements; (Note: Drawings are attached hereto);
8.
Addenda (numbers 1
to
, inclusive);
9. Exhibits to this Agreement (enumerated as follows):
a. Notice of Award (pages 1 to 1 inclusive);
b. CONTRACTOR's Bid Form (pages 1 to 9, inclusive);
c. Documentation submitted by CONTRACTOR prior to Notice of Award
(pages _ to _' inclusive);
d.
10. The following which may be delivered or issued on or after the Effective Date of
the Agreement and are not attached hereto:
a. Notice to Proceed (pages 1 to 1, inclusive);
b. Written Amendments;
c. Work Change Directives;
d. Change Orders.
B. The documents listed in paragraph 9.01.A are attached to this Agreement (except as
. expressly noted otherwise above).
C. There are no Contract Documents other than those listed above in this Article 9.
D. The Contract Documents may only be amended, modified, or supplemented as provided
in paragraph 3.04 of the General Conditions.
ARTICLE 10 - MISCELLANEOUS
10.01 Terms
A. Terms used in this Agreement which are defined in Article 1 of the General Conditions
will have the meanings indicated in the General Conditions and the Supplementary Conditions.
10.02 Assignment of Contract
A. No assignment by a party hereto of any rights under or interests in the Contract
Documents will be binding on another party hereto without the written consent of the party sought to be
bound; and specifically, but without limitation, moneys that may come due and moneys that are due may
not be assigned without such consent (except to the extent that the effect of this restriction may be limited
by law), and unless specifically stated to the contrary in any written consent to an assignment, no
assignment will release or discharge the assignor from any duty or responsibility under the Contract
Documents.
10.03 Successors and Assigns
.
A. OWNER and CONTRACTOR each binds itself, its partners, successors, assigns, and
legal representatives to the other party hereto, its partners, successors, assigns, and legal
representatives in respect to all covenants, agreements, and obligations contained in the Contract
Documents.
00...527\3-00123
Bozeman WRF Phase 1 Early Out Priority Improvements
00500 - 5
8/8/2007
.
.
.
10.04 Severability
A. Any provision or part of the Contract Documents held to be void or unenforceable under
any Law or Regulation shall be deemed stricken. and all remaining provisions shall continue to be valid
and binding upon OWNER and CONTRACTOR. who agree that the Contract Documents shall be
reformed to replace such stricken provision or part thereof with a valid and enforceable provision that
comes as close as possible to expressing the intention of the stricken provision.
10.05 Other Provisions
A. The CONTRACTOR agrees to remedy all defects appearing in the work or developing in
the materials furnished and the workmanship performed under this Agreement during the warranty period
after the date of final acceptance of the work by the OWNER. and further agrees to indemnify and save
the OWNER harmless from any costs encountered in remedying such defects.
00.. .52713-00123
Bozeman WRF Phase 1 Early Out Priority Improvements
00500 - 6
8/8/2007
.
.
.
IN WITNESS WHEREOF, OWNER and CONTRACTOR have signed six copies of this Agreement. Two
counterpart(s) have been delivered to OWNER. two to CONTRACTOR. one to ENGINEER, and one to
the Montana Department of Environmental Quality. All portions of the Contract Documents have been
signed or identified by OWNER and CONTRACTOR or by ENGINEER on their behalf.
This Agreement will be effective on the date shown on page 1 (which is the Effective Date of the
Agreement). [This Agreement shall not be effective unless and until concurred in by the FUNDING
AGENCY's designated representative.]
o~~~
r: rl..y <:I f bo 'c.:e.--."",
I
CONTRACTOR:
~~~S4~illin
, ( ignature)
AttestS ~ V
(Signature)
Address for giving notices:
-=J-OS ~v'\do/v )')Y'Iv'.D
C:Sw-+e A \,01"'/,
\\\. .. ~
........ "
tJ6~~'o . ~q7'S
~/O ~.\~
Phone:" ': (') :
: : :..:
Facsimile;~.~ - 5W..J'~~ b ~
"o.~., '~'... ...
~ SEA~
"I \\'"
",,,,,,,,\\\
Montana Contractors' Registration No
By:
Attest
Address for givi~Q notices:
~\\ E.\'1oiN
?D.~^ \d30
'Eo?QJm()f) . \fIT nq 7~ Ha3D
5~Q-~~{Qg
Facsimile: 5S ~ - ~,'3 lo 9)
Phone:
[CORPORATE SEAL]
Agent for service of process:
The foregoing Contract, including all Contract Documents which are a part thereof, is in due form
according to the law, and is hereby appr~oved.
By: ~/, _ tJ~G/l
. (Ignatu~)........
Attorney of the City of Bozeman, Montana
(Owner)
END OF SECTION
00...52713-00123
8/8/2007
Bozeman WRF Phase 1 Early Out Priority Improvements
00500 - 7
.
o\\idlH.""lt,
",",~OO "'0. ",
~' ',~ ,'-" -A) If,
.,,4."tJ. .,' ..."o,....,~..~
,,'1"Jo " 0..,
::: oS, IlIf fJ',~;
= ()~; JA3A ; =
::!:: G ~2
-0. '~~
\+", 8ft' ..,"Q,,,::
""I "Ii:.' , ." '0' ~ . ..,"
'J ., cat.. ,..
'., ...., " ",
~ ,: f " r 1 , ~ \ , ,
.
.
,
..
PERFORMANCE BOND
.
Any singular reference to Contractor, Surety, Owner or other party shall be considered plural where applicable.
SURETY (Name and Address of Principal Place of Business)
Continental Casualty Company
CNA Center
Chicago, IL 60685
CONTRACTOR (Name and Address):
Dick Anderson Construction, Inc.
705 Bridger Drive, Suite A
Bozeman, MT 59715
OWNER (Name and Address):
City of Bozeman, Montana
411 East Main Street
Bozeman, MT 59715
CONTRACT
Date:~. \C\.aOO"1'
Amount:FORTY-NINE THOUSAND SEVEN HUNDRED NINETY-FOUR AND NO/lOO ($49,794.01)
Descriptions (Name and Location): Bozeman Water Reclamation Facility (WRF) Phase 1 Early Out Improvements
Bozeman, Montana
BOND
Bond Number: 929416475
Date (Not earlier than Contract Date):'Se..P-\-.)C\ .<'SCOt!-
Amount:FORTY-NINE THOUSAND SEVEN HUNDRED NINETY-FOUR AND NOIlOO ($49,794.01)
Modifications to this Bond Form: None
.
Surety and Contractor, intending to be legally bound hereby, subject to the terms printed on the reverse side hereof, do each cause this
Performance Bond to be duly executed on its behalf by its authorized officer, agent or representative.
CONTRACTOR AS PRINCIPAL
Company: Dick Anderson Construction,
. _ \ '"11, al)
...' al OA:''''",
,,' ~TI ........... .~ "
Pres i dent !~~.-o..'O,,';,~~>::-==:.
~ ~ leJ (t\\~ :.
= '<f SEAL ;n =
-~. ....,-
(Space is provided below for siQkes of additional/O ff
parties, if required.) ~ 0...... "" .....~ ~
, ~-" ..' ...
'... .... ........"'.. "
""'" ONT~ "",
"'""',,,\
Signa e:
Name and Title:
Vice
CONTRACTOR AS PRINCIPAL
Company:
Signature:
Name and Title:
(Seal)
.
SURETY
Continental Casualty Company _~ (Seal)
Surety's Name and Corporate Seal
By: ~lt:fJ;</ uJ~ -- ---"
Signatur~itle Beth A. Windom, Attorney-in-Fact
(Attach Power of Attorn -
Attest:
Signature an
COUNTERSIGNED:
SURETY FLYNN INSURANCE AG~
~dJJr
(Seal)
Surety's Name and Corporate Seal
By:
Signature and Title
(Attach Power of Attorney)
Attest:
Signature and Title
EJCDC No. C-610 (2002 Edition)
Originally prepared through the joint efforts of Surety Association of America, Engineers Joint Contract Documents Committee, the Associated General
Contractors of America, and the American Institnte of Architects.
.
.
.
1. Contractor and Surety, jointly and severally, bind themselves, their heirs,
executors, administrators, successors and assigns to the Owner for the performance
of the Contract, which is incorporatcd herein by reference.
2. If Contractor performs the Contract, Surety and Contractor have no obligation
under this Bond, except to participate in conferences as provided in Paragraph 3.1.
3. If there is no Owner Default, Surety's obligation under this Bond shall arise after:
3.1. Owner has notified Contractor and Surety at the addresses described in
Paragraph 10 below, that Owner is considcring declaring a Contractor
Default and has requested and attcmpted to arrange a conference with
Contractor and Surety to be held not later than fifteen days after receipt of
such notice to discuss methods of performing the Contract. If Owner,
Contractor and Surety agree, Contractor shall be allowed a reasonable time
to perform the Contract, but such an agreement shall not waive Owner's
right, if any, subsequently to declare a Contractor Default; and
3.2 The Owner has declared a Contractor Default and formally terminated
Contractor's right to complete the Contract. Such Contractor Default shall
not bc declared earlier than twenty days after Contractor and Surety have
received notice as provided in paragraph 3.1; and
3.3 The Owner has agreed to pay the Balance of the Contract Price to:
I.
The Surety in accordance with the terms of the Contract;
2. Another contractor sclected pursuant to paragraph 4.3 to perform the
Contract.
4. When Owner has satisfied the conditions of Paragraph 3, Surety shall promptly
and at Surety's expense take one of the following actions:
4.1 Arrange for Contractor, with consent of Owner, to perform and complete
the Contract, or
4.2 Undertakc to perform and complete the Contract itself, through its agents or
through independent contractors; or
4.3 Obtain hids or negotiated proposals from qualified contractors acceptable to
Owncr for a contract for performance and completion of the Contract,
arrange for a contract to he prepared for execution by Owner and the
contractor selected with Owner's concurrence, to be secured with
performance and payment bonds executed by a qualified surcty equivalent
to the Bonds issucd on the Contract, and pay to Owner thc amount of
damagcs as described in paragraph 6 in excess of tI'e Balance of the
Contract Price incurred by Owner resulting from Contractor Default; or
4.4
Waivc its right to perform and complete, arrange for completion, or obtain
a new contractor and with reasonable promptness under thc circumstances;
I. After investigation, determine thc amount for which it may be liable
to Owner and, as soon as practicable after the amount is determined,
tender payment therefor to Owner; or
2.
Deny liahility in whole or in part and notify Owner citing reasons
therefor.
5. If Surety does not proceed as provided in Paragraph 4 with reasonable
promptness, Surety shall be deemed to be in default on this Bond 15 days after
receipt of an additional written notice from Owner to Surety demanding that Surety
perform its obligations undcr this Bond, and Owner shall be entitlcd to enforce any
remedy available to Owner. If Surety proceeds as provided in Paragraph 4.4, and
Owner refuses the payment tendered or Surety has denied Iiahility, in whole or in
part, without further notice Owner shall be cntitled to enforce any remedy available
to Owner.
6. After Owner has terminated Contractor's right to complete the Contract, and if
Surety elects to act under Paragraph 4.1, 4.2, or 4.3 ahove, thcn the responsibilities
of Surety to Owner shall not be greater than those of Contractor under thc Contract,
and the responsibilities of Owner to Surety shall not be greater than those of Owner
under the Contract. To a limit of the amount of this Bond, but subject to commitment
by Owner of the Balance of the Contract Price to mitigation of costs and damages on
the Contract, Surety is obligated without duplication for:
6.1 The responsibilities of Contractor for correction of defective Work and
completion of the Contract;
6.2 Additional legal, design professional and delay costs resulting from
Contractor's Default, and resulting from the actions or failure to act of
Surety under Paragraph 4; and
6.3 Liquidated damages, or if no liquidated damages are specified in the
Contract, actual damages caused hy delayed performance or non-
performance of Contractor.
7. Surety shall not be liable to Owner or others for obligations of Contractor that are
unrelated to tbe Contract, and the Balance of the Contract Price shall not be reduced
or set off on account of any such unrelated obligations. No right of action shall
accrue on this Bond to any person or entity other than Owner or its heirs, executors,
administrators, or successors.
8. Surety hereby waives notice of any change, including changes of time, to
Contract or to related subcontracts, purchase orders and other obligations.
9. Any proceeding, legal or equitahle, under this Bond may be instituted in any court
of competent jurisdiction in the location in which the Work or part of he Work is
located and shall be instituted within two years after Contractor Default or within
two years after Contractor ceased working or within two years after Surety refuses or
fails to perform its obligations under this Bond, whichever occurs first. If the
provisions of this paragraph are void or prohibited by law, thc minimum period of
limitation availahle to sureties as a defense in the jurisdiction of the suit shall he
applicable.
10. Notice to Surety, Owner or Contractor sball be mailed or delivered to the
address shown on the signature page.
11. When this Bond has been furnished to comply with a statutory requirement in the
location where the Contract was to be performed, any provision in this Bond
conflicting wid, said statutory or legal requirement shall be deemed deleted herefrom
and provisinns conforming to such statutory or other legal requirement shall be
deemed incorporated herein. The intent is that this Bond shall be construed as a
statutory bond and not as a common law bond.
12. Definitions.
12.1 Balance of me Contract Price: The total amount payable by Owner to
Contractor under the Contract after all proper adjustments have heen made,
including allowance to Contractor of any amounts received or to he
received by Owner in settlement of insurance or other Claims for damages
to which Contractor is entitled, reduced by all valid and proper payments
made to or on behalf of Contractor under the Contract.
12.2 Contract: The agreement between Owner and Contractor identified on the
signature page, including all Contract Documents and changes thereto.
12.3 Contractor Default: Failure of Contractor, which has neither heen remedied
nor waived, to perform or otherwise to comply with the terms of the
Contract.
12.4 Owner Default: Failure of Owner, which has neither been remedied nOr
waived, to pay Contractor as required by the Contract or to perfonn and
complete or comply with the other terms thereof.
FOR INFORMATION ONLY - Name, Address and Telephone
Surety Agency or Broker:
Flynn Insurance Agency
P.O. Box 711
Great Falls, MT 59403
(406) 453-1464
Owner's Representative (engineer or other party):
.
PAYMENT BOND
Any singular reference to Contractor, Surety, Owner. or other party shall be considered plural where applicable.
CONTRACTOR (Name and Address):
Dick Anderson Construction, Inc.
705 Bridger Drive, Suite A
Bozeman, MT 59715
OWNER (Name and Address):
City of Bozeman, Montana
411 East Main Street
Bozeman. MT 59715
SURETY (Name and Address of Principal Place of Business):
Continental Casualty Company
CNA Center
Chicago, IL 60685
CONTRACT
Date:
Amount: FORTY -NINE THOUSAND SEVEN HUNDRED NlNETY.FOUR AND NOlI 00 ($49,794.0 I)
Description (Name and Location): Bozeman Water Reclamation Facility (WRF) Phase I Early Out Improvements
Bozeman, Montana
BOND
Bond Number: 929416475
Date (Not earlier than Contract Date): Cep\-.',\.~CO::},
Amount: FORTY-NINE THOUSAND SEVEN HUNDRED NINETY-FOUR AND NO/IOO ($49,794.01)
Moditications to this Bond Form: None
.urety and Contractor, intending to be legally bound hereby, subject to the terms printed on the reverse side hereof, do each cause
is Payment Bond to be duly executed on its behalf by its authorized officer, agent, or representative.
CONTRACTOR AS PRlNCIP AL
Company: Dick Anderso
Signatu : Seal)
Name and ,,\ ~ ........ ~ ////
~' ~....~POFt...~~,,-:.
Vice presid~"'c.P "~"-:S)~
- . ,.' '. c::. ...
~~f SEAL ~~~
=c,)~ J-=
(Space is provided bel<%~...s1natie~",'iilP~ditional
parties, ifrequired.) I'l'l' 4" ....'-~........ ",
"1, ONT""- \\"
""fI II 1\\\\'
CONTRACTOR AS PRlNCIP AL
Company:
Signature:
Name and Title:
(Seal)
.
SURETY
Continental Casualty Company (~eal)
Surety's Name and Corporate Seal
~~aUrr~~ 1;J~m,y-rn:Facl .
(Attach Power of Attorney)
Attest:
Signature
SURETY
(Seal)
By:
Signature and Title
(Attach Power of Attorney)
Attest:
Signature and Title:
EJCDC No. C-615 (2002 Edition)
Originally prepared through the joint efforts of the Surety Association of America, Engineers Joint Contract Documents Committee, the Associated General
Contractors of America, the American Institute of Architects, the American Subcontractors Association, and the Associated Specialty Contractors.
,.
1. Contractor and Surety, jointly and severally, bind themselves, their heirs,
executors, administrators, successors, and assigns to Owner to pay for labor,
materials, and equipment furnished by Claimants for use in the performance of
.e Contract, which is incorporated herein by reference.
2. With respect to Owner, this obligation shall be null and void if Contractor:
2.1. Promptly makes payment, directly or indirectly, for all sums due
Claimants, and
2.2. Defends, indemnifies, and holds harmless Owner from all claims,
demands, liens, or suits alleging non-payment by Contractor by any
person or entity who furnished labor, materials, or equipment for use
in the performance of the Contract, provided Owner has promptly
notified Contractor and Surety (at the addresses described in
Paragraph 12) of any claims, demands, liens, or suits and tendered
defense of such claims, demands, liens, or suits to Contractor and
Surety, and provided there is no Owner Default.
3. With respect to Claimants, this obligation shall be null and void if
Contractor promptly makes payment, directly or indirectly, for all sums due.
4. Surety shall have no obligation to Claimants under this Bond until:
4.1. Claimant~ who are employed by or have a direct contract with
Contractor have given notice to Surety (at the addresses described in
Paragraph 12) and sent a copy, or notice thereof, to Owner, stating
that a claim is being made under this Bond and, with substantial
accuracy, the amount of the claim.
4.2. Claimants who do not have a direct contract with Contractor:
.
1. Have furnished written notice to Contractor and sent a copy, or
notice thereof, to Owner, within 90 days after having last
performed labor or last furnished materials or equipment included
in the claim stating, with substantial accuracy, the amount of the
claim and the name of the party to whom the materials or
equipment were furnished or supplied, or for whom the labor was
done or performed; and
2. Have either received a rejection in whole or in part from
Contractor, or not received within 30 days of furnishing the above
notice any communication from Contractor by which Contractor
had indicated the claim will be paid directly or indirectly; and
3. Not having been paid within the above 30 days, have sent a written
notice to Surety and sent a copy, or notice thereof, to Owner,
stating that a claim is being made under this Bond and enclosing a
copy of the previous written notice furnished to Contractor.
5. If a notice by a Claimant required by Paragraph 4 is provided by Owner to
Contractor or to Surety, that is sufficient compliance.
6. When a Claimant has satisfied the conditions of Paragraph 4, the Surety
shall promptly and at Surety's expense take the following actions:
6.1. Send an answer to that Claimant, with a copy to Owner, within 45
days after receipt of the claim, stating the amounts that are undisputed
and the basis for challenging any amounts that are disputed.
6.2. Payor arrange for payment of any undisputed amounts.
7. Surety's total obligation shall not exceed the amount of this Bond, and the
amount of this Bond shall be credited for any payments made in good faith by
Surety .
OR INFORMATION ONLY - Name, Address and Telephone
rety Agency or Broker:
Iynn Insurance Agency
P.O. Box 711
Great Falls, MT 59403
(406) 453-1464
8. Amounts owed by Owner to Contractor under the Contract shall be used for
the performance of the Contract and to satisfy claims, if any, under any
performance bond. By Contractor furnishing and Owner accepting this Bond,
they agree that all funds earned by Contractor in the performance of the
Contract are dedicated to satisfy obligations of Contractor and Surety under this
Bond, subject to Owner's priority to use the funds for the completion of the
Work.
9. Surety shall not be liable to Owner, Claimants, or others for obligations of
Contractor that are unrelated to the Contract. Owner shall not be liable for
payment of any costs or expenses of any Claimant under this Bond, and shall
have under this Bond no obligations to make payments to, give notices on
behalf of, or otherwise have obligations to Claimants under this Bond.
10. Surety hereby waives notice of any change, including changes of time, to
the Contract or to related Subcontracts, purchase orders and other ohligations.
11. No suit or action shall be commenced by a Claimant under this Bond other
than in a court of competent jurisdiction in the location in which the Work or
part of the Work is located or after the expiration of one year from the date (1)
on which the Claimant gave the notice required by Paragraph 4.1 or Paragraph
4.2.3, or (2) on which the last labor or service was performed by anyone or the
last materials or equipment were furnished by anyone under the Construction
Contract, whichever of (1) or (2) first occurs. If the provisions of this
paragraph are void or prohibited by law, the minimum period of limitation
available to sureties as a defense in the jurisdiction of the suit shall be
applicable.
12. Notice to Surety, Owner, or Contractor shall be mailed or delivered to the
addresses shown on the signarure page. Actual receipt of notice by Surety,
Owner, or Contractor, however accomplished, shall be sufficient compliance as
of the date received at the address shown on the signature page.
13. When this Bond has been furnished to comply with a statutory requirement
in the location where the Contract was to be performed, any provision in this
Bond conflicting with said statutory requirement shall be deemed deleted
herefrom and provisions conforming to such statutory requirement shall be
deemed incorporated herein. The intent is that this Bond shall be construed as
a statutory Bond and not as a common law bond.
14. Upon request of any person or entity appearing to be a potential
beneficiary of this Bond, Contractor shall promptly furnish a copy of this Bond
or shall permit a copy to be made.
15. DEFINITIONS
15.1. Claimant: An individual or entity having a direct contract with
Contractor, or with a first-tier subcontractor of Contractor, to furnish
labor, materials, or equipment for use in the performance of the
Contract. The intent of this Bond shall be to include without
limitation in the tenns "labor, materials or equipment" that part of
water, gas, power, light, heat, oil, gasoline, telephone service, or
rental equipment used in the Contract, architectural and engineering
services required for performance of the Work of Contractor and
Contractor's Subcontractors, and all other items for which a
mechanic's lien may be asserted in the jurisdiction where the lahor,
materials, or equipment were furnished.
15.2. Contract: The agreement between Owner and Contractor identified on
the signature page, including all Contract Documents and changes
thereto.
15.3. Owner Default: Failure of Owner, which has neither been remedied
nor waived, to pay Contractor as required by the Contract or to
perform and complete or comply with the other terms thereof.
Owner's Representative (engineer or other party):
POWER OF ATTORNEY APPOINTING INDIVIDUAL ATTORNEY-IN-FACT
Know All Men By These Presents, That Continental Casualty Company, an Illinois corporation, National Fire Insurance Company of Hartford, an
"Illinois corporation, and American Casualty Company of Reading, Pennsylvania, a Pennsylvania corporation (herein called "the CNA Companies"), are
duly organized and existing corporations having their principal offices in the City of Chicago, and State of Illinois, and that they do by virtue ofthe
.atures and seals herein affixed hereby make, constitute and appoint
Mark S Nicholls, John D Leaf, Chris Jermunson, Michael E Depner, Billy J Bolt, Beth A Windom, Jenny Taub-Smith,
Jamie M Roe, Kaye U Muzzana, Individually
of Great Falls, MT, their true and lawful Attorney(s)-in-Fact with full power and authority hereby conferred to sign, seal and execute for and on their
behalf bonds, undertakings and other obligatory instruments of similar nature
- In Unlimited Amounts-
and to bind them thereby as fully and to the same extent as if such instruments were signed by a duly authorized officer of their corporations and all the
acts of said Attorney, pursuant to the authority hereby given is hereby ratified and confirmed.
This Power of Attorney is made and executed pursuant to and by authority of the By-Law and Resolutions, printed on the reverse hereof, duly
adopted, as indicated, by the Boards of Directors of the corporations.
In Witness Whereof, the CNA Companies have caused these presents to be signed by their Senior Vice President and their corporate seals to be
hereto affixed on this 30th day of October, 2006.
Continental Casualty Company
National Fire Insurance Company of Hartford
^:fr- Company of Readiog, Peoosylvania
Thomas P. Stillman
Senior Vice President
State of Illinois, County of Cook, ss:
On this 30th day of October, 2006, before me personally came Thomas P. Stillman to me known, who, being by me duly sworn, did depose and say:
that he resides in the City of Chicago, State of Illinois; that he is a Senior Vice President of Continental Casualty Company, an Illinois corporation,
National Fire Insurance Company of Hartford, an Illinois corporation, and American Casualty Company of Reading, Pennsylvania, a Pennsylvania
corporation described in and which executed the above instrument; that he knows the seals of said corporations; that the seals affixed to the said
instrument are such corporate seals; that they were so affixed pursuant to authority given by the Boards of Directors of said corporations and that he
signed his name thereto pursuant to like authority, and acknowledges same to be the act and deed of said corporations.
.......................
: 'OFFICIAl SEAL' :
: MARIA M. MEDINA :
. Not..-y Public. tt_ of...... .
: My CaoJwnitoion bpAo 31,.". :
......................4
My Commission Expires March 15,2009
~ 'nt. YN-~~
Maria M. Medina
Notary Public
CERTIFICATE
I, Mary A. Ribikawskis, Assistant Secretary of Continental Casualty Company, an Illinois corporation, National Fire Insurance Company of
Hartford, an Illinois corporation, and American Casualty Company of Reading, Pennsylvania, a Pennsylvania corporation do hereby certify that the
Power of Attorney herein above set forth is still in force, and further certify that the By-Law and Resolution of the Board of Directors of the corporations
printed on the reverse hereof S~e. In testimony whereof! have hereunto subscribed my name and affixed the seal ofthe said corporations this
\ q day of tyr, ~1=--'
Continental Casualty Company
National Fire Insurance Company of Hartford
American Casualty Company of Reading, Pennsylvania
a~
Assistant Secretary
Form F6853-fl/2001
Authorizing By-Laws and Resolutions
~
ADOPTED BY THE BOARD OF DIRECTORS OF CONTINENTAL CASUALTY COMPANY:
This Power of Attorney is made and executed pursuant to and by authority of the following By-Law duly adopted by the Board of Directors of the
Company.
.
"Article IX-....,Execution of Documents
Section 3. Appointment of Attorney-in-fact. The Chairman of the Board of Directors, the President or any Executive, Senior or Group Vice
President may, from time to time, appoint by written certificates attorneys-in-fact to act in behalf of the Company in the execution of policies of
insurance, bonds, undertakings and other obligatory instruments of like nature. Such attorneys-in-fact, subject to the limitations set forth in their
respective certificates of authority, shall have full power to bind the Company by their signature and execution of any such instruments and to attach the
seal of the Company thererto. The Chairman of the Board of Directors, the President or any Executive, Senior or Group Vice President or the Board of
Directors, may, at any time, revoke all power and authority previously given to any attorney-in-fact."
This Power of Attorney is signed and sealed by facsimile under and by the authority of the following Resolution adopted by the Board of Directors of the
Company at a meeting duly called and held on the 17'~ day of February, 1993.
"Resolved, that the signature of the President or any Executive, Senior or Group Vice President and the seal of the Company may be affixed by
facsimile on any power of attorney granted pursuant to Section 3 of Article IX of the By-Laws, and the signature of the Secretary or an Assistant
Secretary and the seal of the Company may be affixed by facsimile to any certificate of any such power and any power or certificate bearing such
facsimile signature and seal shall be valid and binding on the Company. Any such power so executed and sealed and certified by certificate so executed
and sealed shall, with respect to any bond or undertaking to which it is attached, continue to be valid and binding on the Company."
ADOPTED BY THE BOARD OF DIRECTORS OF AMERICAN CASUALTY COMPANY OF READING, PENNSYLVANIA:
This' Power of Attorney is made and executed pursuant to and by authority of the following By-Law duly adopted by the Board of Directors of the
Company.
"Article VI---Execution of Obligations and Appointment of Attorney-In-Fact
Section 2. Appointment of Attorney-in-fact. The Chairman of the Board of Directors, the President or any Executive, Senior or Group Vice
President may, from time to time, appoint by written certificates attorneys-in. fact to act in behalf of the Company in the execution of policies of
insurance, bonds, undertakings and other obligatory instruments of like nature. Such attorneys-in-fact, subject to the limitations set forth in their
respective certificates of authority, shall have full power to bind the Company by their signature and execution of any such instruments and to attach th.
seal of the Company thereto. The President or any Executive, Senior or Group Vice President may at any time revoke all power and authority previousl
given to any attorney-in-fact."
This Power of Attorney is signed and sealed by facsimile under and by the authority of the following Resolution adopted by the Board of Directors of the
Company at a meeting duly called and held on the 17'~ day of February, 1993.
"Resolved, that the signature of the President or any Executive, Senior or Group Vice President and the seal of the Company may be affixed by
facsimile on any power of attorney granted pursuant to Section 2 of Article VI of the By-Laws, and the signature of the Secretary or an Assistant
Secretary and the seal of the Company may be affixed by facsimile to any certificate of any such power and any power or certificate bearing such
facsimile signature and seal shall be valid and binding on the Company. Any such power so executed and sealed and certified by certificate so executed
and sealed shall, with respect to any bond or undertaking to which it is attached, continue to be valid and binding on the Company."
ADOPTED BY THE BOARD OF DIRECTORS OF NATIONAL FIRE INSURANCE COMPANY OF HARTFORD:
This Power of Attorney is made and executed pursuant to and by authority of the following By-Law duly adopted by the Board of Directors of the
Company.
"Article VII---Execution of Documents
Section 3. Appointment of Attorney-in-Fact. The Chairman of the Board of Directors, the President of any Executive or Senior Vice President
may, from time to time, appoint by written certificates attorneys-in-fact to act in behalf of the Company in the execution of policies of insurance, bonds,
undertakings and other obligatory instruments of like nature. Such attorneys-in-fact, subject to the limitations set forth in their respective certificates of
authority shall have full power to bind the Company by their signature and execution of any such instruments and to attach the seal of the Company
thereto. The Chairman of the Board of Directors, the President or any Executive, Senior Vice President or the Board of Directors, may, at any time,
revoke all power and authority previously given to any attorney-in-fact."
This Power of Attorney is signed and sealed by facsimile under and by the authority of the following Resolution adopted by the Board of Directors of the
Company at a meeting duly called and held on the 171~ day of February, 1993.
"RESOLVED:. That the signature of the President, an Executive Vice President or any Senior or Group Vice President and the seal of the
Corporation may be affixed by facsimile on any power of attorney granted pursuant to the Resolution adopted by this Board of Directors on February I_
1993 and the signature of a Secretary or an Assistant Secretary and the seal of the Corporation may be affixed by facsimile to any certificate of any sucH
power, and any power or certificate bearing such facsimile signature and seal shall be valid and binding on the Corporation. Any such power so
executed and sealed and certified by certificate so executed and sealed, shall with respect to any bond or undertaking to which it-f:i attached,. continue to
be valid and binding on the Corporation." - -
-
. FLVNN
2445 S. Third Street W. Phone (406) 542-5126
Suite B Fax (406) 542-5647
P.O. Box 3868 Toll Free 1-888-922-3586
Missoula, MT 59806 www.flynninsurance.com
.
.
.
INSURANCE
AGENCY
FINANCIAL
SERVICES
-
August 23, 2007
Morrison Maierle, Inc.
Attn: James Nickelson
901 Technology Boulevard
Bozeman, MT 59715
RE:
Project:
Article 5.03 B for Dick Anderson Construction, Inc.
Bozeman Water Reclamation Facility Phase 1
Dear James:
I am writing in regards to Article 5.03 B of the specifications. I have reviewed the
insurance specifications but cannot certify that he contractor is providing the minimum
insurance requirements as required by Article 5. What I can certify is the insurance
provided meets the minimum required limits and provides for the auto, general liability,
employers liability and umbrella coverage's as requested in the insurance provision. The
coverage's are subject to all of the conditions, provisions, limitations and exclusions as
outlined in the policy itself. Nothing in this letter is intended to either amend or alter
the application of the policy itself. If you have any questions please do not hesitate to
give me a call.
Regards,
~~
Account Executive
~
~~ed Choice"
Great Falls Office: 100 Park Drive South, PO. Box 711, Great Falls, MT 59403, (406) 453-1464. Fax (406) 453-0073, Toll Free 1-800-823-3596
Billings Office: 1643 Lewis Ave., Suite 212, P.O. Box 21055, Billings, MT 59104, (406) 248-8763, Fax (406) 248-8791, Toll Free 1-800-823-3576
'ACORQM CERTIFICATE OF LIABILITY INSURANCE
PRODUCER (406) 542-5126
Flynn Insurance Agency
2445 S. Third St. W. Suite B
P.O. Box 3868
issoula, MT 59801
FAX (406)542-5647
DATE (MM/DD/YVYY)
08/22/2007
THIS CERTIFICATE IS ISSUED AS A MATTER OF INFORMATION
ONLY AND CONFERS NO RIGHTS UPON THE CERTIFICATE
HOLDER. THIS CERTIFICATE DOES NOT AMEND, EXTEND OR
ALTER THE COVERAGE AFFORDED BY THE POLICIES BELOW.
URED
INSURERS AFFORDING COVERAGE
INSURERA National Fire Insurance Co of
INSURERB: Continental Casualty Company
INSURER C: Transporation Insurance CO
INSURER D'
INSURER E:
NAIC#
Dick Anderson Construction, Inc.
3424 Highway 12 East
Helena, MT 59601
COVERAGES
THE POLICIES OF INSURANCE LISTED BELOW HAVE BEEN ISSUED TO THE INSURED NAMED ABOVE FOR THE POLICY PERIOD INDICATED, NOTWITHSTANDING
ANY REQUIREMENT, TERM OR CONDITION OF ANY CONTRACT OR OTHER DOCUMENT WITH RESPECT TO WHICH THIS CERTIFICATE MAY BE ISSUED OR
MAY PERTAIN, THE INSURANCE AFFORDED BY THE POLICIES DESCRIBED HEREIN IS SUBJECT TO ALL THE TERMS, EXCLUSIONS AND CONDITIONS OF SUCH
POLICIES, AGGREGATE LIMITS SHOWN MAY HAVE BEEN REDUCED BY PAID CLAIMS,
INSR DO' TYPE OF INSURANCE POLICY NUMBER POLICY EFFECTIVE POLICY EXPIRATION LIMITS
GENERAL LIAlIlLITY G281227182 01/01/2007 01/01/2008 EACH OCCURRENCE $ I,OOO,OOU
- DAMAGE TO RENTED 100,OOU
X COMMERCIAL GENERAL LIABILITY $
- ~ CLAIMS MADE [K] OCCUR 5,OOU
MED EXP (Anyone person) $
-
A PERSONAL & ADV INJURY $ I,OOO,OOU
- 2,000,OOU
GENERAL AGGREGATE $
-
GEN'L AGGREGATE LIMIT APPLIES PF.:R: PRODUCTS - COM PlOP AGG $ 2,OOO,OOU
I nPRO- n
POLICY JECT LOC
AUTOMOBILE LIABll.ITY U2081227196 01/01/2007 01/01/2008 COMBINED SINGLE LIMIT
- (F.:a accident) $ I,OOO,OOU
X ANY AUTO
-
X ALL OWNED AUTOS BODilY INJURY
- $
X SCHEDULED AUTOS (Per person)
B X
HIRED AUTOS BODilY INJURY
- (Per accident) $
X NON-OWNED AUTOS
-
- PROPERTY DAMAGE $
(Per accident)
GARAGF.: LIABILITY AUTO ONLY - EA ACCIDENT $
==1 ANY AUTO OTHER THAN EA ACC $
AUTO ONLY. AGG $
EXCESS/UMBRELLA LIABILITY U2081227201 01/01/2007 01/01/2008 EACH OCCURRENCE $ 8,000,000
:KJ OCCUR D CLAIMS MADE AGGREGATE $ 8,000,000
C $
-
DEDUCTIBLE $
X RETENTION $ 10,OOC $
~XX: G281227182 01/01/2007 01/01/2008 I ;"X~~T ~1,~" I IOJ~-
EMPLOYERS' LIABILITY 1,000,000
A ANY PROPRIETORlPARTNERlEXECUTIVF.: E.L EACH ACCIDENT $
OFFICERlMF.:MSE:R EXCLUDED? F.:,L, DISEASE. EA EMPI.OYEe $ 1,000,000
~~~MtS~r~6~~~6~S helow E,L, DISeASE: - POLICY LIMIT $ 2,000,000
OTHER
DESCRIPTION OF OPERATIONS I LOCATIONS IVEHICLES I EXCLUSIONS ADDED BY ENDORSEMENT I SPECIAL PROVISIONS
roject: Bozeman Water Reclamation Facility Phase I Early Out Improvements
~ob Number: 2752
~ertificate Holder is additional insured if required by written contract.
~*This certificate replaces and superceeds all previous certificates issued**
CERTIFICATE HOLDER
City of Bozeman
Attn: Tom Adams
411 East Main Street
Bozeman, MT 59715
CANCELLATION
SHOULD ANY OF THE ABOVE DESCRIBED POLICIES BE CANCELLED BEFORE THE
EXPIRATION DATE THEREOF, THE ISSUING INSURER WILL ENDEAVOR TO MAIL
~ DAYS WRITTEN NOTICE TO THE CERTIFICATE HOLDE:R NAMED TO THE LEFT,
BUT FAILURE TO MAIL SUCH NOTICE SHALL IMPOSE NO OBI..IGATION OR I..IABII..ITY
OF ANY KIND UPON THE INSURER, ITS AGENTS OR REPRESENTATIVES,
AUTHORIZED REPRESENTATIVE
Tom Sidor/ED
rilF
ACORD 25 (2001/08)
@ACORD CORPORATION 1988
IMPORTANT
If the certificate holder is an ADDITIONAL INSURED, the policy(ies) must be endorsed. A statement
on this certificate does not confer rights to the certificate holder in lieu of such endorsement(s).
If SUBROGATION IS WAIVED, subject to the terms and conditions of the policy, certain policies may
require an endorsement. A statement on this certificate does not confer rights to the certificate
holder in lieu of such endorsement(s).
DISCLAIMER
The Certificate of Insurance on the reverse side of this form does not constitute a contract between
the issuing insurer(s), authorized representative or producer, and the certificate holder, nor does it
affirmatively or negatively amend, extend or alter the coverage afforded by the policies listed thereon.
ACORD 25 (2001/08)
PRODUCER (406)542-5126
Flynn Insurance Agency
2445 S. Third St. W. Suite B
P.O. Box 3868
issoula, MT 59801
FAX (406)542-5647
DATE (MMIDDIVYYY)
08/22/2007
THIS CERTIFICATE IS ISSUED AS A MATTER OF INFORMATION
ONLY AND CONFERS NO RIGHTS UPON THE CERTIFICATE
HOLDER. THIS CERTIFICATE DOES NOT AMEND, EXTEND OR
ALTER THE COVERAGE AFFORDED BY THE POLICIES BELOW.
ACORlt
CERTIFICATE OF LIABILITY INSURANCE
Dick Anderson Construction, Inc.
3424 Highway 12 East
Helena, MT 59601
INSURERS AFFORDING COVERAGE
INSURER A: National Fire Insurance Co of
INSURERB: Continental Casualty Company
INSURER c: Transporation Insurance CO
INSURER D:
INSURER E:
NAIC#
URED
COVERAGES
THE POLICIES OF INSURANCE LISTED BELOW HAVE BEEN ISSUED TO THE INSURED NAMED ABOVE FOR THE POLICY PERIOD INDICATED. NOTWITHSTANDING
ANY REQUIREMENT, TERM OR CONDITION OF ANY CONTRACT OR OTHER DOCUMENT WITH RESPECT TO WHICH THIS CERTIFICATE MAY BE ISSUED OR
MAY PERTAIN. THE INSURANCE AFFORDED BY THE POLICIES DESCRIBED HEREIN IS SUBJECT TO ALL THE TERMS, EXCLUSIONS AND CONDITIONS OF SUCH
POLICIES. AGGREGATE LIMITS SHOWN MAY HAVE BEEN REDUCED BY PAID CLAIMS.
I~~: ~~~~ TYPE OF INSURANCE POLICY NUMBER P~}+~Y EFFECTIVE PR~!f~Y EXPIRATION LIMITS
GENERAL LIABILITY G281227182 01/01/2007 01/01/2008 EACH OCCURRENCE $ 1,000,000
X COMMERCIAl GENERAl liABiliTY DAMAGE TO RENTED $ 100,000
I ClAIMS MADE 0 OCCUR MED EXP (Anyone person) $ 5,000
A PERSONAl & ADV INJURY $ 1,000,000
- 2,000,000
GENERAl AGGREGATE $
- 2,000,000
GEN'l AGGREGATE LIMIT APPLIES PER: PRODUCTS. COMP/OP AGG $
I nPRO. n
POLICY JECT LOC
AUTOMOBILE LIABILITY U2081227196 01/01/2007 01/01/2008 COMBINED SINGlE LIMIT
- (Ea accident) $ 1,000,00(]
X ANY AUTO
X ALL OWNED AUTOS BODILY INJURY
X (Per person) $
SCHEDULED AUTOS
B X
HIRED AUTOS BODILY INJURY
X (Per accident) $
NON-OWNED AUTOS
-
- PROPERTY DAMAGE $
(Per accident)
GARAGE LIABILITY AUTO ONLY - EA ACCIDENT $
=1 ANY AUTO OTHER THAN EA ACC $
AUTO ONLY: AGG $
EXCESS/UMBRELLA LIABILITY U2081227201 01/01/2007 01/01/2008 EACH OCCURRENCE $ 8,000,000
~ OCCUR o CLAIMS MADE AGGREGATE $ 8,000,000
C $
~
DEDUCTIBlE $
X RETENTION $ 10,000 $
~XXX: G281227182 01/01/2007 01/01/2008 I WC STATU. I IO,J~-
EMPLOYERS' LIABILITY E,L. EACH ACCIDENT $ 1,000,000
A ANY PROPRIETOR/PARTNER/EXECUTIVE
OFFICER/MEMBER EXCLUDED" E.L. DISEASE - EA EMPLOYEE $ 1,000,000
If yes, describe under E.L. DISEASE - POLICY LIMIT $ 2,000 000
SPECIAL PROVISIONS below
OTHER
~ESCRIPTION OF OPERATIONS / LOCATIONS I VEHICLES I EXCLUSIONS ADDED BY ENDORSEMENT I SPECIAL PROVISIONS
roject: Bozeman Water Reclamation Facility Phase I Early Out Improvements
~ob Number: 2752
ertificate Holder is additional insured if required by written contract.
>*This certificate replaces and superceeds all previous certificates issued**
RT FICATE HOLDER
Morrison Maierle. Inc.
Attn: James Nickelson
901 Technology Blvd.
Bozeman, MT 59718
CANCELLATION
SHOULD ANY OF THE ABOVE DESCRIBED POLICIES BE CANCELLED BEFORE THE
EXPfRATlON DATE THEREOF. THE ISSUING INSURER WfLL ENDEAVOR TO MAIL
--.!L DAYS WRITTEN NOTICE TO THE CERTIFICATE HOLDER NAMED TO THE LEFT.
BUT FAILURE TO MAIL SUCH NOTICE SHALL IMPOSE NO OBLIGATION OR LIABILITY
OF ANY KIND UPON THE INSURER. ITS AGENTS OR REPRESENTATIVES.
AUTHORIZED REPRESENTATIVE
Tom Sidor/ED
!{/i
ACORD 25 (2001/08)
@ACORDCORPORATION 1988
IMPORT ANT
If the certificate holder is an ADDITIONAL INSURED, the policy(ies) must be endorsed. A statement
on this certificate does not confer rights to the certificate holder in lieu of such endorsement(s).
If SUBROGATION IS WAIVED, subject to the terms and conditions of the policy, certain policies may
require an endorsement. A statement on this certificate does not confer rights to the certificate
holder in lieu of such endorsement(s).
DISCLAIMER
The Certificate of Insurance on the reverse side of this form does not constitute a contract between
the issuing insurer(s), authorized representative or producer, and the certificate holder, nor does it
affirmatively or negatively amend, extend or alter the coverage afforded by the policies listed thereon.
ACORD 25 (2001/08)
ACORQM CERTIFICATE OF LIABILITY INSURANCE
PRODUCER (406)542-5126
Flynn Insurance Agency
2445 S. Third St. W. Suite B
P.O. Box 3868
issoula, MT 59801
RED
FAX (406)542-5647
DATE (MMIDDIYYYY)
08/22/2007
THIS CERTIFICATE IS ISSUED AS A MATTER OF INFORMATION
ONLY AND CONFERS NO RIGHTS UPON THE CERTIFICATE
HOLDER. THIS CERTIFICATE DOES NOT AMEND, EXTEND OR
ALTER THE COVERAGE AFFORDED BY THE POLICIES BELOW.
INSURERS AFFORDING COVERAGE
NAIC#
Dick Anderson Construction,
3424 Highway 12 East
Helena, MT 59601
COVERAGES
Inc.
INSURER A:
INSURER s:
INSURER C'
INSURER D'
INSURER E.
National Fire Insurance Co of
Continental Casualty Company
Transporation Insurance Co
THE POLICIES OF INSURANCE LISTED BELOW HAVE BEEN ISSUED TO THE INSURED NAMED ABOVE FOR THE POLICY PERIOD INDICATED. NOTWITHSTANDING
ANY REQUIREMENT, TERM OR CONDITION OF ANY CONTRACT OR OTHER DOCUMENT WITH RESPECT TO WHICH THIS CERTIFICATE MAY BE ISSUED OR
MAY PERTAIN, THE INSURANCE AFFORDED BY THE POLICIES DESCRIBED HEREIN IS SUBJECT TO ALL THE TERMS, EXCLUSIONS AND CONDITIONS OF SUCH
POLICIES AGGREGATE LIMITS SHOWN MAY HAVE BEEN REDUCED BY PAID CLAIMS.
I~f: ~~~ TYPE OF INSURANCE POLICY NUMBER POLICY EFFECTIVE Pg~!feY EXPIRATION LIMITS
GENERAL LIABILITY G281227182 01/01/2007 01/01/2008 EACH OCCURRENCE $ 1,000,00C
I--
X COMMERCIAL GENERAL LIABILITY DAMAGE TO RENTED $ 100,00Cl
cce,,"c,,c
I-- tJ CLAIMS MADE m OCCUR 5,00Cl
MED EXP (Any one person) $
I--
A PERSONAL & ADV INJURY $ 1,000,00C
I-- 2,000,00C
GENERAL AGGREGATE $
I--
GEN'L AGGREGATE LIMIT APPLIES PER: PRODUCTS" COMP/QP AGG $ 2,000,00C
n nPRO. n
POLICY JECT LOC
AUTOMOBILE LIABILITY U2081227196 01/01/2007 01/01/2008 COMBINED SINGLE LIMIT
c-- $
X ANY AUTO (Ea accident) 1,000,00C
X ALL OWNED AUTOS BODILY INJURY
X (por person) $
SCHEDULED AUTOS
B X
HIRED AUTOS BODILY INJURY
X (Per accident) $
NON-OWNED AUTOS
-
- PROPERTY DAMAGE $
(Per accident)
GARAGE LIABILITY AUTO ONL Y . EA ACCIDENT $
==l ANY AUTO OTHER THAN EA ACC $
AUTO ONLY: AGG $
EXCESS/UMBRELLA LIABILITY U2081227201 01/01/2007 01/01/2008 EACH OCCURRENCE $ 8,000,000
}] OCCUR D CLAIMS MADE AGGREGATE $ 8,000,000
C $
-
DEDUCTIBLE $
X RETENTION $ 10,00Cl $
~XX; G281227182 01/01/2007 01/01/2008 I ,."X%~mWs I IOJ,tI-
EMPLOYERS' LIABILITY 1,000,000
A ANY PROPRIETOR/PARTNER/EXECUTIVE E.L. EACH ACCIDENT $
OFFICER/MEMBER EXCLUDED? E.L. DISEASE - EA EMPLOYEE $ 1,000,000
If yes. describe under E.L. DISEASE - POLICY LIMIT $ 2,000,000
SPECIAL PROVISIONS below
OTHER
p~ESCRIPTlON OF OPERATIONS I LOCATIONS I VEHICLES I EXCLUSIONS ADDEO BY ENDORSEMENT I SPECIAL PROVISIONS
roject: Bozeman Water Reclamation Facility Phase I Early Out Improvements
Job Number: 2752
ertificate Holder is additional insured if required by written contract.
~*This certificate replaces and superceeds all previous certificates issued**
CERTIFI
ER
HDR Engineering
Attn: Daniel Harmon
1715 South Reserve Street
Suite C
Missoula, MT 59801-4708
SHOULD ANY OF THE ABOVE DESCRIBED POLICIES BE CANCELLED BEFORE THE
EXPIRATION DATE THEREOF, THE ISSUING INSURER WILL ENDEAVOR TO MAIL
~ DAYS WRITTEN NOTICE TO THE CERTIFICATE HOLDER NAMED TO THE LEFT,
BUT FAILURE TO MAIL SUCH NOTIC!' SHALL IMPOSE NO OBLIGATION OR LIABILITY
OF ANY KIND UPON THE INSURER. ITS AGENTS OR REPRESENTATIVES.
AUTHORIZED REPRESENTATIVE
Tom Sidor/ED
.".~<:
ACORD 25 (2001/08)
@ACORD CORPORATION 1988
IMPORTANT
If the certificate holder is an ADDITIONAL INSURED, the policy(ies) must be endorsed. A statement
on this certificate does not confer rights to the certificate holder in lieu of such endorsement(s).
If SUBROGATION IS WAIVED, subject to the terms and conditions of the policy, certain policies may
require an endorsement. A statement on this certificate does not confer rights to the certificate
holder in lieu of such endorsement(s).
DISCLAIMER
The Certificate of Insurance on the reverse side of this form does not constitute a contract between
the issuing insurer(s), authorized representative or producer, and the certificate holder, nor does it
affirmatively or negatively amend, extend or alter the coverage afforded by the policies listed thereon.
ACORD 25 (2001/08)
PRODUCER (406)542-5126
Flynn Insurance Agency
2445 S. Third St. W. Suite 8
P.O. Box 3868
issoula, MT 59801
City 0 Bozeman
411 East Main Street
Bozeman, MT 59715
FAX (406)542-5647
DATE (MM/DD/YYYY)
08/23/2007
THIS CERTIFICATE IS ISSUED AS A MATTER OF INFORMATION
ONLY AND CONFERS NO RIGHTS UPON THE CERTIFICATE
HOLDER. THIS CERTIFICATE DOES NOT AMEND, EXTEND OR
ALTER THE COVERAGE AFFORDED BY THE POLICIES BELOW.
~ CORQM
CERTIFICATE OF LIABILITY INSURANCE
INSURERS AFFORDING COVERAGE
INSURER A: CNA Insurance Companies
INSURER 8:
INSURER c:
INSURER D:
INSURER E.
NAIC#
COVERAGES
THE POLICIES OF INSURANCE LISTED BELOW HAVE BEEN ISSUED TO THE INSURED NAMED ABOVE FOR THE POLICY PERIOD INDICATED. NOTWITHSTANDING
ANY REQUIREMENT, TERM OR CONDITION OF ANY CONTRACT OR OTHER DOCUMENT WITH RESPECT TO WHICH THIS CERTIFICATE MAY BE ISSUED OR
MAY PERTAIN, THE INSURANCE AFFORDED BY THE POLICIES DESCRIBED HEREIN IS SUBJECT TO ALL THE TERMS, EXCLUSIONS AND CONDITIONS OF SUCH
POLICIES. AGGREGATE LIMITS SHOWN MAY HAVE BEEN REDUCED BY PAID CLAIMS
IN~: ~~~'~ TYPE OF INSURANCE POliCY NUMBER P~H~Y EFFECTIVE POliCY EXPIRATION liMITS
GENERAl liABIliTY 807082209039 08/09/2007 08/09/2008 EACH OCCURRENCE $ 1,000,000
- DAMAGE TO RENTEO
COMMERCIAl GENERAl liABiliTY $ N/A
- :=J Cl;IMS MADE 0 OCCUR
MED EXP (Anyone person) $ N/A
- -_..~
A X Owners & Contracto PERSONAl & ADV INJURY $ N/~
GENERAl AGGREGATE $ 2,000,00ll
GEN'l AGGREGATE liMIT APPliES PER: PRODUCTS - COMP/OP AGG $ N/A
n nPRO. n
POliCY JECT lOC
AUTOMOBilE liABiliTY COMBINED SINGlE liMIT
I--- (Ea accidonl) $
ANY AUTO
I---
All OWNED AUTOS BODilY INJURY
I--- (Por porson) $
SCHEDULED AUTOS
I---
HIRED AUTOS BODilY INJURY
I--- (per accidonl) $
NON-OWNED AUTOS
I---
PROPERTY DAMAGE $
(Por accidonl)
. GARAGE liABIliTY AUTO ONLY - EA ACCIDENT $
R ANY AUTO OTHER THAN EA ACC $
AUTO ONlY' AGG $
EXCESS/UMBRELLA LIABiliTY EACH OCCURRENCE $
:=J OCCUR D CLAIMS MADE AGGREGATE $
$
~ DEDUCTIBLE $
RETENTION $ $
WORKERS COMPENSATION AND L~~Jm,~;,I' IO~~-
EMPLOYERS' LIABILITY $
ANY PROPRIETOR/PARTNER/EXECUTIVE E.L. EACH ACCIDENT
OFFICER/MEMBER EXCLUDED? El. DISEASE. EA EMPlOYE~ $
~~~~I~tS~~~V1s16'Ns below E.l. DISEASE. POliCY LIMIT $
OTHER
p~ESCRIPTION OF OPERATIONS / LOCATIONS / VEHICLES / EXCLUSIONS ADDED BY ENDORSEMENT / SPECIAL PROVISIONS
roject: Bozeman Waste Water Reclamation Facility (WRF) Phase 1 Early Out Improvements
~*This certificate replaces and superceeds all previous certificates issued**
DER
City of Bozeman
411 East Main Street
Bozeman, MT 59715
SHOULD ANY OF THE ABOVE DESCRIBED POLICIES BE CANCELLED BEFORE THE
EXPIRATION DATE THEREOF, THE ISSUING INSURER WILL ENDEAVOR TO MAIL
.....!L DAYS WRITTEN NOTICE TO THE CERTIFICATE HOLDER NAMED TO THE LEFT,
BUT FAILURE TO MAIL SUCH NOTICE SHALL IMPOSE NO OBliGATION OR LIABILITY
OF ANY KIND UPON THE INSURER, ITS AGENTS OR REPRESENTATIVES.
AUTHORIZED REPRESENTATIVE
-bn5ii?
Tom Sidor/ED
ACORD 25 (2001/08)
@ACORD CORPORATION 1988
IMPORTANT
If the certificate holder is an ADDITIONAL INSURED, the policy(ies) must be endorsed. A statement
on this certificate does not confer rights to the certificate holder in lieu of such endorsement(s).
If SUBROGATION IS WAIVED, subject to the terms and conditions of the policy, certain policies may
require an endorsement. A statement on this certificate does not confer rights to the certificate
holder in lieu of such endorsement(s).
DISCLAIMER
The Certificate of Insurance on the reverse side of this form does not constitute a contract between
the issuing insurer(s), authorized representative or producer, and the certificate holder, nor does it
affirmatively or negatively amend, extend or alter the coverage afforded by the policies listed thereon.
ACORD 25 (2001/08)
PRODUCER (406) 542-5126
Flynn Insurance Agency
2445 S. Third St. W. Suite B
P.O. Box 3868
.ssoula, MT 59801
RED Ci ty of Bozeman
411 East Main Street
Bozeman, MT 59715
FAX (406)542-5647
DATE (MM/DDNYYY)
09/11/2007
THIS CERTIFICATE IS ISSUED AS A MATTER OF INFORMATION
ONLY AND CONFERS NO RIGHTS UPON THE CERTIFICATE
HOLDER, THIS CERTIFICATE DOES NOT AMEND, EXTEND OR
ALTER THE COVERAGE AFFORDED BY THE POLICIES BELOW.
ACORQM
CERTIFICATE OF LIABILITY INSURANCE
INSURERS AFFORDING COVERAGE
INSURER A: CNA Insurance Companies
INSURER B:
INSURER C:
INSURER D:
INSURER E.
NAIC#
COVERAGES
THE POLICIES OF INSURANCE LISTED BELOW HAVE BEEN ISSUED TO THE INSURED NAMED ABOVE FOR THE POLICY PERIOD INDICATED NOTWITHSTANDING
ANY REQUIREMENT, TERM OR CONDITION OF ANY CONTRACT OR OTHER DOCUMENT WITH RESPECT TO WHICH THIS CERTIFICATE MAY BE ISSUED OR
MAY PERTAIN, THE INSURANCE AFFORDED BY THE POLICIES DESCRIBED HEREIN IS SUBJECT TO ALL THE TERMS, EXCLUSIONS AND CONDITIONS OF SUCH
POLICIES. AGGREGATE LIMITS SHOWN MAY HAVE BEEN REDUCED BY PAID CLAIMS.
INSR 00'1 TYPE OF INSURANCE POLICY NUMBER POLICY EFFECTIVE POLICY I;XPIRATION LIMITS
GI;NI;RAL LIABILITY B07082209039 08/09/2007 08/09/2008 EACH OCCURRENCE $ 1,000,OO(
-
COMMERCIAL GI"NERAL LIABILITY DAMAGE TO RENTI;:D $ N/,.l
- ~ CLAIMS MADE [K] OCCUR
MED EXP (Anyone person) $ N/,.l
-
A X Owners & Contracto PERSONAL & ADV INJURY $ N/,.l
-
GENI;:RAL AGGREGATE $ 2,000,00(
-
GEN'L AGGREGATE LIMIT APPLIES PER PRODUCTS. COMP/OP AGG $ N/,.l
I nPRO. n
POLICY JECT LOC
AUTOMOBILE LIABILITY COMBINED SINGLE LIMIT
- $
ANY AUTO (Ea accident)
-
ALL OWNED AUTOS BODILY INJURY
- $
SCHE;DULI"D AUTOS (Per person)
-
HIRED AUTOS BODILY INJURY
- $
NON-OWNE;D AUTOS (Per accident)
-
- PROPERTY DAMAGE $
(Per accident)
GARAGE LIABILITY AUTO ONLY - EA ACCIDENT $
~ ANY AUTO OTHER THAN EA ACC $
AUTO ONLY AGG $
EXCl:SS/UMBRI"LLA LIABILITY EACH OCCURRENCE $
=:=J OCCUR o CLAIMS MADI" AGGRI"GATE $
$
~ DEDUCTlBLI" $
RETl:NTION $ $
WORKl:RS COMPl:N$ATION AND I WC STATU-.I IOJt'-
EMPLOYERS' LIABILITY
ANY PROPRIETOR/PARTNER/EXECUTIVE; E.L EACH ACCIDENT $
OFFICER/MEMBER EXCLUDED? E.L DISEASE - I"A EMPLOYE;" $
~~~~I~tS~~ci~~16'Ns below E.L. DISEASE - POLICY LIMIT $
OTHER
~ESCRIPTION OF OPl:RATIONS I LOCATIONS I VEHICLES I EXCLUSIONS ADDED BY ENDORSEMENT I $Pl:CIAL PROVISIONS
roject: Bozeman Water Reclamation Facility Phase I Early Out Improvements
pob Number: 2752
ertificate Holder is additional insured if required by written contract.
CERTIFICATE HOLD R
CAN
TION
HDR Engineering
Attn: Daniel Harmon
1715 South Reserve Street
Suite C
Missoula, MT 59801-4708
SHOULD ANY OF THE ABOVl: DESCRIBED POLICIES BE CANCELLED BEFORE THE
EXPIRATION DATE THEREOF, THE ISSUING INSURER WILL l:NDEAVOR TO MAIL
.--!L DAYS WRITTEN NOTICE TO THE CERTIFICATE HOLDER NAMED TO THE LEFT,
BUT FAILURE TO MAIL SUCH NOTICE SHALL IMPOSE NO OBLIGATION OR LIABILITY
OF ANY KIND UPON THE INSURER, ITS AGENTS OR REPRESENTATIVES.
AUTHORlll:D REPRESENTATIVE
-;;" ~
Tom Sidor/ED
ACORD 25 (2001/08)
@ACORDCORPORATION 1988
IMPORT ANT
If the certificate holder is an ADDITIONAL INSURED, the policy(ies) must be endorsed. A statement
on this certificate does not confer rights to the certificate holder in lieu of such endorsement(s).
If SUBROGATION IS WAIVED, sUbject to the terms and conditions of the policy, certain policies may
require an endorsement. A statement on this certificate does not confer rights to the certificate
holder in lieu of such endorsement(s).
DISCLAIMER
The Certificate of Insurance on the reverse side of this form does not constitute a contract between
the issuing insurer(s), authorized representative or producer, and the certificate holder, nor does it
affirmatively or negatively amend, extend or alter the coverage afforded by the policies listed thereon.
ACORD 25 (2001/08)
PRODUCER (406) 542-5126
Flynn Insurance Agency
2445 S. Third St. W. Suite B
P.O. Box 3868
jssoula, MT 59801
City 0 Bozeman
411 East Main Street
Bozeman, MT 59715
FAX (406)542-5647
DATE (MM/DDIVYVY)
09/11/2007
THIS CERTIFICATE IS ISSUED AS A MATTER OF INFORMATION
ONLY AND CONFERS NO RIGHTS UPON THE CERTIFICATE
HOLDER. THIS CERTIFICATE DOES NOT AMEND, EXTEND OR
ALTER THE COVERAGE AFFORDED BY THE POLICIES BELOW.
ACDBQM
CERTIFICATE OF LIABILITY INSURANCE
INSURERS AFFORDING COVERAGE
INSURERA. CNA Insurance Companies
INSURER B:
INSURER C;
INSURER 0;
INSURER E:
NAIC#
COVERAGES
THE POLICIES OF INSURANCE LISTED BELOW HAVE BEEN ISSUED TO THE INSURED NAMED ABOVE FOR THE POLICY PERIOD INDICATED. NOTWITHSTANDING
ANY REQUIREMENT, TERM OR CONDITION OF ANY CONTRACT OR OTHER DOCUMENT WITH RESPECT TO WHICH THIS CERTIFICATE MAY BE ISSUED OR
MAY PERTAIN, THE INSURANCE AFFORDED BY THE POLICIES DESCRIBED HEREIN IS SUBJECT TO ALL THE TERMS, EXCLUSIONS AND CONDITIONS OF SUCH
POLICIES. AGGREGATE LIMITS SHOWN MAY HAVE BEEN REDUCED BY PAID CLAIMS
INW ~?~~ TYPI; OF INSURANCE POLICY NUMBI;R P.?k~~Y I;FFI;CTIVI; POLICY I;XPIRATION LIMITS
GENERAL LIABILITY B07082209039 08/09/2007 08/09/2008 EACH OCCURRENCE $ 1,000,000
- DAMAGE TO RENTED N/A
COMMERCIAL GENERAL LIABILITY $
I CLAIMS MADE [K] OCCUR MED EXP (Anyone person) $ N/A
A X Owners & Contracto PERSONAL & ADV INJURY $ N/A
- 2,000,000
GENERAL AGGREGATE $
f-- N/A
GEN'L AGGREGATE LIMIT APPLIES PER: PRODUCTS - COMP/OP AGG $
II nPRO. n
POLICY JECT LOC
AUTOMOBIL.E L.IABIL.ITY COMBINED SINGL.E L.IMIT
'-- (Ea accident) $
ANY AUTO
f---
ALL. OWNED AUTOS BODILY INJURY
- (Per person) $
SCHEDULED AUTOS
-
HIRED AUTOS BODIL. Y INJURY
- (Per accident) $
NON-OWNED AUTOS
-
PROPERTY DAMAGE $
(per accident)
GARAGE L.IABtLlTY AUTO ONL. Y . EA ACCIDENT $
==i ANY AUTO OTHER THAN EA ACC $
AUTO ONLY' AGG $
EXCESS/UMBREL.LA LlABIL.ITY EACH OCCURRENCE $
:=J OCCUR D CLAIMS MADE AGGREGATE $
$
==i DEDUCTIBLE $
RETENTION $ $
WORKERS COMPENSATION AND TWCSTATU- I I OJ.7-
I;MPLOYERS' LIABILITY E.L. EACH ACCIDENT $
ANY PROPRIETOR/PARTNER/EXECUTIVE
OFFICER/MEMBER EXCLUDED? E.L. DISEASE - EA EMPLOYEE $
If yes, describe under E.L. DISEASE - POLICY LIMIT $
SPECIAL PROVISIONS below
OTHER
~ESCRIPTION OF OPERATIONS I LOCATIONS / VEHICLES / EXCLUSIONS ADDED BY ENDORSEMENT f SPECIAL PROVISIONS
roject: Bozeman Water Reclamation Facility Phase I Early Out Improvements
Dab Number: 2752
ertificate Holder is additional insured if required by written contract.
Morrison Maierle, Inc.
Attn: James Nickelson
901 Technology Blvd.
Bozeman, MT 59718
SHOULD ANY OF THl:' ABOVI; DESCRIBED POLICII;S BI; CANCI;LLI;D BEFORE THI;
I;XPIRATION DATE THI;REOF, THE ISSUING INSURI;R WILL I;NDI;AVOR TO MAIL
....iL DAYS WRITTl:'N NOTICI; TO THE CERTIFICATI; HOL.DI;R NAMED TO THE LI;FT,
BUT FAIL.URI; TO MAIL SUCH NOTICE SHALL. IMPOSE NO OBLIGATION OR L.IABILITY
OF ANY KIND UPON THE INSURl:'R, ITS AGI;NTS OR REPRl:'Sl:'NTATIVES.
AUTHORIZI;D RI;PRESIONTATIVE
-,;,,;;jp
Tom Sidor/ED
ACORD 25 (2001/08)
@ACORDCORPORATION 1988
IMPORTANT
If the certificate holder is an ADDITIONAL INSURED, the policy(ies) must be endorsed. A statement
on this certificate does not confer rights to the certificate holder in lieu of such endorsement(s).
If SUBROGATION IS WAIVED, subject to the terms and conditions of the policy, certain policies may
require an endorsement. A statement on this certificate does not confer rights to the certificate
holder in lieu of such endorsement(s).
DISCLAIMER
The Certificate of Insurance on the reverse side of this form does not constitute a contract between
the issuing insurer(s), authorized representative or producer, and the certificate holder, nor does it
affirmatively or negatively amend, extend or alter the coverage afforded by the policies listed thereon.
ACORD 25 (2001/08)
.
MONTANA INTERNATIONAL INSURANCE
A Mernb&r of
POy'tlQo Flnoru:iol Group Inc_
August 28, 2007
Mr. James Nickelson
Morrison Maierle, Inc.
901 Technology Boulevard
Bozeman, MT 59715
RE: Builders Risk Insurance- Bozeman Wastewater Treatment Plant
Dear Mr. Nickelson:
We are the agent for Dick Anderson Construction, Inc. providing the Builder's risk
coverage for the Bozeman Wastewater Treatment Plant project that they are working on
in conjunction with your firm. This letter is to fulfill requirement of the specifications
. that the coverage provided meets your requirements.
We have reviewed the requirements laid out in Article 5 as they apply to the builder's
risk coverage, and have found that the coverage is in compliance with the requirements
with the following exceptions:
1. Earthquake Coverage is limited to $l,OOO,OOO(Section 5.06 A.2).
2. Water Damage is limited to $1,000,000 (Section 5.06 A.2).
3. Materials in transit and in temporary locations are limited to $250,000
(Section 5.06 A.4.)
4. Soft Costs(Section 5.06 A.3.) are limited to $1,000,000
5. The policy includes testing, but excludes Electrical Currents.
6. There is an exclusion for Ordinance or Law(demolition occasioned by
enforcement of laws and regulations).
7. The occupancy provision in the policy is limited to 60 days.(Section 5.06 A.5)
Please let us know if you have any questions.
Sincerely,
~ .
~ ..---?
Z//
. L 1 Downey
Client ACC01.mt Manager
.
3475 Monroe Avenue · PO Box 3089 · Butte, MT 59702"3089 . Phone 406.494.8000 . Fax 406.494]641
An Assurex Global Portner
DIC DE
DATE (MM/DDIYY)
09/10/ 0 7",U~
THIS IS EVIDENCE THAT INSURANCE AS IDENTIFIED BELOW HAS BEEN ISSUED, IS IN FORCE, AND CONVEYS ALL THE
RIGHTS AND PRIVILEGES AFFORDED UNDER THE POLICY.
ODUCER ' ~HONE ..
AI ,No. Extli-
ntana Interna 10na~ ~ns.
Member of Payne Financial Group
P.o. Box 3089
Butte, MT 59701-0638
COMPANY
Cincinnati Insurance Company
P.O. Box 145496
Cincinnati, OH 45250-5496
ACORDTM :EVIDENlCEOiE 'PRDPERTYIN:Sjlil:RIl"'CiE
CODE:
AGENCY ,,_.
CUSTOMER ID #: ? () 7 R q
INSURED
Dick Anderson Construction,
3424 Highway 12 East
Helena, MT 59601
".-~?DE:
EFFECTIVE DATE
01/01/07
EXPIRATION DATE
Inc.
LOAN NUMBER
Builders
POLICY NUMBER
CAP5473733
01/01/08
CONTINUED UNTIL
TERMINATED IF CHECKED
THIS REPLACES PRIOR EVIDENCE DATED:
PROPERlJ'",:II1lFORMA'TIOfll
LOCATION/DESCRIPTION
255 Moss Bridge Road
Bozeman, MT 59715
'Ct>VER4G'E:i~:i!iFCiRMArION
COVERAGE/PERILS/FORMS
BUILDERS RISK COVERAGE INFORMATION
AMOUNT OF INSURANCE
DEDUCTIBLE
Open Reporting Coverage Any One Location:
20,000,000
ft Costs-
orm#: MA229
$1,000,000
Edition Date: 06/01/99
1,000,000
2,500
Annual Audit
Form#: MA461 Edition Date: 06/01/95
Builders' Risk Inland Marine Flood Endorsement 1,000,000 5,000
See Attached Covera e Info.
RE'N1l4irltKS (Including'lllP,$claICondltiol"lE\)
City of Bozeman, HDR Engineering (1715 S. Reserve, Suite C, Missoula MT,
59801), and Morrison Maierle, Inc (901 Technology Blvd, Bozeman MT, 59718) are
listed as additional insured in regards to the Bozeman Wastewater Treatment
plant project.
CANCELLA'TION
'THE POLICY IS SUBJECT TO THE PREMIUMS, FORMS, AND RULES IN EFFEC'T FOR EACH POLICY PERIOD. SHOULD THE
POLICY BE TERMINATED, THE COMPANY WILL GIVE THE ADDITIONAL INTEREST IDENTIFIED BELOW 30 DAYS
WRITTEN NOTICE, AND WILL SEND NOTIFICATION OF ANY CHANGES TO THE POLICY THAT WOULD AFFECT THAT
INTEREST, IN ACCORDANCE WITH THE POLICY PROVISIONS OR AS REQUIRED BY LAW.
ADOI~IONALIN'TEREST
NAME AND ADDRESS
City of Bozeman
411 East Main Street
ozeman, MT 59715
MORTGAGEE ~ADDITIONALINSURED
LOSS PAYE!=___L_L__._._
LOAN #
AUTHORIZED REPRESENTATIVE
I
ACORD?7(3/93)1of
B:O 5
~.1.IY~
Tit#" @:::~~lJRitll,GbRP,OR:ATION 199
COVERAGE/PERILS/FORMS
COVERAGE :liN'l=il1lJRMATtON :(:C.QJ1'I~i.nuedlfr:(i)'~'!i~~SJe1,.)
AMOUNT OF INSURANCE
Form#: MA214 Edition Date: 06/01/95
uilders' Risk Inland Marine Ground Water Endorsement
Form#: MA215 Edition Date: 06/01/95
Builders' Risk inland marine earthquake endorsement
Form#: MA216 Edition Date: 06/01/95
Additional Insured- Builder's Risk
Form#: IA4501 Edition Date: 11/01/S7
Special
Earthquake
Flood
ClII'GEM27J3;(3193)2
of 2
50955
1,000,000
1,000,000
20,000,000
1,000,000
1,000,000
TIB
DEDUCTIBLE
5,000
5,000
5,000
5,000
5,000
Client#: 4861
MTCONTRA
ACORDTM CERTIFICATE OF LIABILITY INSURANCE
DATE (MM/DDIYYYY)
08/09/2007
THIS CERTIFICATE IS ISSUED AS A MATTER OF INFORMATION
ONLY AND CONFERS NO RIGHTS UPON THE CERTIFICATE
HOLDER. THIS CERTIFICATE DOES NOT AMEND, EXTEND OR
ALTER THE COVERAGE AFFORDED BY THE POLICIES BELOW.
PRODUCER
Hoiness LaBar Insurance
Member of Payne financial Group
. Box 30638
illings, MT 59107-0638
Dick Anderson Construction, Inc
3424 Hwy 12 East
Helena, MT 59601
INSURERS AFFORDING COVERAGE
INSURER A_ ACE American Insurance CO.
INSURER B:
INSURER C;
INSURER 0:
INSURER 10:
NAIC#
INSURED
COVERAGES
THE POLICIES OF INSURANCE LISTED BELOW HAVE BEEN ISSUED TO THE INSURED NAMED ABOVE FOR THE POLICY PERIOD INDICATED_ NOTWITHSTANDING
ANY REQUIREMENT. TERM OR CONDITION OF ANY CONTRACT OR OTHER DOCUMENT WITH RESPECT TO WHICH THIS CERTIFICATE MAYBE ISSUED OR
MAY PERTAIN. THE INSURANCE AFFORDED BY THE POLICIES DESCRIBED HEREIN IS SUBJECT TO ALL THE TERMS. EXCLUSIONS AND CONDITIONS OF SUCH
POLICIES. AGGREGATE LIMITS SHOWN MAY HAVE BEEN REDUCED BY PAID CLAIMS.
INSR ~~~: POLICY NUMBER PDO~~~Y ~~rJ8m\E P~'aI~: t'i.X.rA,~~~N LIMITS
LTR TYPE OF INSURANCE
GENERAL LIASILITY EACH OCCURRENCE $
I---- DAMAGE TO RENTED
COMMERCIAL GENERAL LIABILITY $
I---- ~ CLAIMS MADE D OCCUR
MED EXP (Anyone person) $
I----
PERSONAL & ADV INJURY $
I----
GENERAL AGGREGATE $
GEN'L AGGREGATE LIMIT APPLIES PER: PRODUCTS. COMP/OP AGG $
II n PRO- -'n
POLICY JECT LOC
~TOMOBILE LIABILITY COMBINED SINGLE LIMIT $
ANY AUTO (lOa accident)
f--
ALL OWNED AUTOS BODILY INJURY
I---- (Per person) $
SCHEDULED AUTOS
I----
HIRED AUTOS BODILY INJURY
I---- (Per accident) $
f-- NON.OWNED AUTOS
PROPERTY DAMAGE $
(Per accidsnl)
RAGE LIABILITY AUTO ONLY. EA ACCIDENT $
ANY AUTO OTHER THAN lOA ACC $
AUTO ONLY: AGG $
EXCESS/UMBRELLA LIABILITY EACH OCCURRENCE $
tJ OCCUR D CLAIMS MADE AGGREGATE $
$
R DEDUCTIBLE $
RETENTION $ $
WORKERS COMPENSATION AND 1 ,:~~J;~J.~~l 10J~-
EMPLOYERS' LIABILITY EL EACH ACCIDENT $
ANY PROPRIETOR/PARTNER/EXECUTIVE
OFFICERlMEMSER EXCLUDED? E.L. DISEASE - lOA EMPLOYEE $
If yes. describe under E.L. DISEASE - POLICY LIMIT $
SPECIAL PROVISIONS below
A OTHER Workers Comp WCUC44638769 01/01/07 01101108 Coverage A - Statutory
Employers Liabllity-N.IL
DESCRIPTION OF OPERATIONS / LOCATIONS I VEHICLES / EXCLUSIONS ADDED BY ENDORSEMENT I SPECIAL PROVISIONS
Subject to the terms and conditions of the policy as issued by the Insurance Company.
SIR for Work Comp $750,000 each accident. Covers Montana State Resident Employees. All
claims are administered by the Montana Contractor Compensation Fund.
JOB: Bozeman Water Reclamation Facility Phase 1 Early Out Improvements
CERTIFICATE HOLDER
CANCELLATION
City of Bozeman
AUn: Tom Adams
411 E. Main Street
Bozeman, MT 59715
SHOULD ANY OF THE ABOVE DESCRIBED POLICIES BE CANCELLED BEFORE THE EXPIRATION
DATE THEREOF, THE ISSUING INSURER WILL ENDEAVOR TO MAIL --1iO..... DAYS WRITTEN
NOTICE TO THE CERTIFICATE HOLDER NAMED TO THE LEFT, BUT FAILURE TO DO SO SHALL
IMPOSE NO OBLIGATION OR LIABILITY OF ANY KIND UPON THE INSURER, ITS AGENTS OR
REPRESENTATIVES.
AUTHORIZED REPRESENTATIVE
"
ACORD 25 (2001/08) 1 of 2
. #S295720/M263574
VE1
@ ACORD CORPORATION 1988
IMPORTANT
If the certificate holder is an ADDITIONAL INSURED, the policy(ies) must be endorsed. A statement
on this certificate does not confer rights to the certificate holder in lieu of such endorsement(s).
If SUBROGATION IS WAIVED, subject to the terms and conditions of the policy, certain policies may
require an endorsement. A statement on this certificate does not confer rights to the certificate
holder in lieu of such endorsement(s).
DISCLAIMER
The Certificate of Insurance on the reverse side of this form does not constitute a contract between
the issuing insurer(s), authorized representative or producer, and the certificate holder, nor does it
affirmatively or negatively amend, extend or alter the coverage afforded by the pOlicies listed thereon.
ACORD 25-5 (2001/08)
2 of 2
#S295720/M263574
Client#: 4861
MTCONTRA
ACORDTM CERTIFICATE OF LIABILITY INSURANCE
DATE (MMIDDfYYVY)
08/09/2007
THIS CERTIFICATE IS ISSUED AS A MATTER OF INFORMATION
ONLY AND CONFERS NO RIGHTS UPON THE CERTIFICATE
HOLDER. THIS CERTIFICATE DOES NOT AMEND, EXTEND OR
ALTER THE COVERAGE AFFORDED BY THE POLICIES BELOW.
PRODUCER
Hoiness LaBar Insurance
Member of Payne Financial Group
. Box 30638
iIIings, MT 59107-0638
Dick Anderson Construction, Inc
3424 Hwy 12 East
Helena, MT 59601
INSURERS AFFORDING COVERAGE
INSURER A; ACE American Insurance CO.
INSURER B:
INSURER C;
INSURER D:
INSURER E:
NAIC#
INSURED
COVERAGES
THE POLICIES OF INSURANCE LISTED BELOW HAVE BEEN ISSUED TO THE INSURED NAMED ABOVE FOR THE POLICY PERIOD INDICATED. NOTWITHSTANDING
ANY REQUIREMENT, TERM OR CONDITION OF ANY CONTRACT OR OTHER DOCUMENT WITH RESPECT TO WHICH THIS CERTIFICATE MAY BE ISSUED OR
MAY PERTAIN. THE INSURANCE AFFORDED BY THE POLICIES DESCRIBED HEREIN IS SUBJECT TO ALL THE TERMS, EXCLUSIONS AND CONDITIONS OF SUCH
POLICIES. AGGREGATE LIMITS SHOWN MAY HAVE BEEN REDUCED BY PAID CLAIMS.
INSR IADD' TYPE OF INSURANCE P.?LlS':.~.!:~Eg~~\E Pg't;J r~X.rfu~~N
LTR NSR POLICY NUMBER LIMITS
~NERAL LIA61L1TY EACH OCCURRENCE $
5MERCIAL GENERAL LIABILITY DAMAGE TO RENTED $
I--- CLAIMS MADE D OCCUR
I-- MED EXP (Anyone person) $
PERSONAL & ADV INJURY $
GENERAL AGGREGATE $
n'L AGGREAE LIMIT APnS PER: PRODUCTS - COMP/OP AGG $
POLICY P,,fg: LOC
~TOMOBILE LIABILITY COMBINED SINGLE LIMIT $
ANY AUTO (Ea accident)
-
- ALL OWNED AUTOS BODILY INJURY
$
SCHEDULED AUTOS (Per person)
-
HIRED AUTOS BODILY INJURY
- $
NON-OWNED AUTOS (Per accident)
-
. - PROPERTY DAMAGE $
(Per accident)
==iAGE LIABILITY AUTO ONLY - EA ACCIDENT $
ANY AUTO OTHER THAN EA ACC $
AUTO ONLY: AGG $
EXCESS/UMBRELLA LIABILITY EACH OCCURRENCE $
~ OCCUR D CLAIMS MADE AGGREGATE $
$
==i DEDUCTIBLE $
RETENTION $ $
WORKERS COMPENSATION AND I WC STATU-.I IOl~-
EMPLOYERS' LIABILITY
ANY PROPRIETOR/PARTNER/EXECUTIVE EL EACH ACCIDENT $
OFFICER/MEMBER EXCLUDED? EL DISEASE - EA EMPLOYEE $
If yes, describe under E.L. DISEASE - POLICY LIMIT $
SPECIAL PROVISIONS below
A OTHER Workers Comp WCUC44638769 01101/07 01/01108 Coverage A - Statutory
Employers Liability-NIL
DESCRIPTION OF OPERATIONS / LOCATIONS / VEHICLES/ EXCLUSIONS ADDED BY ENDORSEMENT / SPECIAL PROVISIONS
Subject to the terms and conditions of the policy as issued by the Insurance Company.
SIR for Work Comp $750,000 each accident. Covers Montana State Resident Employees. All
claims are administered by the Montana Contractor Compensation Fund.
JOB: Bozeman Water Reclamation Facility Phase 1 Early Out Improvements
CERTIFICATE HOLDER
CANCELLATION
HDR Engineering
Attn: Daniel Harmon
1715 S. Reserve Street
Missoula, MT 59801-4708
SHOULD ANY OF THE ABOVE DESCRIBED POLICIES BE CANCELLED BEFORE THE EXPIRATION
DATE THEREOF. THE ISSUING INSURER WILL ENDEAVOR TO MAIL ......6Q.... DAYS WRITTEN
NOTICE TO THE CERTIFICATE HOLDER NAMED TO THE LEFT, BUT FAILURE TO DO SO SHALL
IMPOSE NO OBLIGATION OR LIABILITY OF ANY KIND UPON THE INSURER, ITS AGENTS OR
ACORD 25 (2001/08) 1 of 2
#S295719/M263574
VE1
@ ACORD CORPORATION 1988
IMPORTANT
If the certificate holder is an ADDITIONAL INSURED, the pOlicy(ies) must be endorsed. A statement
on this certificate does not confer rights to the certificate holder in lieu of such endorsement(s).
If SUBROGATION IS WAIVED, subject to the terms and conditions of the policy, certain policies may
require an endorsement. A statement on this certificate does not confer rights to the certificate
holder in lieu of such endorsement(s).
DISCLAIMER
The Certificate of Insurance on the reverse side of this form does not constitute a contract between
the issuing insurer(s), authorized representative or producer, and the certificate holder, nor does it
affirmatively or negatively amend, extend or alter the coverage afforded by the policies listed thereon.
ACORD 25-$ (2001/08)
2 of 2
#S295719/M263574
Client#: 4861
MTCONTRA
ACORDTM
CERTIFICATE OF LIABILITY INSURANCE
PRODUCER
Hoiness LaBar Insurance
I: ber of Payne Financial Group
ox 30638
BI ngs, MT 59107-0638
RECEIVED
1.11'"
P,UU
DATE (MM/DDIYYVY)
08/09/2007
THIS CERTIFICATE IS ISSUED AS A MATTER OF INFORMATION
ONLY AND CONFERS NO RIGHTS UPON THE CERTIFICATE
HOLDER. THIS CERTIFICATE DOES NOT AMEND, EXTEND OR
A THE COVERAGE AFFORDED BY THE POLICIES BELOW.
,
INSURED
INSURERS AFFORDING COVERAGE
INSURER A: ACE American Insurance Co.
NAIC#
Dick Anderson Construction, Inc
3424 Hwy 12 East
Helena, MT 59601
INSURER B:
INSURER C:
INSURER D:
INSURER E:
COVERAGES
THE POLICIES OF INSURANCE LISTED BELOW HAVE BEEN ISSUED TO THE INSURED NAMED ABOVE FOR THE POLICY PERIOD INDICATED. NOTWITHSTANDING
ANY REQUIREMENT, TERM OR CONDITION OF ANY CONTRACT OR OTHER DOCUMENT WITH RESPECT TO WHICH THIS CERTIFICATE MAY BE ISSUED OR
MAY PERTAIN, THE INSURANCE AFFORDED BY THE POLICIES DESCRIBED HEREIN IS SUBJECT TO ALL THE TERMS, EXCLUSIONS AND CONDITIONS OF SUCH
POLICIES, AGGREGATE LIMITS SHOWN MAY HAVE BEEN REDUCED BY PAID CLAIMS,
INSR ~~~~ PJ>.k{~';ri~f~8mlE P~~fJ r~X~~~N
LTR TYPE OF INSURANCE POLICY NUMBER LIMITS
GENERAL LIABiLiTY EACH OCCURRENCE $
f-- DAMAGE TO RENTED
COMMERCIAL GENERAL LIABILITY cel $
I CLAIMS MADE D OCCUR MED EXP (Anyone peClon) $
PERSONAL & ADV INJURY $
f--
GENERAL AGGREGATE $
f--
GEN'L AGGREGATE LIMIT APPLIES PER: PRODUCTS - COM PlOP AGG $
n n PRO- nLOC
POLICY JECT
AUTOMOBILE LIABILITY COMBINED SINGLE LIMIT
f-- $
ANY AUTO (Ea accident)
f----
ALL OWNED AUTOS BODILY INJURY
f---- $
SCHEDULED AUTOS (Per person)
f--
f---- HIRED AUTOS BODILY INJURY
$
NON-OWNED AUTOS (Per accident)
f--
f-- PROPERTY DAMAGE $
(Per accident)
GARAGE LIABILITY AUTO ONLY - EA ACCIDENT $
R ANY AUTO OTHER THAN EA ACC $
AUTO ONLY: AGG $
EXCESS/UMBRELLA LIABiLiTY EACH OCCURRENCE $
tJ OCCUR D CLAIMS MADE AGGREGATE $
__ ~:~~~~I~~E_~_____~ $
$
~--~ ---..-..----.------- --~~-~-- . I T~~~~'~!TsT-~ ~---~--
WORKERS COMPENSATION AND
EMPLOYERS' LIABILITY
ANY PROPRIETOR/PARTNER/EXECUTIVE E.L. EACH ACCIDENT $
OFFICER/MEMBER EXCLUDED? E.L. DISEASE. EA EMPLOYEE $
If yes, describe under E.L. DISEASE. POLICY LIMIT $
SPECIAL PROVISIONS below
A OTHER Workers Comp WCUC44638769 01/01/07 01/01/08 Coverage A - Statutory
Employers Liability-NIL
DESCRIPTION OF OPERATIONS / LOCATIONS / VEHICLES / EXCLUSIONS ADDEO BY ENDORSEMENT / SPECIAL PROVISIONS
Subject to the terms and conditions of the policy as issued by the Insurance Company.
SIR for Work Comp $750,000 each accident. Covers Montana State Resident Employees. All
claims are administered by the Montana Contractor Compensation Fund.
JOB: Bozeman Water Reclamation Facility Phase 1 Early Out Improvements
CERTIFICATE HOLDER
CANCELLATION
SHOULD ANY OF THE ABOVE DESCRIBED POLICIES BE CANCELLED BEFORE THE EXPIRATION
. Morrison Maierle Inc. DATE THEREOF, THE ISSUING INSURER WILL ENDEAVOR TO MAIL --6D-- DAYS WRITTEN
Attn: James Nickelson NOTICE TO THE CERTIFICATE HOLDER NAMED TO THE LEFT, BUT FAILURE TO DO SO SHALL
901 Technology Blvd IMPOSE NO OBLIGATION OR LIABILITY OF ANY KIND UPON THE INSURER, ITS AGENTS OR
Bozeman, MT 59718 REPRESENTATIVES.
AUTHORIZED REPRESENTATIVE
(\, 11
ACORD 25 2001/08 '-- @I ACORD CORPORATION 19a8
) 1 of 2
#S295718/M263574
VE1
IMPORTANT
If the certificate holder is an ADDITIONAL INSURED, the policy(ies) must be endorsed. A statement
on this certificate does not confer rights to the certificate holder in lieu of such endorsement(s).
If SUBROGATION IS WAIVED, subject to the terms and conditions of the policy, certain policies may
require an endorsement. A statement on this certificate does not confer rights to the certificate
holder in lieu of such endorsement(s).
DISCLAIMER
The Certificate of Insurance on the reverse side of this form does not constitute a contract between
the issuing insurer(s), authorized representative or producer, and the certificate holder, nor does it
affirmatively or negatively amend, extend or alter the coverage afforded by the pOlicies listed thereon.
.
ACORD 25-5 (2001/08) 2 of 2
#S295718/M263574
.
SECTION 00700
GENERAL CONDITIONS
EJCDC DOCUMENT NO. C-700, 2002 EDITION (45 pages)
(Pages are numbered 1 through 45)
.
.
00...52713"0012
Bozeman WRF Phase 1 Early Out Priority Improvements
00100 - 1
512212007
. _ ~ J..' . ~ t.. .
.' ' ~
., ; ~ . ,
,;
;'
,. '; ~ :'
.:.
':....
< ",
.
. ~. "
.
.
.
NOTE: THIS DOCUMENT HAS BEEN AMENDED FOR THIS PROJECT AND CONTROLLING LAW.
This document has important legal consequences; consultation with an attorney is encouraged with respect to its use or
modification. This document should be adapted to the particular circumstances of the contemplated Project and the
Controlling Law.
.
.
-----
ACEC
AM2R1CAN' COUNCIl. OF ENC;fNJl:rr.Jl:TNC CO:vlrANHiS
00...52713-0012
STANDARD
GENERAL CONDITIONS
OF THE
CONSTRUCTION CONTRACT
Prepared by
ENGINEERS JOINT CONTRACT DOCUMENTS COMMITTEE
and
Issued and Published Jointly By
fj National Society of
.. Professional Engineers
Professional Engineers in Private Practlc8
.SCle American Society
~ .. of Civil Engineers
PROFESSIONAL ENGINEERS IN PRIVATE PRACTICE
a practice division of the
NATIONAL SOCIETY OF PROFESSIONAL ENGINEERS
AMERICAN COUNCIL OF ENGINEERING COMPANIES
AMERICAN SOCIETY OF CIVIL ENGINEERS
This document has been approved and endorsed by
-
~
The Associated General Contractors of America .
~
Knowladga for Creating
and Sustaining
lha Buill Envlronmanl
Construction Specifications Institute
Bozeman WRF Phase 1 Early Out Priority Improvements
00700 ~ 2
5/2212007
NOTE: Deletions from the Standard EJCDC General Conditions are shown by strikeout.
Additions to the Standard EJCDC General Conditions are Underlined.
Adaptation of Standard General Conditions prepared bv Morrison-Maierle. Inc.
Initial Issue:
6/30/03
Copyright @2002
National Society of Professional Engineers
1420 King Street, Alexandria, VA 22314
American Council of Engineering Companies
1015 15th Street, N.W., Washington, DC 20005
American Society of Civil Engineers
1801 Alexander Bell Drive, Reston, VA 20191-4400
.
.
These General Conditions have been prepared for use with the Suggested Forms of Agreement Between Owner and
Contractor Nos. C-520 or C-525 (2002 Editions). Their provisions are interrelated and a change in one may necessitate a
change in the other. Comments concerning their usage are contained in the EJCDC Construction Documents, General and
Instructions (No. C-001) (2002 Edition). For guidance in the preparation of Supplementary Conditions, see Guide to the
Preparation of Supplementary Conditions (No. C~800) (2002 Edition).
MMI No. C-700 (2003 Edition)
6/30/03
00.. .52713-0012
Bozeman WRF Phase 1 Early Out Priority Improvements
00700 - 3
5/22/2007
.
.
.
.
TABLE OF CONTENTS
Page
ARTICLE 1 - DEFINITIONS AND TERMINOLOGY .............................................................................................................7
1.01 Defined Terms ............................................... ... ......... ............................ ....... ......................... ........................... ............7
1.02 Terminology... ......... ........ ........ .............. ......... ......... ... ........ ....................... ................................................ ...................9
ARTICLE 2 - PRELIMINARY MATTERS ............................................................................................................................. 10
2.01 Delivery of Bonds and Evidence of Insurance................................................................................ ...........................10
2.02 Copies of Documents ................................................................................................................................................. 10
2.03 Commencement of Contract Times; Notice to Proceed.............................................................................................10
2.04 Starting the Work..... .... ........ ...... ........ .... .... .............. ........... ...... .... ................ ..... .................. .... ........... ..... ............. ..... 10
2.05 Before Starting Construction ..................................................................................................................................... 10
2.06 Preconstruction Conference .............. ... ........ ..... ........... ................ ..... .... .... ... ... ............... ..... ........... .............. ............. 11
2.07 Initial Acceptance of Schedules .................................................................................................................................11
ARTICLE 3 - CONTRACT DOCUMENTS: INTENT, AMENDING, REUSE ...................................................................... 11
3.01 Intent.. ............... ........... ...... ......... ........... ................ .... ......................... ...... ..... ..... ............. ..... .... ....... ...... ...... .... ...... .... 11
3.02 Reference Standards .................................................................................................................................................. 11
3.03 Reporting and Resolving Discrepancies .................................................................................................................... 12
3.04 Amending and Supplementing Contract Documents ................................................................................................. 12
3.05 Reuse of Documents ................................................ ........... ................... ...................... .... ..... ............... ....... ........... ..... 12
3. 06 Electronic Data........................................................................................................................... ............................... 12
ARTICLE 4 - A V AILABILITY OF LANDS; SUB SURF ACE AND PHYSICAL CONDITIONS; HAZARDOUS
ENVIRONMENTAL CONDITIONS; REFERENCE POINTS................................................................................................13
4.01 Availability of Lands... .................. ....................... ..................... ...... ....... ....... ......... ........ ........... ................................. t 3
4.02 Subsurface and Physical Conditions ......................................................................................................................... 13
4.03 Differing Subsurface or Physical Conditions ............................................................................................................ 13
4.04 Underground Facilities......... ................ ..... ....... ...... .............. ....... ... ..' ...... ............ ...... ............... ......... .................. ..... 14
4.05 Reference Points......................................................................................................................... ............................... 15
4.06 Hazardous Environmental Condition at Site .............................................................................................................15
ARTICLE 5 - BONDS AND INSURANCE .............................................................................................................................16
5.01 Performance, Payment, and Other Bonds .................................................................................................................16
5.02 Licensed Sureties and Insurers .................................................................................................................................. 16
5.03 Certificates of Insurance.. ........ ........ ........... ................. .............. .......... ...... ...... .... ........ ... ............................. .... .......... 16
5.04 Contractor's Liability Insurance ............................................................................................................................... 17
5.05 Owner's Liability Insurance ...................................................................................................................................... 18
5.06 Property Insurance - Purchased by Contractor........................................................................................................ 18
5 .07 Waiver of Rights .......... .............................. ............. ......... ...................... ........... .................. .................. ................ ..... 19
5.08 Receipt and Application of Insurance Proceeds ........................................................................................................ 19
5.09 Acceptance of Bonds and Insurance; Option to Replace........................................................................................... 20
5.10 Partial Utilization, Acknowledgment of Property Insurer......................................................................................... 20
ARTICLE 6 - CONTRACTOR'S RESPONSIBILITIES.......................................................................................................... 20
6.01 Supervision and Superintendence.. .... ........ ....... ...... .......... ..................... ..... .................. ......................................... ....20
6.02 Labor; Working Hours ...... ............ .............................. ................ ............ ........... ............... ................... ..... .... ............20
6.03 Services, Materials, and Equipment .......................................................................................................................... 20
6.04 Progress Schedule ...... .... ........ ..................... ........ .... ............ .... .... ........ ...... .............. ........... .... .... ........ ..... ..... ........ .....21
6.05 Substitutes and "Or-Equals" .....................................................................................................................................21
6.06 Concerning Subcontractors, Suppliers, and Others ..................................................................................................22
6.07 Patent Fees and Royalties. ................ ........................................... .......................................... ............. ......... ... ....... ...23
6.08 Perm its.............................................................................................................................. ......................................... 23
6.09 Laws and Regulations. ........ ........ .......... ........... .................... ........... ............ ................ ............................................... 23
6.10 Taxes ................. ...................... ...... ...... .... ..................... ........ ...... ..... ....... ....... .............. .... ..... .... .... ..... ............. ...... ......24
6.11 Use of Site and Other Areas ...................................................................................................................................... 24
6.12 Record Documents ............... .... ............ .... ...... ....... ........ .... .......................................................... ...... ........... ..............24
6.13 Safety and Protection..................... ............. ...... .... ............ ............... ....... ........... ................... ........ ............................. 24
6.14 Safety Representative...... ...... ........ .................. ...... ............ .......................... ..... ............ ......... ........................ .............25
6.15 Hazard Communication Programs ............................................................................................................................25
00" .52713-0012
5/22/2007
Bozeman WRF Phase I Early Out Priority Improvements
00700 - 4
6,16 Emergencies"",.... ,,,,,,,,,,,,,,.,.,,.,,,,,,.,,,.,,.,,,,,.. ,." .""."". """ "...,,,.",,,,,,.,,,, .."" ".".".""", "",,,,,.......,, ...""".,."".",,,,,,, 26
6,17 Shop Drawings and Samples ".""",.",,,.",,,,.,,,.,,,..............,,..,,,,,,,,.".",,,,,,,,,,...,,....,,,,....,,""""........",......"""""".." 26
6.18 Continuing the Work.."".................".....""....."".""".......,."",.....".."...".."......"""",,,.,,,,.........,,......,,,,,,,.,,.,,,,,.,,,,..27 .
6.19 Contractor's General Warranty and Guarantee ..""""""."",,,,,..........,,,,,,..,,,,.",,,,,.,,.,,,,.......,,""""""",,,,,,",,..,,.... 27
6.20 Indemnification ..... .......... ....... .............. ...........,., .,..... ..... ..... ...... ........... ..... ...,.". ........... ....... ............, .".... ............. ......27
6.21 Delegation of Professional Design Services ...."........"."""......."...",...""..""....""..."..............".........""...",,,.,,,,,,,.28
ARTICLE 7 - OTHER WORK AT THE SITE ...",,,,,,,,,,,.....,,,,,..........,,...,,,,,,,,,,,,,,,,,,,,,.,,,,..................,,,,,,.,,,.,,,,,..............."...28
7.01 Related Work at Site "...."""...""......"""",,,,,,,,,,,,,.,,.,,,,.,,,,.,,...,,.......,,,,,,..,,,,.,,,,,"...."......."""",,,,,,,,,.,,.........,,,,...,,.28
7.02 Coordination....................................,.........,.....,.,.,.,.......................................",.............. ...............,.",.,.....................29
7 .03 Legal Relationships "... ",,,,,,,,,,,. ",,,,, "..", "",,,,,,,,,,,,,,,,,,,,,... ."..."". """"",,,,,,. "",,,,,,... ".... "..,,,,,,.,,.,,..,,.,,,, ."" ".......29
ARTICLE 8 R OWNER'S RESPONSIBILITIES ".."",,,,,,,,....,,.,,,,..................,,,,..,,,,...,,...,,.,,,,.,,.........,,,,,,,,,,,,,,,,,................... 29
8.01 Communications to Contractor.". "",,,,,.. ..."" "...""."...""" ........."""" """..." ".". ".............." ..."...."""."" ........ ...... 29
8.02 Replacement of Engineer .".................. .... ....." ..... ...................,.. ..,.,.,..... .... ... ... ...... .............. ...... .................... ...... ......29
8,03 Furnish Data... ......,.. ..... ................,...,.. ....".,..... ... .".. ... .... ................... ...., ... ..... ........ ........ .... .".,.,.. ,..... ..... ......... .........29
8.04 Pay When Due. ".""'''.''"".""". .............. ......... .... ........ ...""",,,,,,,,,,,,.,,,, ".... ..... ........."""""" ....... ........... ",,,,,,, """".29
8.05 Lands and Easements; Reports and Tests"........................."""""."""""."..............".....""......."..........."........"...".29
8,06 Insurance........................,......,........".,.,........................................,.,...,.,...................... .........".,................................. 29
8.07 Change Orders.. .......... ...... ........ "........."".",,,. ""."."""."..".... ..........." "..""", ",,,.,,...,,........ "..... """,,,,,,, .".............29
8.08 Inspections, Tests, and Approvals..... .... ".........."" "... "....."".."................ .."""..""" "". ""........."".."."". ."""....."".29
8.09 Limitations on Owner's Responsibilities ..""....."""""."""....................."",,,,,,,,,,,,,,,.,,,,.,,..........,,,,,,,,,,,.......".........29
8.10 Undisclosed Hazardous Environmental Condition""...."""""""".."."........"..."..""""".."."........"........""......"..... 29
8.11 Evidence of Financial Arrangements ""...."",,,,,,,,,,...,,,,,,,,.,,...,,.,,.........,,..,,,,,,,,,,,....,,,,,,.,,........,,.....,,,,,,."""""""...30
ARTICLE 9 - ENGINEER'S STATUS DURING CONSTRUCTION "."""".............."............""""...""""........"............".. 30
9.01 Owner's Representative.."." ".."....""""....."""."""."." ...... ........"..""." """"".". .............." ."",,,...,,,,,,,,. .................30
9.02 Visits to Site ....... "....."..... "..... "..,,, "",,,,, ".." "."""".".""" ...... ......."" "........." .""".".""" .". ".... "..,,,.....",,,,,,,,..,,,,,,. 30
9 .03 Project Representative....."."" "... "..."" "...... "..."..."", ..."'''.. .....""..". ......."."",,,,,.,,,,,,, ................."..."""".."...""" 30
9.04 Authorized Variations in Work "....."".............,......",,,,,,,,,,,,.,,.,,,,......................,,...,,,,,..,,",,."...............".."""".""" 30
9 ,05 Rejecting Defective Work,,,,,,,....,,,,.. """...".".""."". "..... .....".""""""..."".."..."". ...""""""."..""""."" ......."......" 30
9.06 Shop Drawings, Change Orders and Payments ""........................""""".."...."......................"....""""""................ 30
9.07 Determinationsfor Unit Price Work ,,,,,.",,.,,..........,,.......,,..,,,,........,,,........,,,,......,,...........,,.....,,"""".""...."...........31 .
9.08 Decisions on Requirements of Contract Documents and Acceptability of Work "......................"""...""".............." 31
9.09 Limitations on Engineer's Authority and Responsibilities """"....................."...""...."""...."..........."""........"....",31
ARTICLE 10 - CI-IANGES IN THE WORK; CLAIMS ""......"."""""......."".."......".."",...""..."".................".."...""".""... 31
10.01 Authorized Changes in the Work ......""........."""".."""...""."""".......""...."...."""..""....."...............""""......",31
1 0.02 Unauthorized Changes in the Work........."....""""""""..."".""""""......."""...."""",,,....,,,,.........".."""""..",,,,, 32
1 0.03 Execution of Change Orders ,,,..,,,,,..,,,,,,,,,,,,,,,,,.,,,,.,,,,......,,,,...,,.,,,,,,,,,....,,.....",,...,,,,..,,...,,....,,..".""...."............. 32
1 0.04 Notification to Surety""" "..",,,.,,,,,,.....,,,,. "".".."...." "........ "...... ...""" ...."" ..........."...",,,,,...,,,,..,,.... ...". "......."" 32
1 0.05 Claims. ",,, "..",,, """...,...." ""..""""....".". "...""." "...".. ".." "..... """""."..... ..."... "......",,,,, ""....."....".."". "...."" 32
ARTICLE 11 - COST OF THE WORK; ALLOWANCES; UNIT PRICE WORK ..........................."""."....".......................33
11.01 Cost of the Work """."".".."".""".".."............"."....".."""...".".".""..........".......""".."""".""........"....."""..".. 33
11.02 Allowances""".""".""...""..........."... .................." "''''''''''''.'' ."...""....."." "...". ",,,,,,,,,,,,,,,..... ....""" ".... ",,,,,,,,,,, 34
11.03 Unit Price Work........................""........."""......,,,...........,,,,.........,,....,,.,,",,,,,...,,.,,...,,.,,.....,,.,,..,,..,,,,....",,,,.....",, 34
ARTICLE 12 ~ CHANGE OF CONTRACT PRICE; CHANGE OF CONTRACT TIMES""..."...."""...".."""""."."".."."" 35
12,01 Change of Contract Price ""."".......""...."".........."..."""."",,,,,..,,,,,,,,.........,,......,,,,,,,,,,""..............""."",,,,,,,,,,, 35
12.02 Change of Contract Times """"""."""."...."........................""""""."".""..."................""",......"""......""......... 36
12,03 Delays "......""""". "".""""." .............. ....".." ......... "..." "".".""""" ....... ."........" "... "......""..."......" ...". ",,,,,,,,,,,.. 36
ARTICLE 13 - TESTS AND INSPECTIONS; CORRECTION, REMOVAL OR ACCEPTANCE OF DEFECTIVE WORK
.........................................................................................,..."......,.,................:.........................................................,....,..,........36
13.01 Notice of Defects."."".""""....... ........... ........... "..."""""""".."""""..."."". ............" ".."" ...."....."" ".... ...."."" ....36
13.02 Access to Work"""."."""..""." ".....""..". "...... "...""......"" """.........""". "........ "..." """....""""""""".... ""."""" 36
13.03 Tests and Inspections""..".. ."....."""".. ".."....." "..".."""".""...."."" "...................." ..."........""" ....."" """.."...".36
13.04 Uncovering Work.."""""" ........" ...... ....." "......" ..."". """"."."".".".... "...." ........"" "....""."""...."..""..". """""" 3 7
13.05 Owner May Stop the Work....""""".......".."..""...""".."."."."""......"...........""...""",.""..."""""""".....""""".. 37
13.06 Correction or Removal of Defective Work......."...""."....".."""".."""".""."....."..."".".................."."."..."""....37
1.3 . 07 Correction Period........................................",.,.....,..,...,.,.............."..........................,.,................ ................,........ 37
13.08 Acceptance of Defective Work """".....""."."""."...""""......"......""......".."..........."""..........".."......,............"" 38 .
13.09 Owner May Correct Defective Work .................".",,,,,..,,,,..,,,,,,,,,,,,,,......................,,....,,"''''''''''',,...""..".........".38
ARTICLE 14 - PAYMENTS TO CONTRACTOR AND COMPLETION ...."........................."...."...............".."".......",...", 39
14,01 Schedule of V alues ..."""""."".".............."..."............""",,,,,......,,,,,,.,,,,,,.,,.,,.,,..."...."..".."...."""".....".."""...... 39
14.02 Progress Payments..".. "....."" "..."" ...."....."...,.."".... "..." ..."..... ...........". ",,,,, "..,,,..... .".........".. "....... "........ ".... 39
14.03 Contractor 's Warranty of Title ........."."...."....."..."............."."....".....""."......"".....".".........""....."""""""...... 41
00...52713-0012 Bozeman WRF Phase I Early Out Priority Improvements 5/22/2007
00700 - 5
.
.
.
14 .04 Substantial Completion....................................................................................................................................... ...41
14.05 Partial Utilization ............ ....... ......................................................... .... ..................... ..... ........... ............ ....... ..........41
14.06 Final Inspection........... ....................... .... ............. ..... ..... .............. ........ ....................................... .... ............... ........42
14.07 Final Payment........................................................................................................................ ~............................... 42
14.08 Final Completion Delayed.... ..... .......... ........ ..... .................... .... ............................. ....... ...... ........... ........ ............. ...43
14.09 Waiver of Claims .... ......................... ............... ..... ................. .... ........... .............. .............. ......................................43
ARTICLE 15 - SUSPENSION OF WORK AND TERMINATION ........................................................................................43
15.01 Owner May Suspend Work .................................................................................................................................... 43
15.02 Owner May Terminate for Cause .......................................................................................................................... 43
15.03 Owner May Terminate For Convenience ..............................................................................................................44
15.04 Contractor May Stop Work or Terminate ..............................................................................................................44
ARTICLE 16 ~ DISPUTE RESOLUTION ................................................................................................................................45
16.01 Methods and Procedures .......................................................................................................................................45
ARTICLE 17 - MISCELLANEOUS .........................................................................................................................................45
17.01 Giving Notice ...................... ....... ............ ............... ................................... ........... ........................ .............. ............. 45
17.02 Computation of Times .............................................................................................................,.............................. 45
17.03 Cumulative Remedies............................................................................................................................ ................. 45
17.04 Survival of Obligations ..........................................................................................................................................45
17.05 Controlling Law ............. ................. ........ ...... ............ ........................... ......................... ................................. ........45
17.06 Headings.. ..... ............... ... .... ....... ..... ........ ... ... ....... ..... ..... ................ ...... .................... ..... ....... .............. ........ ............45
rTHE REST OF THIS PAGE INTENTIONALLY LEFT BLANKl
00...52713-0012
5/22/2007
Bozcman WRF Phasc I Early Out Priority Improvements
00700 - 6
GENERAL CONDITIONS
ARTICLE 1 - DEFINITIONS AND TERMINOLOGY
1.01 Defined Terms
A. Wherever used in the Bidding Requirements
or Contract Documents and printed with initial capital
letters, the terms listed below will have the meanings
indicated which are applicable to both the singular and
plural thereof. In addition to terms specifically defmed,
terms with initial capital letters in the Contract
Documents include references to identified articles and
paragraphs, and the titles of other documents or forms.
1. Addenda--Written or graphic instruments
issued prior to the opening of Bids which clarify, correct,
or change the Bidding Requirements or the proposed
Contract Documents.
2. Agreement-- The written instrument which is
evidence of the agreement between Owner and Contractor
covering the Work. The definition of the word "Contract"
is synonymous with the word "Agreement" and is used
interchangeably in the Contract Documents.
3. Application for Ptryment-- The form acceptable
to Engineer which is to be used by Contractor during the
course of the Work in requesting progress or final
payments and which is to be accompanied by such
supporting documentation as is required by the Contract
Documents.
4. Asbestos--Any material that contains more
than one percent asbestos and is friable or is releasing
asbestos fibers into the air above current action levels
established by the United States Occupational Safety and
Health Administration.
5. Bid--The offer or proposal of a Bidder
submitted on the prescribed form setting forth the prices
for the Work to be performed.
6. Bidder-- The individual or entity who submits
a Bid directly to Owner.
7. Bidding
Requirements and the
(including all Addenda).
Documents-- The Bidding
proposed Contract Documents
8. Bidding Requirements--The Advertisement or
Invitation to Bid, Instructions to Bidders, bid security of
acceptable form, if any, and the Bid Form with any
supplements.
9. Change Order--A document recommended by
Engineer which is signed by Contractor and Owner and
authorizes an addition, deletion, or revision in the Work
or an adjustment in the Contract Price or the Contract
Times, issued on or after the Effective Date of the
Agreement.
10. Claim--A demand or assertion by Owner or
Contractor seeking an adjustment of Contract Price or
Contract Times, or both, or other relief with respect to the
terms of the Contract. A demand for money or services by
a third party is not a Claim.
11. Contract-- The entire and integrated written
agreement between the Owner and Contractor concerning
the Work. The Contract supersedes prior negotiations,
representations, or agreements, whether written or oral.
12. Contract Documents-- Those items so
designated in the Agreement. Only printed or hard copies
of the items listed in the Agreement are Contract
Documents. Approved Shop Drawings, other Contractor's
submittals, and the reports and drawings of subsurface
and physical conditions are not Contract Documents.
13. Contract Price--The moneys payable by
Owner to Contractor for completion of the Work in
accordance with the Contract Documents as stated in the
Agreement (subject to the provisions of Paragraph 11.03
in the case of Unit Price Work).
.
.
14. Contract Times--The number of days or the
dates stated in the Agreement to: (i) achieve Milestones, if
any, (ii) achieve Substantial Completion; and (Hi)
complete the Work so that it is ready for final payment as
evidenced by Engineer's written recommendation of final
payment.
15. Contractor--The individual or entity with
whom Owner has entered into the Agreement.
16. Cost of the Work--See Paragraph 11.01.A for
definition.
17. Drawings-- That part of the Contract
Documents prepared or approved by Engineer which
graphically shows the scope, extent, and character of the
Work to be performed by Contractor. Shop Drawings and
other Contractor submittals are not Drawings as so
defined.
18. Effective Date of the Agreement-- The date
indicated in the Agreement on which it becomes effective,
but if no such date is indicated, it means the date on .
which the Agreement is signed and delivered by the last
of the two parties to sign and deliver.
19. Engineer-- The individual or entity named as
such in the Agreement.
00. ..52713-0012
Bozeman WRF Phase 1 Early Out Priority Improvements
00700 - 7
5122/2007
.
20. Engineer's Consultant--An individual or
entity having a contract with Engineer to furnish services
as Engineer's independent professional associate or
consultant with resoect to the Proiect and who is
identified as such in the Suoolementary Conditions.
2.L iM}.. Field Order--A written order issued by
Engineer which requires minor changes in the Work but
which does not involve a change in the Contract Price or
the Contract Times.
22. ;H-;- General Requirements--Sections of
Division I of the Specifications. The General
Requirements pertain to all sections of the Specifications.
23. ;Q., Hazardous Environmental Condition--
The presence at the Site of Asbestos, PCBs, Petroleum,
Hazardous Waste, or Radioactive Material in such
quantities or circumstances that may present a substantial
danger to persons or property exposed thereto in
connection with the Work.
24. ~ Hazardous Waste--The term Hazardous
Waste shall have the meaning provided in Section 1004 of
the Solid Waste Disposal Act (42 USC Section 6903) as
amended from time to time.
.
25. ;M. Laws and Regulations; Laws or
Regulations--Any and all applicable laws, rules,
regulations, ordinances, codes, and orders of any and all
governmental bodies, agencies, authorities, and courts
having jurisdiction.
26. ~ Liens--Charges, security interests, or
encumbrances upon Project funds, real property, or
personal property.
27. ~ Milestone--A principal event specified in
the Contract Documents relating to an intermediate
completion date or time prior to Substantial Completion
of all the Work.
28. n Notice of Award-- The written notice by
Owner to the Successful Bidder stating that upon timely
compliance by the Successful Bidder with the conditions
precedent listed therein, Owner will sign and deliver the
Agreement.
29. ~ Notice to Proceed--A written notice
given by Owner to Contractor fixing the date on which
the Contract Times will commence to run and on which
Contractor shall start to perform the Work under the
Contract Documents.
.
30. ;w. Owner~~ The individual or entity with
whom Contractor has entered into the Agreement and for
whom the Work is to be performed.
00...52713-0012
31. Partial Utilization~~Use by Owner of a
substantially comoleted Dart of the Work for the oumose
for which it is intended (or a related our'Uose) orior to
Substantial Completion of all the Work.
32. ~ PCBs--Polychlorinated biphenyls.
33. :H-, Petroleum~~Petroleum, including crude
oil or any fraction thereof which is liquid at standard
conditions of temperature and pressure (60 degrees
Fahrenheit and 14.7 pounds per square inch absolute),
such as oil, petroleum, fuel oil, oil sludge, oil refuse,
gasoline, kerosene, and oil mixed with other
non-Hazardous Waste and crude oils.
34. ~ Progress Schedule~-A schedule, prepared
and maintained by Contractor, describing the sequence
and duration of the activities comprising the Contractor's
plan to accomplish the Work within the Contract Times.
35. :H:- Project--The total construction of which
the Work to be performed under the Contract Documents
may be the whole, or a part.
36. ~ Project Manual-- The bound documentary
information prepared for bidding and constructing the
Work. A listing of the contents of the Project Manual,
which may be bound in one or more volumes, is
contained in the table(s) of contents.
37. ~ Radioactive Material--Source, special
nuclear, or byproduct material as defined by the Atomic
Energy Act of 1954 (42 USC Section 2011 et seq.) as
amended from time to time.
38. 3& Related Entity -- An officer, director,
partner, employee, agent, consultant, or subcontractor.
39. ~ Resident Project Representative--The
authorized representative of Engineer who may be
assigned to the Site or any part thereof.
40. ~. Samples--Physical examples of materials,
equipment, or workmanship that are representative of
some portion of the Work and which establish the
standards by which such portion of the Work will be
judged.
41. ~ Schedule of Submittals--A schedule,
prepared and maintained by Contractor, of required
submittals and the time requirements to support scheduled
performance of related construction activities.
42. 4G. Schedule of Values-- A schedule, prepared
and maintained by Contractor, allocating portions of the
Contract Price to various portions of the Work and used
as the basis for reviewing Contractor's Applications for
Payment.
Bozeman WRF Phase 1 Early Out Priority Improvements
00700 - 8
5/22/2007
43. 4h Shop Drawings--All drawings, diagrams,
illustrations, schedules, and other data or information
which are specifically prepared or assembled by or for
Contractor and submitted by Contractor to illustrate some
portion of the Work
44. e. Site--Lands or areas indicated in the
Contract Documents as being furnished by Owner upon
which the Work is to be performed, including rights-of~
way and easements for access thereto, and such other
lands furnished by Owner which are designated for the
use of Contractor.
45. ~ Specifications--That part of the Contract
Documents consisting of written requirements for
materials, equipment, systems, standards and
workmanship as applied to the Work, and certain
administrative requirements and procedural matters
applicable thereto.
46. 44:- Subcontractor--An individual or entity
having a direct contract with Contractor or with any other
Subcontractor for the performance of a part of the Work
at the Site.
47. ~ Substantial Completion--The time at
which the Work (or a specified part thereof) has
progressed to the point where, in the opinion of Engineer,
the Work (or a specified part thereof) is sufficiently
complete, in accordance with the Contract Documents, so
that the W ork (or a specified part thereof) can be utilized
for the purposes for which it is intended. The terms
"substantially complete" and "substantially completed" as
applied to all or part of the Work refer to Substantial
Completion thereof.
48. 44- Successful Bidder-- The Bidder
submitting a responsive Bid to whom Owner makes an
award.
49. 4+:- Supplementary Conditions--That part of
the Contract Documents which amends or supplements
these General Conditions.
50. 4S. Supplier--A manufacturer, fabricator,
supplier, distributor, materialman, or vendor having a
direct contract with Contractor or with any Subcontractor
to furnish materials or equipment to be incorporated in the
Work by Contractor or any Subcontractor.
iL. 49-,. Underground Facilities~~AIl underground
pipelines, conduits, ducts, cables, wires, manholes, vaults,
tanks, tunnels, or other such facilities or attachments, and
any encasements containing such facilities, including
those that convey electricity, gases, steam, liquid
petroleum products, telephone or other communications,
cable television, water, wastewater, storm water, other
liquids or chemicals, or traffic or other control systems.
52..w. Unit Price Work--Work to be paid for on
the basis of unit prices.
00...52713-0012
53. -S-h WorkM~The entire construction or the
various separately identifiable parts thereof required to be
provided under the Contract Documents. Work includes
and is the result of performing or providing all labor,
services, and documentation necessary to produce such
construction, and furnishing, installing, and incorporating
all materials and equipment into such construction, all as
required by the Contract Documents.
.
54. ~ Work Change Directive--A written
statement to Contractor issued on or after the Effective
Date of the Agreement and signed by Owner and
recommended by Engineer ordering an addition, deletion,
or revision in the Work, or responding to differing or
unforeseen subsurface or physical conditions under which
the Work is to be performed or to emergencies. A Work
Change Directive will not change the Contract Price or
the Contract Times but is evidence that the parties expect
that the change ordered or documented by a Work Change
Directive will be incorporated in a subsequently issued
Change Order following negotiations by the parties as to
its effect, ifany, on the Contract Price or Contract Times.
1.02 Terminology
A. The following words or terms are not defmed
but, when used in the Bidding Requirements or Contract
Documents, have the following meaning.
B. Intent of Certain Terms or Adjectives
.
1. The Contract Documents include the terms
"as allowed," "as approved," "as ordered", "as directed"
or terms of like effect or import to authorize an exercise
of professional judgment by Engineer. In addition, the
adjectives "reasonable," "suitable," "acceptable,"
"proper," "satisfactory," or adjectives of like effect or
import are used to describe an action or determination of
Engineer as to the Work. It is intended that such exercise
of professional judgment, action or determination will be
solely to evaluate, in general, the Work for compliance
with the requirements of and information in the Contract
Documents and conformance with the design concept of
the completed Project as a functioning whole as shown or
indicated in the Contract Documents (unless there is a
specific statement indicating otherwise). The u.se of any
such term or adjective is not intended to and shall not be
effective to assign to Engineer any duty or authority to
supervise or direct the performance of the Work or any
duty or authority to undertake responsibility contrary to
the provisions of Paragraph 9.09 or any other provision of
the Contract Documents.
C.Day
1. The word "day" means a calendar day of 24
hours measured from midnight to the next midnight.
.
Bozeman WRF Phase 1 Early Out Priority Improvements
00700 - 9
5/22/2007
.
.
.
D. Defective
1. The word "defective," when modifying the
word "Work," refers to Work that is unsatisfactory,
faulty, or deficient in that it:
a. does not conform to the Contract Documents,
or
b. does not meet the requirements of any
applicable inspection, reference standard, test, or
approval referred to in the Contract Documents,
or
c. has been damaged prior to Engineer's
recommendation of fmal payment (unless
responsibility for the protection thereof has been
assumed by Owner at Substantial Completion in
accordance with Paragraph 14.04 or 14.05).
E. Furnish, Install, Perform. Provide
1. The word "furnish," when used in connection
with services, materials, or equipment, shall mean to
supply and deliver said services, materials, or equipment
to the Site (or some other specified location) ready for use
or installation and in usable or operable condition.
2. The word "install," when used in connection
with services, materials, or equipment, shall mean to put
into use or place in fmal position said services, materials,
or equipment complete and ready for intended use.
3. The words "perform" or "provide," when used
in connection with services, materials, or equipment, shall
mean to furnish and install said services, materials, or
equipment complete and ready for intended use.
4. When "furnish,'; "install," "perform," or
"provide" is not used in connection with services,
materials, or equipment in a context clearly requiring an
obligation of Contractor, "provide" is implied.
F. Unless stated otherwise in the Contract
Documents, words or phrases which have a well-known
technical or construction industry or trade meaning are
used in the Contract Documents in accordance with such
recognized meaning.
ARTICLE 2 - PRELIMINARY MATTERS
2.0 I Delivery of Bonds and Evidence of Insurance
A. When Contractor delivers the executed
counterparts of the Agreement to Owner, Contractor shall
also deliver to Owner such bonds as Contractor may be
required to furnish.
00... 52713-0012
B. Evidence of Insurance: Before Owner will
execute the Agreement. and before any Wark at the Site is
started, Contractor and Ovmer shall eaeh-deIiver to Owner
the other, with copies to each additional insured identified
in the Supplementary Conditions, certificates of insurance
(and other evidence of insurance which either of them or
any additional insured may reasonably request) which
Contractor and Owner respectively are lli required to
purchase and maintain in accordance with Article 5.
2.02 Copies of Documents
A. Owner shall furnish to Contractor up to ten
printed or hard copies of the Drawings and Project
Manual. Additional copies will be furnished upon request
at the cost of reproduction.
2.03 Commencement of Contract Times; Notice to
Proceed
A. Following the execution of the Agreement by
the Owner and the Contractor. written Notice to Proceed
with the Work shall be given by the Owner to the
Contractor. The Contract Times will commence to run on
the thirtieth aay after the Effecti';e Date of the Agreement
or, if a Notice to Proceed is given, on the day indicated in
the Notice to Proceed. A Notice to Proceed may be given
at any time within 30 days after the Effective Date of the
Agreement. In no e'/ent will the Contract Times
oommence to I1lR later tRaft tRe sixtieth day after the day
efBiEl epeniRg Sf the thirtieth day after the Effective Date
of the AgreemeRt, \\<RieRevef date is earlier.
2.04 Starting the Work
A. Contractor shall start to perform the Work on
the date when the Contract Times commence to run. No
Work shall be done at the Site prior to the date on which
the Contract Times commence to run.
2.05 Before Starting Construction
A. Preliminary Schedules: Within 10 days after
the Effective Date of the Agreement (unless otherwise
specified in the General Requirements), Contractor shall
submit to Engineer for timely review:
1. a preliminary Progress Schedule; indicating
the times (numbers of days or dates) for starting and
completing the various stages of the Work, including any
Milestones specified in the Contract Documents;
2. a preliminary Schedule of Submittals; and
Bozeman WRF Phase 1 Early Out Priority Improvements
00700 " 10
5/22/2007
3. a preliminary Schedule of Values for all of the
Work which includes quantities and prices of items which
when added together equal the Contract Price and
subdivides the Work into component parts in sufficient
detail to serve as the basis for progress payments during
performance of the Work. Such prices will include an
appropriate amount of overhead and profit applicable to
each item of Work.
4. a preliminary list of construction equipment
with hourly rates. owned or rented bv the Contractor and
all Subcontractors that will be used in the perfonnance of
the Work. The equipment list will include information
necessary to confinn the hourly rates in accordance with
paragraph 11.01A.5.c of these General Conditions
including: make. model. and year of manufacture as well
as the horse power. capacity or weight. and accessories.
2.06
Preconstruction Conference
A. Before any Work at the Site is started, a
conference attended by Owner, Contractor, Engineer, and
others as appropriate will be held to establish a working
understanding among the parties as to the Work and to
discuss the schedules referred to in Paragraph 2.05.A,
procedures for handling Shop Drawings and other
submittals, processing Applications for Payment, and
maintaining required records.
2.07 Initial Acceptance of Schedules
A. At least 10 days before submission oftR6 first
Application for Payment a conf-erenee attended by
Contractor, Engineer, and others as 8fJflrOpriate will be
held to review for acceptability te Engineer as provided
below the schedules submitted in accordance with
Paragraph 2.05.A. Contractor shall have an additienal 10
days to make corrections and adjustments and to eefflfllete
and resubmit the schedules. No progress payment shall be
made tEl CElntractor until aeeeptable schedules are
submitted to Engineer.
2. Contractor's Schedule of Submittals will be
acceptable to Engineer if it provides a workable
arrangement for reviewing and processing the required .
submittals.
3. Contractor's Schedule of Values will be
acceptable to Engineer as to form and substance if it
provides a reasonable allocation of the Contract Price to
component parts of the Work.
4. Contractor's Schedule of Equipment will be
acceotable to Engineer as to fonn and substance if it
provides the necessary information to reference the
equipment and establish the hourly rates in accordance
with paragraph 11.01.A.5.c of these General Conditions.
ARTICLE 3 - CONTRACT DOCUMENTS: INTENT,
AMENDING, REUSE
3.01 Intent
A. The Contract Documents are complementary;
what is required by one is as binding as ifrequired by all.
B. It is the intent of the Contract Documents to
describe a functionally complete Project (or part thereof)
to be constructed in accordance with the Contract
Documents. Any labor, documentation, services,
materials, or equipment that may reasonably be inferred
from the Contract Documents or from prevailing custom
or trade usage as being required to produce the intended
result will be provided whether or not specifically called
for at no additional cost to Owner.
.
C. Clarifications and interpretations of the
Contract Documents shall be issued by Engineer as
provided in Article 9.
A. Prior to the first aoplication for payment all 3.02 Reference Standards
schedules and documents identified in paragraph 2.05.A
of these General Conditions shall be finalized and A. Standards, Specifications, Codes, Laws, and
acceptable to the Engineer and Owner. No orogress Regulations
payment shall be made to Contractor until acceptable
schedules are submitted to Engineer and Owner as 1. Reference to standards, specifications,
provided below. Acceptance of these schedules and manuals, or codes of any technical society, organization,
documents by either Engineer or Owner will neither or association, or to Laws or Regulations, whether such
impose on Engineer or Owner responsibility for the reference be specific or by implication, shall mean the
sequencing. scheduling or progress of the Work and will standard, specification, manual, code, or Laws or
not interfere with or relieve Contractor from Contractor's Regulations in effect at the time of opening of Bids (or on
full responsibility therefore. the Effective Date of the Agreement if there were no
Bids), except as may be otherwise specifically stated in
I. The Progress Schedule will be acceptable to the Contract Documents.
Engineer and Owner if it provides an orderly progression
of the Work to completion within the Contract Times. .
Such acceptance will not impose on Engineer and Owner
responsibility for the Progress Schedule, for sequencing,
scheduling, or progress of the Work nor interfere with or
relieve Contractor from Contractor's full responsibility
therefor.
00...52713-0012 Bozeman WRF Phase 1 Early Out Priority Improvements 5/22/2007
00700 . 11
.
2. No provision of any such standard,
specification, manual or code, or any instruction of a
Supplier shall be effective to change the duties or
responsibilities of Owner, Contractor, or Engineer, or any
of their subcontractors, consultants, agents, or employees
from those set forth in the Contract Documents. No such
provision or instruction shall be effective to assign to
Owner, or Engineer, or any of, their Related Entities, any
duty or authority to supervise or direct the performance of
the Work or any duty or authority to undertake
responsibility inconsistent with the provisions of the
Contract Documents.
3.03 Reporting and Resolving Discrepancies
A. Reporting Discrepancies
1. Contractor's Review of Contract Documents
Before Starting Work: Before undertaking each part of the
Work, Contractor shall carefully study and compare the
Contract Documents and check and verify pertinent
figures therein and all applicable field measurements.
Contractor shall promptly report in writing to Engineer
any conflict, error, ambiguity, or discrepancy which
Contractor may discover and shall obtain a written
interpretation or clarification from Engineer before
proceeding with any Work affected thereby.
.
2. Contractor's Review of Contract Documents
During Performance of Work: If, during the performance
of the Work, Contractor discovers any conflict, error,
ambiguity, or discrepancy within the Contract Documents
or between the Contract Documents and any provision of
any Law or Regulation applicable to the performance of
the Work or of any standard, specification, manual or
code, or of any instruction of any Supplier, Contractor
shall promptly report it to Engineer in writing. Contractor
shall not proceed with the Work affected thereby (except
in an emergency as required by Paragraph 6.16.A) until
an amendment or supplement to the Contract Documents
has been issued by one of the methods indicated in
Paragraph 3.04.
3. Contractor shall not be liable to Owner or
Engineer for failure to report any conflict, error,
ambiguity, or discrepancy in the Contract Documents
unless Contractor knew or reasonably should have known
thereof.
B. Resolving Discrepancies
1. Except as may be otherwise specifically stated
in the Contract Documents, the provisions of the Contract
Documents shall take precedence in resolving any
conflict, error, ambiguity, or discrepancy between the
provisions of the Contract Documents and:
.
a. the provisions of any standard, specification,
manual, code, or instruction (whether or not
specifically incorporated by reference in the
Contract Documents); or
b. the provisions of any Laws or Regulations
applicable to the performance of the Work
(unless such an interpretation of the provisions
of the Contract Documents would result in
violation of such Law or Regulation).
3.04 Amending and Supplementing Contract
Documents
A. The Contract Documents may be amended to
provide for additions, deletions, and revisions in the Work
or to modify the terms and conditions thereof by either a
Change Order or a Work Change Directive.
B. The requirements of the Contract Documents
may be supplemented, and minor variations and
deviations in the Work may be authorized, by one or more
of the following ways:
1. A Field Order;
2. Engineer's approval of a Shop Drawing or
Sample; (Subject to the provisions of Paragraph
6.17.D.3); or
3. Engineer's written interpretation or
clarification.
3.05 Reuse of Documents
A. Contractor and any Subcontractor or Supplier
or other individual or entity performing or furnishing all
of the Work under a direct or indirect contract with
Contractor, shall not:
1. have or acquire any title to or ownership rights
in any of the Drawings, Specifications, or other
documents (or copies of any thereot) prepared by or
bearing the seal of Engineer or Engineer's consultants,
including electronic media editions; or
2. reuse any of such Drawings, Specifications,
other documents, or copies thereof on extensions of the
Project or any other project without written consent of
Owner and Engineer and specific written verification or
adaption by Engineer.
B. The prohibition of this Paragraph 3.05 will
survive fmal payment, or termination of the Contract.
Nothing herein shall preclude Contractor from retaining
copies of the Contract Documents for record purposes.
3.06 Electronic Data
A. Copies of data furnished by Owner or
Engineer to Contractor or Contractor to Owner or
Engineer that may be relied upon are limited to the
printed copies (also known as hard copies). Files in
electronic media format of text, data, graphics, or other
types are furnished only for the convenience of the
receiving party. Any conclusion or information obtained
00 __52713-0012
Bozeman WRF Phase I Early Out Priority Improvements
00700 - 12
5/22/2007
or derived from such electronic files will be at the user's
sole risk. If there is a discrepancy between the electronic
files and the hard copies, the hard copies govern.
B. Because data stored in electronic media
fonnat can deteriorate or be modified inadvertently or
otherwise without authorization of the data's creator, the
party receiving electronic files agrees that it will perfonn
acceptance tests or procedures within 60 days, after which
the receiving party shall be deemed to have accepted the
data thus transferred. Any errors detected within the 60-
day acceptance period will be corrected by the
transferring party.
C. When transferring documents in electronic
media fonnat, the transferring party makes no
representations as to long tenn compatibility, usability, or
readability of documents resulting from the use of
software application packages, operating systems, or
computer hardware differing from those used by the
data's creator.
ARTICLE 4 AVAILABILITY
SUBSURFACE AND PHYSICAL
HAZARDOUS ENVIRONMENTAL
REFERENCE POINTS
OF LANDS;
CONDITIONS;
CONDITIONS;
4.01 Availability of Lands
A. Owner shall furnish the Site. Owner shall
notifY Contractor of any encumbrances or restrictions not
of general application but specifically related to use of the
Site with which Contractor must comply in perfonning
the Work. Owner will obtain in a timely manner and pay
for easements for penn anent structures or pennanent
changes in existing facilities. If Contractor and Owner are
unable to agree on entitlement to or on the amount or
extent, if any, of any adjustment in the Contract Price or
Contract Times, or both, as a result of any delay in
Owner's furnishing the Site or a part thereof, Contractor
may make a Claim therefor as provided in Paragraph
10.05.
B. Upon reasonable written request, Owner shall
furnish Contractor with a current statement of record legal
title and legal description of the lands upon which the
Work is to be perfonned and Owner's interest therein as
necessary for giving notice of or filing a mechanic's or
construction lien against such lands in accordance with
applicable Laws and Regulations.
C. Contractor shall provide for all ~dditional
lands and access thereto that may be required for
temporary construction facilities or storage of materials
and equipment.
00.. _ 52713-00 12
D. If it is necessary or desirable that the
Contractor use land outside of the Owner's easement or
right-of-way. the Contractor shall obtain written consent
from the 1;)roDerty owner and tenant of the land. The
Contractor shall not enter for materials delivery or occupy
for any other Dumose with men. tools. equipment.
construction materials. or with materials excavated from
the site. any private property outside the desi!-,:nated
construction easement boundaries or right-of-way without
written pennission from the oroperty owner and tenant.
.
4.02 Subsurface and Physical Conditions
A. Reports and Drawings: The Supplementary
Conditions identifY:
1. iliose reports of explorations and tests of
subsurface conditions at or contiguous to the Site that
Engineer has used in preparing the Contract Documents;
and
2. iliose drawings of physical conditions in or
relating to existing surface or subsurface structures at or
contiguous to the Site (except Underground Facilities)
iliat Engineer has used in preparing the Contract
Documents.
B. Limited Reliance by Contractor on Technical
Data Authorized: Contractor may rely upon the general .
accuracy of the "technical data" contained in such reports .
and drawings, but such reports and drawings are not
Contract Documents. Such "technical data" is identified
in the Supplementary Conditions. Except for such reliance
on such "technical data," Contractor may not rely upon or
make any claim against Owner or Engineer, or any of
ilieir Related Entities with respect to:
1. ilie completeness of such reports and drawings
for Contractor's purposes, including, but not limited to,
any aspects of the means, methods, techniques,
sequences, and procedures of construction to be employed
by Contractor, and safety precautions and programs
incident thereto; or
2. oilier data, interpretations, opinions, and
infonnation contained in such reports or shown or
indicated in such drawings; or
3. any Contractor interpretation of or conclusion
drawn from any "technical data" or any such other data,
interpretations, opinions, or infonnation.
4.03 Differing Subsurface or Physical Conditions
A. Notice: If Contractor believes that any
subsurface or physical condition at or contiguous to ilie .
Site that is uncovered or revealed either:
1. is of such a nature as to establish that any
"technical data" on which Contractor is entitled to rely as
provided in Paragraph 4.02 is materially inaccurate; or
Bozeman WRF Phase I Early Out Priority Improvements
00700 - 13
5/22/2007
2. is of such a nature as to require a change in the
Contract Documents; or
.
3. differs materially from that shown or indicated
in the Contract Documents; or
4. is of an unusual nature, and differs materially
from conditions ordinarily encountered and generally
recognized as inherent in work of the character provided
for in the Contract Documents;
then Contractor shall, promptly after becoming aware
thereof and before further disturbing the subsurface or
physical conditions or performing any Work in
connection therewith (except in an emergency as required
by Paragraph 6.16.A), notify Owner and Engineer in
writing about such condition. Contractor shall not further
disturb such condition or perform any Work in connection
therewith (except as aforesaid) until receipt of written
order to do so. Contractor shall notify the Owner and
Engineer in writing about differing subsurface or physical
conditions within 5 days of discovery and before
disturbing the subsurface as stated above. No claim for
an adjustment in the contract price or contract times (or
Milestones) will be valid for differing subsurface or
physical conditions if procedures of this paragraph 4.03
are not followed.
.
B. Engineer's Review: After receipt of written
notice as required by Paragraph 4.03.A, Engineer will
promptly review the pertinent condition, determine the
necessity of Owner's obtaining additional exploration or
tests with respect thereto, and advise Owner in writing
(with a copy to Contractor) of Engineer's findings and
conclusions.
C. Possible Price and Times Adjustments
1. The Contract Price or the Contract Times or
both, will be equitably adjusted to the extent that 'the
existence of such differing subsurface or physical
condition causes an increase or decrease in Contractor's
cost of, or time required for, performance of the Work;
subject, however, to the following:
a. such condition must meet anyone or more of
the categories described in Paragraph 4.03.A;
and
b. with respect to Work that is paid for on a Unit
Price Basis, any adjustment in Contract Price
will be subject to the provisions of Paragraphs
9.07 and 11.03.
2. Contractor shall not be entitled to any
adjustment in the Contract Price or Contract Times if:
.
a. Contractor knew of the existence of such
conditions at the time Contractor made a final
commitment to Owner with respect to Contract
Price and Contract Times by the submission of a
Bid or becoming bound under a negotiated
contract; or
00 __52713-0012
b. the existence of such condition could
reasonably have been discovered or revealed as a
result of any examination, investigation,
exploration, test, or study of the Site and
contiguous areas required by the Bidding
Requirements or Contract Documents to be
conducted by or for Contractor prior to
Contractor's making such final commitment; or
c. Contractor failed to give the written notice as
required by Paragraph 4.03.A.
3. If Owner and Contractor are unable to agree
on entitlement to or on the amount or extent, if any, of
any adjustment in the Contract Price or Contract Times,
or both, a Claim may be made therefor as provided in
Paragraph 10.05. However, Owner and Engineer, and any
of their Related Entities shall not be liable to Contractor
for any claims, costs, losses, or damages (including but
not limited to all fees and charges of engineers, architects,
attorneys, and other professionals and all court or
arbitration or other dispute resolution costs) sustained by
Contractor on or in connection with any other project or
anticipated project.
4.04 Underground Facilities
A. Shown or Indicated: The information and data
sho~n or indicated in the Contract Documents with
respect to existing Underground Facilities at or
contiguous to the Site is based on information and data
furnished to Owner or Engineer by the owners of such
Underground Facilities, including Owner, or by others.
Unless it is otherwise expressly provided in the
Supplementary Conditions:
1. Owner and Engineer shall not be responsible
for the accuracy or completeness of any such information
or data; and
2. the cost of all of the following will be
included in the Contract Price, and Contractor shall have
full responsibility for:
a. reviewing and checking all such information
and data,
b. locating all Underground Facilities shown or
indicated in the Contract Documents,
c. coordination of the Work with the owners of
such Underground Facilities, including Owner,
during construction, and
d. the safety and protection of all
Underground Facilities and repairing
damage thereto resulting from the Work.
such
any
B. Not Shown or Indicated
Bozeman WRF Phase 1 Early Out Priority Improvements
00700. 14
5/2212007
E. Contractor shall not be required to resume
Work in connection with such condition or in any affected
area until after Owner has obtained any required permits
related thereto and delivered to Contractor written notice:
(i) specifYing that such condition and any affected area is
or has been rendered safe for the resumption of Work; or
(ii) specifYing any special conditions under which such
Work may be resumed safely. If Owner and Contractor
cannot agree as to entitlement to or on the amount or
extent, if any, of any adjustment in Contract Price or
Contract Times, or both, as a result of such Work
stoppage or such special conditions under which Work is
Bozeman WRF Phase 1 Early Out Priority Improvements 5/22/2007
00700 - 15
1. If an Underground Facility is uncovered or
revealed at or contiguous to the Site which was not shown
or indicated, or not shown or indicated with reasonable
accuracy in the Contract Documents, Contractor shall,
promptly after becoming aware thereof and before further
disturbing conditions affected thereby or performing any
Work in connection therewith (except in an emergency as
required by Paragraph 6.16.A), identify the owner of such
Underground Facility and give written notice to that
owner and to Owner and Engineer. Engineer will
promptly review the Underground Facility and determine
the extent, if any, to which a change is required in the
Contract Documents to reflect and document the
consequences of the existence or location of the
Underground Facility. During such time, Contractor shall
be responsible for the safety and protection of such
Underground Facility.
2. If Engineer concludes that a change in the
Contract Documents is required, a Work Change
Directive or a Change Order will be issued to reflect and
document such consequences. An equitable adjustment
shall be made in the Contract Price or Contract Times, or
both, to the extent that they are attributable to the
existence or location of any Underground Facility that
was not shown or indicated or not shown or indicated
with reasonable accuracy in the Contract Documents and
that Contractor did not know of and could not reasonably
have been expected to be aware of or to have anticipated.
If Owner and Contractor are unable to agree on
entitlement to or on the amount or extent, if any, of any
such adjustment in Contract Price or Contract Times,
Owner or Contractor may make a Claim therefor as
provided in Paragraph 10.05.
4.05 Reference Points
A. Owner shall provide engineering surveys to
establish reference points for construction which in
Engineer's judgment are necessary to enable Contractor
to proceed with the Work. Contractor shall be responsible
for laying out the Work, shall protect and preserve the
established reference points and property monuments, and
shall make no changes or relocations without the prior
written approval of Owner. Contractor shall report to
Engineer whenever any reference point or property
monument is lost or destroyed or requires relocation
because of necessary changes in grades or locations, and
shall be responsible for the accurate replacement or
relocation of such reference points or property
monuments by professionally qualified personnel.
4.06
Hazardous Environmental Condition at Site
A. Reports and Drawings: Reference is made to
the Supplementary Conditions for the identification of
those reports and drawings relating to a Hazardous
Environmental Condition identified at the Site, if any, that
have been utilized by the Engineer in the preparation of
the Contract Documents.
00._.52713-0012
B. Limited Reliance by Contractor on Technical
Data Authorized: Contractor may rely upon the general
accuracy of the "technical data" contained in such reports .
and drawings, but such reports and drawings are not
Contract Documents. Such "technical data" is identified
in the Supplementary Conditions. Except for such reliance
on such "technical data," Contractor may not rely upon or
make any claim against Owner or Engineer, or any of
their Related Entities with respect to:
1. the completeness of such reports and drawings
for Contractor's purposes, including, but not limited to,
any aspects of the means, methods, techniques, sequences
and procedures of construction to be employed by
Contractor and safety precautions and programs incident
thereto; or
2. other data, interpretations, opmlOns and
information .contained in such reports or shown or
indicated in such drawings; or
3. any Contractor interpretation of or conclusion
drawn from any "technical data" or any such other data,
interpretations, opinions or information.
C. Contractor shall not be responsible for any
Hazardous Environmental Condition uncovered or
revealed at the Site which was not shown or indicated in
Drawings or Specifications or identified in the Contract .
Documents to be within the scope of the Work.
Contractor shall be responsible for a Hazardous
Environmental Condition created with any materials
brought to the Site by Contractor, Subcontractors,
Suppliers, or anyone else for whom Contractor is
responsible.
D. If Contractor encounters a Hazardous
Environmental Condition or if Contractor or anyone for
whom Contractor is responsible creates a Hazardous
Environmental Condition, Contractor shall immediately:
(i) secure or otherwise isolate such condition; (ii) stop all
Work in connection with such condition and in any area
affected thereby (except in an emergency as required by
Paragraph 6.16.A); and (Hi) notify Owner and Engineer
(and promptly thereafter confirm such notice in writing).
Owner shall promptly consult. with Engineer concerning
the necessity for Owner to retain a qualified expert to
evaluate such condition or take corrective action, if any.
.
.
agreed to be resumed by Contractor, either party may
make a Claim therefor as provided in Paragraph 10.05.
F. If after receipt of such written notice
Contractor does not agree to resume such Work based on
a reasonable belief it is unsafe, or does not agree to
resume such Work under such special conditions, then
Owner may order the portion of the Work that is in the
area affected by such condition to be deleted from the
Work. If Owner and Contractor cannot agree as to
entitlement to or on the amount or extent, if any, of an
adjustment in Contract Price or Contract Times as a result
of deleting such portion of the Work, then either party
may make a Claim therefor as provided in Paragraph
10.05. Owner may have such deleted portion of the Work
performed by Owner's own forces or others in accordance
with Article 7.
.
G. To the fullest extent permitted by Laws and
Regulations, Owner shall indemnifY and hold harmless
Contractor, Subcontractors, and Engineer, and the
officers, directors, partners, employees, agents,
consultants, and subcontractors of each and any of them
from and against all claims, costs, losses, and damages
(including but not limited to all fees and charges of
engineers, architects, attorneys, and other professionals
and all court or arbitration or other dispute resolution
costs) arising out of or relating to a Hazardous
Environmental Condition, provided that such Hazardous
Environmental Condition: (i) was not shown or indicated
in the Drawings or Specifications or identified in the
Contract Documents to be included within the scope of
the Work, and (ii) was not created by Contractor or by
anyone for whom Contractor is responsible. Nothing in
this Paragraph 4.06. G shall obligate Owner to indemnifY
any individual or entity from and against the
consequences of that individual's or entity's own
negligence.
H. To the fullest extent permitted by Laws and
Regulations, Contractor shall indemnifY and hold
harmless Owner and Engineer, and the officers, directors,
partners, employees, agents, consultants, and
subcontractors of each and any of them from and against
all claims, costs, losses, and damages (including but not
limited to all fees and charges of engineers, architects,
attorneys, and other professionals and all court or
arbitration or other dispute resolution costs) arising out of
or relating to a Hazardous Environmental Condition
created by Contractor or by anyone for whom Contractor
is responsible. Nothing in this Paragraph 4.06.H shall
obligate Contractor to indemnify any individual or entity
from and against the consequences of that individual's or
entity's own negligence.
.
1. The provisions of Paragraphs 4.02, 4.03, and
4.04 do not apply to a Hazardous Environmental
Condition uncovered or revealed at the Site.
ARTICLE 5 - BONDS AND INSURANCE
5.01 Performance, Payment, and Other Bonds
A. Contractor shall furnish performance and
payment bonds, each in an amount at least equal to the
Contract Price as security for the faithful performance and
payment of all of Contractor's obligations under the
Contract Documents. These bonds shall remain in effect
until one year after the date when fmal payment becomes
due or until completion of the correction period specified
in Paragraph 13.07, whichever is later, except as provided
otherwise by Laws or Regulations or by the Contract
Documents. Contractor shall also furnish such other
bonds as are required by the Contract Documents.
B. All bonds shall be in the form prescribed by
the Contract Documents except as provided otherwise by
Laws or Regulations, and shall be executed by such
sureties as are named in the current list of "Companies
Holding Certificates of Authority as Acceptable Sureties
on Federal Bonds and as Acceptable Reinsuring
Companies" as published in Circular 570 (amended) by
the Financial Management Service, Surety Bond Branch,
U.S. Department of the Treasury. All bonds signed by an
agent must be accompanied by a certified copy of the
agent's authority to act. All bonds signed bv an ae:ent
must have a Power of Attorney form attached to the
Bond.
C. If the surety on any bond furnished by
Contractor is declared bankrupt or becomes insolvent or
its right to do business is terminated in any state where
any part of the Project is located or it ceases to meet the
requirements of Paragraph 5.01.B, Contractor shall
promptly notify Owner and Engineer and shall, within 20
days after the event giving rise to such notification,
provide another bond and surety, both of which shall
comply with the requirements of Paragraphs 5.01.B and
5.02.
5.02 Licensed Sureties and Insurers
A. All bonds and insurance required by the
Contract Documents to be purchased and maintained by
Owner or Contractor shall be obtained from surety or
insurance companies that are duly licensed or authorized
in the jurisdiction in which the Project is located to issue
bonds or insurance policies for the limits and coverages
so required. Such surety and insurance companies shall
also meet such additional requirements and qualifications
as may be provided in the Supplementary Conditions.
5.03 Certificates of Insurance
A. Contractor shall deliver to Owner, with copies
to each additional insured identified in the Supplementary
Conditions, certificates of insurance (and other evidence
of insurance requested by Owner or any other additional
insured) which Contractor is required to purchase and
maintain.
00...52713-0012
Bozeman WRF Phase 1 Early Out Priority Improvements
00700 - 16
5/2212007
B. .~wner. shall deliver to Contractor, with copies
to ea~h. addltlon~l msured identified in the Supplementary
CondItlOtlS, certIficates of insurance (and other evidence
of insurance requested by Contractor or any other
additional insured) v.~ieh Owner is requireEl 10 plMc"Rase
and maintain.
. B. An Authorized Representative of the
msurance comoany for the Contractor shall review the
soecified insurance requirements of Article 5 and shall
orovide to each insured and to each additional insured a
letter stating that the requirements of Article 5 have been
reviewed and certifying that the Contractor has as a
mi~imum. provided the insurance coverage as requi~ed by
ArtIcle 5.
. C. All insurance required to be orovided under
ArtIcle 5 shall be written in such a manner as to afford
primary insurance coverage (as opposed to excess or
secondary coverage) as to meet or exceed the insurance
requirements for all insureds and additional insureds and
the respective directors. officers. partners. employees.
agents and other consultants and subcontractors of each
and any of all such additional insureds.
5.04 Contractor's Liability Insurance
A. Contractor shall purchase and maintain such
liability and other insurance as is appropriate for the
Work b~ing performed and as will provide protection
from claIms set forth below which may arise out of or
result from Contractor's performance of the Work and
Contractor's other obligations under the Contract
Documents, whether it is to be performed by Contractor,
any Subcontractor or Supplier, or by anyone directly or
indirectly employed by any of them to perform any of the
Work, or by anyone for whose acts any of them may be
liable:
1. claims under workers' compensation,
disability benefits, and other similar employee benefit
acts;
2. claims for damages ai:!ainst Contractor because
of bodily injury, property damal!e. occupational sickness
accident or disease, or death of or to Contractor';
employees;
. 3. cla~ms for damages because of bodily injury,
SIckness, ef dIsease, oroperty damage. or death of any
person other than Contractor's employees;
4. claims for damages insured by reasonably
available personal injury liability coverage which are
sustained:
a. ~y ~ny person as a result of an offense directly
or mdIrectly related to the employment of such
person by Contractor, or
b. by any other person for any other reason;
00...52713-0012
5. claims for damages, other than to the Work
itself, because of injury to or destruction of tangible
property wherever located, including loss of use resulting
therefrom; and.
6. claims for damages because of bodily injury or
death of any person or property damage arising out of the
ownership, maintenance or use of any motor vehicle.
7. The Liability Policv ourchased by Contractor
~ill provi~e that the definition of bodily iniury will
mclude claIms for mental anguish.
B. The policies of insurance required by this
Paragraph 5.04 shall:
1. with respect to insurance required by
Paragraphs 5.04.A.3 through 5.04.A.6 inclusive, include
as additional insured (subject to any clistomary exclusion
regarding professional Iiaeility) Owner and Engineer
Engineer's Consultants and any other individuals 0;
entities identified in the Supplementary Conditions, all of
whom shall be listed as additional insureds, and include
coverage for the respective officers, directors, partners,
employees, agents, consultants and subcontractors of each
and any of all such additional insureds, and the insurance
af~orded to these additional insureds shall provide
pflmary coverage for all claims covered thereby;
. 2. include at least the specific coverages and be .
wfltten for not less than the limits of liability provided in
the Supplementary Conditions or required by Laws or
Regulations, whichever is greater;
3. include completed operations insurance;
4. include contractual
covering Contractor's indemnity
Paragraphs 6.11 and 6.20;
liability insurance
obligations under
5. contain a provision or endorsement that the
coverage afforded will not be canceled, materially
changed or renewal refused until at least ;W forty-five
(45) days prior written notice has been given to Owner
and Contractor and to each other additional insured
identified in the Supplementary Conditions to whom a
certificate of insurance has been issued (and the
certificates of insurance furnished by the Contractor
pursuant to Paragraph 5.03 will so provide);
6. remain in effect for a period of at least llfltil
one vear following final payment and at all times
thereafter when Contractor may be correcting, removing,
or replacing defective Work in accordance with Paragraph
13.07; and
.
Bozeman WRF Phase 1 Early Out Priority Improvements
00700 -17
5/2212007
.
7. with respect to completed operations
insurance, and any insurance coverage written on a
claims-made basis, remain in effect for at least tw6 three
years after final payment.
a. Contractor shall furnish Owner and each other
additional insured identified in the
Supplementary Conditions, to whom a certificate
of insurance has been issued, evidence
satisfactory to Owner and any such additional
insured of continuation of such insurance at final
payment and ene for each year thereafter until
this provision is satisfied.
5.05 Owner's Liability Insurance
A. In addition to the insurance required to be
provided by Contractor under Paragraph 5.04, Owner, at
Owner's option, may purchase and maintain at Owner's
expense Owner's own liability insurance as will protect
Owner against claims which may arise from operations
under the Contract Documents.
5.06 Property Insurance - Purchased bv Contractor
.
A. Unless otherwise provided in the
Supplementary Conditions, Gwner Contractor shall
purchase and maintain property insurance upon the Work
at the Site in the amount of the full replacement cost
thereof (subject to such deductible amounts as may be
provided in the Supplementary Conditions or required by
Laws and Regulations). This insurance shall:
1. include the interests of Owner, Contractor,
Subcontractors, Sub-subcontractors, and Engineer,
Engineer's Consultants, and any other individuals or
entities identified in the Supplementary Conditions, and
the officers, directors, partners, employees, agents,
consultants and subcontractors of each and any of them,
each of whom is deemed to have an insurable interest and
shall be listed as an insured or additional insured;
2. be written on a Builder's Risk "all-risk" or
open peril or special causes of loss policy form that shall
at--least include insurance for physical loss or damage to
the Work, including machinerv and testinl! of machinery
(including electrical units), temporary buildings, false
work, and materials and equipment in transit, and shall
insure against at least the following perils or causes of
loss: fire, lightning, extended coverage, theft, vandalism
and malicious mischief, earthquake, collapse, debris
removal, demolition occasioned by enforcement of Laws
and Regulations, water damage, (other than caused by
flood) and such other perils or causes of loss as may be
specifically required by the Supplementary Conditions;
.
3. include expenses incurred in the repair or
replacement of any insured property (including but not
limited to fees and charges of engineers and architects);
4. cover materials and equipment in transit for
incorporation in the Work or stored at the Site or at
another location that was agreed to in writing by Owner
prior to being incorporated in the Work, provided that
such materials and equipment have been included in an
Application for Payment recommended by Engineer;
5. be endorsed to allow occupancy and to allow
for partial utilization of the Work by Owner; and
specifically endorse the Builder's Risk policy to allow for
such action;
6. include testing and startup; and
7. be maintained in effect until fmal payment is
made unless otherwise agreed to in writing by Owner,
Contractor, and Engineer with M) 45 days written notice
to each other additional insured to whom a certificate of
insurance has been issued.
B. Owner shall purchase and maintain such
boiler and machinery insurance or additional property
insurance as may be required by the Supplementary
Conditions or Laws and Regulations which will include
the interests of Owner, Contractor, Subcontractors, and
Engineer, and any other individuals or entities identified
in the Supplementary Conditions, and the officers,
directors, partners, employees, agents, consultants and
subcontractors of each and any of them, each of whom is
deemed to have an insurable interest and shall be listed as
an insured or additional insured.
C. Contractor shall be responsible for any
deductible or self-insured retention.
D. G: All the policies of insurance (and the
certificates or other evidence thereof) required to be
purchased and maintained bv Contractor in accordance
with Paragraph 5.06 will contain a provision or
endorsement that the coverage afforded will not be
canceled or materially changed or renewal refused until at
least M) 45 days prior written notice has been given to
Owner and Contractor and to each other additional
insured to whom a certificate of insurance has been issued
and will contain waiver provisions in accordance with
Paragraph 5.07. The qualifications of the insurance
comoany shall comply with the reauirements of paragraph
5.02 and the Supplementarv Conditions.
E. D. Owner shall Rot be responsible for
purchasing and maintaining any property insurance
specified in this Paragraph 5.06 to protect the interests of
Contractor, Subcontraotors, or ethers in the Wark to the
enteet ef any deductible amounts that are identified in the
8Hpplementary Conditions. The risk of loss to the Work
within stich iaemified deductible amount will be borne by
Contractor, Subcontractors, or others suffering any such
loss, and if any of them wishes property insurance
coverage within the limits of such amounts, each may
purchase and maintain it at the purchaser's own expense.
00...52713-0012
Bozeman WRF Phase 1 Early Out Priority Improvements
00700 - 18
5/22/2007
1. loss due to business interruption, loss of use,
or other consequential loss extending beyond direct
physical loss or damage to Owner's property or the Work
caused by, arising out of, or resulting from fire or other
perils whether or not insured by Owner; and
00...52713-0012 Bozeman WRF Phase 1 Early Out Priority Improvements
00700 - 19
F. B. If Contractor requests in writing that other
special insurance be included in the property insurance
policies provided under Paragraph 5.06, Owner shall, if
possible, include such insurance, and the cost thereof will
be charged to Contractor by appropriate Change Order.
Prior to commencement of the Work at the Site, Owner
shall in writing advise Contractor whether or not such
other insurance has been procured by Owner.
G. Oualifications of the mODertv insurance
comDanv shall be as specified III the SUDDlementary
Conditions.
5.07
Waiver of Rights
A. Owner and Contractor intend that all policies
purchased in accordance with Paragraph 5.06 will protect
Owner, Contractor, Subcontractors, ana Engineer,
Engineer's Consultants. and all other individuals or
entities identified in the Supplementary Conditions to be
listed as insureds or additional insureds (and the officers,
directors, partners, employees, agents, consultants and
subcontractors of each and any of them) in such policies
and will provide primary coverage for all losses and
damages caused by the perils or causes of loss covered
thereby. All such policies shall contain provisions to the
effect that in the event of payment of any loss or damage
the insurers will have no rights of recovery against any of
the insureds or additional insureds thereunder. Owner,
ana Contractor, Subcontractors. Engineer. Engineer's
Consultants and all other persons or entities identified in
the Supplementary Conditions to be listed as insureds or
additional insureds under such Dolicies waive all rights
against each other and their respective officers, directors,
partners, employees, agents, consultants and
subcontractors of each and any of them for all losses and
damages caused by, arising out of or resulting from any of .
the perils or causes of loss covered by such policies and
any other property insurance applicable to the Work; and,
in addition, waive all such rights against Subcontractors,
ana Engineer, Engineer's Consultants. and all other
individuals or entities identified in the Supplementary
Conditions to be listed as insured or additional insured
(and the officers, directors, partners, employees, agents,
consultants and subcontractors of each and any of them)
under such policies for losses and damages so caused.
None of the above waivers shall extend to the rights that
any party making such waiver may have to the proceeds
of insurance held by Owner as trustee or otherwise
payable under any policy so issued.
B. Owner waives all rights against Contractor,
Subcontractors, ana Engineer, Engineer's Consultants.
and the officers, directors, partners, employees, agents,
consultants and subcontractors of each and any of them
for:
2. loss or damage to the completed Project or
part thereof caused by, arising out of, or resulting from
fire or other insured peril or cause of loss covered by any
property insurance maintained on the completed Project
or part thereof by Owner during partial utilization
pursuant to Paragraph 14.05, after Substantial Completion
pursuant to Paragraph 14.04, or after final payment
pursuant to Paragraph 14.07.
.
C. Any insurance policy maintained by Owner
covering any loss, damage or consequential loss referred
to in Paragraph 5.07.B shall contain provisions to the
effect that in the event of payment of any such loss,
damage, or consequential loss, the insurers will have no
rights of recovery against Contractor, Subcontractors, Elf
Engineer, or Engineer's Consultants. and the officers,
directors, partners, employees, agents, consultants and
subcontractors of each and any of them.
5.08
Receipt and Application of Insurance Proceeds
A. ,^on)' insured less Losses insured under the
policies of insurance required by Paragraph~ 5.06 and SC-
5.06 that include Owner as a named insured will be
adjusted with Owner and made payable to Owner as
fi9Heiary for the insureds, first named insured. and others.
as their interests may appear, subject to the requirements
of any applicable mortgage clause and of Paragraph
5.08.B. Owner shall deposit in a separate account any
money so received and shall distribute it in accordance
with such agreement as the parties in interest may reach.
If no other special agreement is reached, the damaged
Work shall be repaired or replaced, the moneys so
received applied on account thereof, and the Work and the
cost thereof covered by an appropriate Change Order.
.
B. Owner as fiduciary first named insured shall
have power to adjust and settle any loss with the insurers
unless one of the parties in interest shall object in writing
within 15 days after the occurrence of loss to Owner's
exercise of this power. If such objection be made, Owner
as fiduciary shall make settlement with the insurers in
accordance with such agreement as the parties in interest
may reach. If no such agreement among the parties in
interest is reached, Owner as fiduciary shall adjust and
settle the loss with the insurers and, if required in writing
by any party in interest, Owner as fiduciary shall give
bond for the proper performance of such duties.
Arbitrators shall be chosen as provided in Daragraph
5.08.C. Owner shall in that case make settlement with the
insurers in accordance with the direction of such
arbitrators. If distribution of the insurance oroceeds bv
arbitration is required. the arbitrators will direct such
arbitration.
C. Arbitrators. if required. shall be selected in
accordance with the Construction Industry Arbitration
Rules ofthe American Arbitration Association.
.
5/22/2007
5.09 Acceptance of Bonds and Insurance; Option to
Replace
.
A. If either Owner or Contractor has any
objection to the coverage afforded by or other provisions
of the bonds or insurance required to be purchased and
maintained by the other party in accordance with Article 5
on the basis of non-conformance with the Contract
Documents, the objecting party shall so notify the other
party in writing within 10 days after receipt of the
certificates (or other evidence requested) required by
Paragraph 2.01.B. Owner and Contractor shall each
provide to the other such additional information in respect
of insurance provided as the other may reasonably
request. If either party does not purchase or maintain all
of the bonds and insurance required of such party by the
Contract Documents, such party shall notify the other
party in writing of such failure to purchase prior to the
start of the Work, or of such failure to maintain prior to
any change in the required coverage. Without prejudice to
any other right or remedy, the other party may elect to
obtain equivalent bonds or insurance to protect such other
party's interests at the expense of the party who was
required to provide such coverage, and a Change Order
shall be issued to adjust the Contract Price accordingly.
5.10 Partial Utilization, Acknowledgment of Property
Insurer
.
A. If Owner finds it necessary to occupy or use a
portion or portions of the Work prior to Substantial
Completion of all the Work as provided in Paragraph
14.05, no such use or occupancy shall commence before
the insurers providing the property insurance pursuant to
Paragraph~ 5.06 and SC~5.06 have acknowledged notice
thereof and in writing effected any changes in coverage
necessitated thereby. The insurers providing the property
insurance shall consent by endorsement on the policy or
policies, but the property insurance shall not be canceled
or permitted to lapse on account of any such partial use or
occupancy.
ARTICLE 6 - CONTRACTOR'S RESPONSIBILITIES
6.01 Supervision and Superintendence
.
A. Contractor shall supervise, inspect, and direct
the Work competently and efficiently, devoting such
attention thereto and applying such skills and expertise as
may be necessary to perform the Work in accordance with
the Contract Documents. Contractor shall be solely
responsible for the means, methods, techniques,
sequences, and procedures of construction. Contractor
shall not be responsible for the negligence of Owner or
Engineer in the design or specification of a specific
means, method, technique, sequence, or procedure of
construction which is shown or indicated in and expressly
required by the Contract Documents.
B. At all times during the progress of the Work,
Contractor shall assign a competent resident
superintendent who shall not be replaced without written
notice to Owner and Engineer except under extraordinary
circumstances. The superintendent will be Contractor's
representative at the Site and shall have authority to act on
.behalf of Contractor. All communications given to or
received from the superintendent shall be binding on
Contractor.
6.02 Labor; Working Hours
A. Contractor shall provide competent, suitably
qualified personnel to survey and layout the Work and
perform construction as required by the Contract
Documents. Contractor shall at all times maintain good
discipline and order at the Site. Contractor shall be
responsible to see that the completed Work comolies
accurate Iv with the Contract Documents.
B. Except as otherwise required for the safety or
protection of persons or the Work or property at the Site
or adjacent thereto, and except as otherwise stated in the
Contract Documents, all Work at the Site shall be
performed during regular working hours. Contractor will
not permit the performance of Work on a Saturday,
Sunday, or any legal holiday without Owner's written
consent (which will not be unreaseaaaly withheld) given
after prior written notice to Engineer. Emerl!encv work
may be done without Drior oermission.
6.03 Services, Materials, and Equipment
A. Unless otherwise specified in the Contract
Documents, Contractor shall provide and assume full
responsibility for all services, materials, equipment, labor,
transportation, construction equipment and machinery,
tools, appliances, fuel, power, light, heat, telephone,
water, sanitary facilities, temporary facilities, and all other
facilities and incidentals necessary for the performance,
testing, start-up, and completion of the Work.
B. All materials and equipment incorporated into
the Work shall be as specified or, if not specified, shall be
of good quality and new, except as otherwise provided in
the Contract Documents. All special warranties and
guarantees required by the Specifications shall expressly
run to the benefit of Owner. If required by Engineer,
Contractor shall furnish satisfactory evidence (including
reports of required tests) as to the source, kind, and
quality of materials and equipment.
C. All materials and equipment shall be stored,
applied, installed, connected, erected, protected, used,
cleaned, and conditioned in accordance with instructions
of the applicable Supplier, except as otherwise may be
provided in the Contract Documents.
00...52713-0012
Bozeman WRF Phase 1 Early Out Priority Improvements
00700 . 20
5/2212007
6.04 Progress Schedule
a. in the exercise of reasonable judgment
Engineer determines that:
1) it is at least equal in materials of
construction, quality, durability, appearance,
strength, and design characteristics;
2) it will reliably perform at least
equally well the function and achieve the results
imposed by the design concept of the completed
Project as a functioning whole,
3) it has a proven record ofperforrnance
and availability of responsive service; and
A. Contractor shall adhere to the Progress
Schedule established in accordance with Paragraph 2.07
as it may be adjusted from time to time as provided
below.
1. Contractor shall submit to Engineer fer
acceptance (to the extent indioated in Paragraph 2.07)
with each application for payment an updated oroe:ress
schedule reflecting the amount of work completed and
proposed adjustments in the Progress Schedule that will
not result in changing the Contract Times. Such
adjustments will comply with any provisions of the
General Requirements applicable thereto.
2. Until the undated schedules are submitted to
and acceptable to Engineer and Owner. Owner may
withhold an amount from a nroe:ress payment that is
sufficient to pay the direct expenses that Owner mav
reasonably expect will be necessary to correct any
problems based on Contractor's failure' to submit
acceptable updated schedules. Review and acceptance of
orOl!:ress schedules bv the Engineer will neither impose on
Engineer responsibility for the sequencinl!:. schedulinl!: or
progress of the Work. nor interfere with or relieve
Contractor from Contractor's full responsibility therefore.
b. Contractor certifies that, if approved and
incorporated into the Work:
1) there will be no increase in cost to
the Owner or increase in Contract Times, and
2) it will conform substantially to the
detailed requirements of the item named in the
Contract Documents.
2. Substitute Items
a. If in Engineer's sole discretion an item of
material or equipment proposed by Contractor
does not qualifY as an "or-equal" item under
Paragraph 6.05.A.I, it will be considered a
proposed substitute item.
b. Contractor shall submit sufficient information
as provided below to allow Engineer to
determine that the item of material or equipment
proposed is essentially equivalent to that named
and an acceptable substitute therefore. Requests
for review of proposed substitute items of
material or equipment will not be accepted by
Engineer from anyone other than Contractor.
c. The requirements for review by Engineer will
be as set forth in Paragraph 6.05.A.2.d, as
supplemented in the General Requirements and
as Engineer may decide is appropriate under the
circumstances.
1. ;h Proposed adjustments in the Progress
Schedule that will change the Contract Times shall be
submitted in accordance with the requirements of Article
12. Adjustments in Contract Times may only be made by
a Change Order.
6.05 Substitutes and "Or-Equals"
A. Whenever an item of material or equipment is
specified or described in the Contract Documents by
using the name of a proprietary item or the name of a
particular Supplier, the specification or description is
intended to establish the type, function, appearance, and
quality required. Unless the specification or description
contains or is followed by words reading that no like,
equivalent, or "or~equal" item or no substitution is
permitted, other items of material or equipment or
material or equipment of other Suppliers may be
submitted to Engineer for review under the circumstances
described below.
d. Contractor shall make written application to
Engineer for review of a proposed substitute item
of material or equipment that Contractor seeks to
furnish or use. The application:
1. "Or-Equal" Items: If in Engineer's sole
discretion an item of material or equipment proposed by
Contractor is functionally equal to that named and
sufficiently similar so that no change in related Work will
be required, it may be considered by Engineer as an
"or~equal" item, in which case review and approval of the
proposed item may, in Engineer's sole discretion, be
accomplished without compliance with some or all of the
requirements for approval of proposed substitute items.
For the purposes of this Paragraph 6.05.A.l, a proposed
item of material or equipment will be considered
functionally equal to an item so named if:
1) shall certify that the proposed
substitute item will:
a) perform adequately the functions and
achieve the results called for by the
general design,
b) be similar in substance to that
specified, and
c) be suited to the same use as that
specified;
00...52713-0012
Bozeman WRF Phase 1 Early Out Priority Improvements
00700 - 21
5/22/2007
.
.
.
.
.
2) will state:
a) the extent, if any, to which the use of
the proposed substitute item will
prejudice Contractor's achievement of
Substantial Completion on time;
b) whether or not use of the proposed
substitute item in the Work will require
a change in any of the Contract
Documents (or in the provisions of any
other direct contract with Owner for
other work on the Project) to adapt the
design to the proposed substitute item;
and
c) whether or not incorporation or use
of the proposed substitute item in
connection with the Work is subject to
payment of any license fee or royalty;
3) will identify:
a) all variations of the proposed
substitute item from that specified, and
b) available engineering, sales,
maintenance, repair, and replacement
services;
4) and shall contain an itemized
estimate of all costs or credits that will result
directly or indirectly from use of such substitute
item, including costs of redesign and claims of
other contractors affected by any resulting
change,
B. Substitute Construction Methods or
Procedures: If a specific means, method, technique,
sequence, or procedure of construction is expressly
required by the Contract Documents, Contractor may
furnish or utilize a substitute means, method, technique,
sequence, or procedure of construction approved by
Engineer. Contractor shall submit sufficient information
to allow Engineer, in Engineer's sole discretion, to
determine that the substitute proposed is equivalent to that
expressly called for by the Contract Documents. The
requirements for review by Engineer will be similar to
those provided in Paragraph 6.05.A.2.
D. Special Guarantee: Owner may require
Contractor to furnish at Contractor's expense a special
performance guarantee or other surety with respect to any
substitute.
E. Engineer's Cost Reimbursement: Engineer
will record Engineer's costs in evaluating a substitute
proposed or submitted by Contractor pursuant to
Paragraphs 6.05.A.2 and 6.05.B Whether or not Engineer
approves a substitute item so proposed or submitted by
Contractor Contractor shall reimburse Owner for the
charges of Engineer for evaluating each such proposed
substitute. Contractor shall also reimburse Owner for the
charges of Engineer for making changes in the Contract
Documents (or in the provisions of any other direct
contract with Owner) resulting from the acceptance of
each proposed substitute.
1. Payment for such evaluation and redesign
shall be made at the hourly rates specified in the Bid
Form and made by deduction from the monthly progress
payments and the final payment as the evaluation and
redesign expenses are incurred.
F. Contractor's Expense: Contractor shall
provide all data in support of any proposed substitute or
"or-equal" at Contractor's expense.
6.06 Concerning Subcontractors, Suppliers, and
Others
A. Contractor shall not employ any
Subcontractor, Supplier, or other individual or entity
(including those acceptable to Owner as indicated in
Paragraph 6.06.B), whether initially or as a replacement,
against whom Owner may have reasonable objection.
Contractor shall not be required to employ any
Subcontractor, Supplier, or other individual or entity to
furnish or perform any of the Work against whom
Contractor has reasonable objection.
B. If the Supplementary Conditions require the
identity of certain Subcontractors, Suppliers, or other
individuals or entities to be submitted to Owner in
advance for acceptance by Owner by a specified date
prior to the Effective Date of the Agreement, and if
Contractor has submitted a list thereof in accordance with
the Supplementary Conditions, Owner's acceptance
(either in writing or by failing to make written objection
thereto by the date indicated for acceptance or objection
in the Bidding Documents or the Contract Documents) of
any such Subcontractor, Supplier, or other individual or
entity so identified may be revoked on the basis of
reasonable objection after due investigation. Contractor
shall submit an acceptable replacement for the rejected
Subcontractor, Supplier, or other individual or entity, and
the Contract Price will be adjusted by the difference in the
cost occasioned by such replacement, and an appropriate
Change Order will be issued. No acceptance by Owner of
any such Subcontractor, Supplier, or other individual or
entity, whether initially or as a replacement, shall
constitute a waiver of any right of Owner or Engineer to
reject defective Work.
Bozeman WRF Phase I Early Out Priority Improvements
00700 - 22
C. Engineer's Evaluation: Engineer will be
allowed a reasonable time within which to evaluate each
proposal or submittal made pursuant to Paragraphs 6.05.A
and 6.05.B. Engineer may require Contractor to fwnish
additional data about the proposed substitute item.
Engineer will be the sole judge of acceptability. No "or
equal" or substitute will be ordered, installed or utilized
until Engineer's review is complete, which will be
evidenced by either a Change Order for a substitute or an
approved Shop Drawing for an "or equal." Engineer will
advise Contractor in writing of any negative
determination.
.
00...52713-0012
5/22/2007
G. All Work performed for Contractor by a
Subcontractor or Supplier will be pursuant to an
appropriate agreement between Contractor and the
Subcontractor or Supplier which specifically binds the
Subcontractor or Supplier to the applicable terms and
conditions of the Contract Documents for the benefit of
Owner and Engineer. Whenever any such agreement is
with a Subcontractor or Supplier who is listed as an
additional insured on the property insurance provided in
Paragraph 5.06, the agreement between the Contractor
and the Subcontractor or Supplier will contain provisions
whereby the Subcontractor or Supplier waives all rights A. Contractor shall give all notices required by
against Owner, Contractor, and Engineer, Engineer's and shall comply with all Laws and Regulations
Consultants, and all other individuals or entities identified applicable to the performance of the Work. Except where
in the Supplementary Conditions to be listed as insureds otherwise expressly required by applicable Laws and
or additional insureds (and the officers, directors, Regulations, neither Owner nor Engineer shall be
partners, employees, agents, consultants and responsible for monitoring Contractor's compliance with
subcontractors of each and any of them) for all losses and any Laws or Regulations.
00.. .52713-0012 Bozeman WRF Phase 1 Early Out Priority Improvements
00700 - 23
C. Contractor shall be fully responsible to Owner
and Engineer for all acts and omissions of the
Subcontractors, Suppliers, and other individuals or
entities performing or furnishing any of the Work just as
Contractor is responsible for Contractor's own acts and
omissions. Nothing in the Contract Documents:
1. shall create for the benefit of any such
Subcontractor, Supplier, or other individual or entity any
contractual relationship between Owner or Engineer and
any such Subcontractor, Supplier or other individual or
entity, nor
2. shall anything in the Contract Documents
create any obligation on the part of Owner or Engineer to
payor to see to the payment of any moneys due any such
Subcontractor, Supplier, or other individual or entity
except as may otherwise be required by Laws and
Regulations. Owner or Engineer may furnish to anv such
Subcontractor. Suoolier or other person or organization.
to the extent oracticable. information about amounts oaid
to Contractor in accordance with Contractor's
Aoolications for Payment on account of the particular
Subcontractor's. Suppliers. or other person's or other
organization's Work.
D. Contractor shall be solely responsible for
scheduling and coordinating the Work of Subcontractors,
Suppliers, and other individuals or entities performing or
furnishing any of the Work under a direct or indirect
contract with Contractor.
E. Contractor shall require all Subcontractors,
Suppliers, and such other individuals or entities
performing or furnishing any of the Work to communicate
with Engineer through Contractor.
F. The divisions and sections of the
Specifications and the identifications of any Drawings
shall not control Contractor in dividing the Work among
Subcontractors or Suppliers or delineating the Work to be
performed by any specific trade.
damages caused by, arising out of, relating to, or resulting
from any of the perils or causes of loss covered by such
policies and any other property insurance applicable to the .
Work. If the insurers on any such policies require separate
waiver forms to be signed by any Subcontractor or
Supplier, Contractor will obtain the same.
6.07
Patent Fees and Royalties
A. Contractor shall pay all license fees and
royalties and assume all costs incident to the use in the
performance of the Work or the incorporation in the Work
of any invention, design, process, product, or device
which is the subject of patent rights or copyrights held by
others. If a particular invention, design, process, product,
or device is specified in the Contract Documents for use
in the performance of the Work and if to the actual
knowledge of Owner or Engineer its use is subject to
patent rights or copyrights calling for the payment of any
license fee or royalty to others, the existence of such
rights shall be disclosed by Owner in the Contract
Documents.
B. To the fullest extent permitted by Laws and
Regulations, Contractor shall indemnify and hold
harmless Owner, and Engineer, Engineer's Consultants.
and the officers, directors, partners, employees, agents,
consultants and subcontractors of each and any of them
from and against all claims, costs, losses, and damages
(including but not limited to all fees and charges of
engineers, architects, attorneys, and other professionals
and all court or arbitration or other dispute resolution
costs) arising out of or relating to any infringement of
patent rights or copyrights incident to the use in the
performance of the Work or resulting from the
incorporation in the Work of any invention, design,
process, product, or device not specified in the Contract
Documents.
.
6.08
Permits
A. Unless otherwise provided in the
Supplementary Conditions, Contractor shall obtain and
pay for all construction permits and licenses. Owner shall
assist Contractor, when necessary, in obtaining such
permits and licenses. Contractor shall pay all
governmental charges and inspection fees necessary for
the prosecution of the Work which are applicable at the
time of opening of Bids, or, if there are no Bids, on the
Effective Date of the Agreement. Owner shall pay all
charges of utility owners for connections for providing
permanent service to the Work.
6.09
Laws and Regulations
.
5/22/2007
3. To the fullest extent permitted by Laws and
Regulations, Contractor shall indemnify and hold
hannless Owner, and Engineer, Engineer's Consultants.
and the officers, directors, partners, employees, agents,
consultants and subcontractors of each and any of them
from and against all claims, costs, losses, and damages
(including but not limited to all fees and charges of
engineers, architects, attorneys, and other professionals
and all court or arbitration or other dispute resolution
00...52713-0012 Bozeman WRF Phase 1 Early Out Priority Improvements
00700 - 24
.
B. If Contractor performs any Work knowing or
having reason to know that it is contrary to Laws or
Regulations, Contractor shall bear all claims, costs,
losses, and damages (including but not limited to all fees
and charges of engineers, architects, attorneys, and other
professionals and all court or arbitration or other dispute
resolution costs) arising out of or relating to such Work.
However, it shall not be Contractor's primary
responsibility to make certain that the Specifications and
Drawings are in accordance with Laws and Regulations,
but this shall not relieve Contractor of Contractor's
obligations under Paragraph 3.03.
C. Changes in Laws or Regulations not known at
the time of opening of Bids (or, on the Effective Date of
the Agreement ifthere were no Bids) having an effect on
the cost or time of performance of the Work shall mav be
the subject of an adjustment in Contract Price or Contract
Times. If Owner and Contractor are unable to agree on
entitlement to or on the amount or extent, if any, of any
such adjustment, a Claim may be made therefor as
provided in Paragraph 10.05.
6.1 0 Taxes
.
A. Contractor shall pay all sales, consumer, use,
and other similar taxes required to be paid by Contractor
in accordance with the Laws and Regulations of the place
of the Project which are applicable during the
performance of the Work.
6.11 Use of Site and Other Areas
A. Limitation on Use of Site and Other Areas
1. Contractor shall confine construction
equipment, the storage of materials and equipment, and
the operations of workers to the Site and other areas
permitted by Laws and Regulations, and shall not
unreasonably encumber the Site and other areas with
construction equipment or other materials or equipment.
Contractor shall assume full responsibility for any
damage to any such land or area, or to the owner or
occupant thereof, or of any adjacent land or areas
resulting from the performance of the Work.
2. Should any claim be made by any such owner
or occupant because of the performance of the Work,
Contractor shall promptly settle with such other party by
negotiation or otherwise resolve the claim by arbitration
or other dispute resolution proceeding or at law.
.
costs) arising out of or relating to any claim or action,
legal or equitable, brought by any such owner or occupant
against Owner, Engineer, or any other party indemnified
hereunder to the extent caused by or based upon
Contractor's performance of the Work.
B. Removal of Debris During Performance of the
Work: During the progress of the Work Contractor shall
keep the Site and other areas free from accumulations of
waste materials, rubbish, and other debris. Removal and
disposal of such waste materials, rubbish, and other debris
shall conform to applicable Laws and Regulations.
C. Cleaning: Prior to Substantial Completion of
the Work Contractor shall clean the Site and the Work
and make it ready for utilization by Owner. At the
completion of the Work Contractor shall remove from the
Site all tools, appliances, construction equipment and
machinery, and surplus materials and shall restore to
original condition all property not designated for
alteration by the Contract Documents.
D. Loading Structures: Contractor shall not load
nor permit any part of any structure to be loaded in any
manner that will endanger the structure, nor shall
Contractor subject any part of the Work or adjacent
property to stresses or pressures that will endanger it.
6.12 Record Documents
A. Contractor shall maintain in a safe place at the
Site one record copy of all Drawings, Specifications,
Addenda, Change Orders, Work Change Directives, Field
Orders, and written interpretations and clarifications in
good order and annotated to show changes made during
construction. These record documents together with all
approved Samples and a counterpart of all approved Shop
Drawings will be available to Engineer for reference.
Upon completion of the Work, these record documents,
Samples, and Shop Drawings will be delivered to
Engineer for Owner.
B. The cost of any additional work required of
the Engineer to comolete the record documents due to
failure of the Contractor to maintain adequate record
documents shall be calculated at the hourlv rates specified
in the Bid Form for unscheduled emDlovment of the
Ene:ineer. Payment for such work shall be made bv
deduction from the monthly progress payments and the
final Davment as the costs are incurred.
6.13 Safety and Protection
A. Contractor shall be solely responsible for
initiating, maintaining and supervising all safety
precautions and programs in connection with the Work.
Contractor shall take all necessary precautions for the
safety of, and shall provide the necessary protection to
prevent damage, injury or loss to:
5/22/2007
A. Contractor shall be responsible for
coordinating any exchange of material safety data sheets
or other hazard communication information required to be
made available to or exchanged between or among
employers at the Site in accordance with Laws or
Regulations.
Bozeman WRF Phase 1 Early Out Priority Improvements
00700 - 25
1. all persons on the Site or who may be affected
by the Work;
2. all the Work and materials and equipment to
be incorporated therein, whether in storage on or off the
Site; and
3. other property at the Site or adjacent thereto
including trees, shrubs, lawns, walks, pavements:
roadways, structures, utilities, and Underground Facilities
not designated for removal, relocation, or replacement in
the course of construction.
B. Contractor shall comply with all applicable
Laws and Regulations relating to the safety of persons or
property, or to the protection of persons or property from
damage, injury, or loss; and shall erect and maintain all
necessary safeguards for such safety and protection.
Contractor shall notify owners of adjacent property and of
Underground Facilities and other utility owners when
prosecution of the Work may affect them, and shall
cooperate with them in the protection removal
relocation, and replacement of their property. ' ,
C. All damage, injury, or loss to any property
referred to in Paragraph 6.13.A.2 or 6.13.A.3 caused,
directly or indirectly; in whole or in part, by Contractor,
any Subcontractor, Supplier, or any other individual or
entity directly or indirectly employed by any of them to
perform any of the Work, or anyone for whose acts any of
them may be liable, shall be remedied by Contractor
(except damage or loss attributable to the fault of
Drawings or Specifications or to the 'acts or omissions of
Owner or Engineer or Emdneer's Consultants, or anyone
employed by any of them, or anyone for whose acts any
of them may be liable, and not attributable, directly or
indirectly, in whole or in part, to the fault or negligence of
Contractor or any Subcontractor, Supplier, or other
individual or entity directly or indirectly employed by any
of them).
D. Contractor's duties and responsibilities for
safety and for protection of the Work shall continue until
such time as all the Work is completed and Engineer has
issued a notice to Owner and Contractor in accordance
with Paragraph 14.07.B that the Work is acceptable
(except as otherwise expressly provided in connection
with Substantial Completion).
E. It is expressly understood by the parties to this
Agreement that the Contractor is solely responsible for
initiating. maintaining, and suoervising safety orecautions
and programs in connection with the Work. While Owner
and En~ineer ~av have the rimt to observe and report or
otherwIse reVIew the work. progress and operations of
Contractor and any subcontractors or suooliers. this
observation. report or review shall not relieve Contractor
from any of its covenants and obligations hereunder.
Contractor shall incorporate all safety requirements into
its construction pro !!Tess and work schedules. including
meconstruction and regularly scheduled safety meetings.
posted safety rules, tailgate meetings. and site inspections
00",52713-0012
by safety and other inspectors emoloyed by the
Contractor.
F. The Contractor shall be responsible for and
shall take necessary precautions and provide all material
and equipment to protect. shore. brace. suooort and
maintain all underground work and facilities. including
pioes. conduits. drains. sewers. water mains. gas mains.
cables. etc.. and other underground construction work
uncovered in the proximity. or otherwise affected bv the
construction work performed by him. All oavement.
surfacing. driveways. curbs. walks. buildings. !!Tass areas.
trees. utility poles or gUY wires damaged by the
Contractor's ouerations in the oerformance of this work
shall be repaired and/or reo laced to the satisfaction of the
Owner. Engineer. and affected moperty owner at the
Contractor's expense. The Contractor shall also be
responsible for all damage to streets. roads, highways,
shoulders. ditches. embankments. culverts. bridges. or
other public or mivate property or facility. regardless of
location or character. which may be caused by the work.
including moving. hauling. or otherwise transuorting
eauiument. materials. or men to and from the work or any
part of the site thereof. whether bv him or his
subcontractors. The Contractor shall make satisfactory
and acceptable arrangements with the owner of. or the
agenCV or authority having iurisdiction over. the damaged
property or facility concerning its repair or reolacement or
payment of costs incurred in connection with said
damage.
.
G. The Contractor shall conduct his work so as
to interfere as little as possible with public travel. whether
vehicular or pedestrian. Whenever it is necessary to
cross. obstruct. or close roads. driveways. or walks.
whether uubic or private. the Contractor shall obtain
approval from the !!overning party and shall. at his own
expense. movide and maintain suitable and safe bridges,
detours. and other temporary expedients for the
accommodation of public and mivate drives before
interfering with them. Safety provisions must be entirely
adequate and meet with Citv or State and Federal
regulations to motect the public on these streets and
roads. The provisions for temporary expedients will not
be required when the Contractor has obtained oermission
from the owner and tenant of the private prooertv. or from
!he authority having iurisdiction over public property
Involved. to obstruct traffic at the designated ooint.
6.14 Safety Representative
A. Contractor shall designate a qualified and
experienced safety representative at the Site whose duties
and responsibilities shall be the prevention of accidents
and the maintaining and supervising of safety precautions
and programs.
.
6.15
Hazard Communication Programs
.
5/22/2007
6.16 Emergencies
.
A. In emergencies affecting the safety or
protection of persons or the Work or property at the Site
or adjacent thereto, Contractor is obligated to act to
prevent threatened damage, injury, or loss. Contractor
shall give Engineer prompt written notice if Contractor
believes that any significant changes in the Work or
variations from the Contract Documents have been caused
thereby or are required as a result thereof. If Engineer
determines that a change in the Contract Documents is
required because of the action taken by Contractor in
response to such an emergency, a Work Change Directive
or Change Order will be issued.
6.17 Shop Drawings and Samples
A. Contractor shall submit Shop Drawings and
Samples to Engineer for review and approval in
accordance with the acceptable Schedule of Submittals
(as required by Paragraph 2.07). Each submittal will be
identified as Engineer may require.
1. Shop Drawings
a. Submit number of copies specified in the
General Requirements.
.
b. Data shown on the Shop Drawings will be
complete with respect to quantities, dimensions,
specified performance and design criteria,
materials, and similar data to show Engineer the
services, materials, and equipment Contractor
proposes to provide and to enable Engineer to
review the information for the limited purposes
required by Paragraph 6.17.D.
2. Samples: Contractor shall also submit
Samples to Engineer for review and approval in
accordance with the acceptable schedule of Shop
Drawings and Sample submittals.
a. Submit number of Samples specified in the
Specifications.
b. Clearly identify each Sample as to material,
Supplier, pertinent data such as catalog numbers,
the use for which intended and other data as
Engineer may require to enable Engineer to
review the submittal for the limited purposes
required by Paragraph 6.17.D.
B. Where a Shop Drawing or Sample is required
by the Contract Documents or the Schedule of Submittals,
any related Work performed prior to Engineer's review
and approval of the pertinent submittal will be at the sole
expense and responsibility of Contractor.
.
c. Submittal Procedures
1. Before submitting each Shop Drawing or
Sample, Contractor shall have determined and verified:
a. all field measurements, quantities, dimensions,
specified performance and design criteria,
installation requirements, materials, catalog
numbers, and similar information with respect
thereto;
b. the suitability of all materials with respect to
intended use, fabrication, shipping, handling,
storage, assembly, and installation pertaining to
the performance of the Work;
c. all information relative to Contractor's
responsibilities for means, methods, techniques,
sequences, and procedures of construction, and
safety precautions and programs incident thereto;
and
d. shall also have reviewed and coordinated each
Shop Drawing or Sample
Drawings and Samples
requirements of the Work
Documents.
with other Shop
and with the
and the Contract
2. Each submittal shall bear a stamp or specific
written certification that Contractor has satisfied
Contractor's obligations under the Contract Documents
with respect to Contractor's review and approval of that
submittal.
3. With each submittal, Contractor shall give
Engineer specific written notice of any variations, that the
Shop Drawing or Sample may have from the requirements
of the Contract Documents. This notice shall be both a
written communication separate from the Shop Drawing's
or Sample Submittal; and, in addition, by a specific
notation made on each Shop Drawing or Sample
submitted to Engineer for review and approval of each
such variation.
D. Engineer's Review
1. Engineer will provide timely review of Shop
Drawings and Samples in accordance with the Schedule
of Submittals acceptable to Engineer. Engineer's review
and approval will be only to determine if the items
covered by the submittals will, after installation or
incorporation in the Work, conform to the information
given in the Contract Documents and be compatible with
the design concept of the completed Project as a
functioning whole as indicated by the Contract Docu-
ments.
2. Engineer's review and approval will not
extend to means, methods, techniques, sequences, or
procedures of construction (except where a particular
means, method, technique, sequence, or procedure of
construction is specifically and expressly called for by the
Contract Documents) or to safety precautions or programs
incident thereto. The review and approval of a separate
item as such will not indicate approval of the assembly in
which the item functions.
00...52713-0012
Bozeman WRF Phase 1 Early Out Priority Improvements
00700 - 26
5/2212007
C. B. In any and all claims against Owner or
Engineer or any of their respective consultants, agents,
officers, directors, partners, or employees by any
employee (or the survivor or personal representative of
such employee) of Contractor, any Subcontractor, any
Supplier, or any individual or entity directly or indirectly
employed by any ofthem to perform or furnish any of the
Work, or anyone for whose acts any of them may be
liable, the indemnification obligation under Paragraph
6.20.A shall not be limited in any way by any limitation
on the amount or type of damages, compensation, or
benefits payable by or for Contractor or any such
Subcontractor, Supplier, or other individual or entity
under workers' compensation acts, disability benefit acts,
or other employee benefit acts.
Bozeman WRF Phase 1 Early Out Priority Improvements
00700 . 27
3. Engineer's review and approval shall not
relieve Contractor from responsibility for any variation
from the requirements of the Contract Documents unless
Contractor has complied with the requirements of
Paragraph 6.17.C.3 and Engineer has given written
approval of each such variation by specific written
notation thereof incorporated in or accompanying the
Shop Drawing or Sample. Engineer's review and approval
shall not relieve Contractor from responsibility for
complying with the requirements of Paragraph 6.17.C. I.
E. Resubmittal Procedures
1. Contractor shall make corrections required by
Engineer and shall return the required number of
corrected copies of Shop Drawings and submit, as
required, new Samples for review and approval.
Contractor shall direct specific attention in writing to
revisions other than the corrections called for by Engineer
on previous submittals.
6.18 Continuing the Work
A. Contractor shall carry on the Work and adhere
to the Progress Schedule during all disputes or
disagreements with Owner. No Work shall be delayed or
postponed pending resolution of any disputes or
disagreements, except as permitted by Paragraph 15.04 or
as Owner and Contractor may otherwise agree in writing.
6.19 Contractor's General Warranty and Guarantee
A. Contractor warrants and guarantees to Owner
that all Work will be in accordance with the Contract
Documents and will not be defective. Engineer and its
Related Entities shall be entitled to rely on representation
of Contractor's warranty and guarantee.
B. Contractor's warranty and guarantee
hereunder excludes defects or damage caused by:
I. abuse, modification, or improper maintenance
or operation by persons other than Contractor,
Subcontractors, Suppliers, or any other individual or
entity for whom Contractor is responsible; or
2. normal wear and tear under normal usage.
C. Contractor's obligation to perform and
complete the Work in accordance with the Contract
Documents shall be absolute. None of the following will
constitute an acceptance of Work that is not in accordance
with the Contract Documents or a release of Contractor's
obligation to perform the Work in accordance with the
Contract Documents:
1. observations by Engineer;
2. recommendation by Engineer or payment by
Owner of any progress or final payment;
00...52713.0012
3. the issuance of a certificate of Substantial
Completion by Engineer or any payment related thereto
by Owner;
.
4. use or occupancy of the Work or any part
thereof by Owner;
5. any review and approval ofa Shop Drawing or
Sample submittal or the issuance of a notice of
acceptability by Engineer;
6. any inspection, test, or approval by others; or
7. any correction of defective Work by Owner.
6.20 Indemnification
A. To the fullest extent permitted by Laws and
Regulations, Contractor shall indemnify and hold
harmless Owner, and Engineer, Engineer's Consultants.
and the officers, directors, partners, employees, agents,
consultants and subcontractors of each and any of them
from and against all claims, demands, liability. costs,
losses, and damages (including but not limited to all fees
and charges of engineers, architects, attorneys, and other
professionals and all court or arbitration or other dispute
resolution costs) caused by. arising out of or relating to
the performance of the Work, provided that any such
claim, demand. liability. cost, loss, or damage is
attributable to bodily injury, sickness, disease, mental
anguish. or death, or to injury to or destruction of tangible
property (other than the Work itself), including the loss of
use resulting therefrom but only to the extent caused by
any nogligont act or omission of Contractor, any
Subcontractor, any Supplier, or any individual or entity
directly or indirectly employed by any of them to perform
or furnish any of the Work or anyone for whose acts any
of them may be liable.
.
B. While Owner and Engineer may have the
right to observe or otherwise review the work, progress
and operations of the Contractor. and any Subcontractors
or Suppliers. it is exoresslv understood and agreed that
this observation. report or review shall not relieve the
Contractor from any of its covenants and obligations
hereunder.
.
512212007
.
D. G,. The indemnification obligations of
Contractor under Paragraph 6.20.A shall not extend to the
liability of Engineer and Engineer's Consultants or to the
officers, directors, partners, employees, agents,
consultants and subcontractors arising out of:
1. the preparation or approval of, or the failure to
prepare or approve, maps, Drawings, opinions, reports,
surveys, Change Orders, designs, or Specifications; or
2. giving directions or instructions, or failing to
give them, if that is the primary cause of the injury or
damage.
E. The exceptions to Contractor's
indemnification obligations under paragraph 6.20.D shall
not aoolv to anv claim or demand against Engineer and
EnlZineer's Consultants or to the officers. directors.
oartners. emolovees. alZents and other consultants and
subcontractors of each and any of them which is based on
asserted liability for the reporting or failing to report of
matters relatinlZ to allelZed health and safety violations in
connection with the work of Contractor and any
Subcontractor or Supplier.
6.21 Delegation of Professional Design Services
.
A. Contractor will not be required to provide
professional design services unless such services are
specifically required by the Contract Documents for a
portion of the Work or unless such services are required
to carry out Contractor's responsibilities for construction
means, methods, techniques, sequences and procedures.
Contractor shall not be required to provide professional
services in violation of applicable law.
B. If professional design services or
certifications by a design professional related to systems,
materials or equipment are specifically required of
Contractor by the Contract Documents, Owner and
Engineer will specify all performance and design criteria
that such services must satisfy. Contractor shall cause
such services or certifications to be provided by a
properly licensed professional, whose signature and seal
shall appear on all drawings, calculations, specifications,
certifications, Shop Drawings and other submittals
prepared by such professional. Shop Drawings and other
submittals related to the Work designed or certified by
such professional, if prepared by others, shall bear such
professional's written approval when submitted to
Engineer.
.
C. Owner and Engineer shall be entitled to rely
upon the adequacy, accuracy and completeness of the
services, certifications or approvals performed by such
design professionals, provided Owner and Engineer have
specified to Contractor all performance and design criteria
that such services must satisfy.
D. Pursuant to this Paragraph 6.21, Engineer's
review and approval of design calculations and design
drawings will be only for the limited purpose of checking
for conformance with performance and design criteria
given and the design concept expressed in the Contract
Documents. Engineer's review and approval of Shop
Drawings and other submittals (except design calculations
and design drawings) will be only for the purpose stated
in Paragraph 6.17.D.1.
E. Contractor shall not be responsible for the
adequacy of the performance or design criteria required
by the Contract Documents.
ARTICLE 7 ~ OTHER WORK AT THE SITE
7.01 Related Work at Site
A. Owner may perform other work related to the
Project at the Site with Owner's employees, or via other
direct contracts therefor, or have other work performed by
utility owners. If such other work is not noted in the
Contract Documents, then:
1. written notice thereof will be given to
Contractor prior to starting any such other work; and
2. if Owner and Contractor are unable to agree
on entitlement to or on the amount or extent, if any, of
any adjustment in the Contract Price or Contract Times
that should be allowed as a result of such other work, a
Claim may be made therefor as provided in Paragraph
10.05.
B. Contractor shall afford each other contractor
who is a party to such a direct contract, each utility owner
and Owner, if Owner is performing other work with
Owner's employees, proper and safe access to the Site, a
reasonable opportunity for the introduction and storage of
materials and equipment and the execution of such other
work, and shall properly coordinate the Work with theirs.
Contractor shall do all cutting, fitting, and patching of the
Work that may be required to properly connect or
otherwise make its several parts come together and
properly integrate with such other work. Contractor shall
not endanger any work of others by cutting, excavating,
or otherwise altering their work and will only cut or alter
their work with the written consent of Engineer and the
others whose work will be affected. The duties and
responsibilities of Contractor under this Paragraph are for
the benefit of such utility owners and other contractors to
the extent that there are comparable provisions for the
benefit of Contractor in said direct contracts between
Owner and such utility owners and other contractors.
C. If the proper execution or results of any part
of Contractor's Work depends upon work performed by
others under this Article 7, Contractor shall inspect such
other work and promptly report to Engineer in writing any
5/22/2007
00.. .52713-0012
Bozeman WRF Phase I Early Out Priority Improvements
00700 . 28
delays, defects, or deficiencies in such other work that
render it unavailable or unsuitable for the proper
execution and results of Contractor's Work. Contractor's
failure to so report will constitute an acceptance of such
other work as fit and proper for integration with
Contractor's Work except for latent defects and
deficiencies in such other work.
7.02
Coordination
A. If Owner intends to contract with others for
the performance of other work on the Project at the Site,
the following will be set forth in Supplementary
Conditions:
1. the individual or entity who will have
authority and responsibility for coordination of the
activities among the various contractors will be identified;
2. the specific matters to be covered by such
authority and responsibility will be itemized; and
3. the extent of such authority and
responsibiljties will be provided.
B. Unless otherwise provided in the
Supplementary Conditions, Owner shall have sole
authority and responsibility for such coordination.
7.03
Legal Relationships
A. Paragraphs 7.01.A and 7.02 are not applicable
for utilities not under the control of Owner.
B. Each other direct contract of Owner under
Paragraph 7.01.A shall provide that the other contractor is
liable to Owner and Contractor for the reasonable direct
delay and disruption costs incurred by Contractor as a
result of the other contractor's actions or inactions.
C. Contractor shall be liable to Owner and any
other contractor for the reasonable direct delay and
disruption costs incurred by such other contractor as a
result of Contractor's action or inactions.
ARTICLE 8 - OWNER'S RESPONSIBILITIES
8.01 Communications to Contractor
A. Except as otherwise provided in these General
Conditions, Owner shall issue all communications to
Contractor through Engineer.
8.02
Replacement of Engineer
A. In case of termination of the employment of
Engineer, Owner shall appoint an engineer to whom
Contractor makes no reasonable objection, whose status
under the Contract Documents shall be that of the former
Engineer.
00...52713-0012
8.03 Furnish Data
A. Owner shall promptly furnish the data
required of Owner under the Contract Documents.
.
8.04 Pay When Due
A. Owner shall make payments to Contractor
when they are due as provided in Paragraphs 14.02.C and
14.07.C.
8.05 Lands and Easements; Reports and Tests
A. Owner's duties in respect of providing lands
and easements and providing engineering surveys to
establish reference points are set forth in Paragraphs 4.01
and 4.05. Paragraph 4.02 refers to Owner's identifying
and making available to Contractor copies of reports of
explorations and tests of subsurface conditions and
drawings of physical conditions in or relating to existing
surface or subsurface structures at or contiguous to the
Site that have been utilized by Engineer in preparing the
Contract Documents.
8.06 Insurance
A. Owner's responsibilities, if any, in respect to
purchasing and maintaining liability and property
insurance are set forth in Article 5.
8.07
Change Orders
.
A. Owner is obligated to execute Change Orders
as indicated in Paragraph 10.03.
8.08 Inspections, Tests, and Approvals
A. Owner's responsibility in respect to certain
inspections, tests, and approvals is set forth in Paragraph
13.03.B.
8.09 Limitations on Owner's Responsibilities
A. The Owner shall not supervise, direct, or have
control or authority over, nor be responsible for,
Contractor's means, methods, techniques, sequences, or
procedures of construction, or the safety precautions and
programs incident thereto, or for any failure of Contractor
to comply with Laws and Regulations applicable to the
performance of the Work. Owner will not be responsible
for Contractor's failure to perform the Work in
accordance with the Contract Documents.
8.10 Undisclosed
Condition
Hazardous
Environmental
A. Owner's responsibility in respect to an
undisclosed Hazardous Environmental Condition is set
forth in Paragraph 4.06.
.
Bozeman WRF Phase 1 Early Out Priority Improvements
00700 - 29
5/22/2007
8.11 Evidence of Financial Arrangements
.
A. If and to the extent Owner has agreed to
furnish Contractor reasonable evidence that [mancial
arrangements have been made to satisfy Owner's
obligations under the Contract Documents, Owner's
responsibility in respect thereof will be as set forth in the
Supplementary Conditions.
ARTICLE 9 - ENGINEER'S STATUS DURING
CONSTRUCTION
9.01 Owner's Representative
A. Engineer will be Owner's representative
during the construction period. The duties and
responsibilities and the limitations of authority of
Engineer as Owner's representative during construction
are set forth in the Contract Documents and will not be
changed without written consent of Owner and Engineer.
9.02 Visits to Site
.
A. Engineer will make visits to the Site at
intervals appropriate to the various stages of construction
as Engineer deems necessary in order to observe as an
experienced and qualified design professional the
progress that has been made and the quality of the various
aspects of Contractor's executed Work. Based on
information obtained during such visits and observations,
Engineer, for the benefit of Owner, will determine, in
general, if the Work is proceeding in accordance with the
Contract Documents. Engineer will not be required to
make exhaustive or continuous inspections on the Site to
check the quality or quantity of the Work. Engineer's
efforts will be directed toward providing for Owner a
greater degree of confidence that the completed Work will
conform generally to the Contract Documents. On the
basis of such visits and observations, Engineer will keep
Owner informed of the progress of the Work and will
endeavor to guard Owner against defective Work.
B. Engineer's visits and observations are subject
to all the limitations on Engineer's authority and
responsibility set forth in Paragraph 9.09. Particularly, but
without limitation, during or as a result of Engineer's
visits or observations of Contractor's Work Engineer will
not supervise, direct, control, or have authority over or be
responsible for Contractor's means, methods, techniques,
sequences, or procedures of construction, or the safety
precautions and programs incident thereto, or for any
failure of Contractor to comply with Laws and
Regulations applicable to the performance ofthe Work.
.
9.03 Project Representative
Work. The authority and responsibilities of any such
Resident Project Representative and assistants will be as
provided in the Supplementary Conditions, and
limitations on the responsibilities thereof will be as
provided in Paragraph 9.09. If Owner designates another
representative or agent to represent Owner at the Site who
is not Engineer's consultant, agent or employee, the
responsibilities and authority and limitations thereon of
such other individual or entity will be as provided in the
Supplementary Conditions.
9.04 Authorized Variations in Work
A. Engineer may authorize minor variations in
the Work from the requirements of the Contract
Documents which do not involve an adjustment in the
Contract Price or the Contract Times and are compatible
with the design concept of the completed Project as a
functioning whole as indicated by the Contract
Documents. These may be accomplished by a Field Order
and will be binding on Owner and also on Contractor,
who shall perform the Work involved promptly. If Owner
or Contractor believes that a Field Order justifies an
adjustment in the Contract Price or Contract Times, or
both, and the parties are unable to agree on entitlement to
or on the amount or extent, if any, of any such adjustment,
a Claim may be made therefor as provided in Paragraph
10.05.
B. However. there will be no relaxing,
substituting or aualifYing any portion of the
Specifications. unless such change is approved in writing
by the Engineer and Owner.
9.05 Rejecting Defective Work
A. Engineer will have authority to reject Work
which Engineer believes to be defective, or that Engineer
believes will not produce a completed Project that
conforms to the Contract Documents or that will prejudice
the integrity of the design concept of the completed
Project as a functioning whole as indicated by the
Contract Documents. Engineer will also have authority to
require special inspection or testing of the Work as
provided in Paragraph 13.04, whether or not the Work is
fabricated, installed, or completed.
9.06 Shop Drawings, Change Orders and Payments
A. In connection with Engineer's authority, and
limitations thereof, as to Shop Drawings and Samples, see
Paragraph 6.17.
B. In connection with Engineer's authority, and
limitations thereof, as to design calculations and design
drawings submitted in response to a delegation of
professional design services, if any, see Paragraph 6.21.
C. In connection with Engineer's authority as to
Change Orders, see Articles 10, 11, and 12.
A. If Owner and Engineer agree, Engineer will
furnish a Resident Project Representative to assist
Engineer in providing more extensive observation of the
00. __52713-0012 Bozeman WRF Phase 1 Early Out Priority Improvements
00700 - 30
5/22/2007
D. In connection with Engineer's authority as to
Applications for Payment, see Article 14.
9.07 Determinationsfor Unit Price Work
A. Engineer will determine the actual quantities
and classifications of Unit Price Work performed by
Contractor. Engineer will review with Contractor the
Engineer's preliminary determinations on such matters
before rendering a written decision thereon (by
recommendation of an Application for Payment or
otherwise). Engineer's written decision thereon will be
final and binding (except as modified by Engineer to
reflect changed factual conditions or more accurate data)
upon Owner and Contractor, subject to the provisions of
Paragraph 10.05.
9.08 Decisions on Requirements of Contract
Documents and Acceptability of Work
A. Engineer will be the initial interpreter of the
requirements of the Contract Documents and judge of the
acceptability of the Work thereunder. All matters in
question and other matters between Owner and Contractor
arising prior to the date final payment is due relating to
the acceptability of the Work, and the interpretation of the
requirements of the Contract Documents pertaining to the
performance of the Work, will be referred initially to
Engineer in writing within 30 days ofthe event giving rise
to the question.
B. Engineer will, with reasonable promptness,
render a written decision on the issue referred. If Owner
or Contractor believe that any such decision entitles them
to an adjustment in the Contract Price or Contract Times
or both, a Claim may be made under Paragraph 10.05.
The date of Engineer's decision shall be the date of the
event giving rise to the issues referenced for the purposes
of Paragraph 1O.05.B.
C. Engineer's written decision on the issue
referred will be final and binding on Owner and
Contractor, subject to the provisions of Paragraph 10.05.
D. When functioning as interpreter and judge
under this Paragraph 9.08, Engineer will not show
partiality to Owner or Contractor and will not be liable in
connection with any interpretation or decision rendered in
good faith in such capacity.
9.09 Limitations on Engineer's Authority and
Responsibilities
A. Neither Engineer's authority or responsibility
under this Article 9 or under any other provision of the
Contract Documents nor any decision made by Engineer
in good faith either to exercise or not exercise such
authority or responsibility or the undertaking, exercise, or
performance of any authority or responsibility by
Engineer shall create, impose, or give rise to any duty in
contract, tort, or otherwise owed by Engineer to
Contractor, any Subcontractor, any Supplier, any other
individual or entity, or to any surety for or employee or
agent of any of them.
.
B. Engineer will not supervise, direct, control, or
have authority over or be responsible for Contractor's
means, methods, techniques, sequences, or procedures of
construction, or the safety precautions and programs
incident thereto, or for any failure of Contractor to
comply with Laws and Regulations applicable to the
performance of the Work. Engineer will not be
responsible for Contractor's failure to perform the Work
in accordance with the Contract Documents.
C. Engineer will not be responsible for the acts
or omissions of Contractor or of any Subcontractor, any
Supplier, or of any other individual or entity performing
any of the Work.
D. Engineer's review of the final Application for
Payment and accompanying documentation and all
maintenance and operating instructions, schedules,
guarantees, bonds, certificates of inspection, tests and
approvals, and other documentation required to be
delivered by Paragraph 14.07.A will only be to determine
generally that their content complies with the
requirements of, and in the case of certificates of
inspections, tests, and approvals that the results certified
indicate compliance with the Contract Documents.
.
E. The limitations upon authority and
responsibility set forth in this Paragraph 9.09 shall also
apply to Engineer's Consultants. if any, the Resident
Project Representative, if any, and assistants, if any.
ARTICLE 10 - CHANGES IN THE WORK; CLAIMS
10.01 Authorized Changes in the Work
A. Without invalidating the Contract and without
notice to any surety, Owner may, at any time or from time
to time, order additions, deletions, or revisions in the
Work by a Change Order, or a Work Change Directive.
Upon receipt of any such document, Contractor shall
promptly proceed with the Work involved which will be
performed under the applicable conditions of the Contract
Documents (except as otherwise specifically provided).
B. If Owner and Contractor are unable to agree
on entitlement to, or on the amount or extent, if any, of an
adjustment in the Contract Price or Contract Times, or
both, that should be allowed as a result of a Work Change
Directive, a Claim may be made therefor as provided in
Paragraph 10.05.
.
00...52713-0012
Bozeman WRF Phase 1 Early Out Priority Improvements
00700 - 31
5/22/2007
10.02 Unauthorized Changes in the Work
.
A. Contractor shall not be entitled to an increase
in the Contract Price or an extension of the Contract
Times with respect to any work perfonned that is not
required by the Contract Documents as amended,
modified, or supplemented as provided in Paragraph 3.04,
except in the case of an emergency as provided in
Paragraph 6.16 or in the case of uncovering Work as
provided in Paragraph 13.04.B.
10.03 Execution o/Change Orders
A. Owner and Contractor shall execute
appropriate Change Orders recommended by Engineer
covering:
1. changes in the Work which are: (i) ordered by
Owner pursuant to Paragraph 1O.01.A, (ii) required
because of acceptance of defective Work under Paragraph
13.08.A or Owner's correction of defective Work under
Paragraph 13.09, or (iii) agreed to by the parties;
2. changes in the Contract Price or Contract
Times which are agreed to by the parties, including any
undisputed sum or amount of time for Work actually
perfonned in accordance with a Work Change Directive;
and
.
3. changes in the Contract Price or Contract
Times which embody the substance of any written
decision rendered by Engineer pursuant to Paragraph
10.05; provided that, in lieu of executing any such
Change Order, an appeal may be taken from any such
decision in accordance with the provisions of the Contract
Documents and applicable Laws and Regulations, but
during any such appeal, Contractor shall carry on the
Work and adhere to the Progress Schedule as provided in
Paragraph 6.18.A.
10.04 Notification to Surety
A. If notice of any change affecting the general
scope of the Work or the provisions of the Contract
Documents (including, but not limited to, Contract Price
or Contract Times) is required by the provisions of any
bond to be given to a surety, the giving of any such notice
will be Contractor's responsibility. The amount of each
applicable bond will be adjusted to reflect the effect of
any such change.
10.05 Claims
.
A. Engineer's Decision Required: All Claims,
except those waived pursuant to Paragraph 14.09, shall be
referred to the Engineer for decision. A decision by
Engineer shall be required as a condition precedent to any
exercise by Owner or Contractor of any rights or remedies
either may otherwise have under the Contract Documents
or by Laws and Regulations in respect of such Claims.
B. Notice: Written notice stating the general
nature of each Claim, shall be delivered by the claimant to
Engineer and the other party to the Contract promptly (but
in no event later than 30 days) after the start of the event
giving rise thereto. The responsibility to substantiate a
Claim shall rest with the party making the Claim. Notice
of the amount or extent of the Claim, with supporting data
shall be delivered to the Engineer and the other party to
the Contract within 60 days after the start of such event
(unless Engineer allows additional time for claimant to
submit additional or more accurate data in support of such
Claim). A Claim for an adjustment in Contract Price shall
be prepared in accordance with the provisions of
Paragraph 12.01.B. A Claim for an adjustment in Contract
Time shall be prepared in accordance with the provisions
of Paragraph 12.02.B. Each Claim shall be accompanied
by claimant's written statement that the adjustment
claimed is the entire adjustment to which the claimant
believes it is entitled as a result of said event. The
opposing party shall submit any response to Engineer and
the claimant within 30 days after receipt of the claimant's
last submittal (unless Engineer allows additional time).
C. Engineer's Action: Engineer will review each
Claim and, within 30 days after receipt of the last
submittal of the claimant or the last subrriittal of the
opposing party, if any, take one of the following actions
in writing:
1. deny the Claim in whole or in part,
2. approve the Claim, or
3. notify the parties that the Engineer is unable to
resolve the Claim if, in the Engineer's sole discretion, it
would be inappropriate for the Engineer to do so. For
purposes of further resolution of the Claim, such notice
shall be deemed a denial.
D. In the event that Engineer does not take action
on a Claim within said 30 days, the Claim shall be
deemed denied.
E. Engineer's written action under Paragraph
1O.05.C or denial pursuant to Paragraphs 10.05.C.3 or
1O.05.D will be final and binding upon Owner and
Contractor, unless Owner or Contractor invoke the
dispute resolution procedure set forth in Article 16 within
30 days of such action or denial.
F. No Claim for an adjustment in Contract Price
or Contract Times will be valid if not submitted in
accordance with this Paragraph 10.05.
00...52713-0012
Bozeman WRF Phase I Early Out Priority Improvements
00700 - 32
5/2212007
f. Losses and damages (and related expenses)
caused by damage to the Work, not compensated
by insurance or otherwise, sustained by
Contractor in connection with the performance
of the Work (except losses and damages within
the deductible amounts of property insurance
established in accordance with Paragraph
5.06.D), provided such losses and damages have
resulted from causes other than the negligence of
Contractor, any Subcontractor, or anyone
directly or indirectly employed by any of them or
for whose acts any of them may be liable. Such
Bozeman WRF Phase 1 Early Out Priority Improvements 5/22/2007
00700 - 33
ARTICLE 11 COST OF THE WORK;
ALLOWANCES; UNIT PRICE WORK
11.01 Cost of the Work
A. Costs Included: The term Cost of the Work
means the sum of all costs, except those excluded in
Paragraph 11.01.B, necessarily incurred and paid by
Contractor in the proper performance of the Work. When
the value of any Work covered by a Change Order or
when a Claim for an adjustment in Contract Price is
determined on the basis of Cost of the Work, the costs to
be reimbursed to Contractor will be only those additional
or incremental costs required because of the change in the
Work or because of the event giving rise to the Claim.
Except as otherwise may be agreed to in writing by
Owner, such costs shall be in amounts no higher than
those prevailing in the locality of the Project, shall include
only the following items, and shall not include any of the
costs itemized in Paragraph 11.01.8.
1. Payroll costs for employees in the direct
employ of Contractor in the performance of the Work
under schedules of job classifications agreed upon by
Owner and Contractor. Such employees shall include,
without limitation, superintendents, foremen, and other
personnel employed full time at the Site. Payroll costs for
employees not employed full time on the Work shall be
apportioned on the basis of their time spent on the Work.
Payroll costs shall include, but not be limited to, salaries
and wages plus the cost of fringe benefits, which shall
include social security contributions, unemployment,
excise, and payroll taxes, workers' compensation, health
and retirement benefits, bonuses, sick leave, vacation and
holiday pay applicable thereto. The expenses of
performing Work outside of regular working hours, on
Saturday, Sunday, or legal holidays, shall be included in
the above to the extent authorized by Owner.
2. Cost of all materials and equipment furnished
and incorporated in the Work, including costs of
transportation and storage thereof, and Suppliers' field
services required in connection therewith. All cash
discounts shall accrue to Contractor unless Owner
deposits funds with Contractor with which to make
payments, in which case the cash discounts shall accrue to
Owner. All trade discounts, rebates and refunds and
returns from sale of surplus materials and equipment shall
accrue to Owner, and Contractor shall make provisions so
that they may be obtained.
3. Payments made by Contractor to
Subcontractors for Work performed by Subcontractors. If
required by Owner, Contractor shall obtain competitive
bids from subcontractors acceptable to Owner and
Contractor and shall deliver such bids to Owner, who will
then determine, with the advice of Engineer, which bids,
if any, will be acceptable. If any subcontract provides that
the Subcontractor is to be paid on the basis of Cost of the
Work plus a fee, the Subcontractor's Cost of the Work
00...52713-0012
and fee shall be determined in the same manner as
Contractor's Cost of the Work and fee as provided in this
Paragraph 11.01.
4. Costs of special consultants (including but not
limited to engineers, architects, testing laboratories,
surveyors, attorneys, and accountants) employed for
services specifically related to the Work.
5. Supplemental costs including the following:
a. The proportion of necessary transportation,
travel, and subsistence expenses of Contractor's
employees incurred in discharge of duties
connected with the Work.
b. Cost, including transportation and
maintenance, of all materials, supplies,
equipment, machinery, appliances, office, and
temporary facilities at the Site, and hand tools
not owned by the workers, which are consumed
in the performance of the Work, and cost, less
market value, of such items used but not
consumed which remain the property of
Contractor.
c. Rentals of all construction equipment and
machinery, and the parts thereof whether rented
from Contractor or others in accordance with
rental agreements approved by Owner with the
advice of Engineer, and the costs of
transportation, loading, unloading, assembly,
dismantling, and removal thereof. All such costs
shall be in accordance with the terms of said
rental agreements. The rental of any such
equipment, machinery, or parts shall cease when
the use thereof is no longer necessary for the
Work.
d. Sales, consumer, use, and other similar taxes
related to the Work, and for which Contractor is
liable, imposed by Laws and Regulations.
e. Deposits lost for causes other than negligence
of Contractor, any Subcontractor, or anyone
directly or indirectly employed by any of them or
for whose acts any of them may be liable, and
royalty payments and fees for permits and
licenses.
.
.
.
.
losses shall include settlements made with the
written consent and approval of Owner. No such
losses, damages, and expenses shall be included
in the Cost of the Work for the purpose of
determining Contractor's fee.
g. The cost of utilities, fuel, and sanitary
facilities at the Site.
h. Minor expenses such as telegrams, long
distance telephone calls, telephone service at the
Site, expresses, and similar petty cash items in
connection with the Work.
i. The costs of premiums for all bonds and
insurance Contractor is required by the Contract
Documents to purchase and maintain.
B. Costs Excluded: The term Cost of the Work
shall not include any of the following items:
.
1. Payroll costs and other compensation of
Contractor's officers, executives, principals (of
partnerships and sole proprietorships), general managers,
safety managers, engineers, architects, estimators,
attorneys, auditors, accountants, purchasing and
contracting agents, expediters, timekeepers, clerks, and
other personnel employed by Contractor, whether at the
Site or in Contractor's principal or branch office for
general administration of the Work and not specifically
included in the agreed upon schedule of job classifications
referred to in Paragraph l1.01.A.l or specifically covered
by Paragraph l1.01.A.4, all of which are to be considered
administrative costs covered by the Contractor's fee.
2. Expenses of Contractor's principal and branch
offices other than Contractor's office at the Site.
3. Any part of Contractor's capital expenses,
including interest on Contractor's capital employed for
the Work and charges against Contractor for delinquent
payments.
4. Costs due to the negligence of Contractor, any
Subcontractor, or anyone directly or indirectly employed
by any of them or for whose acts any of them may be
liable, including but not limited to, the correction of
defective Work, disposal of materials or equipment
wrongly supplied, and making good any damage to
property.
5. Other overhead or general expense costs of
any kind and the costs of any item not specifically and
expressly included in Paragraphs 1 1.0 LA and 11.01.B.
.
C. Contractor's Fee: When all the Work is
performed on the basis of cost-plus, Contractor's fee shall
be determined as set forth in the Agreement. When the
value of any Work covered by a Change Order or when a
Claim for an adjustment in Contract Price is determined
on the basis of Cost of the Work, Contractor's fee shall be
determined as set forth in Paragraph l2.01.C.
D. Documentation: Whenever the Cost of the
Work for any purpose is to be determined pursuant to
Paragraphs 1 LOLA and 11.01.B, Contractor will establish
and maintain records thereof in accordance with generally
accepted accounting practices and submit in a form
acceptable to Engineer an itemized cost breakdown
together with supporting data.
11.02 Allowances
A. It is understood that Contractor has included
in the Contract Price all allowances so named in the
Contract Documents and shall cause the Work so covered
to be performed for such sums and by such persons or
entities as may be acceptable to Owner and Engineer.
B. Cash Allowances
1. Contractor agrees that:
a. the cash allowances include the cost to
Contractor (less any applicable trade discounts)
of materials and equipment required by the
allowances to be delivered at the Site, and all
applicable taxes; and
b. Contractor's costs for unloading and handling
on the Site, labor, installation , overhead, profit,
and other expenses contemplated for the cash
allowances have been included in the Contract
Price and not in the allowances, and no demand
for additional payment on account of any of the
foregoing will be valid.
C. Contingency Allowance
1. Contractor agrees that a contingency allowance, if any,
is for the sole use of Owner to cover unanticipated costs.
D. Prior to final payment, an appropriate Change
Order will be issued as recommended by Engineer to
reflect actual amounts due Contractor on account of Work
covered by allowances, and the Contract Price shall be
correspondingly adjusted.
11.03 Unit Price Work
A. Where the Contract Documents provide that
all or part of the Work is to be Unit Price Work, initially
the Contract Price will be deemed to include f9r all Unit
Price Work an amount equal to the sum of the unit price
for each separately identified item of Unit Price Work
times the estimated quantity of each item as indicated in
the Agreement.
B. The estimated quantities of items of Unit
Price Work are not guaranteed and are solely for the
purpose of comparison of Bids and determining an initial
Contract Price. Determinations of the actual quantities
and classifications of Unit Price Work performed by
Contractor will be made by Engineer subject to the
provisions of Paragraph 9.07.
00...52713-0012
Bozeman WRF Phase 1 Early Out Priority Improvements
00700 - 34
5f2212007
2. where the Work involved is not covered by
unit prices contained in the Contract Documents, by a
mutually agreed lump sum (which may include an
allowance for overhead and profit not necessarily in
accordance with Paragraph 12.01.C.2); or
00.. .52713-0012 Bozeman WRF Phase I Early Out Priority Improvements
00700 - 3S
C. Each unit price will be deemed to include an
amount considered by Contractor to be adequate to cover
Contractor's overhead and profit for each separately
identified item.
D. Owner or Contractor may make a Claim for
an adjustment in the Contract Price in accordance with
Paragraph 10.05 if:
1. the quantity of any item of Unit Price Work
perfonned by Contractor differs materially and
significantly from the estimated quantity of such item
indicated in the Agreement; and
2. there is no corresponding adjustment with
respect any other item of Work; and
I. the quantity of a oarticular item of Unit Price
Work perfonned bv Contractor differs by more than 25
percent from the estimated quantity of such item indicated
in the Agreement: and
2. the total cost of the particular individual item
of Unit Price Work amounts to 10 percent or more of the
Contract Price which is the total sum of all schedules (if
any): and
3. Contractor believes that Contractor is entitled
to an increase in Contract Price as a result of having
incurred additional expense or Owner believes that Owner
is entitled to a decrease in Contract Price and the parties
are unable to agree as to the amount of any such increase
or decrease.
ARTICLE 12 - CHANGE OF CONTRACT PRICE;
CHANGE OF CONTRACT TIMES
12.01 Change of Contract Price
A. The Contract Price may only be changed by a
Change Order. Any Claim for an adjustment in the
Contract Price shall be based on written notice submitted
by the party making the Claim to the Engineer and the
other party to the Contract in accordance with the
provisions of Paragraph 10.05.
B. The value of any Work covered by a Change
Order or of any Claim for an adjustment in the Contract
Price will be detennined as follows:
I. where the Work involved is covered by unit
prices contained in the Contract Documents, by
application of such unit prices to the quantities of the
items involved (subject to the provisions of Paragraph
11.03); or
3. where the Work involved is not covered by
unit prices contained in the Contract Documents and
agreement to a lump sum is not reached under Paragraph .
12.01.B.2, on the basis of the Cost of the Work
(detennined as provided in Paragraph 11.01) plus a
Contractor's fee for overhead and profit (detennined as
provided in Paragraph 12.01.C).
C. Contractor's Fee: The Contractor's fee for
overhead and profit shall be detennined as follows:
1. a mutually acceptable fixed fee; or
2. if a fixed fee is not agreed upon, then a fee
based on the following percentages of the various portions
of the Cost ofthe Work:
a. for costs incurred under Paragraphs II. 0 LA. I
and 11.01.A.2, the Contractor's fee shall be 15
percent;
b. for costs incurred under Paragraph 11.01.A.3,
the Contractor's fee shall be five percent;
c. where one or more tiers of subcontracts are on
the basis of Cost of the Work plus a fee and no
fixed fee is agreed upon, the intent of Paragraph
12.01.C.2.a is that the Subcontractor who
actually perfonns the Work, at whatever tier, will
be paid a fee of 15 percent of the costs incurred .
by such Subcontractor under Paragraphs
11.01Al and 11.01.A.2 and that any higher tier
Subcontractor and Contractor will each be paid a
fee of five percent of the amount paid to the next
lower tier Subcontractor;
d. no fee shall be payable on the basis of costs
itemized under Paragraphs 11.01.A.4, 11.01.A.5,
and 11.01.B;
e. the amount of credit to be allowed by
Contractor to Owner for any change which
results in a net decrease in cost will be the
amount of the actual net decrease in cost plus a
deduction in Contractor's fee by an amount equal
to five percent of such net decrease; and
f. when both additions and credits are involved
in anyone change, the adjustment in
Contractor's fee shall be computed on the basis
of the net change in accordance' with Paragraphs
12.0 I.C.2.a through 12.0 l.e2.e, inclusive.
D. Lump sum quotations for modifications to the
Work shall include substantiatinl! documentation with an
itemized breakdown of direct proiect related Contractor
and Subcontractor costs. includinl! labor. materials.
rentals. and approved services as summarized in
paral!faphs 11.0IA.I through 11.01.A.4: and overhead
and profit (fixed fee) as defined in paragraph 12.01.C.
.
5/22/2007
12.02 Change of Contract Times
.
A. The Contract Times may only be changed by
a Change Order. Any Claim for an adjustment in the
Contract Times shall be based on written notice submitted
by the party making the Claim to the Engineer and the
other party to the Contract in accordance with the
provisions of Paragraph 10.05.
B. Any adjustment of the Contract Times
covered by a Change Order or any Claim for an
adjustment in the Contract Times will be determined in
accordance with the provisions of this Article 12.
12.03 Delays
A. Where Contractor is prevented from
completing any part of the Work within the Contract
Times due to delay beyond the control of Contractor, the
Contract Times will be extended in an amount equal to
the time lost due to such delay if a Claim is made therefor
as provided in Paragraph 12.02.A. Delays beyond the
control of Contractor shall include, but not be limited to,
acts or neglect by Owner, acts or neglect of utility owners
or other contractors performing other work as
contemplated by Article 7, fires, floods, epidemics,
abnormal weather conditions, or acts of God.
.
B. If Owner, Engineer, or other contractors or
utility owners performing other work for Owner as
contemplated by Article 7, or anyone for whom Owner is
responsible, delays, disrupts, or interferes with the
performance or progress of the Work, then Contractor
shall be entitled to an equitable adjustment in the Contract
Price or the Contract Times , or both. Contractor's
entitlement to an adjustment of the Contract Times is
conditioned on such adjustment being essential to
Contractor's ability to complete the Work within the
Contract Times.
C. If Contractor is delayed in the performance or
progress of the Work by fire, flood, epidemic, abnormal
weather conditions, acts of God, acts or failures to act of
utility owners not under the control of Owner, or other
causes not the fault of and beyond control of Owner and
Contractor, then Contractor shall be entitled to an
equitable adjustment in Contract Times, if such
adjustment is essential to Contractor's ability to complete
the Work within the Contract Times. Such an adjustment
shall be Contractor's sole and exclusive remedy for the
delays described in this Paragraph 12.03.C.
.
D. Owner, Engineer and the Related Entities of
each of them shall not be liable to Contractor for any
claims, costs, losses, or damages (including but not
limited to all fees and charges of Engineers, architects,
attorneys, and other professionals and all court or
arbitration or other dispute resolution costs) sustained by
Contractor on or in connection with any other project or
anticipated project.
E. Contractor shall not be entitled to an
adjustment in Contract Price or Contract Times for delays
within the control of Contractor. Delays attributable to
and within the control of a Subcontractor or Supplier shall
be deemed to be delays within the control of Contractor.
F. Should the Contractor request a construction
shutdown due to the reasons listed in paragraph 12.03.A
and should a shutdown be aouroved by the Engineer and
Owner. all work on the oroiect shall cease. The Engineer
will not be available for work insoection during such
shutdowns and anv work completed by the Contractor
during such shutdown will not be acceoted by the
Engineer or Owner.
ARTICLE 13 TESTS AND INSPECTIONS;
CORRECTION, REMOVAL OR ACCEPTANCE OF
DEFECTIVE WORK
13.01 Notice of Defects
A. Prompt notice of all defective Work of which
Owner or Engineer has actual knowledge will be given to
Contractor. All defective Work may be rejected,
corrected, or accepted as provided in this Article 13.
13.02 Access to Work
A. Owner, Engineer, their consultants and other
representatives and personnel of Owner, independent
testing laboratories, and governmental agencies with
jurisdictional interests will have access to the Site and the
Work at reasonable times for their observation,
inspecting, and testing. Contractor shall provide them
proper and safe conditions for such access and advise
them of Contractor's Site safety procedures and programs
so that they may comply therewith as applicable.
13.03 Tests and Inspections
A. Contractor shall give Engineer timely notice
of readiness of the Work for all required inspections,
tests, or approvals and shall cooperate with inspection and
testing personnel to facilitate required inspections or tests.
B. Owner shall employ and pay for the services
of an independent testing laboratory to perform all
inspections, tests, or approvals required by the Contract
Documents except:
1. for inspections, tests, or approvals covered by
Paragraphs 13.03.C and 13.03.D below;
2. that costs incurred in connection with tests or
inspections conducted pursuant to Paragraph 13.04.B
shall be paid as provided in said Paragraph 13.04.C; and
3. as otherwise specifically provided in the
Contract Documents.
00...52713-0012
Bozeman WRF Phase 1 Early Out Priority Improvements
00700 - 36
5/2212007
C. If Laws or Regulations of any public body
having jurisdiction require any Work (or part thereof)
specifically to be inspected, tested, or approved by an
employee or other representative of such public body,
Contractor shall assume full responsibility for arranging
and obtaining such inspections, tests, or approvals, pay all
costs in connection therewith, and furnish Engineer the
required certificates of inspection or approval.
D. Contractor shall be responsible for arranging
and obtaining and shall pay all costs in connection with
any inspections, tests, or approvals required for Owner's
and Engineer's acceptance of materials or equipment to
be incorporated in the Work; or acceptance of materials,
mix designs, or equipment submitted for approval prior to
Contractor's purchase thereof for incorporation in the
Work. Such inspections, tests, or approvals shall be
perfonned by organizations acceptable to Owner and
Engineer.
E. If any Work (or the work of others) that is to
be inspected, tested, or approved is covered by Contractor
without written concurrence of Engineer, it must, if
requested by Engineer, be uncovered for observation.
F. Uncovering Work as provided in Paragraph
13.03.E shall be at Contractor's expense unless
Contractor has given Engineer timely notice of
Contractor's intention to cover the same and Engineer has
not acted with reasonable promptness in response to such
notice.
13.04 Uncovering Work
A. If any Work is covered contrary to the written
request of Engineer, it must, if requested by Engineer, be
uncovered for Engineer's observation and replaced at
Contractor's expense.
B. If Engineer considers it necessary or advisable
that covered Work be observed by Engineer or inspected
or tested by others, Contractor, at Engineer's request,
shall uncover, expose, or otherwise make available for
observation, inspection, or testing as Engineer may
require, that portion of the Work in question, furnishing
all necessary labor, material, and equipment.
C. If it is found that the uncovered Work is
defective, Contractor shall pay all claims, costs, losses,
and damages (including but not limited to all fees and
charges of engineers, architects, attorneys, and other
professionals and all court or arbitration or other dispute
resolution costs) arising out of or relating to such
uncovering, exposure, observation, inspection, and
testing, and of satisfactory replacement or reconstruction
(including but not limited to all costs of repair or
replacement of work of others); and Owner shall be
entitled to an appropriate decrease in the Contract Price. If
the parties are unable to agree as to the amount thereof,
Owner may make a Claim therefor as provided in
Paragraph 10.05.
00...52713-0012
D. If, the uncovered Work is not found to be
defective, Contractor shall be allowed an increase in the
Contract Price or an extension of the Contract Times, or .
both, directly attributable to such uncovering, exposure,
observation, inspection, testing, replacement, and
reconstruction. If the parties are unable to agree as to the
amount or extent thereof, Contractor may make a Claim
therefor as provided in Paragraph 10.05.
13.05 Owner May Stop the Work
A. If the Work is defective, or Contractor fails to
supply sufficient skilled workers or suitable materials or
equipment, or fails to perfonn the Work in such a way
that the completed Work will confonn to the Contract
Documents, Owner may order Contractor to stop the
Work, or any portion thereof, until the cause for such
order has been eliminated; however, this right of Owner
to stop the Work shall not give rise to any duty on the part
of Owner to exercise this right for the benefit of
Contractor, any Subcontractor, any Supplier, any other
individual or entity, or any surety for, or employee or
agent of any of them.
13.06 Correction or Removal of Defective Work
A. Promptly after receipt of notice, Contractor
shall correct all defective Work, whether or not
fabricated, installed, or completed, or, if the Work has
been rejected by Engineer, remove it from the Project and .
replace it with Work that is not defective. Contractor shall
pay all claims, costs, losses, and damages (including but
not limited to all fees and charges of engineers, architects,
attorneys, and other professionals and all court or
arbitration or other dispute resolution costs) arising out of
or relating to such correction or removal (including but
not limited to all costs of repair or replacement of work of
others).
B. When correcting defective Work under the
tenns of this Paragraph 13.06 or Paragraph 13.07,
Contractor shall take no action that would void or
otherwise impair Owner's special warranty and guarantee,
ifany, on said Work.
13.07 Correction Period
A. If within one year after the date of Substantial
Completion (or such longer period of time as may be
prescribed by the tenns of any applicable special
guarantee required by the Contract Documents) or by any
specific provision of the Contract Documents, any Work
is found to be defective, or if the repair of any damages to
the land or areas made available for Contractor's use by
Owner or pennitted by Laws and Regulations as
contemplated in Paragraph 6.11.A is found to be
defective, Contractor shall promptly, without cost to
Owner and in accordance with Owner's written
instructions:
.
Bozeman WRF Phase 1 Early Out Priority Improvements
00700 . 37
5/22/2007
A. If, instead of requiring correction or removal
and replacement of defective Work, Owner (and, prior to
Engineer's recommendation of final payment, Engineer)
prefers to accept it, Owner may do so. Contractor shall
pay all claims, costs, losses, and damages (including but
not limited to all fees and charges of engineers, architects,
attorneys, and other professionals and all court or
arbitration or other dispute resolution costs) attributable to
Owner's evaluation of and determination to accept such D. Contractor shall not be allowed an extension
defective Work (such costs to be approved by Engineer as of the Contract Times because of any delay in the
to reasonableness) and the diminished value of the Work performance of the Work attributable to the exercise by
to the extent not otherwise paid by Contractor pursuant to Owner of Owner's rights and remedies under this
this sentence. If any such acceptance occurs prior to Paragraph 13.09.
00.. .52713.0012 Bozeman WRF Phase 1 Early Out Priority Improvements
00700 - 38
1. repair such defective land or areas; or
.
2. correct such defective Work; or
3. if the defective Work has been rejected by
Owner, remove it from the Project and replace it with
Work that is not defective, and
4. satisfactorily correct or repair or remove and
replace any damage to other Work, to the work of others
or other land or areas resulting therefrom.
B. If Contractor does not promptly comply with
the terms of Owner's written instructions, or in an
emergency where delay would cause serious risk of loss
or damage, Owner may have the defective Work
corrected or repaired or may have the rejected Work
removed and replaced. All claims, costs, losses, and
damages (including but not limited to all fees and charges
of engineers, architects, attorneys, and other professionals
and all court or arbitration or other dispute resolution
costs) arising out of or relating to such correction or repair
or such removal and replacement (including but not
limited to all costs of repair or replacement of work of
others) will be paid by Contractor.
.
C. In special circumstances where a particular
item of equipment is placed in continuous service before
Substantial Completion of all the Work, the correction
period for that item may start to run from an earlier date if
so provided in the Specifications.
D. Where defective Work (and damage to other
Work resulting therefrom) has been corrected or removed
and replaced under this Paragraph 13.07, the correction
period hereunder with respect to such Work will be
extended for an additional period of one year after such
correction or removal and replacement has been
satisfactorily completed.
E. Contractor's obligations under this Paragraph
13.07 are in addition to any other obligation or warranty.
The provisions of this Paragraph 13.07 shall not be
construed as a substitute for or a waiver of the provisions
of any applicable statute of limitation or repose.
13.08
Acceptance of Defective Work
.
Engineer's recommendation of final payment, a Change
Order will be issued incorporating the necessary revisions
in the Contract Documents with respect to the Work, and
Owner shall be entitled to an appropriate decrease in the
Contract Price, reflecting the diminished value of Work
so accepted. If the parties are unable to agree as to the
amount thereof, Owner may make a Claim therefor as
provided in Paragraph 10.05. If the acceptance occurs
after such recommendation, an appropriate amount will be
paid by Contractor to Owner.
13.09 Owner May Correct Defective Work
A. If Contractor fails within a reasonable time
after written notice from Engineer to correct defective
Work or to remove and replace rejected Work as required
by Engineer in accordance with Paragraph 13.06.A, or if
Contractor fails to perform the Work in accordance with
the Contract Documents, or if Contractor fails to comply
with any other provision of the Contract Documents,
Owner may, after seven days written notice to Contractor,
correct or remedy any such deficiency.
B. In exercising the rights and remedies under
this Paragraph 13.09, Owner shall proceed expeditiously.
Tn connection with such corrective or remedial action,
Owner may exclude Contractor from all or part of the
Site, take possession of all or part of the Work and
suspend Contractor's services related thereto, take
possession of Contractor's tools, appliances, construction
equipment and machinery at the Site, and incorporate in
the Work all materials and equipment stored at the Site or
for which Owner has paid Contractor but which are stored
elsewhere. Contractor shall allow Owner, Owner's
representatives, agents and employees, Owner's other
contractors, and Engineer and Engineer's consultants
access to the Site to enable Owner to exercise the rights
and remedies under this Paragraph.
C. All claims, costs, losses, and damages
(including but not limited to all fees and charges of
engineers, architects, attorneys, and other professionals
and all court or arbitration or other dispute resolution
costs) incurred or sustained by Owner in exercising the
rights and remedies under this Paragraph 13.09 will be
charged against Contractor, and a Change Order will be
issued incorporating the necessary revisions in the
Contract Documents with respect to the Work; and Owner
shall be entitled to an appropriate decrease in the Contract
Price. If the parties are unable to agree as to the amount of
the adjustment, Owner may make a Claim therefor as
provided in Paragraph 10.05. Such claims, costs, losses
and damages will include but not be limited to all costs of
repair, or replacement of work of others destroyed or
damaged by correction, removal, or replacement of
Contractor's defective Work.
5/22/2007
ARTICLE 14 - PAYMENTS TO CONTRACTOR AND
COMPLETION
14.01 Schedule of Values
A. The Schedule of Values established as
provided in Paragraph 2.07.A will serve as the basis for
progress payments and will be incorporated into a fonn of
Application for Payment acceptable to Engineer. Progress
payments on account of Unit Price Work will be based on
the number of units completed.
14.02 Progress Payments
A. Applications for Payments
1. At least 20 days before the date
established in the Agreement for each progress
payment (but not more often than once a month),
Contractor shall submit to Engineer for review an
Application for Payment filled out and signed by
Contractor covering the Work completed as of the
date of the Application and accompanied by such
supporting documentation as is required by the
Contract Documents. If payment is requested on the
basis of materials and equipment not incorporated in
the Work but delivered and suitably stored at the Site
or at another location agreed to in writing, the
Application for Payment shall also be accompanied
by a bill of sale, invoice, or other documentation
warranting that Owner has received the materials and
equipment free and clear of all Liens and evidence
that the materials and equipment are covered by
appropriate property insurance or other arrangements
to protect Owner's interest therein, all of which must
be satisfactory to Owner. Payments for materials in
storage shall be based only upon the actual cost of
the materials and egui\:lment to Contractor and shall
not include any overhead or profit. Bill of Sale.
invoice or other document warranting clear title for
materials in storae:e will be waived for the material in
storage included in the first progress payment
application. However. proof of payment and clear
title must be submitted with Application No.2 for all
material included in Application No.1. Without
such documentation amounts paid for materials in
storage will be deducted from subseauent pavrnents.
Bee:innine: with the second application. all reauests
for pavrnent for materials in storage shall be
accompanied by Bill of Sale. invoice or other
document warranting clear title as required above.
2. Beginning with the seoond Application for
Payment, each f.pplicatiofi shall include an affidavit Elf
Contractor stating that all previous progress payments
received on account of ~he Work have been applied on
accel:lflt te discharge Contractor's legitimate obligations
associated with prier }\.pplications for Payment.
3. The amount of retainage with respect to
progress payments will be as stipulated in the Agreement.
00.. .52713-0012
2. Each application for progress pavment shall be
accompanied bv Contractor's updated schedule of
operations. or progress report. with such shop drawings
schedules. procurement schedules. value of materials on
hand included in a\:lplication. and other data specified
herein or reasonably required by Owner or Engineer. The
Owner reserves the rie:ht to require submission of monthly
certified payrolls by the Contractor. After the first
progress payment which requests payment for materials in
stora€!:e has been made bv the Contractor to the Owner,
the Contractor must submit with the following month's
pavrnent reauest. evidence satisfactory to the Owner that
such material has been paid for. Failure to provide this
evidence with the first request and subsequent requests
will result in withholdin!!: from subsequent progress
vavments the amount in dispute requested for materials in
storage in accordance with Paragraph I4.02B.
.
3. The Owner may retain a portion of the amount
otherwise due the Contractor. Except as state law
otherwise provides. the amount retained by the Owner
shall be as stipulated in the Agreement. In accordance
with state law the Owner may accept deposited securities
in lieu of cash retainage. Retainae:e may be used bv the
Owner to offset costs for any of the losses enumerated in
Paragraphs 14.02.B.5.a throue:h 14.02.B.5.d inclusive.
14.02.D.1.a through 14.02.D.1.d inclusive. or I5.0l.C. In
addition. retainage may be used bv the Owner to protect
against loss from failure by the Contractor to complete
necessarY work and to offset any liquidated damae:es due
Owner.
.
4. Liquidated damages for unscheduled
employment of the Ene:ineer shall be calculated at the
hourly rates indicated in the Bid Fonn. Liquidated
damages shall be paid bv deduction from monthly progress
pay estimates and the fmal pay estimate. as the liquidated
damages are incurred.
5. Each application for pro!!:ress \:layment shall be
accompanied bv a statement of certification by the
Contractor that no claim exists ae:ainst the Owner or
En!!:ineer unless exoresslv stated otherwise: that the
pavrnent claimed represents the actual value of the work
accomplished: that the work accomplished and materials
supplied are in accordance with the Contract Documents:
that the auantities claimed were properly determined: and
that all labor provisions have been complied with in full.
B. Review of Applications
1. Engineer will, within 10 days after receipt of
each Application for Payment, either indicate in writing a
recommendation of payment and present the Application
to Owner or return the Application to Contractor
indicating in writing Engineer's reasons for refusing to
recommend payment. In the latter case, Contractor may
make the necessary corrections and resubmit the
Application.
.
2. Engineer's recommendation of any payment
requested in an Application for Payment will constitute a
representation by Engineer to Owner, based on Engineer's
Bozeman WRF Phase 1 Early Out Priority Improvements
00700 - 39
5/22/2007
.
observations on the Site of the executed Work as an
experienced and qualified design professional and on
Engineer's review of the Application for Payment and the
accompanying data and schedules, that to the best of
Engineer's knowledge, information and belief:
a. the Work has progressed to the point
indicated;
b. the quality of the Work is generally in
accordance with the Contract Documents
(subject to an evaluation of the Work as a
functioning whole prior to or upon Substantial
Completion, to the results of any subsequent
tests called for in the Contract Documents, to a
final determination of quantities and
classifications for Unit Price Work under
Paragraph 9.07, and to any other qualifications
stated in the recommendation); and
c. the conditions precedent to Contractor's being
entitled to such payment appear to have been
fulfilled in so far as it is Engineer's
responsibility to observe the Work.
3. By recommending any such payment Engineer
will not thereby be deemed to have represented that:
.
a. inspections made to check the quality or the
quantity of the Work as it has been performed
have been exhaustive, extended to every aspect
of the Work in progress, or involved detailed
inspections of the Work beyond the
responsibilities specifically assigned to Engineer
in the Contract Documents; or
b. that there may not be other matters or issues
between the parties that might entitle Contractor
to be paid additionally by Owner or entitle
Owner to withhold payment to Contractor.
4. Neither Engineer's review of Contractor's
Work for the purposes of recommending payments nor
Engineer's recommendation of any payment, including
final payment, will impose responsibility on Engineer:
a. to supervise, direct, or control the Work, or
b. for the means, methods, techniques,
sequences, or procedures of construction, or the
safety precautions and programs incident thereto,
or
.
c. for Contractor's failure to comply with Laws
and Regulations applicable to Contractor's
performance ofthe Work, or
d. to make any examination to ascertain how or
for what purposes Contractor has used the
moneys paid on account of the Contract Price, or
e. to determine that title to any of the Work,
materials, or equipment has passed to Owner free
and clear of any Liens.
5. Engineer may refuse to recommend the whole
or any part of any payment if, in Engineer's opinion, it
would be incorrect to make the representations to Owner
stated in Paragraph 14.02.B.2. Engineer may also refuse
to recommend any such payment or, because of
subsequently discovered evidence or the results of
subsequent inspections or tests, revise or revoke any such
payment recommendation previously made, to such extent
as may be necessary in Engineer's opinion to protect
Owner from loss because:
a. the Work is defective, or completed Work has
been damaged, requiring correction or
replacement;
b. the Contract Price has been reduced by
Change Orders;
c. Owner has been required to correct defective
Work or complete Work in accordance with
Paragraph 13.09; or
d. Engineer has actual knowledge of the
occurrence of any of the events enumerated in
Paragraph 15.02A
C. Payment Becomes Due
I. Ten days after presentation of the Application
for Payment to Owner with Engineer's recommendation,
the amount recommended will (subject to the provisions
of Paragraph 14.02.D) become due, and when due will be
paid by Owner to Contractor.
D. Reduction in Payment
1. Owner may refuse to make payment of the full
amount recommended by Engineer because:
a. claims have been made
account of Contractor's
furnishing of the Work;
against Owner on
performance or
b. Liens have been filed in connection with the
Work, except where Contractor has delivered a
specific bond satisfactory to Owner to secure the
satisfaction and discharge of such Liens;
c. there are other items entitling Owner to a
set-off against the amount recommended,
including liquidated damages: or
d. Owner has actual knowledge of the occurrence
of any of the events enumerated in Paragraphs
14.02.B.5.a through 14.02.B.5.c or Paragraph
15.02.A.
00...52713-0012
Bozeman WRF Phase 1 Early Out Priority Improvements
00700 - 40
5/22/2007
2. If Owner refuses to make payment of the full
amount recommended by Engineer, Owner will give
Contractor immediate written notice (with a copy to
Engineer) stating the reasons for such action and promptly
pay Contractor any amount remaining after deduction of
the amount so withheld. Owner shall promptly pay
Contractor the amount so withheld, or any adjustment
thereto agreed to by Owner and Contractor, when
Contractor corrects to Owner's satisfaction the reasons for
such action.
3. If it is subsequently detennined that Owner's
refusal of payment was not justified, the amount
wrongfully withheld shall be treated as an amount due as
detennined by Paragraph 14.02.C.l.
14.03 Contractor's Warranty of Title
A. Contractor warrants and guarantees that title
to all Work, materials, and equipment covered by any
Application for Payment, whether incorporated in the
Project or not, will pass to Owner no later than the time of
payment free and clear of all Liens.
B. Neither recommendation of anv proe:ress
pavment bv Ene:ineer. nor pavment bv the Owner to
Contractor. nor anv use or occupancv of the Work or any
part thereof will release the Contractor from complying
with the Contract Documents. Specifically the Contractor
shall maintain in accordance with Article 5. mooertv
insurance on all Work. materials. and equipment whether
incorporated in the proiect or not and whether included in
an application for payment or not. for the full insurable
value thereof. Passing title to Owner for materials and
equipment included in an application for payment does
not relieve the Contractor of the Contractor's oblie:ation to
provide insurance (including property insurance), as
required in Article 5 of these General Conditions and the
Supplementary Conditions. All insurance shall remain in
effect as provided in Article 5.
14.04 Substantial Completion
A. When Contractor considers the entire Work
ready for its intended use Contractor shall notify Owner
and Engineer in writing that the entire Work is
substantially complete (except for items specifically listed
by Contractor as incomplete) and request that Engineer
issue a certificate of Substantial Completion.
B. Promptly after Contractor's notification,
Owner, Contractor, and Engineer shall make an
inspection of the Work to detennine the status of
completion. If Engineer does not consider the Work
substantially complete, Engineer will notify Contractor in
writing giving the reasons therefor.
C. If Engineer considers the Work substantially
complete, Engineer will deliver to Owner a tentative
certificate of Substantial Completion which shall fix the
date of Substantial Completion. There shall be attached to
the certificate a tentative list of items to be completed or
00...52713-0012
corrected before fmal payment. Owner shall have seven
days after receipt of the tentative certificate during which
to make written objection to Engineer as to any provisions .
of the certificate or attached list. If, after considering such
objections, Engineer concludes that the Work is not
substantially complete, Engineer will within 14 days after
submission of the tentative certificate to Owner notify
Contractor in writing, stating the reasons therefor. If, after
consideration of Owner's objections, Engineer considers
the Work substantially complete, Engineer will within
said 14 days execute and deliver to Owner and Contractor
a defmitive certificate of Substantial Completion (with a
revised tentative list of items to be completed or
corrected) reflecting such changes from the tentative
certificate as Engineer believes justified after
consideration of any objections from Owner.
D. At the time of delivery of the tentative
certificate of Substantial Completion, Engineer will
deliver to Owner and Contractor a written
recommendation as to division of responsibilities pending
final payment between Owner and Contractor with
respect to security, operation, safety, and protection of the
Work, maintenance, heat, utilities, insurance, and
warranties and guarantees. Unless Owner and Contractor
agree otherwise in writing and so infonn Engineer in
writing prior to Engineer's issuing the definitive
certificate of Substantial Completion, Engineer's
aforesaid recommendation will be binding on Owner and
Contractor until final payment. .
E. Owner shall have the right to exclude
Contractor from the Site after the date of Substantial
Completion subject to allowing Contractor reasonable
access to complete or correct items on the tentative list.
14.05 Partial Utilization
A. Prior to Substantial Completion of all the
Work, Owner may use or occupy any substantially
completed part of the Work which has specifically been
identified in the Contract Documents, or which Owner,
Engineer, and Contractor agree constitutes a separately
functioning and usable part of the Work that can be used
by Owner for its intended purpose without significant
interference with Contractor's performance of the
remainder of the Work, subject to the following
conditions.
1. Owner at any time may request Contractor in
writing to pennit Owner to use or occupy any such part of
the Work which Owner believes to be ready for its
intended use and substantially complete. If and when
Contractor agrees that such part of the Work is
substantially complete, Contractor will certify to Owner
and Engineer that such part of the Work is substantially .
complete and request Engineer to issue a certificate of
Substantial Completion for that part of the Work.
Bozeman WRF Phase 1 Early Out Priority Improvements
00700 - 41
5/22/2007
.
2. Contractor at any time may notifY Owner and
Engineer in writing that Contractor considers any such
part of the Work ready for its intended use and
substantially complete and request Engineer to issue a
certificate of Substantial Completion for that part of the
Work.
3. Within a reasonable time after either such
request, Owner, Contractor, and Engineer shall make an
inspection of that part of the Work to determine its status
of completion. If Engineer does not consider that part of
the Work to be substantially complete, Engineer will
notify Owner and Contractor in writing giving the reasons
therefor. If Engineer considers that part of the Work to be
substantially complete, the provisions of Paragraph 14.04
will apply with respect to certification of Substantial
Completion of that part of the Work and the division of
responsibility in respect thereof and access thereto.
4. No use or occupancy or separate operation of
part ofthe Work may occur prior to compliance with the
requirements of Paragraph 5.10 regarding property
insurance.
.
B. Owner has the right to take possession of or
use anv completed or substantiallv completed portions of
the work at any time. but such taking possession or use
will not be deemed an acceptance of anv work not
completed in accordance with the Contract Documents.
Owner's use of any facilities so identified in the Contract
Documents will not be grounds for extension of the
contract time or change in the contract orice. Owner's
use of any facilities not specifically identified in the
Contract Documents will be in accordance with
conditions agreed to prior to such use. and any extra costs
or delays in completion incurred and oroperly claimed by
Contractor will be equitably adiusted with a Change
Order. Facilities substantially completed in accordance
with the Contract Documents which are occupied or used
by Owner prior to substantial completion of the entire
work will be done in accordance with Article 14.04.
Guarantee periods for accepted or substantially completed
work including mechanical and electrical equipment will
commence upon the start of continuous use by Owner.
All tests and instruction of Owner's personnel must be
satisfactorily completed. and Owner shall assume
responsibility for and operation of all facilities occupied
or used exceot as may arise through portions of work not
vet comt'leted bv Contractor. If the work has been
substantially completed and the Engineer certifies that full
completion thereof is materially delayed through no fault
of the Contractor. the Owner shall. without terminating
the Agreement. make payment of the balance due for the
portion ofthe work fullv completed and accepted.
14.06
Final Inspection
.
A. Upon written notice from Contractor that the
entire Work or an agreed portion thereof is complete,
Engineer will promptly make a final inspection with
Owner and Contractor and will notify Contractor in
writing of all particulars in which this inspection reveals
00...52713-0012
that the Work is incomplete or defective. Contractor shall
immediately take such measures as are necessary to
complete such Work or remedy such deficiencies.
B. After Contractor has remedied all deficiencies
to the satisfaction of the Owner and Engineer and
delivered all construction records. maintenance and
operating instructions. schedules. guarantees. bonds.
certificates of inspection. and other documents (all as
required by the Contract Documents). Owner and
Contractor shall be oromptly notified in writing bv
Engineer that the work is acceptable.
14.07
Final Payment
A. Application for Payment
1. After Contractor has, in the opinion of
Engineer, satisfactorily completed all corrections
identified during the [mal inspection and has delivered, in
accordance with the Contract Documents, all maintenance
and operating instructions, schedules, guarantees, bonds,
certificates or other evidence of insurance certificates of
inspection, marked~up record documents (as provided in
Paragraph 6.12), and other documents, Contractor may
make application for final payment following the
procedure for progress payments.
2. The final Application for Payment shall be
accompanied (except as previously delivered) by:
a. all documentation called for in the Contract
Documents, including but not limited to the
evidence of insurance required by Paragraph
5.04.B.7;
b. consent of the surety, if any, to final payment;
c. a list of all Claims against Owner that
Contractor believes are unsettled; and
d. complete and legally effective releases or
waivers (satisfactory to Owner) of all Lien rights
arising out of or Liens filed in connection with
the Work.
3. In lieu of the releases or waivers of Liens
specified in Paragraph 14.07.A.2 and as approved by
Owner, Contractor may furnish receipts or releases in full
and an affidavit of Contractor that: (i) the releases and
receipts include all labor, services, material, and
equipment for which a Lien could be filed; and (ii) all
payrolls, material and equipment bills, and other
indebtedness connected with the Work for which Owner
or Owner's property might in any way be responsible have
been paid or otherwise satisfied. If any Subcontractor or
Supplier fails to furnish such a release or receipt in full,
Contractor may furnish a bond or other collateral
satisfactory to Owner to indemnify Owner against any
Lien.
Bozeman WRF Phase 1 Early Out Priority Improvements
00700 . 42
5/22/2007
B. Engineer's Review of Application and
Acceptance
1. If, on the basis of Engineer's observation of
the Work during construction and [mal inspection, and
Engineer's review of the final Application for Payment
and accompanying documentation as required by the
Contract Documents, Engineer is satisfied that the Work
has been completed and Contractor's other obligations
under the Contract Documents have been fulfilled,
Engineer will, within ten days after receipt of the final
Application for Payment, indicate in writing Engineer's
recommendation of payment and present the Application
for Payment to Owner for payment. At the same time
Engineer will also give written notice to Owner and
Contractor that the Work is acceptable subject to the
provisions of Paragraph 14.09. Otherwise, Engineer will
return the Application for Payment to Contractor,
indicating in writing the reasons for refusing to
recommend final payment, in which case Contractor shall
make the necessary corrections and resubmit the
Application for Payment.
C. Payment Becomes Due
I. Thirty days after the presentation to Owner of
the Application for Payment and accompanying
documentation, the amount recommended by Engineer,
less any sum Owner is entitled to set off against
Engineer's recommendation, including but not limited to
liquidated damages, will become due and , will be paid by
Owner to Contractor.
14.08 Final Completion Delayed
A. If, through no fault of Contractor, final
completion of the Work is significantly delayed, and if
Engineer so confirms, Owner shall, upon receipt of
Contractor's final Application for Payment (for Work
fully completed and accepted) and recommendation of
Engineer, and without terminating the Contract, make
payment of the balance due for that portion of the Work
fully completed and accepted. If the remaining balance to
be held by Owner for Work not fully completed or
corrected is less than the retainage stipulated in the
Agreement, and if bonds have been furnished as required
in Paragraph 5.01, the written consent of the surety to the
payment of the balance due for that portion of the Work
fully completed and accepted shall be submitted by
Contractor to Engineer with the Application for such
payment. Such payment shall be made under the terms
and conditions governing final payment, except that it
shall not constitute a waiver of Claims.
14.09 Waiver of Claims
A. The making and acceptance of final payment
will constitute:
I. a waiver of all Claims by Owner against
Contractor, except Claims arising from unsettled Liens,
from defective Work appearing after final inspection
pursuant to Paragraph 14.06, from failure to comply with
the Contract Documents or the terms of any special
guarantees specified therein, or from Contractor's
continuing obligations under the Contract Documents;
and
.
2. a waiver of all Claims by Contractor against
Owner other than those previously made in accordance
with the requirements herein and expressly acknowledged
by Owner in writing as still unsettled.
ARTICLE IS - SUSPENSION OF WORK AND
TERMINATION
15.01 Owner May Suspend Work
A. At any time and without cause, Owner may
suspend the Work or any portion thereof for a period of
not more than 90 consecutive days by notice in writing to
Contractor and Engineer which will fix the date on which
Work will be resumed. Contractor shall resume the Work
on the date so fixed. Contractor shall be granted an
adjustment in the Contract Price or an extension of the
Contract Times, or both, directly attributable to any such
suspension if Contractor makes a Claim therefor as
provided in Paragraph 10.05.
.
15.02 Owner May Terminatefor Cause
A. If the Contractor fails to comolete the work
required by the Contract Documents. or upon +he
occurrence of anyone or more of the following events,
will justifY termination. the Owner may terminate the
Agreement relatine: to the whole Work or any portion
thereof for cause:
1. Contractor's persistent failure to perform the
Work in accordance with the Contract Documents
(including, but not limited to, failure to supply sufficient
skilled workers or suitable materials or equipment or
failure to adhere to the Progress Schedule established
under Paragraph 2.07 as adjusted from time to time
pursuant to Paragraph 6.04);
2. Contractor's disregard of Laws or Regulations
of any public body having jurisdiction;
3. Contractor's disregard of the authority of
Engineer; or
4. Contractor's violation in any substantial way
of any provisions of the Contract Documents.
.
B. If one or more of the events identified in
Paragraph 15.02.A occur, Owner may, after giving
Contractor (and surety) seven days written notice of its
intent to terminate the services of Contractor:
00.. .52713-0012
Bozeman WRF Phase 1 Early Out Priority Improvements
00700 . 43
5/22/2007
.
1. exclude Contractor from the Site, and take
possession of the Work and of all Contractor's tools,
appliances, construction equipment, and machinery at the
Site, and use the same to the full extent they could be
used by Contractor (without liability to Contractor for
trespass or conversion),
2. incorporate in the Work all materials and
equipment stored at the Site or for which Owner has paid
Contractor but which are stored elsewhere, and
3. complete the Work as Owner may deem
expedient.
.
C. If Owner proceeds as provided in Paragraph
15.02.B, Contractor shall not be entitled to receive any
further payment until the Work is completed. If the
unpaid balance of the Contract Price exceeds all claims,
costs, losses, and damages (including but not limited to all
fees and charges of engineers, architects, attorneys, and
other professionals and all court or arbitration or other
dispute resolution costs) sustained by Owner arising out
of or relating to completing the Work, such excess will be
paid to Contractor. If such claims, costs, losses, and
damages exceed such unpaid balance, Contractor shall
pay the difference to Owner. Such claims, costs, losses,
and damages incurred by Owner will be reviewed by
Engineer as to their reasonableness and, when so
approved by Engineer, incorporated in a Change Order.
When exercising any rights or remedies under this
Paragraph Owner shall not be required to obtain the
lowest price for the Work performed.
D. Notwithstanding Paragraphs 15.02.B and
I5.02.C, Contractor's services will not be terminated if
Contractor begins within seven days of receipt of notice
of intent to terminate to correct its failure to perform and
proceeds diligently to cure such failure within no more
than 30 days of receipt of said notice.
E. Where Contractor's services have been so
terminated by Owner, the termination will not affect any
rights or remedies of Owner against Contractor then
existing or which may thereafter accrue. Any retention or
payment of moneys due Contractor by Owner will not
release Contractor from liability.
F. If and to the extent that Contractor has
provid~d a performance bOJ).d under the provisions of
Paragraph 5.01.A, the termination procedures of that bond
shall supersede the provisions of Paragraphs 15.02.B and
I5.02.C.
15.03 Owner May Terminate For Convenience
.
A. Upon seven days written notice to Contractor
and Engineer, Owner may, without cause and without
prejudice to any other right or remedy of Owner,
terminate the Contract. In such case, Contractor shall be
paid for (without duplication of any items):
00__.52713-0012
1. completed and acceptable Work executed in
accordance with the Contract Documents prior to the
effective date of termination, including fair and
reasonable sums for overhead and profit on such Work;
2. expenses sustained prior to the effective date
of termination in performing services and furnishing
labor, materials, or equipment as required by the Contract
Documents in connection with uncompleted Work, plus
fair and reasonable sums for overhead and profit on such
expenses;
3. all claims, costs, losses, and damages
(including but not limited to all fees and charges of
engineers, architects, attorneys, and other professionals
and all court or arbitration or other dispute resolution
costs) incurred in settlement of terminated contracts with
Subcontractors, Suppliers, and others; and
4. reasonable expenses directly attributable to
termination.
B. Contractor shall not be paid on account of loss
of anticipated profits or revenue or other economic loss
arising out of or resulting from such termination.
15.04 Contractor May Stop Work or Terminate
A. If, through no act or fault of Contractor, (i)
the Work is suspended for more than 90 consecutive days
by Owner or under an order of court or other public
authority, or (ii) Engineer fails to act on any Application
for Payment within 30 days after it is submitted, or (iii)
Owner fails for 30 days to pay Contractor any sum finally
determined to be due, then Contractor may, upon seven
days written notice to Owner and Engineer, and provided
Owner or Engineer do not remedy such suspension or
failure within that time, terminate the Contract and
recover from Owner payment on the same terms as
provided in Paragraph 15.03.
B. In lieu of terminating the Contract and
without prejudice to any other right or remedy, if
Engineer has failed to act on an Application for Payment
within 30 days after it is submitted, or Owner has failed
for 30 days to pay Contractor any sum fmally determined
to be due, Contractor may, seven days after written notice
to Owner and Engineer, stop the Work until payment is
made of all such amounts due Contractor, including
interest thereon. The provisions of this Paragraph 15.04
are not intended to preclude Contractor from making a
Claim under Paragraph 10.05 for an adjustment in
Contract Price or Contract Times or otherwise for
expenses or damage directly attributable to Contractor's
stopping the Work as permitted by this Paragraph.
Bozeman WRF Phase I Early Out Priority Improvements
00700 - 44
5(22/2007
ARTICLE 16 - DISPUTE RESOLUTION
16.01 Methods and Procedures
A. Either Owner or Contractor may request
mediation of any Claim submitted to Engineer for a
decision under Paragraph 10.05 before such decision
becomes final and binding. The mediation will be
governed by the Construction Industry Mediation Rules
of the American Arbitration Association in effect as of the
Effective Date of the Agreement. The request for
mediation shall be submitted in writing to the American
Arbitration Association and the other party to the
Contract. Timely submission of the request shall stay the
effect of Paragraph lO.05.E.
B. Owner and Contractor shall participate in the
mediation process in good faith. The process shall be
concluded within 60 days of filing of the request. The
date of termination of the mediation shall be determined
by application of the mediation rules referenced above.
C. If the Claim is not resolved by mediation,
Engineer's action under Paragraph lO.05.C or a denial
pursuant to Paragraphs 10.05.C.3 or lO.05.D shall become
final and binding 30 days after termination of the
mediation unless, within that time period, Owner or
Contractor:
I. elects in writing to invoke any dispute
resolution process provided for in the Supplementary
Conditions, or
2. agrees with the other party to submit the
Claim to another dispute resolution process, or
3. gives written notice to the other party of their
intent to submit the Claim to a court of competent
jurisdiction.
ARTICLE 17 - MISCELLANEOUS
17.01 Giving Notice
A. Whenever any provISIOn of the Contract
Documents requires the giving of written notice, it will be
deemed to have been validly given if:
I. delivered in person to the individual or to a
member of the firm or to an officer of the corporation for
whom it is intended, or
2. delivered at or sent by registered or certified
mail, postage prepaid, to the last business address known
to the giver of the notice.
00...52713-0012
B. The business address for e:iving notices of
Contractor given in the Agreement is hereby desie:nated
as the Dlace to which all notices. letters. and other .
communication to Contractor will be mailed or delivered.
The address for giving notices to Owner given in the
Agreement is herebv designated as the Dlace to which all
notices. letters. and other communication to Owner shall
be mailed or delivered. Either party may change its
address at any time bv an instrument in writine: delivered
to Engineer and to the other party.
17.02 Computation of Times
A. When any period of time is referred to in the
Contract Documents by days, it will be computed to
exclude the first and include the last day of such period. If
the last day of any such period falls on a Saturday or
Sunday or on a day made a legal holiday by the law of the
applicable jurisdiction, such day will be omitted from the
computation.
17.03 Cumulative Remedies
A. The duties and obligations imposed by these
General Conditions and the rights and remedies available
hereunder to the parties hereto are in addition to, and are
not to be construed in any way as a limitation of, any
rights and remedies available to any or all of them which
are otherwise imposed or available by Laws or
Regulations, by special warranty or guarantee, or by other .
provisions of the Contract Documents. The provisions of
this Paragraph will be as effective as if repeated
specifically in the Contract Documents in connection with
each particular duty, obligation, right, and remedy to
which they apply.
17.04 Survival of Obligations
A. All representations, indemnifications,
warranties, and guarantees made in, required by, or given
in accordance with the Contract Documents, as well as all
continuing obligations indicated in the Contract
Documents, will survive final payment, completion, and
acceptance of the Work or termination or completion of
the Contract or termination of the services of Contractor.
17.05 Controlling Law
A. This Contract is to be governed by the law of
the state in which the Project is located.
17.06 Headings
A. Article and paragraph headings are inserted
for convenience only and do not constitute parts of these
General Conditions.
.
Bozeman WRF Phase 1 Early Out Priority Improvements
00700 - 45
5/22/2007
SECTION 00810
SUPPLEMENTARY CONDITIONS TO THE GENERAL CONDITIONS
.
These Supplementary Conditions to the General Conditions amend or supplement the Standard General
Conditions of the Construction Contract (No. C-700, 2002 Edition) and other provisions of the Contract
Documents as indicated below. All provisions which are not so amended or supplemented remain in full
force and effect.
The terms used in these Supplementary Conditions which are defined in the General Conditions have the
meanings indicated in the General Conditions. Additional terms used in these Supplementary Conditions
have the meanings indicated below, which are applicable in both the singular and plural thereof.
Index of Supplementary Conditions to the General Conditions
Article or
Paragraph No. Title or Subject Matter
.
SC-1.01.A.20 Engineer's Consultants
SC-1.01.A.55 Day
SC-2.01 Delivery of Bonds
SC-2.07 Initial Acceptance of Schedules
SC-3.03.B.1.c Resolving Discrepancies
SC-4.02 Subsurface and Physical Conditions - Technical Data
SC-4.04.A.3 Underground Facilities
SC-4.05 Reference Points
SC-4.06 Hazardous Environmental Condition at Site - "Technical Data"
SC-5.02 Licensed Sureties and Insurers
SC-5.03 Certificates of Insurance
SC-5.04 Contractor's Liability Insurance
SC-5.06 Property Insurance - Purchased by Contractor
SC~6.02 Labor; Working Hours
SC-6.03 Services, Materials, and Equipment
SC-6.06 Concerning Subcontractors, Suppliers and Others
SC-6.17 Shop Drawings and Samples
SC-7.01 Related Work at the Site
SC-9.03 Project Representative
SC-11.01.A.5.c Equipment Rental Rates - Use of Blue Book
SC-12.03 Delays
SC-13.03 Tests and Inspections
SC-13.13. B Safety and Protection
SC-14.02.B Progress Payments- Whole or Partial Payment Refused by Engineer
SC-14.02.C Progress Payments ~ Payment Becomes Due
SC-14.02.D Progress Payments - Full Payment Refusal by Owner
SC-14.07.B Final Payment - Refusal by Engineer
SC-14.07.C Final Payment ~ Payment Becomes Due
SC-16.01 Dispute Resolution - Mediation
SC-17. 04. B Survival of Obligation - Statutes of Limitation
SC-1.01.A.20 ENGINEER'S CONSULTANTS
SC-1.01.A.20 Engineer's Consultants - The following persons, firms or corporations have provided or will
provide professional services to the Engineer for the Project:
Service
Company Name
.
Secondary Clarifier Diffusion Well Distribution Morrison-Maierle, Inc.
Baffle Improvements and Field Engineering
00.. .52713-00123
Bozeman WRF Phase 1 Early Out Priority Improvements
00810 - 1
6/2212007
SC-1.01.A.55 DAY
Add a paragraph immediately after paragraph SC-1.01.A.54. to read as follows:
55. Day-A "calendar day" unless otherwise directed within these Contract Documents.
.
SC-2.01 DELIVERY OF BONDS
Add a new paragraph immediately after paragraph 2.01.A of the General Conditions which is to read:
"B. Engineer shall furnish to Contractor six copies of the Agreement and other Contract
Documents bound therewith. Contractor shall execute the Agreement, insert executed copies of the
required Bonds and Power of Attorney and Certificates of Insurance and submit all copies to the Owner.
Owner shall execute all copies and return two copies to the Contractor who shall promptly deliver one
copy to his Surety. Owner shall also furnish a counterpart or conformed copy to the Engineer and MDEQ
and shall retain two copies."
SC-2.07 INITIAL ACCEPTANCE OF SCHEDULES
Delete the first paragraph of 2.07.A of the General Conditions in its entirety and insert the following in its
place:
"A. Prior to the first application for payment all schedules and documents identified in
paragraph 2.05.A of these General Conditions shall be finalized and submitted to the Engineer and
Owner. Until acceptable schedules are submitted to Engineer and Owner as provided below, Owner may
withhold an amount from a 'progress payment that is sufficient to pay the direct expenses that Owner may
reasonably expect will be necessary to correct any problems based on Contractor's failure to submit
acceptable schedules. The progress schedule shall be CPM form or other acceptable format that shows
estimated time for each work item, and starting and completion dates for each part of the Work. .
Acceptance of these schedules and documents by either Engineer or Owner will neither impose on
Engineer or Owner responsibility for the sequencing, scheduling or progress of the Work, and will not
interfere with or r~lieve Contractor from Contractor's full responsibility therefore."
SC-3.03.B RESOLVING DISCREPANCIES
Add a new paragraph immediately after paragraph 3.0.3.B.1.b of the General Conditions which is to read:
"c. In the event that any provision of the Contract Documents conflicts with another
provision of the Contract Documents, the provision in the Contract Documents first listed below
shall generally govern except as otherwise specifically stated:
1. Standard Form of Agreement
2. Performance and Payment Bond
3. Addenda to Contract Documents
4. Legal and Procedural Documents:
a. Proposal
b. Proposal Guaranty
c. Instructions to Bidders
d. Invitation to Bid
5. Special Provisions
6. Drawings
7. Detailed Specifications Requirements (Technical Specifications)
8. Supplementary Conditions
9. General Conditions"
.
00...52713-00123
Bozeman WRF Phase 1 Early Out Priority Improvements
00810-2
6t22/2007
.
.
.
SC-4.02 SUBSURFACE AND PHYSICAL CONDITIONS - TECHNICAL DATA
Add the following new paragraph(s) immediately after paragraph 4.02.B of the General Conditions:
"C. In the preparation of Drawings and Specifications, Engineer or Engineer's Consultants
relied upon the following drawings of physical conditions in or relating to existing surface and
subsurface structures (except Underground Facilities) which are at or contiguous to the site of the
Work:
1. Drawings dated 1969 prepared by Thomas Dean, and Hoskins, Inc., Great Falls and
Bozeman, Montana, entitled Bozeman, Montana Wastewater Treatment Plant consisting of 38
drawing sheets.
2. Drawings dated 1981 prepared by Thomas, Dean, and Hoskins, Inc., Great Falls,
Bozeman, and Kalispell, Montana, entitled Construction Drawings, Bozeman, Montana
Wastewater Treatment Plant, Phase 1 consisting of 94 drawing sheets.
3. Specifications and Drawings dated May 2002, prepared by Morrison-Maierle, Inc.,
entitled Wastewater Treatment Modifications, Bozeman, Montana, 57 drawing sheets.
4. Specifications and Drawings dated February 2004, prepared by Morrison-Maierle, Inc.
entitled Wastewater Treatment Improvements, Bozeman, Montana, 76 drawing sheets.
D. Copies of reports and drawings itemized in SC-4.02.C and SC-4.02-D that are not
included with Bidding documents may be examined at HDR Engineering, Inc's Missoula office and at
Morrison-Maierle, Inc.'s Helena Office or the Bozeman City Office during regular business hours. These
reports and drawings are not part of the Contract Documents, but the "technical data" contained therein
upon which Contractor is entitled to rely as identified and established above are incorporated therein by
reference. Contractor is not entitled to rely upon other information and data utilized by Engineer and
Engineer's Consultants in the preparation of Drawings and specifications."
SC-4.04 UNDERGROUND FACILITIES
Add the following new paragraph immediately after paragraph 4.04.A.2 of the General Conditions:
"3. At least 2 but not more than 10 business days before beginning any excavation, the
Contractor shall, according to MCA 69-4-501, notify all owners of underground facilities and coordinate
the Work with the owners of such underground facilities. The information shown or indicated in the
Contract Documents with respect to existing underground facilities is based on information and data
obtained from the owners of the facilities without field exploration, and as such, Owner and Engineer are
not responsible for the accuracy or completeness of such information or data."
SC-4.05 REFERENCE POINTS
Add the following paragraphs immediately after paragraph 4.05.A of the General Conditions which are to
read:
"B. The baselines and benchmarks to be furnished by the Owner are designated on the
Drawings. If lost or destroyed by the Contractor, the baselines and benchmarks will be re-established by
the Engineer. The cost of re-establishing disturbed baselines or benchmarks shall be calculated at the
hourly rates specified in the Bid Form for unscheduled employment of the Engineer. Payment for such
work shall be made by deduction from the monthly progress payments and the final payment as the costs
are incurred.
C. All other staking required by the Contractor to complete the work, including line and/or
grade stakes, slope stakes, bluetops, etc., shall be provided by the Contractor.
00...52713-00123
Bozeman WRF Phase 1 Early Out Priority Improvements
00810 - 3
6/2212007
D. Construction surveys shall be done under the direction of a Registered Professional
Engineer or Land Surveyor experienced in construction layout work.
.
E. The Contractor shall notify the Engineer of any discrepancies between plan locations and
verified field locations or dimensions. All connections of new facilities to existing facilities (concrete and
other critical horizontal or vertical dimensions) shall be verified by the Contractor prior to starting
construction. Any differences between the plans and field construction surveys will be resolved by the
Engineer.
F. When required, the Contractor shall provide a survey crew during normal working hours
to assist the Engineer in checking lines and elevations in the Contractor's layout and for measuring
quantities for payment purposes as the work proceeds. The Contractor shall cooperate with the Engineer
so that the checking and measuring may be accomplished with the least interference to the Contractor's
operations."
SCR5.02 LICENSED SURETIES AND INSURERS
Add the following immediately after paragraph 5.02.A of the General Conditions:
"B. Without limiting any of the other obligations or liabilities of the Contractor, Contractor shall
secure and maintain such insurance from an insurance company (or companies) authorized to write
insurance in the state of the project location, with minimum "A.M. Best Rating" of A-, VI, as will protect the
Contractor, the vicarious acts of subcontractors, the Owner, the Engineer, the Engineer's Consultants, and
the respective directors, officers, partners, agents, employees and other consultants and subcontractors of
each and any of all such additional insureds from claims for bodily injury (including sickness, disease and
mental anguish), death, and property damage which may arise from operations and completed operations
under this Agreement. Contractor shall not commence work under this Agreement until such insurance
has been obtained and certificates of insurance, with binders, or certified copies of the insurance policy
shall have been filed with the Owner and the Engineer." .
SC~5.03 CERTIFICATES OF INSURANCE
Add the following paragraphs immediately after paragraph 5.03. B of the General Conditions:
"C. Failure of Owner to demand such certificates or other evidence of full compliance with
these insurance requirements or failure of Owner to identify a deficiency from evidence provided shall not
be construed as a waiver of Contractor's obligations to maintain such insurance.
D. By requiring such insurance and insurance limits herein, Owner does not represent that
coverage and limits will necessarily be adequate to protect Contractor, and such coverage and limits shall
not be deemed as a limitation on Contractor's liability under the indemnities granted to Owner in the
Contract Documents."
SC-5.04 CONTRACTOR'S LIABILITY INSURANCE
Add the following new paragraph immediately after paragraph 5.04.B of the General Conditions:
"C. The limits of liability for the insurance required by paragraph 5.04 of the General
Conditions shall provide coverages for not less than the following amounts or greater where required by
Law or Regulations:
1. Workers' Compensation and Related Coverages under Paragraphs 5.04.A1 and
5.04.A2 of the General Conditions:
a.
State
Statutory
.
b.
Applicable Federal (e.g. Longshoremens)
Statutory
00.._52713-00123
Bozeman WRF Phase 1 Early Out Priority Improvements
00810-4
6/22/2007
.
.
.
c.
Employer's Liability
$1.000.000.00
2.
General Liability:
Contractor's General Liability Insurance under paragraphs 5.04.A.3 through 5.04.A.6 of
the General Conditions, which shall also include premises-operations; independent
contractor's operations protection; contractual liability; personal injury; broad form
property damage (including explosion, collapse, blasting and underground damage,
where applicable); and completed operations and product liability coverages. The
General Aggregate Limit shall apply separately to each of the Contractor's projects.
a. GENERAL AGGREGATE PER PROJECT $5.000.000.00
b. Products - Completed Operations Aggregate $5.000.000.00
c. Personal and Advertising
Injury (Each Occurrence) $5.000,000.00
d. Bodily Injury and
Property Damage (Each Occurrence) $5.000,000.00
e. Contractor's Liability Insurance under 5.04.A.3 through 5.04.A.6 may be satisfied
by primary insurance or a combination of primary and excess or umbrella
insurance. Primary occurrence limit cannot be less than $1,000,000.00. The
deductible, if any, may not exceed $5,000.00 per occurrence.
f.
In the event the General Aggregate limit is diminished by an amount greater
than $500,000, Contractor shall provide notice to Owner of this fact, and shall
again provide such notice on each subsequent occasion on which the General
Aggregate limit is again diminished by an amount greater than $500,000.
g. In addition to other requirement in the General Conditions, coverage will include
the following at a minimum: Premises - Operations, Operations of Independent
Contractor, Contractual Liability, Personal Injury, Product and Completed
Operations, Broad Form Property Damage (to include explosion, collapse,
blasting, and underground where applicable), and Per Project Aggregate
Endorsement.
3. Automobile Liability under paragraph 5.04.A.6 of the General Conditions:
a.
Combined Single Limit (bodily injury and property damage)
Each Accident
$ 5.000.000.00
b. Coverage to be written on a Symbol 1 (one) any auto basis, to include all owned,
hired, and non-owned vehicles.
c. Contractor's Automobile Liability Insurance under 5.04.A.6 may be satisfied by
primary insurance or a combination of primary and excess or umbrella insurance.
Primary occurrence limit can not be less than $1,000,000.00. The deductible, if
any, may not exceed $5,000.00 per accident.
4. The Contractual Liability Coverage required by Paragraph 5.04.B.4 of the General
Conditions shall provide coverage for not less than the following amounts:
a.
General Aggregate Per Project
$ 5.000.000.00
00.. .52713-00123
6n2/2007
Bozeman WRF Phase 1 Early Out Priority Improvements
00810-5
b.
$ 5.000.000.00
Each Occurrence
(Bodily Injury and Property Damage)
OWNERS and CONTRACTORS Protective Policy - Purchased By CONTRACTOR:
.
5.
In addition to the insurance required to be provided by Contractor under paragraph 5.04.A.1
through 5.04.A.6 inclusive, Contractor shall purchase and maintain a separate Owners and
Contractors Protective Policy (OCP) to protect Owner against claims which may arise from
operations under the Contract Documents, with limits of liability as specified below. This liability
insurance shall include as additional insureds the Engineer and the Engineer's Consultants, and
include coverage for the respective directors, officers, partners, employees, agents and other
consultants and subcontractors of all such additional insureds.
b.
Each Occurrence
(Bodily Injury and Property Damage)
$2.000.000.00
$1.000.000.00
a.
General Aggregate
The insurance policy will contain a provision or endorsement that the coverage afforded will not
be cancelled, materially changed or renewal refused until at least forty~five (45) days prior written
notice has been given to Owner and to each other additional insured (and the certificates of
insurance furnished to Owner and each other additional insured will so provide).
6. Additional Insureds:
a. With respect to insurance required by paragraphs 5.04.A.3 through 5.04.A.6,
inclusive, include the following as additional insureds. Use Additional Insured
Endorsement CG 20 32, or equivalent acceptable to the Owner and Engineer.
OWNER - City of Bozeman, Montana
ENGINEER - HDR Engineering, Inc.
ENGINEER'S Consultants - Morrison-Maierle, Inc.
.
b. With respect to the Owner's and Contractor's Protective Policy (OPC) insurance
required by paragraph SC-5.0.4.C.5, include the following as additional insureds.
Use Additional Insured Endorsement CG 20 32, or equivalent acceptable to the
Owner or Engineer.
ENGINEER - HDR Engineering, Inc.
ENGINEER'S Consultants - Morrison-Maierle, Inc."
SC~5.06 PROPERTY INSURANCE - PURCHASED BY CONTRACTOR
A. With respect to the Contractor's property insurance coverage required by paragraph
5.06.A of the General Conditions, include the following as an insured or additional insured:
"OWNER: City of Bozeman, Montana
SUBCONTRACTORS: (Contractor to list Subcontractors)
ENGINEER: HDR Engineering, Inc.
ENGINEER'S Consultants: Morrison-Maierle, Inc."
B. Deductible may not exceed $5,000 unless approved by appropriate Change Order.
SC~6.02 LABOR; WORKING HOURS
Add the following new paragraphs immediately after paragraph 6.02.B of the General Conditions: .
"C. Working hours for the Contractor shall be limited to the hours between 7:00 a.m. and
00...52713-00123
Bozeman WRF Phase 1 Early Out Priority Improvements
00810 - 6
6/22/2007
.
.
.
7:00 p.m. and shall not exceed 10 hours per day with authorized overtime. With Owner and Engineer
approval the Contractor may work a four day, ten hour per day work week. The Contractor must notify
the Owner and Engineer in writing three (3) days in advance of his intention to work during other periods
to allow assignment of additional inspection personnel when they are reasonably available. Emergency
work may be done without prior permission.
D. If a resident project representative is reasonably available, the Engineer may authorize
the Contractor to perform work during periods other than normal working hours and/or days. The cost of
this inspection will be calculated at the hourly rate specified in the Bid Form for unscheduled employment
of the Engineer and will be deducted from the monthly progress payments and final payment as the costs
are incurred."
SC-6.03 SERVICES, MATERIALS, AND EQUIPMENT
Add the following paragraphs immediately after paragraph 6.03.C of the General Conditions
which are to read as follows:
"d. To ensure standardization and uniformity in all parts of the work under this Contract, like
items of equipment shall be the products of one manufacturer. Like items of certain materials shall be the
products of one manufacturer.
E. Uniformity in like equipment items is required in order to provide the Owner with
interchangeability capabilities, simplified spare parts inventory, and standardized maintenance programs
and manufacturer's services.
F. Uniformity in certain like material items is required in order to provide the Owner with a
simplified spare materials inventory, continuity in patterns, color, and texture; and a standardized
procedure for maintenance care and manufacturer's services.
G. Visible architectural items such as exterior finishes, floor and wall covering, ceiling
materials, doors, windows, cabinetwork, paint, and miscellaneous appurtenances, when specified alike
shall be standardized.
H. Generally, material items exempt from standardization include structural steel, reinforcing
steel, building insulation, roofing materials, sheet metal, materials specified only by reference to a
recognized standard, and items hidden from view where interchangeability, color, and texture is not a
significant factor for standardization.
I. The Contractor shall inform his suppliers and subcontractors of these requirements, and
shall provide the necessary coordination to accomplish the standardization specified."
SC-6.06 CONCERNING SUBCONTRACTORS, SUPPLIERS AND OTHERS
The following provisions supplement paragraphs 6.06.A and 6.06.B of the General Conditions and
paragraph 12.01 of the Instructions to Bidders:
"A The Contractor shall not sublet any part of the work embraced within this contract without
the consent of the Owner, and the Owner reserves the right to withdraw at any time from any
subcontractor whose work has proven unsatisfactory, the right to be engaged in or employed upon any
part of the work. The amount of the work sublet on this project shall not exceed 50 percent.
B. In accordance with Instruction to Bidders, paragraph 12.01, within seven (7) days after
bids are opened, the apparent low bidder, and any other Bidder so requested, shall submit a list of all
Subcontractors, Suppliers, or other persons or organizations (including those who are to furnish the
principal items of materials and equipment) to Owner. An experience statement with pertinent information
as to similar projects and other evidence of qualification for each named Subcontractor, Supplier and
00.. .52713-00123
Bozeman WRF Phase 1 Early Out Priority Improvements
00810 -7
6/22/2007
other persons or organizations shall be furnished. Acceptance and substitution of proposed
Subcontractors, Suppliers, or other persons or organization prior to Notice of Award is governed by .
Instructions to 8idders paragraph 12.01. The Contractor may not change Subcontractors, Suppliers, or
other persons and organizations accepted by Owner prior to the Notice of Award without the written
permission of the Owner.
C.
Revocation of Subcontractor, Supplier, or other persons or organizations
acceptance after the Effective Date of the Agreement is governed by General
Condition 6.06.8."
SC~6.13 SAFETY AND PROTECTION
Add new paragraph to the end of paragraph 6.13.8 of the General Conditions as follows:
"It is expressly understood by the parties to this Agreement that the CONTRACTOR is solely
responsible for initiating, maintaining, and supervising safety precautions and programs in connection
with the Work. The right of the OWNER and ENGINEER to observe or otherwise review the Work and
operations shall not relieve the CONTRACTOR from any of his covenants and obligations hereunder.
CONTRACTOR shall incorporate all safety requirements into his construction progress and work
schedules including preconstruction and scheduled monthly safety meetings, posted safety rules, tailgate
meetings and site inspections by safety and other inspectors employed by the CONTRACTOR.
The CONTRACTOR shall be responsible for and shall take necessary precautions and provide all
material and equipment to protect, shore, brace, support and maintain all underground pipes, conduits,
drains, sewers, water mains, gas mains, cables, etc., and other underground construction uncovered in
the proximity, or otherwise affected by the construction work performed by him. All pavement, surfacing,
driveways, curbs, walks, buildings, grass areas, trees, utility poles or guy wires damaged by the
CONTRACTOR'S operations in the performance of this work shall be repaired and lor replaced to the
satisfaction of the OWNER, ENGINEER, and affected property owner at the CONTRACTOR'S expense. .
The CONTRACTOR shall also be responsible for all damage to streets, roads, highways, shoulders,
ditches, embankments, culverts, bridges, or other public or private property or facility, regardless of
location or character, which may be caused by moving, hauling, or otherwise transporting equipment,
materials, or men to and from the work or any part of site thereof, whether by him or his subcontractors.
The CONTRACTOR shall make satisfactory and acceptable arrangements with owner of, or the agency
or authority having jurisdiction over, the damaged property or facility concerning its repair or replacement
or payment of costs incurred in connection with said damage.
The CONTRACTOR shall conduct his work so as to, interfere as little as possible with public
travel, whether vehicular or pedestrian. Whenever it is necessary to cross, obstruct, or close roads,
driveways, and walks, whether public or private, the CO NT ACTOR shall obtain approval from the
governing party and shall, at his own expense, provide and maintain suitable and safe bridges, detours,
and other temporary expedients for the accommodation of public and private drives before interfering with
them. The provisions for temporary expedients will not be required when the CONTRACTOR has
obtained permission from the owner and tenant of the private property, or from the authority having
jurisdiction over public property involved, to obstruct traffic at the designated point.
Safety provisions must be entirely adequate and meet with City or State and Federal regulations
to protect the public on these streets and roads."
SC~6.11 SHOP DRAWINGS AND SAMPLES
Add the following paragraphs immediately after paragraph 6.17.E of the General Conditions:
"F. Contractor shall furnish required submittals with sufficient information and accuracy in
order to obtain required approval of an item with no more than three submittals. Engineer will record .
Engineer's time for reviewing subsequent submittals of Shop Drawings, samples or other items requiring
approval and Contractor shall reimburse Owner for Engineer's charges for such time.
00...52713-00123
Bozeman WRF Phase 1 Early Out Priority Improvements
00810-8
6/2212007
.
.
.
G. In the event that Contractor requests a substitution for a previously approved item,
Contractor shall reimburse Owner for Engineer's charges for such time unless the need for such
substitution is beyond the control of Contractor.
Work by others at the site and other coordination issues are defined in Section 01010, COQRDINA TlON
AND SITE CONDITIONS in these Contract Documents".
SCR9.03 PROJECT REPRESENTATIVE
Change the second sentence of paragraph GC-9.03.A to read as follows:
"The responsibilities and authority and limitations theron of any such Resident Project Representative and
assistance will be provided in paragraph 9.10, the Supplementary Conditions, and Specification Section
00821."
Add a new paragraph immediately after paragraph GC-9.03.A, which is to read as follows:
"ENGINEER's Resident Project Representative(s) shall not authorize any deviation from the Contract
Documents or substitutions of materials or equipment, unless authorized by ENGINEER."
SCR11.01.A.5.c. EQUIPMENT RENTAL RATES - USE OF BLUE BOOK
Delete paragraph 11.01.A.5.c. of the General Conditions in its entirety and insert the following in its place:
"11.01.A.5.c The cost for the use of all construction equipment and machinery and parts thereof
whether owned by the Contractor or rented by others shall be calculated as follows. Cost will
include the costs of transportation, loading, unloading, assembly, dismantling and removal thereof
for equipment involved only in the changed portion of the work covered under the cost of the
Work method. Transportation, loading, and assembly costs will not be included for equipment
already on the site which is being used for other portions of the Work. The cost of any such
equipment, machinery, or parts shall cease when the use thereof is no longer necessary for the
Work. Hourly equipment and machinery rates may be calculated from the Rental Rate Blue Book
for Construction Equipment, and the Equipment List submitted according to GC-2.05.A.4 and GC-
2.07.A, and as follows:
1. For working equipment, the hourly rate shall be the monthly rental rate divided by 176
hours per month plus the hourly operating cost.
2. For equipment on standby, the hourly rate shall be 50 percent of the monthly rental rate
divided by 176 hours per month, and the hourly operating cost shall not be applied.
3. For specialized equipment rented for a short duration used for change order work or
additional work not part of the scope of work bid, the equipment rental rates will be
negotiated prior to the work being performed.
4. Use of Blue Book rates, and review and approval of equipment rates associated with
equipment lists submitted according to GC-2.05.A.4 and GC-2.07.A shall not extend to
the settlement of any claim submitted under GC-10.05 and GC-12.01. In claim
settlements, actual costs are recoverable, not blue book rates or rates approved with
submittals of schedules of value or equipment lists."
SCR12.03. DELAYS
In the second sentence of General Conditions 12.03. after the words "or acts of God" add: "but shall not
include strikes or labor disputes."
Add a new paragraph after paragraph GC 12.03.A which is to read as follows:
00...52713-00123
Bozeman WRF Phase I Early Out Priority Improvements
00810-9
6/2212007
"Time extensions will not be granted for rain, wind, flood, or other natural phenomena of normal
intensity for the locality where Work is performed. For purposes of determining extent of delay .
attributable to unusual whether phenomena, a determination shall be made by comparing the
weather for a minimum continuous period of at least one-fourth of the Contract Time involved with
the average of the preceding 5 -year climatic range during the same time interval based on U.S.
Weather Bureau statistics for the locality where the Work is performed."
G. The Contractor shall schedule the Work to be completed within the Contract Time(s) stipulated in
the Agreement, including an allowance for time lost due to abnormally cold weather, abnormal
precipitation, or other natural phenomena that is abnormal for south western Montana. Such
events will not constitute justification for an extension of the Contract Time(s) unless 1) they are
considered outside the normal natural weather patterns for the project area, 2) the occurrence is
agreed upon by both the Engineer and Contractor during the event, and 3) the total number of
working days lost to such events exceeds five percent of the total Contract Time(s). Any claim by
the Contractor for an extension of the Contract Times(s) due to abnormal weather conditions
must be submitted to the Engineer within two business days of the occurrence of the abnormal
weather condition to be considered by the Engineer for an adjustment to the Contract Time(s).
Once the total number of working days exceeds five percent of the Contract Time(s), the Contract
Time(s) will be adjusted by the actual number of working days affected."
SC-13.03 TESTS AND INSPECTIONS
Replace paragraph 13.03.B of the General Conditions with the following:
"B. All quality control and compliance testing of work accomplished will be performed by the
Contractor, or designated representative, where specified at no additional cost to the Owner. Where the
specifications state that certain tests will be performed by the Owner, these tests will be done at no cost
to the Contractor except all tests for work or materials that fail to meet specified requirements shall be .
borne by the Contractor and shall be deducted from his progress payments. Where the specifications
require that certain materials are to be tested for suitability or in final position by the Contractor, the
Contractor shall provide at his own expense by retaining the services of a certified independent testing
laboratory. The Engineer will direct where and when tests are performed."
SC-14.02.B PROGRESS PAYMENTS - WHOLE OR PARTIAL PAYMENT REFUSAL BY ENGINEER
Add the following paragraph 14.02.B.6 to the General Conditions:
"6. Engineer may also refuse to recommend the whole or any part of any payment if, in
Engineer's opinion, there exists:
a. Unsatisfactory progress of the Work;
b. Failure to remedy defective Work or materials;
c. Disputed Work or materials;
d. Failure to comply with material provisions of the Contract Documents;
e. Failure of the Contractor to make timely payment upon request, including but not
limited to payment for labor, equipment, materials, subcontracts, taxes, fees,
professional services, rent, and royalties;
f. Damage to the Owner; or
g.
The existence of reasonable evidence that the Work cannot be completed for the
unpaid balance of the Contract Price."
.
00._ .52713-00123
Bozeman WRF Phase 1 Early Out Priority Improvements
00810-10
6/22/2007
SC-14.02.C PROGRESS PAYMENTS - PAYMENT BECOMES DUE
. Delete paragraph 14.02.C.1 of the General Conditions in its entirety and insert the following in its place:
"1. The Owner will, upon presentation to him of the Contractor's Application for Payment,
with Engineer's recommendation, review and act upon said payment request once each month on or
about the day of each month stipulated by the Owner at the preconstruction conference Payment will
become due 21 days after the Owner approves the application for payment and will be paid by Owner to
Contractor within 30 days after actual receipt of the Application for Payment by Engineer subject to the
provisions of Paragraph 14.02.0.1."
SC-14.02.D PROGRESS PAYMENTS - FULL PAYMENT REFUSAL BY OWNER
Add the following paragraph 14.02.0.1.e. to the General Conditions:
"e. there exists:
i.
ii.
iii.
iv.
v.
.
vi.
vii.
Unsatisfactory progress of the Work;
Failure to remedy defective Work or materials;
Disputed Work or materials;
Failure to comply with material provisions of the Contract Documents.
Failure of the Contractor to make timely payment upon request, including but not
limited to payment for labor, equipment, materials, subcontracts, taxes, fees,
professional services, rent, and royalties;
Damage to the Owner; or
The existence of reasonable evidence that the Work cannot be completed for the
unpaid balance of the Contract Price."
Delete Paragraph 14.02.0.2. of the General Conditions in its entirety and replace it with the following:
"2. If Owner refuses to make payment of the full amount recommended by Engineer, Owner
will give Contractor written notice (with a copy to Engineer) within 30 days of actual receipt of the
Application for Payment by Engineer, stating the reasons for such action and promptly pay Contractor any
amount remaining after deduction of the amount so withheld. Owner may only withhold an amount from a
payment that is sufficient to pay the direct expenses that the Owner may reasonably expect will be
necessary to correct any problems created by the items listed in Paragraph 14.02.0.1. Owner shall
promptly pay Contractor the amount so withheld, or any adjustment thereto agreed to by Owner and
Contractor, when Contractor corrects to Owner's satisfaction the reasons for such action."
SC-14.07.B FINAL PAYMENT - REFUSAL BY ENGINEER
Add the following sentence to the end of Paragraph 14.07.B.1 of the General Conditions:
"Engineer may refuse to recommend final payment if, in Engineer's opinion, there exists:
.
b.
a. Unsatisfactory progress of the Work;
Failure to remedy defective Work or materials;
OO'd 52713-00123
Bozeman WRF Phase 1 Early Out Priority Improvements
00810 - 11
6/22/2007
c. Disputed Work or materials;
d.
Failure of the Contractor to make timely payment upon request, including but not limited
to payment for labor, equipment, materials, subcontracts, taxes, fees, professional
services, rent, and royalties;
.
e. Damage to the Owner; or
f. The existence of reasonable evidence that the Work cannot be completed for the unpaid
balance of the Contract Price."
SC-14.07.C FINAL PAYMENT - PAYMENT BECOMES DUE
Delete Paragraph 14.07.C.1. of the General Conditions in its entirety and replace it with the following:
"1. Thirty-days (30) days after the Engineer actually receives the final Application for
Payment and accompanying documentation, the amount recommended by Engineer (subject to the
provisions of Paragraphs 14.02.D. and 14.07.B. of these General Conditions), will become due, and when
due will be paid by Owner to Contractor within Twenty one (21) days."
SC-16.02 DISPUTE RESOLUTION - MEDIATION
Replace Section 16.01 of the General Conditions with the following:
16.01 Methods and Procedures
A. Either Owner or Contractor may request mediation of any Claim submitted to Engineer
for a decision under Paragraph 10.05 before such decision becomes final and binding. Notice of the
demand for mediation will be filed in writing with the other party to the Agreement and a copy will be sent .
to Engineer for information. Once the other party receives the request for mediation they must notify the
requestor if they desire to participate in mediation. If both parties agree to participate in mediation the
parties shall establish mutually agreeable rules to abide by during the mediation process. Owner or
Contractor may exercise such rights or remedies as either may otherwise have under the Contract
Documents or Laws or Regulations in respect of any dispute that is not agreed upon during mediation.
B. Except as provided in paragraph SC-16.02.C. below, no mediation arising out of or
relating to the Contract Documents shall include by consolidation, joinder, or in any other manner any
other person or entity (including Engineer, Engineer's Consultant and the officers, directors, agents,
employees or consultants of any of them) who is not a party to this contract unless:
1. the inclusion of such other individual or entity is necessary if complete relief is to
be afforded among those who are already parties to the mediation; and
2. such other individual or entity is substantially involved in a question of law or fact
which is common to those who are already parties to the mediation, and which
will arise in such proceedings; and
3. the written consent of the other individual or entity sought to be included and of
Owner and Contractor has been obtained for such inclusion, which consent shall
make specific reference to this paragraph; but no such consent shall constitute
consent to mediation of any dispute not specifically described in such consent or
to mediation with any party not specifically identified in such consent.
C. Notwithstanding paragraph SC-16.02.B, if a Claim or counterclaim, dispute or other
matter in question between Owner and Contractor involves the Work of a Subcontractor, either Owner or .
Contractor may join such Subcontractor as a party to the mediation between Owner and Contractor
hereunder. Contractor shall include in all subcontracts required by paragraph GC-6.06.G specific
00... 52713-00 123
Bozeman WRF Phase 1 Early Out Priority Improvements
00810 - 12
6122/2 007
.
.
.
provision whereby the Subcontractor consents to being joined in a mediation between Owner and
Contractor involving the work of such Subcontractor. Nothing in this paragraph SC-16.02.C nor in the
provision of such subcontract consenting to joinder shall create any claim, right or cause of action in favor
of Subcontractor and against Owner, Engineer or Engineer's Consultants that does not otherwise exist.
SC-17.04
SURVIVAL OF OBLIGATIONS ~ STATUTES OF LIMITATIONS
Add the following new paragraph immediately after 17.04.A. of the General Conditions:
"8. Causes of action between the parties or the Engineer pertaining to acts or failures to act
shall be deemed to have accrued and the applicable statutes of limitations shall commence to run in any
and all events not later than the date of final payment to the Contractor. The Contractor shall include this
provision in all contracts he enters into with subcontractors, consultants and suppliers who provide any
work, products or services for this project."
END OF SECTION
00.. .52713-00123
Bozeman WRF Phase 1 Early Out Priority Improvements
00810. 13
6/22/2007
. r
.
SECTION 00821
DUTIES, RESPONSIBILITIES AND LIMITATIONS OF THE
RESIDENT PROJECT REPRESENTATIVE
.
A. General:
1. RPR is ENGINEER's agent at the site, will act as directed by and under the supervision of
ENGINEER, and will confer with ENGINEER regarding RPR's actions. RPR's dealings in
matters pertaining to the on-site work shall in general be with ENGINEER and
CONTRACTOR keeping OWNER advised as necessary. RPR's dealings with
subcontractors shall only be through or with the full knowledge and approval of
CONTRACTOR RPR shall generally communicate with OWNER with th knowledge of
and under the direction of ENGINEER
B. Duties and Responsibilities ofRPR:
I. Schedules: Review the progress schedule, schedule of Shop Drawing submittals and schedule
of values prepared by CONTRACTOR and consult with ENGINEER concerning
acceptability.
2. Conferences and Meetings: Attend meetings with CONTRACTOR, such as preconstruction
conferences, progress meetings, job conferences and the project-related meetings, and
prepare and circulate copies of minutes therof.
3. Liaison:
a. Serve as ENGINEER's liaison with CONTRACTOR, working principally through
CONTRACTOR's superintendent and assist in understanding the intent of the Contract
Documents; and assist ENGINEER in serving as OWNER's liaison with
CONTRACTOR
b. Assist in obtaining from OWNER additional details or information, when required for
proper execution of the Work.
4. Shop Drawings and Samples:
a. Record date of receipt of Shop Drawings and samples.
b. Receive samples which are furnished at the site by CONTRACTOR, and notify
ENGINEER of availability of samples for examination.
c. Advise ENGINEER and CONTRACTOR of the commencement of any Work requiring
Shop Drawings or sample if the submittal has not been approved by ENGINEER.
5. Review of Work, Rejection of Defective Work, Inspections and Tests:
a. Conduct on-site observations of the Work in progress to assist ENGINEER in
determining if the Work is in general proceeding in accordance with the Contract
Documents.
b. Report to ENGINEER whenever RPR believes that any Work is unsatisfactory, faulty or
defective or does not conform to the Contract Documents, or has been damaged, or does
not meet the requirements of any inspection, test or approval required to be made, and
advise ENGINEER of Work the RPR believes should be corrected or rejected or should
be uncovered for observation, or requires special testing, inspection or approval.
c. Verify that tests, equipment and systems startup and operating and maintenance training
are conducted in the presence of appropriate personnel, and the CONTRACTOR
maintains adequate records thereof; and observe record and report to ENGINEER
appropriate details relative to the test procedures and startup.
d. Accompany visiting inspectors representing public or other agencies having jurisdiction
over the Project, record the results of these inspections and report to ENGINEER
6. Interpretation of Contract documents: Report to ENGINEER when clarifications and
interpretations of the Contract Documents are needed and transmit to CONTRACTOR
clarification and interpretations as issued by ENGINEER
7. Modifications: Consider and evaluate CONTRACTOR's suggestions for modifications in
Drawings or Specifications and report with RPR's recommendations to ENGINEER.
Transmit to CONTRACTOR decisions as issued by ENGINEER.
.
00...52713-00123
Bozeman WRF Phase I Early Out Priority Improvements
00821 - I
612212007
8. Records:
a. Maintain at the job site orderly files for correspondence, reports of job conferences,
Shop Drawings and samples, reproductions of original Contract Documents including all
Work Directive Changes, Addenda, Change Orders, Field Orders, additional Drawings
issued subsequent to the execution of the Contract, ENGINEER's clarifications and
interpretations of the Contract Documents, progress reports, and other Project related
documents.
b. Keep a detailed and accurate diary or log book, recording CONTRACTOR hours on the
job site, weather conditions, prime and subcontractor daily work force, daily log of
equipment onsite or on standby, data relative to questions of Work Directive Changes,
Change Orders or changed conditions, list of job site visitors, daily activities, decisions,
observations in general, and specific observations in more detail as in the case of
observing test procedures; and send copies to ENGINEER.
c. Record names, addresses and telephone numbers of all CONTRACTORS,
subcontractors and major suppliers of materials and equipment.
9. Reports: Furnish ENGINEER periodic reports as required of progress of the Work and of
CONTRACTOR's compliance with the progress schedule and schedule of Shop Drawing
and sample submittals.
a. Consult with ENGINEER in advance of scheduled major test, inspections or start of
important phases or the Work.
b. Draft proposed Change Orders and Work Directive Changes, obtaining backup material
from CONTRACTOR and recommend to ENGIEER Change Orders, Work Directive
Changes, and Field Orders.
c. Report immediately to ENGINEER and OWNER upon the occurrence of any accident.
10. Payment Requests: Review applications for payment with CONTRACTOR for compliance
with the established procedure for their submission and forward with recommendations to
ENGINEER, noting particularly the relationship of the payment requested to the schedule of
values, Work completed and materials and equipment delivered at the site but not
incorporated in the Work.
11. Certificates, Maintenance and Operations Manuals: During the course of the Work, verify
that certificates, maintenance and operation manuals and other data required to be assembled
and furnished by CONTRACTOR are applicable to the items actually installed and in
accordance with the Contract Documents, and have this material delivered to ENGINEER for
review and forwarding to OWNER prior to final payment for the Work.
12. Completion:
a. Submit to CONTRACTOR, and ENGINEER a list of observed items requiring
completion or correction before ENGINEER may issue a Certificate of Substantial
Completion.
b. Assess completion or correction of items noted under 11.2..12.1, advise ENGINEER on
their status, and make recommendation of Engineer regarding issuance of a Certificate of
Substantial completion.
c. Conduct fmal inspection in the company of ENGINEER, OWNER and CONTRACTOR
and prepare a final list of items to be completed or corrected.
d. Observe that all items on fmallist have been completed or corrected and make
recommendations to ENGINEER concerning final acceptance.
C. Resident Project Representative Limitations of Authority:
1. Shall not authorize any deviation from the Contract Documents or substitution of materials or
equipments, unless authorized by ENGINEER.
2~ Shall not exceed limitations of ENGINEER's authority as set forth in the Agreement or the
Contract Documents.
3. Shall not undertake any of the responsibilities of CONTRACTOR, subcontra<;tors or
CONTRACTOR's superintendent.
4. Shall not advise on, issue directions relative to or assume control over any aspect of the
means, methods, techniques, sequences or procedures of construction unless such advice or
directions are specifically required by the Contract Documents.
00...52713-00123
Bozeman WRF Phase 1 Early Out Priority Improvements
00821 .2
6/2212007
.
.
.
.
.
.
5. Shall not advise on, issue directions regarding or assume control over safety precautions and
programs in connection with the Work.
6. Shall not accept Shop Drawing or sample submittals from anyone other that
CONTRACTOR.
7. Shall not authorize OWNER to occupy the Project in whole or in part.
8. shall not participate in specialized field or laboratory tests or inspections conducted by others
except as specifically authorized by ENGINEER.
END OF SECTION
00...52713-00123
Bozeman WRF Phase 1 Early Out Priority Improvements
00821 - 3
6/2212007
.
.
.
SECTION 00830
FEDERAL PREVAILING WAGE RATE DETERMINATION (DAVIS BACON
RATES FOR PUBLIC WORKS CONTRACTS IN MONTANA)
00.. .52713-00123
Bozeman WRF Phase 1 Early Out Priority Improvements
00830 - 1
5/4/2007
",,
.
MONTANA PREVAILING WAGE RATES
Heavy Construction
Rates effective: March 10, 2006
Brian Schweitzer, Governor
State of Montana
Keith Kelly, Commissioner
Department of labor & Industry
.
To obtain copies of prevailing wage rate schedules, contact:
Research and Analysis Bureau, Workforce Services Division
Montana Department of Labor and Industry
P. O. Box 1728, 840 Helena Ave.
Helena, MT 59624-1728
Phone 406-444-2430 FAX 406-444-2638
Toll free 800-541-3904
TOO 406-444-0532
We're also on the Internet at: www.ourfactsyourfuture.org
For information relating to public works projects and payment of
prevailing wage rates visit ERD at:
www.mtwagehourbopa.com or contact them at
Employment Relations Division
Montana Department of Labor and Industry
P. O. Box 6518
Helena, MT 59604-6518
Phone 406-444-5600
TDD 406-444-5549
The Research and Analysis Bureau welcomes questions, comments and suggestions from the public. In addition, we'll do our
best to provide information in accessible format, on request, in compliance with the Americans with Disabilities Act.
.
1
Heavy Construction - Montana
MONTANA PREVAILING WAGE REQUIREMENTS
.
Heavv Construction
The Commissioner of the Department of Labor and Industry, in accordance with Sections 18-2-40] and 18-2-
402 of the Montana Code Annotated, has determined the standard prevailing rate of wages for the
occupations listed in this publication.
The wages specified herein control the prevailing rate of wages for the purposes of 18-2-40], et seq., Montana
Code Annotated. It is required that each employer pay, as a minimum, the rate of wages, including fringe
benefits and zone pay applicable to those occupations in which the work is being performed, as provided in the
attached wage determinations.
All Montana Prevailing Wage Rates are available on the Internet at: www.ourfactsyourfuture.org or by
contacting the Research and Analysis Bureau at (800) 541-3904 or TDD (406) 444-0532. In addition, this
publication provides general information concerning compliance with Montana's Prevailing Wage Law and
payment of prevailing wages. For detailed compliance information relating to Public Works projects and
payment of prevailing wage rates, please consult the Regulations on the Internet at:
www.mtwagehourbopa.com or contact the Labor Standards Bureau at (406) 444-5600 or TDD (406) 444-
5549.
.
Keith Kelly
Commissioner
Department of Labor and Industry
State of Montana
.
2
Heavy Construction - Montana
. TABLE OF CONTENTS
MONTANA PREVAILING WAGE REQUIREMENTS:
A. Date of Publication............... ............ ......... ............. ............. .... 4
B. Definition of Heavy Construction........................................... 4
C. Definition of Public Works Projects........................................4
D. Prevailing Wage Schedule................. ................................ ......4
E. Fringe Benefits....... ........... ...... ............................ .......... . . ........5
F. Apprentices............................................. ~...... .......... . . ..............5
G. Posting Notice of Prevailing Wage................................ .........5
H. Employment Preference................................................ ..........5
I. Rates to use for Projects................................................ ...........5
.
.
3
Heavy Construction - Montana
A. Date of Publication: March 10,2006
.
B. Definition of Heavy Construction
The Administrative Rules of Montana (ARM) 24.17.501 (4) - (4)(a), Public Works Contracts For Construction
Services Subject to Prevailing Rates, states that "Heavy construction projects include, but are not limited to,
those projects that are not properly classified as either 'building construction', or 'highway construction.'
Heavy construction projects include, but are not limited to, antenna towers, bridges (major bridges designed for
commercial navigation), breakwaters, caissons (other than building or highway), canals, channels, channel cut-
offs, chemical complexes or facilities (other than buildings), cofferdams, coke ovens, dams, demolition (not
incidental to construction), dikes, docks, drainage projects, dredging projects, electrification projects (outdoor),
fish hatcheries, flood control projects, industrial incinerators (other than building), irrigation projects, jetties,
kilns, land drainage (not incidental to other construction), land leveling (not incidental to other construction),
land reclamation, levees, locks and waterways, oil refineries (other than buildings), pipe lines, ponds, pumping
stations (prefabricated drop-in units - not buildings), railroad construction, reservoirs, revetments, sewage
collection and disposal lines, sewers (sanitary, storm, etc.), shoreline maintenance, ski tows, storage tanks,
swimming pools (outdoor), subways (other than buildings), tipples, tunnels, unsheltered piers and wharves,
viaducts (other than highway), water mains, waterway construction, water supply lines (not incidental to
building), water and sewage treatment plants (other than buildings) and wells."
Federal Davis-Bacon wage rates as published in U.S. Department of Labor General Wage Decision No.
MT20030001 Modification No.14 have been adopted by the Montana Department of Labor and Industry for use
in Heavy Construction projects and are included in this publication. These rates apply statewide or as shown in .
MT20030001 Modification No. 14.
C. Definition of Public Works Projects
The Montana Code Annotated (18-2-401 (11 )(a)) defines "public works contract" as "a contract for construction
services let by the state, county, municipality, school district, or political subdivision or for nonconstruction
services let by the state, county, municipality, or political subdivision is which the total cost of the contract is in
excess of $25,000."
D. Prevailing Wage Schedule
This publication covers only Heavy Construction occupations and rates in the specific localities mentioned
herein. These rates will remain in effect until superseded by a more current publication. Current prevailing wage
rates schedules for Building Construction, Highway Construction and Non-construction Services occupations
can be found on the Internet at www.ourfactsyourfuture.org or by contacting the Research and Analysis
Bureau at (800) 541-3904 or TDD (406) 444-0532.
E. Fringe Benefits
Section 18-2-412 of the Montana Code Annotated states that:
"(1 )... a contractor or subcontractor may:
.
4
Heavy Construction - Montana
. (a) pay the amount of fringe benefits and the basic hourly rate of pay that is part of the standard
prevailing rate of wages directly to the worker or employee in cash;
(b) make an irrevocable contribution to a trustee or a third person pursuant to a fringe benefit fund, plan,
or program that meets the requirements of the Employee Retirement Income Security Act of 1974 or that is a
bona fide program approved by the United States Department of Labor; or
(c) make payments using any combination of methods set forth in subsections (1)(a) and (l)(b) so that
the aggregate of payments and contributions is not less than the standard prevailing rate of wages, including
fringe benefits for health and welfare and pension contributions that meet the requirements of the Employee
Retirement Income Security Act of 1974, travel, or other bona fide programs approved by the United States
Department of Labor, that is applicable to the district for the particular type of work being perfonned.
(2) The fringe benefit fund, plan, or program described in subsection (1)(b) must provide benefits to workers or
employees for health care, pensions on retirement or death, life insurance, disability and sickness insurance, or
bona fide programs that meet the requirements of the Employee Retirement Income Security Act of 1974 or that
are approved by the United States Department of Labor."
Fringe benefits are paid for all hours worked (straight time and overtime hours). However, fringe benefits are
not to be considered a part of the hourly rate of pay for calculating overtime, unless there is a collectively
bargained agreement in effect that specifies otherwise.
Employers are obligated to pay the wage rates and fringes as listed in the booklet, including the zone hourly rate
e when applicable. For heavy and highway construction occupations, the vacation benefit amount is not included
in the prevailing wage rate, unless stated otherwise.
F. Apprentices
Wage rates for apprentices registered in approved federal or state apprenticeship programs are contained in
those programs. lIowever, apprentices not registered in approved federal or state apprenticeship programs will
be paid the prevailing wage rate when working on a public works contract.
G. Posting Notice of Prevailing Wages
Section 18-2-406, Montana Code Annotated, provides that contractors, subcontractors, and employers who are
performing work or providing services under public works contracts as provided in this part shall post in a
prominent and accessible site on the project or work area, not later than the first day of work, a legible statement
of all wages to be paid to the employees on such site or work area.
H. Employment Preference
Sections 18-2-403 and 18-2-409, Montana Code Annotated require contractors to give preference to the
employment of bona fide Montana residents in the performance of work on public works contracts.
I. Rates to Use for Projects
e. Rates to be used on a public works project are those that are in effect at the time the project and bid
specifications are advertised.
5
Heavy Construction - Montana
.
MONTANA STATEWIDE PREVAILING
DAVIS-BACON
Rates Effective: March 10, 2006
HEAVY CONSTRUCTION WAGE RATES
General Wage Determinations Issued Under
the Davis-Bacon and Related Acts
.
State: Montana
Construction Types: Heavy
Counties: Montana Statewide.
.
6
Heavy Construction - Montana
.
ZONE DEFINITIONS
HEAVY CONSTRUCTION PROJECTS
CARPENTERS, *CEMENT MASONS, LABORERS, POWER EQUIPMENT OPERATORS
AND TRUCK DRIVERS
The zone hourly rates applicable to each project shall be
determined by measuring the road miles over the shortest
practical maintained route from the nearest County Court House
of the following listed towns to the center of the job:
BILLINGS, BOZEMAN, BUTTE, GREAT FALLS, HAVRE, HELENA,
KALISPELL, LEWISTOWN, MILES CITY, MISSOULA
Zone 1:
Zone 2:
Zone 3:
o to 30 miles - Base Pay
30 to 60 miles - Base Pay + $2.95
Over 60 miles - Base Pay + $4.70
*CEMENT MASONS ZONES: The above cities plus DILLON, GLASGOW,
GLENDIVE, SIDNEY
. Modification
o
1
2
3
4
5
6
7
8
9
10
11
12
13
14
Number
.
Publication Date
06/13/2003
11/07/2003
11/28/2003
01/23/2004
03/05/2004
04/09/2004
05/07/2004
09/10/2004
10/08/2004
04/01/2005
04/08/2005
04/22/2005
OS/27/2005
06/24/2005
09/09/2005
7
Heavy Construction - Montana
* CARP0028-002 06/01/2005
.
Rates
Fringes
Carpenters: (Zone 1)
Carpenter & Pi1ebuck........$ 19.60
Millwright. . . . . . . . . . . . . . . . . . . . . $ 21.60
7.80
7.80
CARP0028-004 06/01/2004
Rates
Fringes
Diver Tender...................$ 27.30
Dive r. . . . . . . . . . . . . . . . . . . . . . . . . . $ 57. 50
7.45
7.45
ELEC0044-001 06/01/2002
Beaverhead, Big Horn, Blaine, Broadwater, Carbon, Carter,
Cascade, Chouteau, Custer, Daniels, Dawson, Deer Lodge, Fallon,
Fergus, Gallatin, Garfield, Glacier, Golden Valley, Granite,
Hill, Jefferson, Judith, Basin, Lewis And Clark, Liberty,
Madison, McCone, Meagher, Mineral, Missoula, Musse1shell, Park,
Petroleum, Phillips, Pondera, Powder River, Powell, Prairie,
Ravalli, Richland, Roosevelt, Rosebud, Sheridan, Silver Bow,
Stillwater, Sweet Grass, Teton, Toole, Treasure, Valley,
Wheatland, Wibaux, And Yellowstone Counties
.
Rates
Fringes
Line Construction
( 1 ) Lineman................. $ 25,. 79
(2) Equipment Operator......$ 20.63
(3) Experienced Groundman...$ 16.76
4.25%+6.71
4.25%+6.34
4.25%+6.07
ELEC0233-001 06/01/2004
Blaine, Broadwater, Cascade, Chouteau, Fergus, Glacier, Hill,
Judith Basin, Lewis & Clark, Liberty, Meagher, Petroleum,
Phillips, Pondera, Teton, Valley, and Wheatland Counties
Rates
Fringes
Electrician......... ...........$ 23.26
3%+8.04
.
8
Heavy Construction - Montana
~ELEC0233-002 06/01/2004
Beaverhead, Deer Lodge, Granite, Jefferson, Madison, Powell, And
Silver Bow Counties
Rates
Fringes
Electrician....................$ 23.25
3%+8.49
* ELEC0532-001 06/01/2005
Gallatin, Park, And Sweet Grass Counties
Rates
Fringes
Electrician....................$ 22.94
4.25%+8.00
ELEC0532-003 06/01/2004
Big Horn, Carbon, Carter, Custer, Daniels, Dawson, Fallon,
Garfield, Golden Valley, McCone, Musselshell, Powder River,
Prairie, Richland, Roosevelt, Rosebud, Sheridan, Stillwater,
Treasure, Wibaux And Yellowstone Counties
~
Rates
Fringes
Electrician......... ...........$ 24.08
4.25%+8.64
ELEC0768-001 03/01/2005
Flathead, Lake, Lincoln, Mineral, Missoula, Ravalli, And
Sanders Counties
Rates
Fringes
Electrician.. ..................$ 25.20
9.16
~
9
Heavy Construction - Montana
ELEC0768-003 04/01/2005
.
Flathead, Lake, And Lincoln Counties
Rates
Fringes
Line Construction
(1) Cable Splicer...........$ 30.39
(2) Lineman.................$ 27.97
( 3 ) Groundman............... $ 1 7 . 47
(4) Line Equipment Operator.$ 21.67
(5) Pole Sprayer............$ 22.57
(6) Tree Trimmer............$ 23.42
(7) Utility Locator.........$ 15.40
10.76
10.59
9.92
10.22
10.28
10.35
9.78
ENGI0400-001 05/01/2005
Rates
Fringes
Power Equipment Operator
( Zone 1)
Group 1..................... $ 20. 62
Group 2..................... $ 21.09
Group 3..................... $ 21.49
Group 4..................... $ 22.15
Group 5..................... $ 22.65
Group 6..................... $ 23. 75
Group 7..................... $ 24. 25
7.55
7.55
7.55
7.55
7.55
7.55
7.55
.
POWER EQUIPMENT OPERATORS CLASSIFICATIONS
GROUP 1: Air Compressor; Auto Fine Grader; Belt Finishing
Machine; Boring Machine, small; Cement Silo; Crane, A-Frame
Truck Crane; Crusher Conveyor; DW-10, 15, and 20 Tractor
Roller; Farm Tractor; Forklift; Form Grader; Front-end
Loader under 1 cu yd; Heavy Duty Drills; Herman Nelson
Heater; Mulching Machine; Oiler, all except Cranes. &
Shovels; Pumpman.
GROUP 2: Air Doctor; Backhoe/Excavator/Shovel to and
including 3 cu yd; Bit Grinder; Bituminous Paving Travel
Plant; Boring Machine, large; Broom, self-propelled;
Concrete Travel Batcher; Concrete Float & Spreader;
Concrete Bucket Dispatcher; Concrete Finish Machine;
Concrete Conveyor; Distributor; Dozer, Rubber- Tired, Push
& Side Boom; Elevating Grader/Gradall; Field Equipment
Serviceman; Front-end Loader 1 cu yd to including 5 cu yd;
Grade Setter; Heavy Duty Drills, all types; Hoist/Tugger,
.
10
Heavy Construction - Montana
.
.
.
all; Hydralift & similar; Industrial Locomotive; Motor
Patrol, except Finish; Mountain Skidder; Oiler - Cranes &
Shovels; Pavement Breaker, EMSCO; Power Saw,
self-propelled; pugmill; Pumpcrete/Grout Machine; Punch
Truck; Roller, other than Asphalt; Roller, Sheepsfoot,
self- propelled; Roller, 25 tons and over; Ross Carrier;
Rotomill under 6 ft; Trenching Machine; Washing/Screening
Plant.
GROUP 3: Asphalt Paving Machine; Asphalt Screed;
Backhoe/Excavator/Shovel over 3 cu yd; Cableway Highline;
Concrete Batch Plant; Concrete Curing Machine; Concrete
Pump; Cranes, Creter; Cranes, Electric Overhead; Cranes, 24
tons and under; Curb Machine/Slip Form Paver; Finish Dozer;
Front-end Loader over 5 cu yd; Mechanic/Welder; Pioneer
Dozer; Roller, Asphalt (Breakdown & Finish); Rotomill, over
6 ft; Scraper, single, twin, or pulling Belly Dump; Yo-Yo
Cat.
GROUP 4: Asphalt/Hot Plant Operator; Cranes, 25 tons to 44
tons; Crusher Operator; Finish Motor Patrol; Finish Scraper.
GROUP 5: Cranes, 45 tons to including 74 tons; Crane, Tower,
all.
GROUP 6: Cranes, 75 tons to including 149 tons; Crane,
Whirley, all.
GROUP 7: Cranes, 150 tons to including 250 tons (add $1.00
for every 100 tons over 250 tons); Crane, Stiff-Leg or
Derrick; Helicopter Hoist.
IRON0841-002 07/01/2003
Remaining Counties
Rates
Fringes
Ironworker... ..................$ 19.20
12.51
11
Heavy Construction - Montana
LAB00098-001 05/01/2004
.
Rates
Fringes
Laborers: (Zone 1)
Group 1..................... $ 14.52
Group 2..................... $ 1 7 . 34
Group 3.....................$ 17.48
Group 4..................... $ 18.20
5.50
5.50
5.50
5.50
LABORERS CLASSIFICATIONS
GROUP 1: Flagperson
GROUP 2: All General Labor work; Burning Bar; Bucket man;
Carpenter Tender; Caisson Worker; Cement Mason Tender;
Cement Handler (dry); Chuck Tender; Choker Setter; Concrete
worker; Curb Machine-Lay Down; Crusher and Batch worker;
Fence Erector; Form Setter; Form Stripper; Heater Tender;
Landscaper; Pipe Wrapper; Pot Tender; Powderman Tender;
Rail and Truck Loaders and Unloaders; Riprapper; Sealants
for concrete and other materials; Sign Erection, Guard Rail
and Jersey Rail; Stake Jumper; Spike Driver; Signalman;
Tail Haseman; Tool Checker and Houseman; Traffic Control
worker.
.
GROUP 3: Concrete Vibrator; Dumpman (Grademan); Equipment
Handler; Geotextile and Liners; High-Pressure Nozzleman;
Jackhammer (Pavement Breaker); Laser Equipment; Non-Riding
Rollers; Pipelayer; Posthole Digger (Power); Power Driven
Wheelbarrow; Rigger; Sandblaster; Sod Cutter-Power;
Tampers; Creosote Handler
GROUP 4: Asphalt Raker; Asbestos Laborer; Cutting Torch;
Grade Setter; Hazmat Worker; High- Scaler; Power Saws
(Faller & Concrete); Powderman ($1.00 per hour above Group
4 rate); Rock & Core Drill; Tank/Vessel Cleaner; Track or
Truck mounted Wagon Drill; Welder including Air Arc
.
12
Heavy Construction - Montana
. PAIN0260-001 07/01/2002
Blaine, Broadwater, Cascade, Chouteau, Daniels, Fergus,
Garfield, Glacier, Granite (South Of A Line Running East & West
Through The Southern City Limits Of Phillipsburg), Hill,
Jefferson, Judith Basin, Lewis And Clark, Liberty, McCone,
Meagher, Petroleum, Phillips, Pondera, Powell (South Of A Line
Running East & West Through The Southern City Limits Of
Helmsville), Richland, Roosevelt, Sheridan, Teton, Toole,
Valley, And Wheatland Counties
Rates
Fringes
Painter. . . . . . . . . . . . . . . . . . . . . . . . $ 13.85
1%+3.45
PAIN0260-002 07/01/2002
Flathead, Granite (North Of A Line Running East & West Through
The Southern City Limits Of Phillipsburg), Lake, Lincoln,
Mineral, Missoula, Powell (North Of A Line Running East & West
Through The Southern City Limits Of Helmsville), Ravalli, And
Sanders Counties
.
Rates
Fringes
Painter. . . . . . . . . . . . . . . . . . . . . . . . $ 16.85
1%+3.45
PAIN1922-001 06/01/2001
Beaverhead, Big Horn, Carbon, Carter, Custer, Dawson, Deer
Lodge, Fallon, Gallatin, Golden Valley, Jefferson, Madison,
Musselshell, Park, Powder River, prairie, Rosebud, Silver Bow,
Stillwater, Sweet Grass, Treasure, Wibaux, And Yellowstone
Counties
Rates
Fringes
Painter (Industrial, includes
industrial plants, tanks,
pipes, bridges) ..... ...........$ 17.80
7.63
.
13
Heavy Construction - Montana
PLASOl19-001 05/01/2005
.
Statewide (except Deer Lodge, Jefferson, Powell, and Silver Bow
Counties)
Rates
Fringes
Cement Masons: (Zone 1)
Area 1...................... $ 17. 71
Area 2......................$ 18.82
6.20
6.20
AREA 1: Statewide (except Deer Lodge, Jefferson, Powell, and
Silver Bow Counties)
AREA 2: Deer Lodge, Jefferson, Powell, And Silver Bow
Counties
PLUM0030-003 09/01/2004
Bighorn, Blaine, Carbon, Carter, Cascade, Chouteau, Custer,
Daniels, Dawson, Fallon, Fergus, Garfield, Glacier, Golden
Valley, Hill, Judith Basin, Liberty, McCone, Meagher,
Musselshe11, Petroleum, Phillips, Pondera, Powder River,
Prairie. Richland, Roosevelt, Rosebud, Sheridan, Stillwater,
Teton, Toole, Treasure, Valley, Wheatland, Wibaux And
Yellowstone Counties
.
Rates
Fringes
Plumber. . . . . . . . . . . . . . . . . . . . . . . . $ 24.50
Industrial - Power
Generating Plants...........$ 26.85
10.65
10.65
* PLUM0041-001 07/01/2005
Beaverhead, Broadwater, Deer Lodge, Gallatin, Granite,
Jefferson, Lewis And Clark, Madison, Park, Powell, Silver Bow,
And Sweet Grass Counties
Rates
Fringes
Plumber. . . . . . . . . . . . . . . . . . . . . . . . $ 24.70
9.55
.
14
Heavy Construction - Montana
~ PLUM0459-001 05/01/2004
Flathead, Glacier, Lake, Lincoln, Mineral, Missoula, Ravalli,
And Sanders
Rates
Fringes
PI urnbe r. . . . . . . . . . . . . . . . . . . . . . . . $ 23. 41
9.30
TEAM0002-001 06/01/2003
Rates
Fringes
Truck drivers: (Zone 1)
Group 1.....................$ 13.31
Group 2..................... $ 17.34
5.31
5.31
TRUCK DRIVERS CLASSIFICATIONS:
GROUP 1: Pilot Car
.
GROUP 2: All Combination Trucks and Concrete Mixers;
Distributor Driver; All Dry Batch Trucks; Dumpman, Gravel
Spreader Box Operator; All Dump Trucks and similar
equipment including DW 20, DW 21, or Euclid Tractor;
Dumpsters; Flat Trucks; Servicemen; Lowboys, Four-Wheel
Trailers; Float Semi-Trailer; Lumber Carriers, Lift Trucks
& Fork Lifts; Pick-up Driver hauling material; Powder
Truck (Bulk Unloader type); Power Boom; Service Truck
Dirvers, Fuel Truck Drivers, Tiremen; All Water Tank
Drivers; Petroleum Products Drivers; Trucks with Power
Equipment such as Winch, A-Frame Truck, Crane, Hydralift,
Gout-Crete Truck, and Combination Mulching, Seeding &
Fertilizing Truck; Truck Mechanic
WELDERS - Receive rate prescribed for craft performing
operation to which welding is incidental.
~---~~~--~------~-----------------------------~~----------------
----------------------------~~----~~~----------------------~---~
Unlisted classifications needed for work not included within
the scope of the classifications listed may be added after
award only as provided in the labor standards contract clauses
( 2 9 C FR 5. 5 ( a ) ( 1 ) ( i i) ) .
.
15
Heavy Construction - Montana
In the listing above, the "SU" designation means that rates
listed under the identifier do not reflect collectively
bargained wage and fringe benefit rates. Other designations
indicate unions whose rates have been determined to be
prevailing.
.
----~-~~-----------~-~--~-~-~~~----~-~~-~~---------------~----~~
-~-----------~----------------------------------------------~---
END OF GENERAL DECISION
.
.
16
Heavy Construction - Montana
.
.
MISCELLANEOUS FORMS
.
.
.
.
REQUEST FOR INFORMATION (RFI)
PROJECT: Phase 1 Early Out Priority Improvements
RFINO.:
Bozeman Water Reclamation Facility
HDR PROJECT NO.: 00...52713-00123
DATE:
HDR Engineering, Inc.
Signature
Owner
Contractor
REPLY:
DATE:
HDR Engineering, Inc.
Signature
Owner
Contractor
.
.
.
CHANGE PROPOSAL REQUEST
(Not A Change Order)
HDR ENGINEERING, INC.
Project:
Bozeman WFR Phase 1 Early Out Priority Improvements
CPR No.:
CPR Date:
Date Sent to Contractor:
Date Rec'd from Contractor:
TO:
Please furnish your proposal for executing the following changes(s):
HDR Date:
TO: HDR Engineering, Inc.
Proposal:
Cost
Credit
(A time extension is not required for this modification unless otherwise detailed and justified:)
Contractor
Date
TO:
Accepted/Not Accepted
Accepted/Not Accepted
HDR: Date
Owner: Date
CHANGE ORDER
No.
DATE OF ISSUANCE
EFFECTIVE DATE
.
OWNER
Contract:
Project:
ENGINEER
CONTRACTOR
OWNER's Contract No.
ENGINEER's Contract No.
You are directed to make the following changes in the Contract Documents:
Description:
Reason for Change Order:
Attachments: (List documents supporting change)
.
CHANGE IN CONTRACT PRICE:
Original Contract Price
$
Net Increase (Decrease) from previous Change
Orders No. - to -
$
Contract Price prior to this Change Order:
$
Net increase (decrease) of this Change Order:
$
Contract Price with all approved Change Orders:
$
I CHANGE IN CONTRACT TIMES: I
Original Contract Times:
Substantial Completion:
Ready for final payment: (days or dates)
Net change from previous Change Orders No. ~ to
No. -
Substantial Completion:
Ready for final payment: ( davs)
Contract Times prior to this Change Order:
Substantial Completion:
Ready for final payment: (davs or dates)
Net increase (decrease) this Change Order:
Substantial Completion:
Ready for final payment:
(days)
Contract Times with all approved Change Orders:
Substantial Completion:
Ready for final payment:
(days or dates)
Contractor certifies and agrees that there are no additional costs or claims for extra work, additional time, delays or
omitted items, of any nature whatsoever, associated with the subject change order items, except as identified and set
forth herein and unless expressly stated otherwise in the Change Order. And further, that the price agreed-upon herein
represents the full cost and value for the subject work performed and the materials supplied under the terms of the
contract and that the work quantities and value were properly determined and are correct.
CONTRACTOR (Authorized Signature)
RECOMMENDED BY:
Date
(ENGINEER - Signature)
Date
.
APPROVED BY:
OWNER (Authorized Signature)
Date
EJCDC 1910-8-B (1996 Edition
Prepared by the Engineers Joint Contract Documents Committee and endorsed by The Associated General Contractors of America and the
Construction Specifications Institute.
CHANGE ORDER
INSTRUCTIONS
A.
GENERAL INFORMATION
This document was developed to provide a un iform format for handling contract changes that affect Contract Price
or Contract Times. Changes that have been initiated by a Work Change Directive must be incorporated into a
subsequent Change Order if they affect Price or Times.
Changes that affect Contract Price or Contract Times should be promptly covered by a Change Order. The practice
of accumulating Change Orders to reduce the administrative burden may lead to unnecessary disputes.
If Milestones have been listed in the Agreement, any effect of a Change Order thereon should be addressed.
For supplemental instructions and minor changes not involving a change in the Contract Price or Contract Times, a
Field Order should be used.
B. COMPLETING THE CHANGE ORDER FORM
Engineer normally initiates the form, including a description of the changes involved and attachments based upon
documents and proposals submitted by Contractor, or requests from Owner, or both.
Once Engineer has completed and signed the form, all copies should be sent to Owner or Contractor for approval,
depending on whether the Change Order is a true order to the Contractor or the formalization of a negotiated
agreement for a previously performed change. After approval by one contracting party, all copies should be sent to
the other party for approval. Engineer should make distribution of executed copies after approval by both parties.
If a change only applies to price or to times, cross out the part of the tabulation that does not apply.
.
.
.
.
.
.
Field Order
No.
Date of Issuance:
Effective Date:
Project:
Owne~s Contract No.:
Bozeman WRF Phase 1 Early Out
City of Bo~eman
Contract:
Date of Contract:
Contractor:
Enginee~s Project No.:
00...52713-00123
Attention:
You are hereby directed to promptly execute this Field Order issued in accordance with General Conditions Paragraph 9.05A., for
minor changes in the Work without changes in Contract Price or Contract Times. If you consider that a change in Contract Price or
Contract Times is required, please notify the Engineer immediately and before proceeding with this Work.
Reference:
(Specification Section(s))
(Drawing(s) I Detail(s))
Description:
Attachments:
I Engineer:
Receipt Acknowledged by (Contractor):
Date:
Copy to Owner
.
.
.
Work Change Directive
No.
Date of Issuance:
Effective Date:
Project:
Bozeman WRF Phase 1 Early Out
Contract:
I Owner:
I City of Bozeman
Owne~s Contract No.:
Date of Contract:
Contractor:
Enginee~s Project No.:
00...52713-00123
You are directed to proceed promptly with the following change(s):
Item No.
Description
Attachments (list documents supporting change):
Purpose for Work Change Directive:
D Authorization for Work described herein to proceed on the basis of Cost of the Work due to:
D Nonagreement on pricing of proposed change.
D Necessity to expedite Work described herein prior to agreeing to changes on Contract Price and Contract Time.
Estimated change in Contract Price and Contract Times:
Contract Price $
Contract Time
(increase/decrease)
(increase/decrease)
days
If the change involves an increase, the estimated amounts are not to be exceeded without further authorization.
Recommended for Approval by Engineer:
Date
Authorized for Owner by:
Date
Accepted for Contractor by:
Date
Approved by Funding Agency (if applicable):
Date:
.
.
.
ORDER TO CONTRACTOR TO SUSPEND WORK
Federal/State Project Number
Suspend Work Order No.
DATE:
HDR Engineering Inc., 00...52713-00123
TO:
PROJECT AND LOCATION
OWNER:
By reason of
which renders it impracticable for you to secure specified results on the work required by your contract, you
are hereby directed to suspend work (minor operations excepted), at the close of work on "
You will resume major operations only when authorized to do so in writing by a Resume Work Order.
Under the terms of your contract for the above subject project, Contract Time will (will not) continue to be
charged during the period work is suspended. (See General Conditions, Articles 12 and 15 and applicable
Supplementary Conditions). calendar days are allowed to complete this project and_
calendar days have been allowed for approved extra and/or additional work. At the close of work on
the date specified above, of the calendar days have been used and there
remain calendar days in which to complete the contract.
Please sign all five copies in the space provided and return them to this office. One approved copy will be
returned for your files.
CONTRACTOR
OWNER
Receipt Acknowledged, Date:
BY:
BY:
TITLE:
TITLE:
Address for Correspondence:
cc: HDR Engineering, Inc..
Morrison-Maierle, Inc.
.
.
.
ORDER TO CONTRACTOR TO RESUME WORK
Federal/State Project Number
Resume Work Order No.
DATE:
HDR Engineering, Inc. Project Number
TO:
PROJECT AND LOCATION
OWNER:
The Suspend Work Order, dated , directed you to suspend work on your contract, for the
reasons and conditions described therein. Conditions are now favorable to the continuation of the work, you are
hereby directed to resume major operations on this project effective
Under the terms of your contract for this project, Contract Time was (was not) charged during the period work was
suspended.
At the close of work on the date specified in the last Suspend Work Order, of the _calendar days
Contract Time had been used. calendar days were charged during the period work was suspended,
therefore, on the date this resume work order is effective, calendar days of Contract Time remain.
The (revised) contract completion date is
20~.
Please sign all five copies in the space provided and return them to this office. One approved copy will be returned for
your file.
CONTRACTOR
OWNER
BY:
Receipt Acknowledged, Date:
BY:
TITLE:
TITLE:
Address for Correspondence:
cc: HDR Engineering, Inc.
.
.
.
Contractor's Application and
Certificate for Payment
Paae 1 of 3
To: Mr. Bob Murray From (Contractor): Dan Harmon
City of Bozeman HDR Engineering, Inc.
20 E. Olive 1715 South Reserve, Suite C
Bozeman, MT 59715 Missoula, MT 59801
Owne~s Project No.: Contracto~s Project No.: Enginee~s Project No.: 00...52713-00123
For (Contract): AppUcaUon No.: Application Period:
Application for Payment
Change Order Summary
1. ORIGINAL CONTRACT SUM... ........ .......... ............ ...... ....... .................
Change Orders approved by Owner ~dditions Oed uctions
Number Date Approved
TOTALS
NET CHANGE BY CHANGE ORDERS
Contractor's Ce rtification
The undersigned Contractor certifies that to the best of the Contractor's knowledge,
information and belief, the Work covered by this Application for Payment has been compieted
in accordance with the Contract Documents, that all amounts have been paid by the
Contractor for Work for which previous Certificates for Payment were issued and payments
received from the Owner, and that current payment shown herein is now due.
ICo","""
By:
IDate:
FORM IlI-40 15-4 (May 91)
Copyright t 991 HDR Engineering, Inc.
2. Net change by Change Orders........ .......... ........ .......... ........................
3. CONTRACT SUM TO DATE (Line 1t2)................................................
4. TOTAL COMPLETED AND STORED TO DATE ...................................
(Column F on Progress Estimate)
5. TOTAL AMOUNT DUE TO DATE .........................................................
6. RETAINAGE: . $
5% of Completed Work and Stored Material (Line 4) .......... ..............
7. AMOUNT ELIGIBLE TO DATE ............................................................. $
8. LESS PREVIOUS PAYMENTS (Line 8 from prior Certificate) ........... $
9. AMOUNT DUE THIS APPLICATION.....................................................
10. BALANCE TO FINISH, PLUS RETAINAGE $
(Column G on Progress Estimate). . . . . . . . . . . . . . . . . . . . . . . . . . .
Payment Of~
IHDR Engineering, Inc.
By:
I is recommended.
IDale:
.
.
Contractor's Progress Eenate
Pace 2 of 3
or (contract): IApplication Number:
Appl icali on Period: IApplication Date:
A B C I D E' F G
Item IScheduled Work Completed Materials Presently ~otal Completed % ~atance torinlsh
~alue Stored (not in C or D) Ian d Sto red to B-F)
pate (C+D+E) F
(B)
Spec. ~eCl. NO. uescnptlon rom I-'revlous his t enoa
Application (C+D)
lotals
FORM III-40 15-4.FRM (Ver 1.1 ]\'fay 91)
Copyright 1991 HDR Engineering, Inc.
.
.
Slored Malerial SltJ'lary
aqe 0
or l comract): I"'ppllcallon Number:
IAPP Ica Ion I-'enoo: I'"'P P lca Ion LJate:
nvolce NO. ~~op urawl~ l!'{Iatenals ::;IOrea t-'reVIOUS1Y ;;:norea tnlS Montn In CO rpo ratea In vvarK Ir!la.en.al.s
ransmitlal o. Description Remaining
in Storage ($)
ld1jlle ~mount ~r:nount ::;U0101al IId<;ile f:\moum
(MonthNear) $) ($) (MonthNear) ($)
.
P 3 f3
FORl,,1 IlI-40IS-4.FRM (Ver 1.1 May 91)
Copyrighll991 HDR Engineering, me.
Certificate of Substantial Completion
Project: Bozeman WRF Phase 1 Ear1y Out Improvements lowner. City of Bozeman
Contract:
Owne~s Contract No.:
Date of Contract:
Contractor.
Enginee~s Project No.: 00...52713
This [tentative] [definitive] Certificate of Substantial Completion applies to:
o All Work under the Contract Documents:
o The following specified portions:
Date of Substantial Completion
The Work to which this Certificate applies has been inspected by authorized representatives of Owner, Contractor and Engineer,
and found to be substantially complete. The Date of Substantial Completion of the Project or portion thereof designated above is
hereby declared and is also the date of commencement of applicable warranties required by the Contract Documents, except as
stated below.
A [tentative] [revised tentative] [definitive] list of items to be completed or corrected, is attached hereto. This list may not be all-
inclusive, and the failure to include any items on such list does not alter the responsibility of the Contractor to complete all Work in
accordance with the Contract Documents.
The responsibilities between OWNER and CONTRACTOR for security, operation, safety, maintenance, heat, utilities,
insurance and warranties shall be as provided In the Contract Documents except as amended as follows:
o Amended Responsibilities 0 Not Amended
Owner's Amended Responsibilities:
Contractor's Amended Responsibilities:
The following documents are attached to and made part of this Certificate:
This Certificate does not constitute an acceptance of Work not in accordance with the Contract Documents nor is it a release of
Contractor's obligation to complete the Work in accordance with the Contract Documents.
Executed by Engineer
Date
Accepted by Contractor
Date
Accepted by Owner
Date
.
.
.
.
.
.
CONTRACTOR'S CERTIFICATE AND RELEASE
FROM:
(Name of Contractor)
TO: City of Bozeman
20 E. Olive
Bozeman, MT 59715
REFERENCE CONTRACT NUMBER
entered into the
day of
20 , between the City of Bozeman and
of
(Name of Contractor)
for the purpose of
(City)
(State)
(Type of Operation)
within the limits of the City of Bozeman.
KNOW ALL MEN BY THESE PRESENTS:
1. The undersigned hereby certifies that there is due from and payable by the City of Bozeman to the
Contractor under the Contract and duly approved Change Orders and modifications the balance of
2. The undersigned further certifies that in addition to the amount set forth in Paragraph I, there are
outstanding and unsettled the following items which he claims are just and due owing by the City of
Bozeman:
(a)
(b)
(c)
(d)
(Itemize claims and amounts due. If none, so state)
3. The undersigned further certifies that all work required under this Contract including work required
under Change Orders numbered: _' _' _' and _' has been performed in accordance with
the terms thereof, and that there are no unpaid claims for materials, supplies or equipment and no
claims of laborers or mechanics for unpaid wages arising out of the performance of this Contract, and
that the wage rates paid by the Contractor and all Subcontractors were in conformity with the Contract
provisions relating to said wage rates.
4.
Except for the amounts stated under Paragraphs I and II hereof, the undersigned has received from
the City of Bozeman all sums of money payable to the undersigned under or pursuant to the above-
mentioned Contract or any modification or change thereof.
5. That in consideration of the payment of the amount stated in Paragraph I hereof the undersigned
does hereby release the City of Bozeman from any and all claims arising under or by virtue of this
Contract, except the amount listed in Paragraph II hereof, provided, however, that if for any reason
the City of Bozeman does not pay in full the amount stated in Paragraph I hereof, said deduction shall
be automatically included under Paragraph II as an amount which the Contractor has not released but .
will release the City of Bozeman from any and all claims of any nature whatsoever arising out of said
Contract or modification thereof, and will execute such further releases or assurances as the City of
Bozeman may request. Further, in consideration of the payment of the amount stated in Paragraph I
hereof, the undersigned agrees to hold the City of Bozeman harmless from any and all costs, liability
or expense of any kind in any way arising out of the contract referenced herein, or any subcontracts
awarded pursuant thereto.
IN WITNESS WHEREOF, the undersigned has signed and sealed this instrument this
day of
,20_.
(Contractor)
(Signature)
(Title)
, being first duly sworn on oath, deposes and says, first, that
he is the
of the
(Title)
(Name of Company)
second, that he has read the foregoing certificate by him subscribed as
(Title)
.
of the
(Name of Company)
Affiant further states that the matters and things stated therein are, to the best of his knowledge and belief,
true.
(Signature)
Subscribed and sworn to before me this
, day of
,20
My commission expires
(Notary)
.
.
.
.
lil"1
Shop Drawing Transmittal No.
(Spec Section) (Series)
Project Name: Bozeman WRF Phase 1 Early Out Priority Improvements Date Received:
Project Owner: City of Bozeman Checked By:
Contractor: HDR Engineering, Inc. Log Page:
Address: Address: HDR No.:
1715 S. Reserve St. Suite C
Missoula, MT 59801
Spec Section:
Drawing/Detail No.:
Attn: Attn: 1st. Sub T ReSub. I
Date Transmitted: Previous Transmittal Date:
Item No. Description Manufacturer MfrNendor Dwg or Data No. Action Taken'
No. Copies
Remarks:
, The Action Desianated Above is in Accordance with the Followina Leaend:
A - Furnish as Submitted
B . Furnish as Noted
o - Rejected
E - Engineer's review not required
1. Submittal not required.
2. Supplemental Information. Submittal retained for
informational purposes only.
3. Information reviewed and approved on prior
submittal.
4. See comments.
C ' Revise and Submit
1. Not enough information for review.
2. No reproducibles submitted.
3. Copies illegible.
4. Not enough copies submitted.
5. Wrong sequence number.
6. Wrong resubmittal number.
7. Wrong spec. section.
8. Wrong form used.
9. See comments.
Comments:
Distribution:
Contractor U
I
By
I
Date
OtherU
FileU
Field U
Owner U
.
.
.
1il'1
O&M Manual Transmittal No.
(Spec Section)
(Series)
Project Name: Bozeman WRF Phase 1 Early Out Priority Improvements Date Received:
Project Owner: City of Bozeman Checked By:
Contractor: Owner: City of Bozeman Log Page:
Address: Address: HeR No.:
411 East Main Street
Bozeman, MT 59715
Attn: Attn:
1st. Sub. I I I ReSub. I
I I I I.
Date Transmitted: IPrevlous Transmittal Date: I I I I
No. Description of Item Manufacturer Dwg. or Data No. Action T aken*
Copies
Remarks:
1T0: From:
HDR Engineering, Inc.
Date:
. The Action designated above is in accordance with the following legend:
A - Acceptable, provide two additional copies and final electronic copy 5. Lubrication & maintenance instructions.
6. Troubleshooting guide.
B . Furnish as Noted 7. Parts list and ordering instructions.
8. Organization (index and tabbing).
C - Revise and Resubmit 9. Wiring diagrams & schematics specific to installation.
This Operation and Maintenance Manual Submittal is deficient in 10. Outline, cross section & assembly diagrams.
the following area: 11. Test data & performance curves.
1. Equipment record sheets. 12. Tag or equipment identification numbers.
2. Functional description. 13. Other - see comments.
3. Assembly, disassembly, installation, alignment,
adjustment & checkout instructions. o - Rejected
4. Operating instructions.
Comments:
By Date
Dlsllibution: Icontractor I I IFlle I I rield I I jowner I I Other I I
.
DEACTIVATION REQUEST
No.
TO: HDR ENGINEERING
Request that we have pennission to remove the following described equipment! pipe/conduit from service:
Equipment/pipe/conduit name:
Shown on Sheet ~ Date requested for deactivation
Length of out of service time
. Phase
Provide xerox copy of Plan Sheet effected equipment
.
Contractor Date
TO:
Temporary piping/wiring does not need to be installed to maintain process flow.
Scheduled down time will not affect treatment and this equipment/pipeline/wiring is not critical to treatment
process.
Request approved/denied
Bozeman, MT Date
.
HDR
Date
.
.
.
Ji)'1
Equipment Record
Page 1 of 2
Project Name: Bozeman WRF
Phase 1 Early Out Priority
Equipment Maintenance Data Summary
Equip. Description
Date Installed
. .1
I
,..'
Equip. Location
Cost
Project Equip. Tag No.
Shop Dwg. Trans. No.
Equip. Manuf.
Manuf. Address
Local Vendor
~endor Address
BREAK-IN MAINTENANCE REQUIREMENTS (INITIAL OIL CHANGES, ETC.)
PREVENTIVE MAINTENANCE REQUIREMENTS
PeriNo.
RECOMMENDED SPARE PARTS
Part Name
Quantity Equip.
Make
Serial No.
Model No.
HP
PH
Code
Nema
Misc.
Equip.
Make
Serial No.
Model No.
HP
TDH
PSI
Misc.
Pege
Date Started
1,1-0;
Estimated Life
Spec. Sec.
Phone
Phone
of
D W M Q S A
Hours
D W M Q S A
Hours
ELECTRICAL NAMEPLATE DATA
V.
RPM
Ins. CI.
CAmb.
IDNo.
Frame No.
Amp.
SF
Des.
Temp. Rise
HZ
Duly
Type
Rating
MECHANICAL NAMEPLATE DATA
RPM
Imp. Sz.
Assy. No.
fDNo.
Frame No.
Cap.
Des.
Case No.
Lubricant Information on followino oaoe
Size
CFM
.
.
L,
.
li1\
Equipment Record
Page 2 of 2
Lubrication Summary
EnuinmentDescnotion I Proiect Eauip. Tag No. I Paoe of
Lubricant Point I
Manufacturer Product AGMA # SAE# ISO
dl 1
a.
~
1:' 2
l'l 3
15
"
...J 4
5
Lubricant Point
Manufacturer Prod uct AGMA # SAE# ISO
dl 1
a.
~
1:' 2
J~ 3
.0
:J
...J 4
5
LUbricant Point
Manufacturer Product AGMA # SAE# ISO
<II
a. 1
~
'E 2
l'l 3
~
:J
...J 4
5
Lubricant Paint
Manufacturer Product AGMA # SAE# ISO
... 1
a.
~
1:' 2
l'l 3
.C
Ll
:J
...J 4
5
Lubricant Point
Manufacturer Product AGMA # SAE# ISO
... 1
a.
~
1:' 2
l'l 3
.C
Ll
:J
...J 4
5
Lubricant Point
Manufacturer Product AGMA # SAE# ISO
<II
a. 1
~
1:' 2
l'l 3
-;:;
Ll
:J
...J 4
5
.
.
DIVISION 1
GENERAL REQUIREMENTS
.
.
.
.
,:(~
.'t'
SECTION 01010
SUMMARY OF WORK
PART 1 ~ GENERAL
1.1 SUMMARY
"
1.2
A. General work included in this section:
1. Furnish all labor, materials, and equipment required in accordance with provisions of the
Contract Documents.
2. Completely coordinate with work of all other trades.
3. Although such work may not be specifically indicated, furnish and install all miscellaneous
items incidental to or necessary.
4. Coordination of system shutdowns with Owner.
5. Coordination of equipment installation with existing conditions and other trades.
B. Related sections include but are not necessarily limited to:
1. Division 0 - Bidding Requirements, Contract Forms, and Conditions of the Contract.
2. Division I - General Requirements.
WORK COVERED BY CONTRACT
A. Work to be performed includes:
I. All labor, equipment, and materials for the City of Bozeman WRF Phase I Early Out
Priority Improvements Project, generally consisting of the mechanical rehabilitation of
existing basin sluice gates, the installation of Owner provided mechanical mixers, including
rail, hoist, and mounting equipment, appurtenances, demolition and revision to the existing
diffusion well directional baftles on existing Secondary Clarifier No.2, and all other
miscellaneous items associated with Work according to the plans and specifications.
B. Bid Form:
1. The Bid Form, Section 00301, includes four (4) separate bid items for the project. The work
defmed in each Bid Item is described in detail in Section 00301, Article 4.A.
1.3 CONTRACTOR'S USE OF PREMISES
A. Contractor shall limit his use of the premises for Work and storage and allow for:
1. Owner occupancy.
2. Uninterrupted operation of existing adjacent facilities.
B. Coordinate use of premises under direction of Owner.
C. Contractor assumes full responsibility for the protection and safekeeping of products and
materials Contractor has stored on or off of the site.
D. Contractor shall move any stored products, or materials, under Contractor's responsibility, which
interfere with operations of Owner or separate contractor/subcontractor.
E. Contractor shall obtain and pay for the use of any additional storage or work areas if needed for
Contractor operations.
F. Contractor shall confine all materials and equipment to the areas as shown on the plans.
G. Contractor shall restore any areas used for materials storage, trailers, offices, equipment storage,
or employee and subcontractor parking to their original condition or better.
00...52713-00123
Bozeman WRF Phase I Early Out Priority Improvements
01010 - I
6/6tl007
H. Contractor shall provide necessary temporary covers and safety items to prevent materials and
tools from unintentionally falling into the basins. In the event equipment, tools, or other
materials unintentionally fall into the active basins, Contractor shall notify the Owner
immediately and retrieve the item(s) at Owner's direction.
1.4 WORK SEQUENCE
.
A. Construct work in stages to allow for the Owner's continuous operation of adjacent wastewater
treatment facilities. Coordinate construction schedule and operations with the Owner. The
Contractor shall plan, schedule, and coordinate his construction operations and activities in a
manner that will facilitate the progress of the work included in these Contract Documents. Since
there is considerable interfacing with the Owner's operating staff, it is imperative that the
Contractor work closely in the preparation of the schedule.
B. General: Following is a suggested general work sequence for the construction of critical work
items. The sequence is intended to achieve the goal of continuous use of the affected facilities
except for specifically described shutdowns. Work elements shown are not necessarily on a
critical path and may be done simultaneously. Critical work elements shown are not necessarily
complete and others may occur as the Work proceeds. The Contractor shall submit a detailed
work sequence schedule to accomplish the Work in accordance with Section 01060. All
facilities are to be considered operational at all times unless specifically designated for shutdown
in the following sequence. Shutdown periods are consecutive 7 -day weeks, 24-hour periods,
workday hours, or otherwise shown. The Owner will oerform activities that are underlined. All
other activities shall be performed by the Contractor as part of the approved work sequence
schedule. Special emphasis items have been shown in bold type. Installation of equipment shall
also include startup activities as specified in Section 01650.
1. Sluice Gate Removal, Rehabilitation and Replacement (Bid Item No.1):
a. The Contractor, per plans and specifications, shall have all of the necessary equipment,
materials and facility on site prior to draining and performing work within the aeration
basin cells.
b. Once the Contractor has the above mentioned equipment, materials and facility on site,
the Contractor shall coordinate the drainin~ and bv pass influent flow to other
aeration cells by the Owner. It shall be assumed dewaterine: ofthe basin cell pairs shall
take a single calendar-day to complete bv the Owner.
c. The aeration cells shall be drained in the following order. two at a time: Aeration Cells
No.1 & 2, No.2 & 3 and NO.3 & 4 in a clock wise or similar fashion.
d. Once ~e aeration cells have been drained, the Contractor shall perform the
necessary work according to Bid Item No.1, and the necessary parts of work
according to Bid Item No.2, for the installation of the mixer mounting equipment,
which includes the rail, hoist and mounting brackets prior to refilling the aeration cells.
e. The Contractor shall provide, maintain and operate the necessary pumping
equipment for the removal of the wash down water and aeration cell leaks. The
Contractor shall coordinate the discharge location with the Owner prior to performing
the said work.
f. The Contractor shall coordinate with all other trades.
2. Installation of Owner provided Aeration Basin Mixers and Associated Mounting, Rail and
Hoist Equipment (Bid Item No.2):
a. The Contractor, per plans and specifications, shall have all of the necessary equipment,
materials and facility on site prior to draining and performing work within the aeration
cells. The Contractor shall fully protect the existing aeration basin diffuser air grid and
aeration diffusers.
b. Ot).ce the Contractor has the above mentioned equipment, materials and facility on site
and in accordance with Section 01011, the Contractor shall coordinate the draining
and bv pass influent flow to other aeration cells with the Owner.
.
.
00.. .52713-00123
Bozeman WRF Phase 1 Early Out Priority Improvements
01010-2
6/6/2007
.
.
.
c. The aeration cells shall be drained in the following order; two at a time: Aeration Cells
No. 1 & 2, No.2 & 3 and No.3 & 4 in a clock wise or similar fashion. The Contractor
is encouraged to complete the Bid Items No.2 work concurrent with the work
associated with Bid Item No.1. It shall be assumed dewatering of the basin cell pairs
shall take a single calendar-day to comolete bv the Owner.
d. Once the aeration cells have been drained, the Contractor shall perform the
necessary work according to Bid Item No.1 and the necessary parts of work
according to Bid Item No.2 for the installation of the mixer mounting equipment,
which includes the rail, hoist and mounting brackets prior to refilling the aeration cells.
Once the cells have been rehabilitated, the Contractor shall coordinate the arrival
and training date and installation ofthe mixers with the Owner, in accordance with
Section 01011, so that the Owner's electrician can install and route the necessary
controls and power for the mixers. The Contractor shall allow enough time for the
Owners electrician to install the necessary power and controls.
e. The Contractor shall provide, maintain and operate the necessary pumping
equipment for the removal of the wash down water and precipitation or minor aeration
cell leak. The Contractor shall coordinate the discharge location with the Owner prior
to performing the said work.
f. The Contractor shall coordinate with all other trades.
3. Modifications and Improvements to Secondary Clarifier No.4 Mechanism Influent
Diffusion Well Distribution Baffles (Bid Item No.3):
a. The Contractor, per specification, shall have all of the necessary equipment, materials
and facility on site prior to draining and performing work within the Secondary
Clarifier No.4.
b. Once the Contractor has the above mentioned equipment, materials and facility onsite,
the Contractor shall coordinate the draining and bypass of the clarifier by the
Owner.
4. General Conditions (Bid Item No.4):
a. This work, according to Bid Item No.4, includes the Contractor's
mobilization/demobilization, taxes insurance, permits and all other work not
specifically defmed in the other Bid Items for a complete and operable facility.
C. The Contractor shall schedule and coordinate all work to be completed by the number of days
provided in the Agreement.
D. Contractor shall not close any lines, open valves, or take any other action which would affect the
operation of existing systems. Modifications of operations of existing systems will be
performed by Owners operations staff only. Such actions will be considered by the Owner upon
5 working days written notice to the Owner.
E. Any existing plant equipment, facilities, and appurtenances, such as water lines, gas lines,
electrical cables, sludge lines, structures, vehicles, etc., which are damaged by the Contractor
during construction, even though inadvertently, will be repaired immediately by Contractor at
his own expense.
F. Contractor shall conduct all on-site work during regular working hours which are defmed as
weekdays, 7:00 a.m. to 7:00 p.m., holidays excluded. Contractor may apply to work outside of
regular working hours as provided in the General Conditions.
1.5 OWNER OCCUPANCY
A. Owner will occupy the premises during the entire period of construction for the conduct of
normal operations.
1.6
SUBSTANTIAL COMPLETION
A. For the purposes of establishing when the Project is substantially complete and suitable for its
intended purpose, the following functional components and work elements shall be completed:
I. All work inspected per the plans and specifications.
00...52713-00123
Bozeman WRF Phase 1 Early Out Priority Improvements
01010 - 3
6/6/2007
B. Final completion of total project: Additional work elements that shall be completed include:
I. Any required repairs to Contractor staging and storage areas.
2. Clean up.
3. Items outlined within Section 00500.
.
1.7 REGULATORY REQUIREMENTS
A. Comply with all Federal, State, and local laws, regulations, codes, and ordinance applicable to
the Work.
B. References in the Contract Documents to local codes shall mean State of Montana and City of
Bozeman, MT.
C. Other standards and codes that apply to the Work are designated in the Specifications.
1.8 ACCESS BY GOVERNMENT OFFICIALS
A. Authorized representatives of governmental agencies shall at all times have access to the Work
where it is in preparation or progress. Contractor shall provide proper facilities for access and
inspection.
1.9 EASEMENTS AND RIGHTS-OF-WAY
A. Confine construction operations to the immediate vicinity of the Bozeman Water Reclamation
Facility and use due care in placing construction tools, equipment, and supplies, so as to cause
the least possible damage to property and interference with traffic.
1.10 PROTECTION OF PUBLIC AND PRIVATE PROPERTY
A. Restore to their original condition, pavement, surfacing, driveways, curbs, walks, buildings,
utility poles, guy wires, fences, and other surface structures affected by construction operations,
together with sod and shrubs, in yards and parking areas, whether within or outside the
easement.
.
B. Use new materials for replacements of all items.
C. Contractor shall be responsible for all damage to streets, roads, highways, shoulders, ditches,
embankments, culverts, bridges, and other public or private property, regardless of location or
character, that may be caused by transporting equipment, materials, or workers to or from the
Work or any part or site thereof, whether by Contractor or Contractor's subcontractors or
suppliers.
D. Make satisfactory and acceptable arrangements with the owner of, or the agency or authority
having jurisdiction over, any damaged property concerning its repair, replacement, or payment
of costs incurred in connection with the damage.
E. Keep fire hydrants and water control valves free from .obstruction and available for use at all
times.
PART 2 - PRODUCTS (NOT USED)
PART 3 - EXECUTION (NOT USED)
END OF SECTION
.
00...52713-00123
Bozeman WRF Phase 1 Early Out Priority Improvements
01010 - 4
6/612007
.
SECTION 01011
OWNER FURNISHED EQUIPMENT
PART 1 ~ GENERAL
1.1 SUMMARY
A. General work included in this section:
1. Unloading, storage, assembly and installation offour (4) aeration basin mixers and associated
equipment purchased by the Owner under a separate equipment procurement contract. Work
shall include coordination and scheduling of manufacturer's field services for equipment.
B. Related Sections include but are not necessarily limited to:
1. Division O.
2. Division 1.
1.2 DELIVERY
A. The suppliers for the equipment procurement contract are expected to deliver equipment to the site
and perform special services in accordance with the following schedule.
1. Schedule for:
a. Aeration Basin Mixers
Event No Earlier Than No Later Than
.
Deliver mixer guide rails and in-basin
supports
Deliver mixers and associated hoists to
Site
Perform Manufacturer's
Field Services
July 21,2007
August 15,2007
July 21, 2007
August 22, 2007
August 27,2007
August 31, 2007
B. Immediately on delivery of the equipment, Contractor, Owner, and Engineer shall inspect shipment to
assure compliance with the Contract Documents and accepted submittals, and that products are
properly protected and undamaged:
1. Contractor and Owner shall agree in writing to conditions of delivery.
2. All parts and equipment shall be delivered to the Bozeman Water Reclamation Facility.
a. Deliveries must be made between 8:00 am and 3:00 pm on weekdays.
b. No deliveries on holidays.
1.3 UNLOADING
A. Contractor shall unload all Owner purchased parts and equipment associated with the aeration basin
mixers:
1. Owner shall give Contractor a minimum of24 hours notice as to the time of delivery.
2. Owner shall inform Contractor of the type of equipment required to unload the parts and
equipment prior to delivery.
3. Contractor shall unload parts and equipment within 24 hours of the time of delivery (does not
include weekends or holidays):
a. Owner shall pay for all delivery truck and driver's time except that due to Contractor's failure
to unload equipment within 24 hours oftime of delivery.
b. Contractor shall pay for additional delivery truck and driver's time resulting from
. Contractor's failure to unload parts and equipment within 24 hours of time of delivery.
c. Goods shall be delivered between 8:00 am and 3:00 pm, Monday through Friday.
.
00.. .52713-00123
Bozeman WRF Phase 1 Early Out Mixer Procurement
01011 -1
6/22/2007
1.4 STORAGE
A. Contractor shall store all parts and equipment in accordance with the requirements of specification
section 01600.
B. Contractor shall remove from on~site storage, unpack, assemble, and install equipment in accordance
with the manufacturer's instructions.
1.5 INSTALLATION
A. Contractor shall install all parts and equipment in accordance with the contract documents and the
equipment manufacturer's instructions:
1. Shop drawings for equipment covered by this section will be supplied by the Owner.
2. Digester gasholder cover equipment as defmed on the Contract Drawings shall be installed by the
Procurement Contractor.
1.6 FIELD QUALITY CONTROL
A. Inspect delivery:
1. Contractor, Owner, and Engineer shall inspect all goods associated with the equipment upon
delivery.
2. All products that are damaged, used, or in any other way unsatisfactory for use on the project
shall be rejected.
3. Immediately upon delivery the Procurement Contractor or authorized representative thereof shall
inspect and certifY that equipment has been stored in accordance with the manufacturer's
instructions:
a. Contractor shall immediately remedy deficiencies until storage is certified.
B. Manufacturer's Field Services:
1. Contractor shall assist the Owner in scheduling manufacturer's field services within the time
frame specified in this section:
a. Site visits to be between 8:00 a.m. and 4:00 pm, Monday through Friday.
b. Contractor shall provide 10 days written request to Owner for manufacturer's field services.
2. Owner shall pay for manufacturer's field representative to provide the following services:
a. Inspect, check, and adjust equipment as required and approve installation.
b. Be present when equipment is placed in operation.
c. Check for proper operation.
d. Check for motor overloads by measuring amperage and voltage on each phase.
3. The cost of additional site visits or rescheduling of site visits due wholly or in part to deficiencies
in the Contractor's work or scheduling shall be paid for by Contractor:
a. The Owner shall deduct from any payments due Contractor the cost of such visits, and a
change order shall be issued reducing the contract amount.
END OF SECTION
00.. .52713-00123
Bozeman WRF Phase 1 Early Out Mixer Procurement
01011 - 2
6/22/2007
.
.
.
.
.
.
SECTION 01035
ENVIRONMENTAL HAZARD INFORMATION
PART 1 - GENERAL
1.1 SUMMARY
1.2
A. This Section provides information on known environmental hazards identified as being present, or
potentially present, in the reservoirs.
B. Environmental hazards identified include municipal biological wastewater.
MUNICIPAL BIOLOGICAL WASTEWATER
A. Execution'
1. General
a. Conduct the work in strict compliance with Federal, Montana, and local regulations
governing worker protection.
2. Compliance Program
a. Develop a written Compliance Program to establish and implement practices and
procedures for protecting the health of those employees exposed to municipal waste
water. This program is in addition to other OSHA hazard communication and general
safety and health requirements of the project. Revise and update the program if
changes in conditions result in new or increased worker exposures or modifications in
the control practices.
b. IdentifY the methods of compliance that will be used to reduce worker exposures to
municipal wastewater.
c. Confmn that regular inspections of the work area will be made by a competent person.
IdentifY the project competent person by name in the compliance program and indicate
the frequency of inspections that will be undertaken, not to be less than daily.
1) All labeling, marking, and placarding is the responsibility of the Contractor.
B. Control of Noise:
1. Control noise by fitting equipment with appropriate mufflers.
2. The maximum noise level at the project fence is 80 dB.
C. Completion of Work:
1. Upon completion of work, leave area in a clean, natural looking condition.
2. Ensure all signs oftemporary construction and activities incidental to construction of
required permanent work are removed.
END OF SECTION
00.. .52713-00123
Bozeman WRF Phase 1 Early Out Priority Improvements
01035 - 1
5/1612007
. SECTION 01060
SPECIAL CONDITIONS
PART 1 - GENERAL
1.1 PRE CONSTRUCTION CONFERENCE
A. A preconstruction conference shall be held at the Bozeman WRF, 255 Moss Bridge Road,
Bozeman, Montana, Control Room, after award of Contract.
1. Engineer will notify the Contractor as to the date and time of the conference two (2) weeks
in advance of the proposed date.
2. Contractor's Project Manager and Project Superintendent and Contractor's Subcontractor
Representatives shall attend.
1.2 CONTRACTOR'S SUPERINTENDENT'S FIELD OFFICE
.
A. Establish at site of Project.
B. Equipment: Telephone, telecopy, mailing address, and sanitary facilities.
C. Assure attendance at this office during the normal working day.
D. At this office, maintain complete field file of Shop Drawings, posted Contract Drawings and
Specifications, and other files offield operations including provisions for maintaining "As
Recorded Drawings."
E. Remove field office from site upon acceptance of the entire work by the Owner.
1.3 DRAWINGS AND CONTRACT DOCUMENTS FOR CONTRACTOR USE
A. Refer to General Conditions.
B. Contractor shall pick up all "no-charge" documents within 10 days from date of Notice to
Proceed.
C. Additional documents after "no-charge" documents will be furnished to Contractor at cost.
1.4 TESTING
A. Required testing, testing procedures, reports, certificates, and costs associated with all phases of
securing required satisfactory test information which may be required by individual sections of
Specifications or Drawings are the full responsibility of the Contractor.
1.5 ORDER OF CONSTRUCTION AND CONSTRUCTION SCHEDULE
.
A. Construction operations will be scheduled to allow the Owner uninterrupted operation of
existing adjacent facilities.
1. Coordinate connections with existing work to ensure timely completion of interfaced items.
B. At no time shall Contractor or his employees modify operation of the existing facilities or start
construction modifications without approval of the Owner except in emergency to prevent or
minimize ,damage.
,IIi:. ".
C. Within 10 days after award of Contract, submit for approval a critical path type schedule.
1. Account for schedule of Subcontracts.
2. Include proper sequence of construction, various crafts, purchasing time, Shop Drawing
approval, material delivery, equipment fabrication, startup, demonstration, and similar time
consuming factors.
3. Show on schedule as a minimum, earliest starting, earliest completion, latest starting, latest
finish, and free and total float for each task or item.
00...52713-00123
Bozeman WRF Phase 1 Early Out Priority Improvements
01060 -1
5/16/2007
D. Evaluate schedule no less than monthly.
1. Update, correct, and rerun schedule and submit to Engineer in triplicate with pay application
to show rescheduling necessary to reflect true job conditions.
2. When shortening of various time intervals is necessary to correct for behind schedule
conditions, indicate actions to implement to accomplish work in shorter duration.
3. Information shall be submitted to Engineer in writing with revised schedule.
1.6 PROJECT MEETINGS
.
A. Construction Meetings:
1. The Engineer will conduct construction meetings involving:
a. Contractor's project manager.
b. Contractor's project superintendent.
c. Owner's designated representative(s).
d. Engineer's designated representative(s).
e. Contractor's subcontractors as appropriate to the work in progress.
f. Owner's Construction Quality Control Consultant.
2. Meetings will be conducted every two (2) weeks.
3. The Engineer will take meeting minutes and submit copies of meeting minutes to
participants and designated recipients identified at the Preconstruction Conference.
a. Corrections, additions or deletions to the minutes shall be noted and addressed at the
following meeting.
4. The Engineer will schedule meetings for most convenient time frame.
5. The Engineer will have available at each meeting full chronological files of all previous
meeting minutes.
6. The Contractor shall have available at each meeting up-to-date record drawings.
B. Pre-Installation Conferences:
I. Coordinate and schedule with Resident Project Representative and Engineer for each
material, product or system specified.
a. Conferences to be held prior to initiating installation, but not more than one (I) week
before scheduled initiation of installation.
b. Review manufacturers recommendations and Contract Documents Specifications.
2. Contractor's Superintendent and individual who will actually act as foreman ofthe
installation crew (installer), if other than the Superintendent, shall attend.
1.7 SPECIAL CONSIDERATIONS
.
A. Contractor shall be responsible for negotiations of any waivers or alternate arrangements
required to enable transportation of materials to the site.
B. Maintain conditions of access road to site such that access is not hindered as the result of
construction related deterioration.
1.8 TEMPORARY UTILITIES
A. Power:
1. Contractor shall arrange for temporary power service to the Contractor's field offices and to
Contactor's storage sheds
2. Equipment testing:
a. Owner will pay for energy.
b. Contractor to pay all costs for temporary wiring, if needed.
B. Water:
1. Provide all water required for construction purposes, except as otherwise indicated.
2. Provide all drinking water required by personnel. Pay all costs.
C. Sanitary Facilities
1. Provide sanitary facilities.
a. As required by law and regulations.
.
00.. .52713-00123
Bozeman WRF Phase 1 Early Out Priority Improvements
01060 -2
5/16/2007
.
.
.
b. No less than one each (men and women) facility for every ten employees of Contractor
and Subcontractors at site.
c. Service, clean and maintain facilities and enclosures.
D. Telephone:
1. Provide temporary telephone services for Contractor's needs during performance of this
contract. Pay all installation and removal costs for temporary telephone service. Pay all
monthly charges and other fees.
1.9 DESIGN CONDITIONS
A. Seismic zone: IBC 2002,3.
B. Wind load: 50 LBS/SF.
C. Average site elevation: 4608.
D. Outside air temperature:
1. ~20 DegF minimum.
2. 100 DegF maximum.
PART 2 ~ PRODUCTS ~ (NOT APPLICABLE TO THIS SECTION)
PART 3 - EXECUTION ~ (NOT APPLICABLE TO THIS SECTION)
END OF SECTION
00...52713-00123
Bozeman WRF Phase I Early Out Priority Improvements
01060 -3
5/16/2007
.
.
.
SECTION 01150
MEASUREMENT AND PAYMENT
PART 1 - APPLICATIONS FOR PAYMENT
1.1 GENERAL
A. Submit applications for payment to Owner in accordance with the schedule established by
Conditions of the Contract and Agreement between Owner and Contractor.
B. Additional requirements specified elsewhere:
1. Lump Sum Price: Agreement.
2. Progress Payments, Retainages, and Final Payment: Conditions of the Contract and
Agreement.
3. Schedule of Values: Section 01370.
1.2 FORMAT AND DATA REQUIRED
A. Submit applications typed on attached Contractor's Application and Certificate of Payment, or a
similar form, with itemized data typed on 8-1/2 inches x 11 inches white paper continuation
sheets.
B. Provide itemized data on continuation sheet:
1. Format, schedules, line items, and values: Those of the Schedule of Values.
1.3 PREPARATION OF APPLICATION FOR EACH PROGRESS PAYMENT
A. Application form:
1. Fill in required information, including that for Change Orders executed prior to the date of
submittal application.
2. Fill in summary of dollar values to agree with the respective totals indicated on the
continuation sheets.
3. Execute certification with the signature of a responsible officer of the Contractor's firm.
B. Continuation sheets:
1. Fill in total list of all scheduled component items of Work, with item number and the
scheduled dollar value for each item.
2. Fill in the dollar value in each column for each scheduled line item when work has been
performed or products stored, rounding off values to nearest dollar.
3. List each Change Order executed prior to the date of submission at the end of the
continuation sheets.
a. List by Change Order number and description, as for an original component item of
work.
1.4
SUBSTANTIATING DATA FOR PROGRESS PAYMENTS
A. When Owner requires substantiating data, Contractor shall submit suitable information, with a
cover letter identifying:
1. Proj\l,yt.
2. Application number and date.
3. Detailed list of enclosures.
4. For stored products:
a. Item number and identification as shown on application.
b. Description of specific material stored at the site (upon verification of payment from
supplier).
B. Submit one copy of data and cover letter for each copy of application.
00, ..52713-00123
Bozeman WRF Phase 1 Early Out Priority Improvements
01150 - 1
5/1612007
1.5 PREPARATION OF APPLICATION FOR FINAL PAYMENT
.
A. Fill in application form as specified for progress payments.
1.6 SUBMITTAL PROCEDURE
A. Applications for payment must be agreed upon by the Contractor and Owner and submitted to
Owner on or before the first Monday of each month. If statement is not received in final form
prior to this date, the application may not be processed until the following payment period.
B. Number: Five (5) copies of each application.
C. When Owner finds the application properly completed and correct, he will finalize a Certificate
for Payment, with a copy to Contractor.
PART 2 - PART 2 - PRODUCTS (NOT USED)
PART 3 - PART 3 . EXECUTION (NOT USED)
END OF SECTION
.
.
00.. .52713-00123
Bozeman WRF Phase 1 Early Out Priority Improvements
01150 - 2
5116/2007
.
.
.
SECTION 01340
SUBMITTALS
PART 1 - GENERAL
1.1
SUMMARY
1.2
A. Section Includes:
1. Mechanics and administration of the submittal process for:
a. Shop Drawings.
b. Samples.
c. Miscellaneous submittals.
d. Operation and Maintenance Manuals.
2. General content requirements for Shop Drawings.
3. Content requirements for Operation and Maintenance Manuals.
B. Related Sections include but are not necessarily limited to:
1. Division 0 - Bidding Requirements, Contract Forms, and Conditions of the Contract.
2. Division 1 - General Requirements.
3. Sections in Divisions 2 through 16 identifying required submittals.
DEFINITIONS
1.3
A. Shop Drawings:
1. See General Conditions.
2. Product data and samples are Shop Drawing information.
B. Operation and Maintenance Manuals (O&M Manuals):
1. Data collected for the Owner's use.
2. Contain information related to the operation and maintenance of equipment and packaged
systems.
C. Miscellaneous Submittals:
1. Submittals other than Shop Drawings and O&M Manuals.
2. Representative types of miscellaneous submittal items include but are not limited to:
a. Construction schedule.
b. Concrete, soil compaction, and pressure test reports.
c. HV AC test and balance reports.
d. Installed equipment and systems performance test reports.
e. Manufacturer's installation certification letters.
f. Instrumentation arid control commissioning reports.
g. Warranties.
h. Service agreements.
i. Construction photographs.
j. Survey data.
k. Cost breakdown (Schedule of Values).
SUBMITTAL SCHEDULE
A. Schedule of Shop Drawings:
1. Submitted and approved within 30 days of receipt of Notice to Proceed.
2. Account for multiple transmittals under any specification section where partial submittals
will be transmitted.
B. Shop Drilwings: Submittal and approval,Jj'rior to construction.
00...52713-00123
Bozeman WRF Phase 1 Early Out Priority Improvements
01340 - 1
5/16/2007
C. Operation and Maintenance Manuals and Equipment Record Sheets: Initial submittal within 30
days after date Shop Drawings are approved.
1.4 PREPARATION OF SUBMITTALS
.
A. General:
I. All submittals and all pages of all copies of a submittal shall be completely legible.
2. Submittals which, in the Engineer's sole opinion, are illegible will be returned without
review.
B. Shop Drawings:
1. Scope of any submittal and letter of transmittal:
a. Limited to one specification section.
b. Do not submit under any specification section entitled (in part) "Basic Requirements"
unless the product or material submitted is specified in a "Basic Requirements" section.
2. Numbering letter of transmittal:
a. Include as prefix the specification section number followed by a series number, "-xx",
beginning with "0 I" and increasing sequentially with each additional transmittal.
b. If more than one submittal under any specification section, assign consecutive series
numbers to subsequent transmittal letters.
3. Describing transmittal contents:
a. Provide listing of each component or item in submittal capable of receiving an
independent review action.
b. IdentifY for each item:
1) Manufacturer and Manufacturer's drawing or data number.
2) Contract Document tag number(s).
3) Unique page numbers for each page of each separate item.
c. When submitting "or-equal" items that are not the products of named manufacturers,
include the words "or-equal" in the item description.
4. Contractor stamping:
a. General:
1) Contractor's review and approval stamp shall be applied either to the letter of
transmittal or a separate sheet preceding each independent item in the submittal.
a) Contractor's signature and date shall be original ink signature.
b) Shop Drawing submittal stamp shall read "(Contractor's Name) has satisfied
Contractor's obligations under the Contract Documents with respect to
Contractor's review and approval as stipulated under General Conditions
Paragraph 6.17D."
c) Letters of transmittal may be stamped only when the scope of the submittal is
one item.
2) Submittals containing multiple independent items shall be prepared with an index
sheet for each item listing the discrete page numbers for each page of that item,
which shall be stamped with the Contractor's review and approval stamp.
a) Individual pages or sheets of independent items shall be numbered in a manner
that permits Contractor's review and approval stamp to be associated with the
entire contents of a particular item.
b. Electronic stamps:
1) Contractor may electronically embed Contractor's review and approval stamp to
either the letter of transmittal or a separate index sheet preceding each independent
item in the submittal.
2) Contractor's signature and date on electronically applied stamps shall be original
ink signature.
5. Resubmittals:
a. Number with original root number and a suffix letter starting with "A" on a (new)
duplicate transmittal form.
b. Do not increase the scope of any prior transmittal.
c. Account for all components of prior transmittal.
.
.
00.. .52713-00123
Bozeman WRF Phase I Early Out Priority Improvements
01340.2
5/1612007
.
1) Ifitems in prior transmittal received "A" or "B" Action code, list them and indicate
"A" or "B" as appropriate.
a) Do not include submittal information for items listed with prior "A" or "B"
Action in resubmittal.
2) Indicate "Outstanding-To Be Resubmitted At a Later Date" for any prior "C" or
"D" Action item not included in resubmittal.
a) Obtain Engineer's approval to exclude items.
6. For 8-1/2 x 11 IN, 8-1/2 x 14 IN, and 11 x 17 IN size sheets, provide three (3) copies of
each page for Engineer plus the number required by the Contractor.
a. The number of copies required by the Contractor will be defmed at the Preconstruction
Conference, but shall not exceed 5.
b. All other size sheets:
1) Submit one (1) reproducible transparency or high resolution print and one (1)
additional print of each drawing until approval is obtained.
2) Utilize mailing tube; do not fold.
3) The Engineer will mark and return the reproducible to the Contractor for his
reproduction and distribution.
7. Provide clear space (3 IN SQ) for Engineer stamping of each component defined in
PREPARATION OF SUBMITTALS - Contractor Stamping.
8. Contractor shall not use red color for marks on transmittals.
a. Duplicate all marks on all copies transmitted, and ensure marks are photocopy
reproducible.
b. Outline Contractor marks on reproducible transparencies with a rectangular box.
9. Transmittal contents:
a. Coordinate and identify Shop Drawing contents so that all items can be easily verified
by the Engineer.
b. Identify equipment or material use, tag number, drawing detail reference, weight, and
other project specific information.
c. Provide sufficient information together with technical cuts and technical data to allow
an evaluation to be made to determine that the item submitted is in compliance with the
Contract Documents.
d. Submit items such as equipment brochures, cuts of fixtures, product data sheets or
catalog sheets on 8-1/2 x II IN pages.
1) Indicate exact item or model and all options proposed.
e. When a Shop Drawing submittal is called for in any specification section, include as
appropriate, scaled details, sizes, dimensions, performance characteristics, capacities,
test data, anchoring details, installation instructions, storage and handling instructions,
color charts, layout drawings, rough~in diagrams, wiring diagrams, controls, weights
and other pertinent data in addition to information specifically stipulated in the
specification section.
1) Arrange data and performance information in format similar to that provided in
Contract Documents.
2) Provide, at minimum, the detail specified in the Contract Documents.
f. If proposed equipment or materials deviate from the Contract Drawings or
Specifications in any way, clearly note the deviation and justify the said deviation in
detail in a separate letter immediately following transmittal sheet.
10. Samples:
a. Identification:
1) Identify sample as to transmittal number~ manufacturer, item, use, type, project
designation, tag number, standard specification section or drawing detail reference,
color, range, texture, fmish and other pertinent data.
2) If identifying information cannot be marked directly on sample without defacing or
adversely altering samples, provide a durable tag with identifying information
securely attached to the sample.
b. Include application specific brochures, and installation instructions.
.
.
00.. .52713-00123
Bozeman WRF Phase 1 Early Out Priority Improvements
01340-3
5/16/2007
c. Provide Contractor's stamp of approval on samples or transmittal form as indication of
Contractor's checking and verification of dimensions and coordination with interrelated
work.
d. Resubmit samples ofrejected items.
C. Miscellaneous Submittals:
1. Prepare in the format and detail specified in specification requiring the miscellaneous
submittal.
D. Operation and Maintenance Manuals:
1. Number transmittals for Operation and Maintenance Manual with original root number of
the approved Shop Drawing for the item.
2. Submittal format:
a. Interim and final submittals:
1) Submit electronically on Compact Disk (CDROM) in Portable Document Format
(PDF).
2) Each manual shall have a Table of Contents or Index with each listed item linked
to its corresponding topic.
3) All pages within the PDF document are to be generated at actual size for optimal
resolution quality (Le., 22 IN x 34 IN drawings rendered as such, etc.).
4) Ensure all pages are rotated properly so that the majority ofthe text or drawing
border is upright on the screen.
5) Do not password protect and/or lock the PDF document.
6) Submit two (2) paper copies.
b. Final submittals:
1) Ensure that all comments and annotations that are made on the interim submittals
are addressed.
3. Identify resubmittals with the original number plus a suffix letter starting with "A."
4. Paper copy submittals:
a. Submit Operation and Maintenance Manuals printed on 8w 1/2 x 11 IN size heavy first
quality paper with standard three-hole punching and bound in stiff metal hinged binder
constructed as a three-ring style.
1) Provide binders with titles on front and on spine of binder.
2) Tab each section of manuals for easy reference with plastic-coated dividers.
3) Provide index for each manual.
4) Provide plastic sheet lifters prior to first page and following last page.
b. Reduce drawings or diagrams bound in manuals to an 8-1/2 x 11 IN or 11 x 17 IN size.
1) However, where reduction is not practical to ensure readability, fold larger
drawings separately and place in vinyl envelopes which are bound into the binder.
2) Identify vinyl envelopes with drawing numbers.
5. Transmittal contents:
a. Submission of Operation and Maintenance Manuals is applicable but not necessarily
limited to:
1) Major equipment.
2) Equipment used with electrical motor loads of 1/6 HP nameplate or greater.
3) Specialized equipment including valves and instrumentation and control system
components for HV AC and process systems such as meters, recorders, and
transm itters.
4) Valves greater than 12 IN DIA.
5) Water control gates.
b. Operation and maintenance manuals shall include, but not necessarily be limited to, the
following detailed information, as applicable:
1) Equipment function, normal operating characteristics, limiting operations.
2) Assembly, disassembly, installation, alignment, adjustment, and checking
instructions.
3) Operating instructions for start-up, routine and normal operation, regulation and
control, shutdown, and emergency conditions.
.
.
.
00...52713-00123
Bozeman WRF Phase 1 Early Out Priority Improvements
01340 - 4
5/16/2007
.
4) Lubrication and maintenance instructions.
5) Guide to "troubleshooting."
6) Parts list and predicted life of parts subject to wear.
7) Outline, cross~section, and assembly drawings; engineering data; and electrical
diagrams, including elementary diagrams, wiring diagrams, connection diagrams,
word description of wiring diagrams and interconnection diagrams.
8) Test data and performance curves.
9) As-constructed fabrication or layout drawings and wiring diagrams if different than
approved Shop Drawings.
10) A list of recommended spare parts with a price list and a list of spare parts
provided under these Specifications.
11) Copies of installation instructions, parts lists or other documents packed with
equipment when delivered.
12) Instrumentation or tag numbers relating the equipment back to the Contract
Documents.
13) Include a filled-out, type-written copy ofthe Equipment Record Sheet, Exhibits Cl
and C2 as the first page(s) of each Operation and Maintenance Manual.
a) Complete maintenance requirements in detail. Simple reference to the Manual
is not acceptable.
14) For equipment items involving components or subunits, an Equipment Record
Sheet for each operating component or subunit is required.
TRANSMITTAL OF SUBMITTALS
1.5
A. Shop Drawings, Samples and Operation and Maintenance Manuals:
1. Transmit all submittals to:
.
HDR
1715 South Reserve Street, Suite C
Missoula, MT 59801
Attn: Dan Harmon P.E.
2. Utilize two (2) copies the Shop Drawing Transmittal Form to transmit all Shop Drawings
and samples.
3. Utilize two (2) copies ofthe O&M Manual Transmittal Form to transmit all Operation and
Maintenance Manuals.
4. All submittals must be from Contractor.
a. Submittals will not be received from or returned to subcontractors.
b. Operation and Maintenance Manual submittal stamp may be Contractor's standard
approval stamp.
5. Provide submittal information defining specific equipment or materials utilized on the
project.
a. Generalized product information, not clearly defining specific equipment or materials
to be provided, will be rejected.
B. Miscellaneous Submittals:
1. Transmit under Contractor's standard letter of transmittal or letterhead.
2. Submit in triplicate or as specified in individual specification section.
3. Transmitto:
.
HDR
1715 South Reserve Street, Suite C
Missoula, MT 59801
Atln: Dan Harmon P.E.
00...52713-00123
Bozeman WRF Phase 1 Early Out Priority Improvements
01340 - 5
5/16/2007
4. Provide copy ofletter of transmittal without attachments to Engineer's Resident Project
Representative.
C. Expedited Return Delivery:
1. Include prepaid express envelope or airbill in submittal transmittal package for any
submittals Contractor expects or requires express return mail.
2. Inclusion of prepaid express envelope or airbill does not obligate Engineer to conduct
expedited review of submittal.
D. Electronic submittals will not be accepted.
E. Fax Transmittals:
1. Permitted on a case-by-case basis to expedite review when approved by Engineer.
2. Requires hard copy transmittal to immediately follow.
a. Engineer will proceed with review of fax transmittal.
b. Engineer's approval or rejection comments will be recorded and returned on hard copy
transmittal.
3. Provisions apply to both:
a. Initial transmittal contents.
b. Supplemental information required to make initial transmittal contents complete.
1.6 ENGINEER'S REVIEW ACTION
.
A. Shop Drawings and Samples:
1. Items within transmittals will be reviewed for overall design intent and will receive one of
the following actions:
a. A - FURNISH AS SUBMITTED.
b. B - FURNISH AS NOTED (BY ENGINEER).
c. C - REVISE AND RESUBMIT.
d. D - REJECTED.
e. E - ENGINEER'S REVIEW NOT REQUIRED.
2. Submittals received will be initially reviewed to ascertain inclusion of Contractor's approval
stamp.
a. Submittals not stamped by the Contractor or stamped with a stamp containing language
other than that specified herein will not be reviewed for technical content and will be
returned without any action.
3. In relying on the representation on the Contractor's review and approval stamp, Owner and
Engineer reserve the right to review and process poorly organized and poorly described
submittals as follows:
a. Submittals transmitted with a description identifying a single item and found to contain
multiple independent items:
1) Review and approval will be limited to the single item described on the transmittal
letter.
2) Other items identified in the submittal will:
a) Not be logged as received by the Engineer.
b) Be removed from the submittal package and returned without review and
comment to the Contractor for coordination, description and stamping.
c) Be submitted by the Contractor as a new series number, not as are-submittal
number.
b. Engineer, at Engineer's discretion, may revise the transmittal letter item list and
descriptions, and conduct review.
1) Unless Contractor notifies Engineer in writing that the Engineer's revision of the
transmittal letter item list and descriptions was in error, Contractor's review and
approval stamp will be deemed to have applied to the entire contents of the
submittal package.
4. Submittals returned with Action "A" or "B" are considered ready for fabrication and
installation.
.
.
00...52713-00123
Bozeman WRF Phase I Early Out Priority Improvements
01340 - 6
5/16/2007
.
a. If for any reason a submittal that has an "A" or "B" Action is resubmitted, it must be
accompanied by a letter defining the changes that have been made and the reason for
the resubmittal.
b. Destroy or conspicuously mark "SUPERSEDED" all documents having previously
received "A" or "B" Action that are superseded by a resubmittal.
5. Submittals with Action "A" or "B" combined with Action "C" (Revise and Resubmit) or
"D" (Rejected) will be individually analyzed giving consideration as follows:
a. The portion ofthe submittal given "C" or "D" will not be distributed (unless previously
agreed to otherwise at the Preconstruction Conference).
1) One copy or the one transparency of the "C" or "D" drawings will be marked up
and returned to the Contractor.
a) Correct and resubmit items so marked.
b. Items marked "A" or "B" will be fully distributed.
c. If a portion of the items or system proposed are acceptable, however, the major part of
the individual drawings or documents are incomplete or require revision, the entire
submittal may be given "C" or "D" Action.
1) This is at the sole discretion of the Engineer.
2) In this case, some drawings may contain relatively few or no comments or the
statement, "Resubmit to maintain a complete package."
3) Distribution to the Owner and field will not be made (unless previously agreed to
otherwise).
6. Failure to include any specific information specified under the submittal paragraphs of the
Specifications will result in the submittal being returned to the Contractor with "C" or "D"
Action.
7. Calculations required in individual specification sections will be received for information
purposes only, as evidence calculations have been performed by individuals meeting
specified qualifications, and will be returned stamped "E. Engineer's Review Not Required"
to acknowledge receipt.
8. Transmittals of submittals which the Engineer considers as "Not Required" submittal
information, which is supplemental to but not essential to prior submitted information, or
items of information in a transmittal which have been reviewed and received "A" or "B"
Action in a prior submittal, will be returned with Action "E. Engineer's Review Not
Required. "
9. Samples may be retained for comparison purposes.
a. Remove samples when directed. Include in bid all costs of furnishing and removing
samples.
10. Approved samples submitted or constructed, constitute criteria for judging completed work.
a. Finished work or items not equal to samples will be rejected.
B. Operation and Maintenance Manuals:
1. Engineer will review and indicate one of the following review actions:
a. ACCEPTABLE.
b. FURNISH AS NOTED.
c. REVISE AND RESUBMIT.
d. REJECTED.
2. Acceptable submittals will be retained with the transmittal form returned with a request for
five additional copies.
3. Deficient submittals will be returned along with the transmittal form which will be marked
to indicate deficient areas.
.
.
00.. .52713-00123
Bozeman WRF Phase 1 Early Out Priority Improvements
01340 - 7
5/16/2007
PART 2 - PRODUCTS - NOT USED
.
PART 3 - PRODUCTS - NOT USED
END OF SECTION
.
.
00,. .52713-00123
Bozeman WRF Phase 1 Early Out Priority Improvements
01340-8
5/16/2007
.
SECTION 01370
SCHEDULE OF VALUES
PART 1 ~ GENERAL
1.1 DESCRIPTION
A. Submit to Owner a Schedule of Values allocated to the various portions ofthe Work within ten
(10) days after Effective Date of Agreement.
B. Upon request of Owner, support the values with data that will substantiate correctness.
C. An unbalanced Schedule of Values providing overpayment of Contractor on items of the Work
that will be performed early will not be accepted.
D. Revise and resubmit the Schedule of Values until acceptable to Owner. No Applications for
Payment shall be submitted until Schedule of Values is accepted.
E. The Schedule of Values, when accepted by Owner, shall be used only as the basis for the
Contractor's Applications for Payment.
F. Additional requirements specified elsewhere:
1. Section 01150: Measurement and Payment.
FORM AND CONTENT OF SCHEDULE OF VALUES
1.2
.
A. Type schedule on 8-1/2 IN by 11 IN white paper in a format indicated to page 2 of 3 of
Contractor's Application and Certificate of Payment; Contractor's standard forms and automated
printout will be considered for approval by Engineer upon Contractor's request. Identify
schedule with:
1. Title of Project and location.
2. Engineer and Project number.
3. Name and address of Contractor.
4. Contract designation.
5. Date of submission.
B. Schedule shall list the installed value of the component parts of the Work in sufficient detail to
serve as a basis for computing values for progress payments during construction.
C. Follow the Table of Contents of this Project Manual as the format for listing component items:
I . Breakdown shall be by specification section.
2. Identify each line item with the number and title of the respective major section of the
Specifications.
D. For each major line item list subvalues of major products or operations under the item.
E. Such items as bond and insurance premiums, temporary construction facilities, and job
mobilization and demobilization shall be listed separately:
I. Bonds and insurance premiums will be paid in the first application for payment. Contractor
shall submit invoice from surety and insurance company(ies).
2. If Contractor elects to be paid for temporary construction facilities, this will be paid on a
monthly basis based upon the monthly lease or rent payments.
3. If the Contractor elects to be paid for mobilization he shall also enter a cost for
demobilization:
a. Mobilization/demobilization cost shall not exceed 2 percent of the bid.
b. Demobilization costs shall not be less than 50 percent of mobilization costs.
4. Mobilization, Bonds and Insurance and temporary facilities may be included in first pay
application provided Contractor is on-site and performing work.
.
00...52713-00123
Bozeman WRF Phase 1 Early Out Priority Improvements
01370-1
5/412007
5. Demobilization shall only be paid after all work is complete, punch list and warranty items
are resolved, and all items listed in Section 01010 for substantial and final completion are
completed.
F. For the various portions of the Work:
1. Each item shall include a directly proportional amount of the Contractor's overhead and
profit.
2. For items on which progress payments will be requested for stored materials, break down
the value into:
a. The cost of the materials, delivered and unloaded.
b. The total value of labor for installing the material, including Contractor's overhead and
profit.
3. Cost of preparing and submitting Shop Drawings shall be included in each item. Shop
Drawings will not be a separate payment item.
4. . Sales taxes as required by State of Montana Tax Commission for each item.
G. The sum of all values listed in the schedule shall equal the total Contract Price.
1.3 SUBSCHEDULE OF UNIT MATERIAL VALUES
.
A. Submit a subschedule of unit costs and quantities for:
1. Products on which progress payments will be requested for stored products.
B. The form of submittal shall parallel that of the Schedule of Values, with each item identified the
same as the line item in the Schedule of Values.
C. The unit quantity for bulk materials shall include an allowance for normal waste.
D. The unit values for the materials shall be broken down into:
1. Cost of the material, delivered and unloaded at the site, with taxes paid.
2. Installation costs, including Contractor's overhead and profit.
.
END OF SECTION
.
00...52713-00123
Bozeman WRF Phase I Early Out Priority Improvements
01370 - 2
5/4/2007
. SECTION 01400
QUALITY CONTROL
PART 1 ~ LABORATORY TESTS
1.1 GENERAL
A. Contractor will coordinate with the Owner's basin mixer supplier and manufacturer's
representative for provision of manufacturer's Field Services.
1.2 CONTRACTOR'S RESPONSIBILITIES
A. Furnish incidental labor and facilities:
1. To provide access to Work to be tested.
2. To obtain and handle samples at the Project site or at the source of the product to be tested.
3. To facilitate inspections and tests
4. For storage and curing of test samples.
1.3 SUBMITTALS
A. Schedule of Manufacturer's field services.
PART 2 w SHOP TESTS (NOT USED)
.
PART 3 ~ MANUFACTURER'S FIELD SERVICES
3.1 GENERAL
A. Owner shall pay for the services of manufacturer's representatives to perform the specified
services.
B. Contractor shall schedule manufacturer's field services to avoid conflicting with other field work.
C. Related requirements specified elsewhere:
1. Inspections and testing required by laws, ordinances, rules, regulations, orders, or approvals
of public authorities: Conditions of the Contract.
3.2 QUALIFICATION OF MANUFACTURER'S REPRESENTATIVE
A. Authorized representative ofthe manufacturer.
B. Experienced in the application and installation ofthe subject equipment and capable of providing
a quality training program to Owner staff.
3.3
SERVICES PROVIDED BY REPRESENTATIVE
.
A. Manufacturer's representative to perform installation and pre~operation check:
I. Inspect, check, and adjust equipment as required and approve installation.
2. Be present when equipment is placed in operation.
3. Check for proper operation.
4. Check for motor overloads by measuring amperage and voltage on each phase.
5. Revisit the site as often as required to correct all problems and until equipment installation
and operation are acceptable to Engineer.
B. Instruct Owner's personnel in the operation and maintenance of the equipment.
00.. .52713-00123
Bozeman WRF Phase I Early Out Priority Improvements
01400- I
5/22/2007
C. Furnish 5 copies of completed Manufacturer's Field Service Report (enclosed at end of this
Section) to Engineer, through Contractor, certifying that:
1. Equipment is properly installed and lubricated.
2. Equipment is in accurate alignment.
3. Equipment is free from any undue stress imposed by connecting piping and anchor bolts.
4. Equipment has operated satisfactorily under design conditions.
D. Instructions of Owner's Personnel:
1. Prior to final inspection or acceptance, fully instruct Owner's designated operating and
maintenance personnel in the operation, adjustment and maintenance of all products,
equipment and systems.
2. Operation and maintenance information shall constitute the basis of instruction. Review
contents of information with personnel in full detail to explain all aspects of operations and
maintenance.
3. Training must be scheduled minimum thirty (30) days in advance with the Owner. Prior to
scheduling training, an agenda that lists the topics to be covered and time that will be spent
on each topic must be submitted and approved by Engineer. Trainer shall be available to
Owner for a minimum period of8 consecutive hours between 7:00 a.m. and 5:00 p.m. local
time.
.
PART 4 - FIELD TESTING
4.1 GENERAL
A. Contractor shall schedule all field testing to avoid conflicting with other manufacturer's field
services and other field testing.
B. Related requirements specified elsewhere:
1. Inspection and testing required by laws, ordinances, rules, regulations, orders, or approvals
of public authorities: Conditions of the Contract.
4.2 TESTING
.
A. Provide all required materials, labor, equipment, water, and power required for testing.
1. Owner shall provide water required for testing water reservoir for water tightness and piping
leakage testing.
.e. Perform all tests in presence of Engineer.
C. Prepare and submit to Engineer 5 copies of Manufacturer's Field Service Report detailing the
results of the tests and identifying corrective action for materials and equipment that fail to pass
field tests.
D. Repair all materials and equipment that fail during testing with no additional compensation.
PART 5 - SCHEDULES
5.1 MANUFACTURER'S FIELD SERVICES
A. Manufacturer's field services shall be provided for the following Contractor supplied equipment:
1. Section 11948: Aeration Basin Mixers.
.
00...52713-00123
Bozeman WRF Phase 1 Early Out Priority Improvements
01400- 2
5/22/2007
.
MANUFACTURER FIELD SERVICE REPORT
CONTRACT:
I. Description
A. Specification Section Number:
B. Manufacturer:
C. Representative:
D. Type of Service: Initial_ Interim_ Final
". General Review
A. The above referenced equipment/material/supplies have been inspected, checked,
and adjusted. Yes_ No_
(please explain)
B. The above referenced equipment/material/supplies were placed upon properly
prepared or suitable substrate. DNA_ Yes_ No_
. (please explain)
C. The above referenced equipment/material/supplies are free from any undue stress
imposed by any connected piping, anchor bolts or any other load.
DNA_ Yes_ No_
(please explain)
D. The above referenced equipment/material/supplies have operated under design
conditions. DNA_ Yes_ No_
(please explain)
E. The above referenced equipment/material/supplies have been installed per the
manufacturer's recommendations and the Procurement Documents, are approved,
and require no corrective work. Yes_No_
(please explain)
.
00...52713-00123
Bozeman WRF Phase 1 Early Out Priority Improvements
01400- 3
5/22/2007
F. The above referenced equipmenUmaterial/supplies are acceptable to the
manufacturer as installed providing the following corrective action is performed
(please list):
1.
2.
3.
4.
5.
.
III. Inspection Checklist
Item
OK
Readinas or
Comments
A. Bearings
B. Belts
C. Lubrication Levels
D. Vibration (Report attached)
E. AMPS
F. Volts
G. Rotation
H. Alignment
I. Anchor Bolts
J. Grout
K. Substrate Approval
L. Other
1. Motor Megger Test
Insulation
.
See attached Motor
Resistance Test
2.
3.
.
00.. .52713-00123
Bozeman WRF Phase 1 Early Out Priority Improvements
01400-4
5/22f2007
.
.
.
IV.
O&M Manuals
The O&M manual as presented contains all information required for proper operation,
maintenance, and instruction of this system. DNA_ Yes_ No_
(please explain)
V. Preventive Maintenance
The preventive maintenance summary outlined in the O&M manual is acceptable for
operation of the system throughout the warranty period. DNA_ Yes_ No_
(please explain)
VI. Spare Parts
All spare parts specified with the system are in new condition and are available on-site
for transfer to the Owner. DNA_ Yes_ No_
(please explain)
VII.
Operator Training/Classroom Instruction
Operator training and classroom instruction has been performed per the requirements of
the Procurement Documents. DNA_ Yes_ No_
(please explain)
VIII. Remarks:
00. _ .52713-00123
Bozeman WRF Phase 1 Early Out Priority Improvements
01400- 5
5/22/2007
IX. Certification
.
I hereby certify, that I, , am a duly authorized
representative of the manufacturer, that I am empowered by the manufacturer to
inspect, approve, and operate his equipment. That I am authorized to make
recommendations required to assure that the equipment furnished by the manufacturer
is complete and operational, except as modified herein. I also certify that all information
contained herein is true and accurate.
By:
Authorized Representative
For:
Date:
X. Acknowledgements
By:
For:
(Contractor)
Date:
By:
.
For:
HDR EngineerinQ,lnc
(Engineer)
Date:
END OF SECTION
.
00.. . 52713-00 123
Bozeman WRF Phase I Early Out Priority Improvements
01400- 6
5/2212007
.
.
.
SECTION 01600
PRODUCT DELIVERY, STORAGE, AND HANDLING
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Scheduling of product delivery.
2. Packaging of products for delivery.
3. Protection of products against damage from:
a. Handling.
b. Exposure to elements or harsh environments.
B. Related Sections include but are not necessarily limited to:
1. Division 0 - Bidding Requirements, Contract Forms, and Conditions ofthe Contract.
2. Division 1 - General Requirements.
C. Payment:
1. No payment will be made to Contractor for equipment or materials not properly stored and
insured or without approved shop drawings.
a. Previous payments for items will be deducted from subsequent progress estimate(s) if
proper storage procedures are not observed.
1.2
DELIVERY
A. Scheduling:
1. Schedule delivery of products or equipment as required to allow timely installation and to
avoid prolonged storage.
B. Packaging:
1. Deliver products or equipment in manufacturer's original unbroken cartons or other
containers designed and constructed to protect the contents from physical or environmental
damage.
C. Identification:
1. Clearly and fully mark and identifY as to manufacturer, item, and installation location.
D. Protection and Handling:
1. Provide manufacturer's instructions for storage and handling.
PART 2 - PRODUCTS - (NOT APPLICABLE TO THIS SECTION)
PART 3 - EXECUTION
3.1
PROTECTION, STORAGE AND HANDLING
A. Manufacturer's Instruction:
1. Protect all products or equipment in accordance with manufacturer's written directions.
a. Store products or equipment in location to avoid physical damage to items while in
storage.
b. Handle products or equipment in accordance with manufacturer's recommendations and
instructions.
2. Protect equipment from exposure to elements and keep thoroughly dry.
00.. .52713-00123
Bozeman WRF Phase 1 Early Out Priority Improvements
01600 - 1
5/4/2007
3. When space heaters are provided in equipment, connect and operate heaters during storage
until equipment is placed in service.
3.2 STORAGE FACILITIES
.
A. Owner shall provide temporary storage of mixer equipment and fiberglass stop gate assemblies.
Contractor shall coordinate with Owner for access.
3.3 FIELD QUALITY CONTROL
A. Inspect Deliveries:
1. Inspect all products or equipment delivered to the site prior to unloading. Reject all products
or equipment that are damaged, used, or in any other way unsatisfactory for use on Project.
B. Monitor Storage Area:
1. Monitor storage area to ensure suitable temperature and moisture conditions are maintained.
END OF SECTION
.
.
00...52713-00123
Bozeman WRF Phase I Early Out Priority Improvements
01600-2
5/4/2007
. SECTION 01640
PRODUCT SUBSTITUTIONS
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. The procedure for requesting substitution approval for a product which is specified by
descriptive or perfonnance criteria or defmed by reference to one or more of the following:
a. Name of manufacturer.
b. Name of vendor.
c. Trade name.
d. Catalog number.
2. This Section does not address substitutions for major equipment. See "Instructions to
Bidders."
.
B. Related Sections include but are not necessarily limited to:
1. Division 0 ~ Bidding Requirements, Contract Fonns, and Conditions of the Contract.
2. Division 1 - General Requirements.
C. Requests for Substitution - General:
1. Base all bids on materials, equipment, and procedures specified.
2. Certain types of equipment and kinds of material are described in specifications by means of
references to names of manufacturers and vendors, trade names, or catalog numbers. When
this method of specifying is used, it is not intended to exclude from consideration other
products bearing other manufacturer's or vendor's names, trade names, or catalog numbers,
provided said products are capable of accomplishing the same tasks as the products
specifically indicated.
3. Other types of equipment and kinds of material may be acceptable.
QUALITY ASSURANCE
1.2
A. In making request for substitution or in using an approved product, Contractor represents:
1. He has investigated proposed product, and has detennined that it is adequate or superior in
all respects to that specified, and that it will perfonn function for which it is intended.
2. He will provide same guarantee for substitute item as for product specified.
3. He will coordinate installation of accepted substitution into work, to include building
modifications if necessary, making such changes as may be required for work to be
complete in all respects.
4. He waives all claims for additional costs related to substitution which subsequently arise.
1.3 DEFINITIONS
1.4
A. Product: Manufactured material or equipment.
PROCEDURE FOR REQUESTING SUBSTITUTION
.
A. Considered after award of Contract.
1. Considered only if:
a. Or-equals are unavailable due to strike, discontinued production of products meeting
specified requirements, or other factors beyond control of Contractor; or,
b. Contractor proposes a cost reduction incentive to the Owner.
B. Written requests through Contractor only.
C. Transmittal Mechanics:
00.. .52713-00123
Bozeman WRF Phase 1 Early Out Priority Improvements
01640 ~ 1
5/4/2007
1. Follow the transmittal mechanics prescribed for Shop Drawings in Section 01340. Product
substitution will be treated in a manner similar to "deviations," as described in Paragraph
1.4A.9.f. of Section 01340. List the letter describing the deviation and justifications on the
transmittal form in the space provided under the column with the heading
"DESCRIPTION." Include in the transmittal letter, either directly or as a clearly marked
attachment, the items listed in Paragraph D below.
D. Transmittal Contents:
1. Product identification:
a. Manufacturer's name.
b. Telephone number and representative contact name.
c. Specification section or drawing reference of originally specified product, including
discrete name or tag number assigned to original product in the Contract Documents.
2. Manufacturer's literature clearly marked to show compliance of proposed product with
Contract Documents.
3. Itemized comparison of original and proposed product addressing product characteristics
including but not necessarily limited to:
a. Size.
b. Composition or materials of construction.
c. Weight.
d. Electrical or mechanical requirements.
4. Product experience:
a. Location of past projects utilizing product.
b. Name and telephone number of persons associated with referenced projects
knowledgeable concerning proposed product.
c. Available field data and reports associated with proposed product.
5. Data relating to changes in construction schedule.
6. Data relating to changes in cost.
7. Samples:
a. At request of Engineer.
b. Full size if requested by Engineer.
c. Held until substantial completion.
d. Engineer not responsible for loss or damage to samples.
1.5 APPROVAL OR REJECTION
.
.
A. Written approval or rejection of substitution given by the Engineer.
B. Engineer reserves the right to require proposed product to comply with color and pattern of
specified product if necessary to secure design intent.
C. In event substitution results in a change of Contract price or time, provisions in General
Conditions will be applied for adjustment.
D. Substitutions will be rejected if:
1. Submittal is not through the Contractor with his stamp of approval.
2. Requests are not made in accordance with this Section.
3. In the Engineer's opinion, acceptance will require substantial revision of the original design.
4. In the Engineer's opinion, substitution will not perform adequately the function consistent
with the design intent.
PART 2. PRODUCTS. (NOT APPLICABLE TO THIS SECTION)
PART 3. EXECUTION - (NOT APPLICABLE TO THIS SECTION)
.
END OF SECTION
00.. .52713-00123
Bozeman WRF Phase 1 Early Out Priority Improvements
01640 - 2
5/4/2007
. SECTION 01700
CONTRACT CLOSEOUT
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Description of procedures to be followed and related work required to accomplish an
orderly transfer of Project deliverables from the Contractor to the City. .
B. Related Sections include but are not necessarily limited to:
1. Division 0 - Bidding Requirements, Contract Forms, and Conditions of the Contract.
2. Division 1 - General Requirements.
1.2 DEFINITIONS
A. Punch List: The stated qualification accompanying the Owner's Certificate of Substantial
Completion or any list of construction items found to be deficient or incomplete through review
of the Work by Owner and communicated in writing to Contractor at any time during the
Contract Period.
1.3
SUBMITTALS
.
A. Final Completion:
1. After compliance with Substantial Completion and Punchlist, Contractor to notify Owner
that the Contractor considers the entire Work to have progressed to Final Completion and
provide the following:
a. Lien waivers;
b. Evidence of payments, if required by City;
c. Warranties.
PART 2 - PRODUCTS
2.1 CONSTRUCTION PRODUCTS
A. All construction products not used must be removed from the site in their entirety or,
arrangements shall be made with City for final disposition on site.
PART 3 - EXECUTION
3.1 INSPECTION FOR FINAL ACCEPTANCE AND PAYMENT
.
A. When the items of Work on the Punch List(s) have been completed, and Owner considers the
Work of the entire Project is complete, Contractor shall submit written certification that:
1. Contract Documents have been reviewed.
2. Work has been inspected by Owner for compliance with Contract Documents.
3. Workhas been completed in accordance with Contract Documents.
4. Work has received Final Cleaning: Section 01710.
5. Work is completed and ready for final inspection.
B. Owner will make an inspection with the Contractor to verify the status of completion within 10
working days after receipt of such certification.
C. Should Owner consider that the Work is incomplete or defective:
00.. .52713-00123
Bozeman WRF Phase 1 Early Out Priority Improvements
01700 - 1
5/4/2007
1. Owner: Notify the Contractor in writing within 5 working days, listing the incomplete or
defective work.
2. Contractor: Remedy the stated deficiencies within 10 working days, and send a second
written certification to Owner that the Work is complete.
3. Owner will reinspect the Work after he has been notified by Contractor.
D. When Owner finds the Work acceptable in accordance with the Contract Documents: Owner
requests Contractor to make closeout submittals.
E. Reinspection costs incurred by the Owner related to reinspection or rework will be billed and
deducted by the Owner from the final payment to the Contractor not limited to Owner,
architects, attorney and other professional costs.
.
3.2 FINAL APPLICATION FOR PAYMENT
A. Complete demobilization prior to submitting final application for payment.
B. Submit final application for payment in accordance with procedures and requirements stated in
the Conditions of the Contract.
C. Prior to the acceptance of the Work and final payment, the City will require from the Contractor
a certificate in form substantially as follows:
"I (We) hereby certify that all Work has been performed and materials supplied in accordance
with the Contract Documents for the above Work, and that:
1. There have been no unauthorized substitutions of subcontractors; nor have any subcontracts
been entered into without the names of the subcontractors having been submitted to the City
prior to the start of such subcontracted Work;
2. No subcontract was assigned or transferred or performed by any subcontractor other than
the original subcontractor, without prior notice having been submitted to the City together
with the names of all subcontractors;
3. All claims for material and labor and other services performed in connection with these
specifications have been paid."
D. See Section 00500 for additional requirements. Submit lien releases from all subcontractors and
suppliers. Submit consent of surety for final payment.
E. Owner will review application and recommend final payment within 10 working days of receipt
of application.
.
END OF SECTION
.
00.. .52713-00123
Bozeman WRF Phase 1 Early Out Priority Improvements
01700.2
5/4/2007
.
SECTION 01710
CLEANING
PART 1. GENERAL
1.1 SUMMARY
A. Section Includes:
1. Intermediate and final cleaning of Work not including special cleaning of closed systems
specified elsewhere.
B. Related Sections include but are not necessarily limited to:
1. Division 0 - Bidding Requirements, Contract Forms, and Conditions ofthe Contract.
2. Division I - General Requirements.
1.2 STORAGE AND HANDLING
A. Store cleaning products and cleaning wastes in containers specifically designed for those
materials.
1.3 SCHEDULING
A. Schedule cleaning operations so that dust and other contaminants disturbed by cleaning process
will not fall on newly painted surfaces.
.
PART 2 - PRODUCTS
2.1 MATERIALS
A. Cleaning Agents:
1. Compatible with surface being cleaned.
2. New and uncontaminated.
3. For Manufactured Surfaces: Material recommended by manufacturer.
PART 3 - EXECUTION
3.1 CLEANING - GENERAL
A.
S.
C.
D.
E.
F.
G.
. H.
00...52713-00123
Prevent accumulation of wastes that create hazardous conditions.
Conduct cleaning and disposal operations to comply with laws and safety orders of governing
authorities.
Do not dispose of volatile wastes such as mineral spirits, oil, or paint thinner in storm or sanitary
drains or sewers.
Dispose of degradable debris at an approved solid waste disposal site.
Dispose of nondegradable debris at an approved solid waste disposal site or in an alternate
manner approved by Engineer and regulatory agencies.
Handle materials in a controlled manner with as few h~dlings as possible.
Do not drop or throw materials from heights greater than 4 FT or less than 4 FT if conditions
warrant greater care.
On completion ofwork,-leave area in a clean, natural looking condition.
Bozeman WRF Phase 1 Early Out Priority Improvements
01710-1
5/4n007
1. Remove all signs of temporary construction and activities incidental to construction of
required permanent Work.
I. Do not bum on-site.
.
3.2 INTERIOR CLEANING
A. Cleaning During Construction:
1. Keep work areas clean so as not to hinder health, safety or convenience of personnel in
existing facility operations.
2. At maximum weekly intervals, dispose of waste materials, debris, and rubbish.
3. Vacuum clean interior areas when ready to receive finish painting.
a. Continue vacuum cleaning on an as-needed basis, until substantial completion.
B. Final Cleaning:
1. Complete immediately prior to Demonstration Period.
2. Remove grease, mastic, adhesives, dust, dirt, stains, fingerprints, labels, and other foreign
materials from sight-exposed surfaces.
3. Wipe all lighting fixture reflectors, lenses, lamps and trims clean.
4. Wash and shine glazing and mirrors.
5. Polish glossy surfaces to a clear shine.
6. Ventilating systems:
a. Clean permanent filters and replace disposable filters if units were operated during
construction.
b. Clean ducts, blowers and coils if units were operated without filters during
construction.
7. Replace all burned out lamps.
8. Broom clean process area floors.
9. Mop office and control room floors.
3.3 EXTERIOR (SITE) CLEANING
.
A. Cleaning During Construction:
1. Construction debris:
a. Confine in strategically located container(s):
1) Cover to prevent blowing by wind.
2) Haul from site minimum once a week.
b. Remove from work area to container daily.
2. Vegetation: Keep weeds and other vegetation trimmed to 3 IN maximum height.
3. Soils, sand, and gravel deposited on paved areas and walks:
a. Remove as required to prevent muddy or dusty conditions.
b. Do not flush into storm sewer system.
B. Final Cleaning:
1. Remove trash and debris containers from site.
a. Re-seed areas disturbed by location of trash and debris containers.
2. Clean paved roadways.
3.4 FIELD QUALITY CONTROL
A. Immediately prior to Demonstration Period, conduct an inspection with Engineer to verify
condition of all work areas.
END OF SECTION
.
00.. .52713-00123
Bozeman WRF Phase 1 Early Out Priority Improvements
01710-2
5/412007
.
.
.
SECTION 02072
DEMOLITION, CUTTING AND PATCHING
PART 1 w GENERAL
1.1 SUMMARY
A. Section Includes:
1. Demolition, cutting and patching of existing construction where shown on Drawings, or as
required to accommodate new work shown or specified.
B. Related Sections include but are not necessarily limited to:
1. Division 0 - Bidding Requirements, Contract Forms, and Conditions of the Contract.
2. Division 1 - General Requirements.
3. Section 09905 - Painting and Protective Coatings.
1.2 SUBMITTALS
A. Shop Drawings:
1. See Section 01340 for requirements for the mechanics and administration of the submittal
process.
2. Indicating manufacturer and type of:
a. Proposed nonshrink grout.
b. Epoxy bonding adhesive.
c. Proposed materials and methods to be used for matching and repairing existing
construction.
1.3 DELIVERY, STORAGE, AND HANDLING
A. General:
1. Salvage items (basin central weir gates), designated for Owner's salvage, as a functional
unit.
2. Clean, list and tag for storage.
3. Protect from damage and deliver to location designated.
1.4 SITECONDITIONS
A. Perform preliminary investigations as required to ascertain extent of work.
1.5 SEQUENCING AND SCHEDULING
')
A. Coordinate and reschedule work as required to preclude interference with other operations.
PART 2 - PRODUCTS
2.1
ACCEPTABLE MANUFACTURERS
A. Subject to compliance with the Contract Documents, the following products and manufacturers
are acceptable:
I. Nonshrink grout:
a. Supreme Grout by Gifford Hill.
b. Masterflow 713 Plus by BASF Building Systems.
c. Sika Grout 212 by Sika.
2. Epoxy bonding adhesive:
a. Euco No.452 MV by Euclid Chemical Co.
b. Sikadur 32, Hi-Mod by Sika Corporation.
00__52713-00123
Bozeman WRF Phase I Early Out Priority Improvements
02072 - I
5/4/2007
B. Submit request for substitution in accordance with Specification Section 01640.
2.2 MATERIALS
.
A. Temporary Partitions or Basin Protection Barriers:
1. Plywood: 1/2 IN minimum for interior or exterior use.
B. Nonshrink Grout:
1. Nonmetallic, noncorrosive and nonstaining.
2. Premixed with only water to be added in accordance with manufacturer's instructions at
jobsite.
3. Grout to produce a positive but controlled expansion. Mass expansion not to be created by
gas liberation or by other means.
4. Minimum compressive strength at 28 days to be 6500 psi.
5. Coat exposed edges of grout with a cure/seal compound recommended by grout
manufacturer.
C. Epoxy Bonding Adhesive:
1. Two component, moisture insensitive adhesive manufactured for the purpose of bonding
fresh concrete to hardened concrete.
PART 3 - EXECUTION
3.1 PREPARATION
A. Provide temporary partitions as required in aeration basins to protect existing aerator.
1. Construct partitions of braced plywood in exterior areas.
E. Provide covered passageways where necessary to ensure safe passage of persons in or near areas
of work.
C. Provide substantial barricades and safety lights as required.
D. Provide temporary weather protection as necessary.
3.2 INST ALLA TION
.
A. Cutting and Removal:
1. Remove existing work indicated to be removed, or as necessary for installation of new
work.
2. Neatly cut and remove materials, and prepare all openings to receive new work.
3. Remove masonry or concrete in small sections.
B. Removal of Existing Anchor Bolts or Other Protruding Elements:
1. Removed to a depth of 1/2 IN from finished surface.
2. Fill void with non-shrink grout.
C. Matching and Patching:
1. Walls, ceilings, floors or partitions:
a. Repair abutting walls, ceilings, floors or partitions disturbed by removal.
b. Match and patch existing construction disturbed during installation of new work.
2. Methods and materials:
a. Similar in appearance, and equal in quality to adjacent areas for areas or surfaces being
repaired.
b. Subject to review of Engineer.
D. Salvaged Items:
1. Thoroughly dry and clean all metal surfaces.
2. Dispose of items or materials not designated for Owner's salvage or reuse. Promptly remove
from site.
3. Do not store or sell Contractor salvaged items or materials on site.
.
00.. .52713-00123
Bozeman WRF Phase 1 Early Out Priority Improvements
02072 - 2
5/412007
.
.
.
E. Clean Up:
1. Transport debris and legally dispose of off site.
END OF SECTION
00...52713-00123
5/4/2007
Bozeman WRF Phase I Early Out Priority Improvements
02072 - 3
.
SECTION 05505
METAL FABRICATIONS
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Custom fabricated metal items and certain manufactured units not otherwise indicated to be
supplied under work of other Sections.
2. Design of all temporary bracing not indicated on Drawings.
B. Related Sections include but are not necessarily limited to:
l. Division 0 - Bidding Requirements, Contract Forms, and Conditions of the Contract.
2. Division 1 - General Requirements.
QUALITY ASSURANCE
1.2
.
A. Referenced Standards:
1. Aluminum Association (AA):
a. ADMwl, Aluminum Design Manual.
b. 45, Designation System for Aluminum Finishes.
2. American Institute of Steel Construction (AISC):
a. Manual of Steel Construction - Allowable Stress Design (ASD).
b. Specifications for Structural Steel Buildings (referred to herein as AISC specification).
3. ASTM International (ASTM):
a. A6, Standard Specification for General Requirements for Rolled Structural Steel Bars,
Plates, Shapes, and Sheet Piling.
b. A36, Standard Specification for Carbon Structural Steel.
c. A123, Standard Specification for Zinc (Hot-Dip Galvanized) Coatings on Iron and Steel
Products.
d. AIS3, Standard Specification for Zinc Coating (Hot-Dip) on Iron and Steel Hardware.
e. A666, Standard Specification for Annealed or Cold- Worked Austenitic Stainless Steel
Sheet, Strip, Plate, and Flat Bar.
f. B308, Standard Specification for Aluminum-Alloy 6061-T6 Standard Structural
Profiles.
g. B632, Standard Specification for Aluminum-Alloy Rolled Tread Plate.
h. F467, Specification for Nonferrous Nuts for General Use.
i. F468, Specification for Nonferrous Bolts, Hex Cap Screws, and Studs for General Use.
j. FS93, Specification for Stainless Steel Bolts, Hex Cap Screws, and Studs.
4. American Welding Society (A WS):
a. AS.I, Standard Specification for Carbon Steel Electrodes for Shielded Metal Arc
Welding.
b. Dl.l, Structural Welding Code Steel.
c. D 1.2, Structural Welding Code Aluminum.
DEFINITIONS
1.3
.
A. Installer or Applicator:
1. Installer or applicator is the person actually installing or applying the product in the field at
the Project site.
2. Installer and applicator are synonymous.
B. Hardware: As defined in ASTM A1S3.
00.. .52713-00123
Bozeman WRF Phase 1 Early Out Priority Improvements
05505 - I
5/15(2007
C. Galvanizing: Hot~dip galvanizing per ASTM Al23 or ASTM A153 with minimum coating of
2.0 OZ of zinc per square foot of metal (average of specimens) unless noted otherwise or
dictated by standard.
1.4 SUBMITTALS
.
A. Shop Drawings:
1. See Section 01340 for requirements for the mechanics and administration of the submittal
process.
2. Fabrication and/or layout drawings and details:
a. Submit drawings for all fabrications and assemblies.
1) Include erection drawings, plans, sections, details and connection details.
b. Identify materials of construction, shop coatings and third party accessories.
1.5 DELIVERY, STORAGE AND HANDLING
A. Deliver and handle fabrications to avoid damage.
B. Store above ground on skids or other supports to keep items free of dirt and other foreign debris
and to protect against corrosion.
PART 2 - PRODUCTS
2.1 ACCEPTABLE MANUFACTURERS
A. Subject to compliance with the Contract Documents, the following manufacturers are
acceptable:
1. Galvanizing repair paint:
a. ZRC Products.
B. Submit request for substitution in accordance with Specification Section 01640.
2.2 MATERIALS
.
A. Steel:
1. Structural:
a. W~shapes and WT-shapes: ASTM A992, Grade 50.
b. All other plates and rolled sections: ASTM A36.
2. Bolts and nuts:
a. ASTM A307, Grade A.
3. Welding electrodes: A WS 01.1, E70 Series.
4. Steel forgings: ASTM A668.
B. Stainless Steel:
1. Minimum yield strength of30,000 psi and minimum tensile strength of75,000 psi.
a. Bars, shapes: ASTM A276, Type 304.
b. Bolts and nuts: ASTM F593, Type 304.
2. Minimum yield strength of25,000 psi and minimum tensile strength of70,000 psi.
a. Strip, plate and flat bar for welded connections, ASTM A666, Type 304L.
3. Welding electrodes: In accordance with A WS for metal alloy being welded.
C. Aluminum:
1. Alloy 6061- T6, 32,000 psi tensile yield strength minimum.
a. ASTM B221 and ASTM B308 for shapes including beams, channels, angles, tees and
zees.
b. Weir plates, baffles and deflector plates, ASTM B209.
D. Washers: Same material and alloy as found in accompanying bolts and nuts.
E. Embedded Anchor Bolts:
.
00...52713-00123
Bozeman WRF Phase 1 Early Out Priority Improvements
05505 - 2
5/1512007
.
1. Type 304 or 316 stainless steel with matching nut and washer.
F. Galvanizing Repair Paint:
I. High zinc dust content paint for regalvanizing welds and abrasions.
2. Dried film shall contain not less than 93 percent zinc dust by weight.
3. Similar to ZRC by ZRC Products.
4. VOC: 0 LBS per GAL.
G. Dissimilar Materials Protection: Coat all aluminum surfaces to be in contact with concrete with
minimum 6 mil epoxy coating.
2.3 MANUFACTURED UNITS
A. Aluminum Checkered Plate (alternative plate material):
I. Conform to ASTM B632.
a. Diamond pattern: Use one (1) pattern throughout Project.
b. Material: Type 6061- T6.
2. Design live load: Not less than 100 psfplus a concentmted load 0000 LBS with maximum
deflection of 1/300 of span under a superimposed live load of 50 psf.
3. Reinforce as necessary with aluminum angles.
4. Plate sections:
a. Maximum 3 FT wide.
b. Minimum 3/8 IN thick.
c. Maximum 100 LBS per section if required to be removable.
5. Provide joints at center of all openings unless shown otherwise.
a. Reinforce joints and openings with additional angles to provide required load carrying
capacity .
2.4 FABRICATION
. A. Verify field conditions and dimensions prior to fabrication.
B. Form materials to shapes indicated with straight lines, true angles, and smooth curves.
1. Grind smooth all rough welds and sharp edges.
a. Round all comers to approximately 1/16 IN nominal radius.
C. Provide drilled or punched holes with smooth edges.
1. Punch or drill for field connections and for attachment of work by other trades.
D. Weld Permanent Shop Connections:
1. Welds to be continuous fillet type unless indicated otherwise.
2. Full penetration butt weld at bends in stair stringers and ladder side rails.
3. Weld structural steel in accordance with A WS DI.1 using Series E70 electrodes conforming
to AWS A5.I.
4. Weld aluminum in accordance with A WS DI.2.
5. All headed studs to be welded using automatically timed stud welding equipment.
6. Grind smooth welds that will be exposed.
E. Conceal fastenings where practicable.
F. Fabricate work in shop in as large assemblies as is practicable.
G. Maximum tolerance for difference in depth between checkered plate or grating depth and seat or
support angle depth: 118 IN.
H. Maximum distance between edge of grating or checkered plate and face of embedded seat angle
or face of wall or other structural member: 1/4 IN.
2.5
SOURCE QUALITY CONTROL
.
A. Surface Preparation:
1. Refer to Section 09905 for surface preparation requirements.
00...52713-00123
Bozeman WRF Phase 1 Early Out Priority Improvements
05505 - 3
5/15fl007
B. Shop Applied Paint Coating Application:
1. Refer to Section 09905 for painting requirements.
.
PART 3 - EXECUTION
3.1 PREPARATION
A. Provide items to be built into other construction in time to allow their installation.
1. If such items are not provided in time for installation, cut in and install.
B. Prior to installation, inspect and verify condition of substrate.
1. Installation of product constitutes installer's acceptance of substrate condition for product
compatibility.
C. Correct surface defects or conditions which may interfere with or prevent a satisfactory
installation.
1. Field welding aluminum is not permitted unless approved in writing by Engineer.
3.2 lNST ALLA TION
A. Set metal work level, true to line, plumb.
]. Shim and grout as necessary.
B. Bolt Field Connections: Where practicable, conceal fastenings.
C. Grind welds smooth where field welding is required.
D. Field cutting grating or checkered plate to correct fabrication errors is not acceptable.
1. Replace entire section.
E. Remove all burrs and radius all sharp edges and comers of miscellaneous plates, angles, framing
system elements, etc.
F. Unless noted or specified otherwise:
1. Connect aluminum to aluminum with 1/2 IN DIA aluminum bolts.
a. Provide dissimilar metals protection.
G. Coat aluminum surfaces in contact with dissimilar materials in accordance with Section 09905.
H. Repair damaged galvanized surfaces in accordance with ASTM A780.
I. Prepare damaged surfaces by abrasive blasting or power sanding.
2. Apply galvanizing repair paint to minimum 6 mils DFT in accordance with manufacturer's
instructions.
.
3.3 CLEANING
A. After erection, installation or application, clean all miscellaneous metal fabrication surfaces of
all dirt, weld slag and other foreign matter.
B. Provide surface acceptable to receive field applied paint coatings specified in Section 09905.
END OF SECTION
.
00...52713-00123
Bozeman WRF Phase I Early Out Priority Improvements
05505 - 4
5/1512007
.
.
DIVISION 7
THERMAL AND MOISTURE PROTECTION
.
.
SECTION 07900
JOINT SEALANTS
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Sealant work.
B. Related Sections include but are not necessarily limited to:
1. Division 0 - Bidding Requirements, Contract Forms, and Conditions of the Contract.
2. Division 1 ~ General Requirements.
C. Work included consists of but is not necessarily limited to:
1. Sealing all joints which will permit penetration moisture.
a. Work may include the following:
1) Sealant at basin stop plates and weirs.
2) Other joints where calking or sealant is indicated.
QUALITY ASSURANCE
1.2
.
A. Referenced Standards:
1. American Concrete Institute (ACI):
a. 302.1 R, Guide for Concrete Floor and Slab Construction.
2. ASTM International (ASTM):
a. C834, Standard Specification for Latex Sealants.
b. C920, Standard Specification for Elastomeric Joint Sealants.
3. National Sanitation Foundation International (NSF).
4. Underwriters Laboratories, Inc., (UL).
DEFINITIONS
1.3
A. "Caulk(ing)," "calk(ing)," and "sealant": Joint sealant work.
B. Installer or Applicator:
1. Installer or applicator is the person actually installing or applying the product in the field at
the Project site.
2. Installer and applicator are synonymous.
1.4 SUBMITTALS
A. Shop Drawings:
1. See Section 01340 for requirements for the mechanics and administration of the submittal
process.
2. Product technical data including:
a. Acknowledgement that products submitted meet requirements of standards referenced.
b. Manufacturer's installation instructions.
c. Manufacturer's recommendations for joint cleaner, primer, backer rod, tooling and bond
breaker.
B. Miscellaneous Submittals: See Section 01340 for requirements for the mechanics and
administration of the submittal process.
DELIVERY, STORAGE, AND HANDLING
1.5
.
A. Deliver material in manufacturer's original unopened containers with labels intact: Labels shall
indicate contents and expiration date on material.
00...52713-00123
Bozeman WRF Phase 1 Early Out Priority Improvements
07900 . 1
5/1512007
PART 2 ~ PRODUCTS
.
2.1 ACCEPTABLE MANUFACTURERS
A. Subject to compliance with the Contract Documents, the following manufacturers are
acceptable:
1. Polysulfide rubber sealant:
a. Pecora.
b. Sonneborn.
c. Morton Polymer Systems.
2. Backer rod, compressible filler, primer, joint cleaners, bond breaker: As recommended by
sealant manufacturer.
B. Submit request for substitution in accordance with Specification Section 01640.
2.2 MATERIALS
A. Sealants - General:
1. Provide colors matching materials being sealed.
2. Where compound is not exposed to view in fmished work, provide manufacturer's color
which has best performance.
3. Nonsagging sealant for vertical and overhead horizontal joints.
4. Sealants for horizontal joints: Self-leveling pedestrian/traffic grade.
B. Sealant Backer Rod and/or Compressible Filler:
I. Closed cell polyethylene, polyethylene jacketed polyurethane foam, or other flexible,
nonabsorbent, nonbituminous material recommended by sealant manufacturer to:
a. Control joint depth.
b. Break bond of sealant at bottom of joint.
c. Provide proper shape of sealant bead.
d. Serve as expansion joint filler.
C. Polysulfide Rubber Sealant:
1. One (1) or two (2) component.
2. Meet ASTM C920.
a. Pecora Synthacalk GC2+.
b. Sonneborn - Sonolastic - two-part polysulfide sealant.
c. Morton Polymer Systems - Thiokol Sealants.
.
PART 3 ~ EXECUTION
3.1 PREPARATION
A. Before use of any sealant, investigate its compatibility with j oint surfaces, fillers and other
materials in joint system.
B. Use only compatible materials.
C. Where required by manufacturer, prime joint surfaces.
I. Limit application to surfaces to receive calking.
2. Mask off adjacent surfaces.
D. Provide joint depth for joints receiving polyureajoint filler in accordance with manufacturer's
recommendations.
3.2 INSTALLATION
A. Install products in accordance with manufacturer's instructions and UL requirements.
B. Clean all joints.
.
00...52713-00123
Bozeman WRF Phase 1 Early Out Priority ImprovementJJ
07900 - 2
5/1512007
.
.
.
C. Make all joints water and airtight.
D. Make depth of sealing compounds, except expanding foam and polyurea sealant, not more than
one-half width of joint, but in no case less than 1/4 IN nor more than 1/2 IN unless
recommended otherwise by the manufacturer.
E. Provide correctly sized backer rod, compressible filler or compressible sealant in all joints to
depth recommended by manufacturer:
1. Take care to not puncture backer rod and compressible filler.
2. Provide joint backer rod as recommended by the manufacturer for polyurea joint filler.
F. Apply bond breaker where required.
G. Tool sealants using sufficient pressure to fill all voids.
H. Upon completion, leave calking with smooth, even, neat finish.
I. Where piping, conduit, ductwork, etc., penetrate wall, seal each side of wall opening.
J. Install compressible sealant to position at indicated depth.
1. Take care to avoid contamination of sides of joint.
2. Protect side walls of joint (to depth of finish sealant).
3. Install with adhesive faces in contact with joint sides.
4. Install finish sealant where indicated.
3.3 SCHEDULE
A. Furnish sealant as indicated for the following areas:
1. Sealant which will be immersed in wastewater or sewage: Polysulfide.
END OF SECTION
00...52713-00123
Bozeman WRF Phase 1 Early Out Priority Improvements
07900 . 3
5/1512007
.
SECTION 09905
PAINTING AND PROTECTIVE COATINGS
PART 1 ~ GENERAL
1.1 SUMMARY
A. Section Includes:
I. High perfonnance industrial coatings (HPIC).
2. Architectural paints (AP).
3. Special coatings (SC).
4. Any other coating, thinner, accelerator, inhibitor, etc., specified or required as part of a
complete System specified in this Section.
5. Minimum surface preparation requirements.
B. Related Sections include but are not necessarily limited to:
1. Division 0 - Bidding Requirements, Contract Fonns, and Conditions of the Contract.
2. Division I - General Requirements.
3. Section 03348 - Concrete Finishing and Repair of Surface Defects.
4. Section 05505 - Metal Fabrications.
5. Section 11005 - Equipment: Basic Requirements.
QUALITY ASSURANCE
1.2
.
A. Referenced Standards:
I. ASTM International (ASTM):
a. D4258, Standard Practice for Surface Cleaning Concrete for Coating.
b. D4259, Standard Practice for Abrading Concrete.
c. D4261, Standard Practice for Surface Cleaning Concrete Unit Masonry for Coating.
d. 04262, Standard Test Method for pH of Chemically Cleaned or Etched Concrete
Surfaces.
e. 04263, Standard Test Method for Indicating Moisture in Concrete by the Plastic Sheet
Method.
f. E84, Standard Test Method for Surface Burning Characteristics of Building Materials.
2. American Water Works Association (A WW A).
3. NACE International (NACE).
4. National Bureau of Standards (NBS):
a. Certified Coating Thickness Calibration Standards.
5. National Fire Protection Association (NFPA):
a. 101, Life Safety Code.
6. National Sanitation Foundation International (NSF).
7. Steel Door Institute/American National Standards Institute (SOl/ANSI):
a. A250.10, Test Procedure and Acceptance Criteria For Prime Painted Steel Surfaces for
Steel Doors.
8. The Society for Protective Coatings (SSPC):
a. PA 2, Measurement of Dry Paint Thickness with Magnetic Gages.
b. SP I, Solvent Cleaning.
c. SP 2, Hand Tool Cleaning.
d. SP 3, Power Tool Cleaning.
9. The Society for Protective Coatings/NACE International (SSPC/NACE):
a. SP 5/NACE No. I, White Metal Blast Cleaning.
b. SP 6/NACE No.3, Commercial Blast Cleaning.
c. SP 7/NACE No.4, Brush-off Blast Cleaning.
d. SP 10/NACE No.2, Near-White Blast Cleaning.
.
00.. .52713-00123
Bozeman WRF Phase I Early Out Priority Improvements
09905 - I
5/22/2007
e. SP 12/NACE No.5, Surface Preparation and Cleaning of Steel and Other Hard Materials
by High and Ultrahigh Pressure Water Jetting Prior to Recoating.
f. SP 13/NACE No.6, Surface Preparation of Concrete.
B. Qualifications:
1. Coating manufacturer's authorized representative shall provide written statement attesting
that applicator has been instructed on proper preparation, mixing and application procedures
for coatings specified.
2. Applicators shall have minimum of 10 years experience in application of similar products on
similar project.
a. Provide references for minimum of three (3) different projects completed in last five (5)
years with similar scope of work.
b. Include name and address of project, size of project in value (painting) and contact
person.
C. Miscellaneous:
1. Furnish paint through one (1) manufacturer unless noted otherwise.
2. Coating used in all corridors and stairways shall meet requirements ofNFPA 101 and
ASTM E84.
D. Deviation from specified mil thickness or product type is not allowed without written
authorization of Engineer.
E. Material shall not be thinned unless approved, in writing, by paint manufacturer's authorized
representative.
1.3 DEFINITIONS
A. Installer or Applicator;
1. Installer or applicator is the person actually installing or applying the product in the field at
the Project site.
2. Installer and applicator are synonymous.
B. Approved Factory Finish: Finish on a product in compliance with the finish specified in the
section where the product is specified or in Section 11005.
C. Corrosive Environment: Immersion in, or not more than 6 IN above, or subject to frequent
condensation, spillage or splash of a corrosive material such as water, wastewater, or chemical
solution; or chronic exposure to corrosive, caustic or acidic agent, chemicals, chemical fumes,
chemical mixture, or solutions with pH range of 5 to 9.
D. Highly Corrosive Environment: Immersion in, or not more than 6 IN above, or subject to
frequent condensation, spillage or splash of a corrosive material such as water, wastewater, or
chemical solution; or chronic exposure to corrosive, caustic or acidic agent, chemicals, chemical
fumes, chemical mixture, or solutions with pH range below 5 or above 9.
E. Exposed Exterior Surface:
1. Surface which is exposed to weather but not necessarily exposed to view as well as surface
exposed to view.
2. Exterior surfaces are considered corrosive environment.
F. Finished Area: One that has finish called for on Room Finish Schedule or is indicated, on
Drawings, to be painted.
G. Paint includes the following:
1. High performance industrial coatings (HPIC) include: Epoxies, urethanes, vinyl ester,
waterborne vinyl acrylic emulsions, acrylates, silicones, alkyds, acrylic emulsions and any
other coating listed as a HPIC.
H. Surface Hidden from View: Surfaces such as those within pipe chases, and between top side of
ceilings (including drop-in tile ceilings) and underside of floor or roof structure above.
00...52713-00123
Bozeman WRF Phase I Early Out Priority Improvements
09905 - 2
5/22/2007
.
.
'.
.
I. AP: Architectural paints.
J. HPIC: High performance industrial coatings..
K. SC: Special coatings.
L. VOC: Volatile organic compounds.
SUBMITTALS
1.4
.
A. Shop Drawings:
1. See Section 01340 for requirements for the mechanics and administration of the submittal
process.
2. Product technical data including:
a. Acknowledgement that products submitted meet requirements of standards referenced.
b. Manufacturer's application instructions.
c. Manufacturer's surface preparation instructions.
d. If products being used are manufactured by Company other than listed in Article 2.2,
provide complete individual data sheet comparison of proposed products with specified
products including application procedure, coverage rates and verification that product is
designed for intended use.
e. Contractor's written plan of action for containing airborne particles created by blasting
operation and location of disposal of spent contaminated blasting media.
f. Coating manufacturer's recommendation on abrasive blasting.
g. Manufacturer's recommendation for universal barrier coat.
3. Manufacturer's statement regarding applicator instruction on product use.
4. Applicator experience qualifications.
a. No submittal information will be reviewed until Engineer has received and approved
applicator qualifications.
5. Certification that coating systems proposed for use have been reviewed and approved by
Senior Corrosion Specification Specialist employed by the coating manufacturer.
B. Samples:
1. Manufacturer's full line of colors for Engineer's color selection.
2. After initial color selection by Engineer provide two 3 x 5 IN samples of each color selected.
C. Miscellaneous Submittals:
1. See Section 01340 for requirements for the mechanics and administration of the submittal
process.
2. Approval of application equipment.
3. Applicator's daily record:
a. Submit daily record at end of each week in which painting work is performed.
DELIVERY, STORAGE, AND HANDLING
1.5
A. Deliver in original containers, labeled as follows:
1. Name or type number of material.
2. Manufacturer's name and item stock number.
3. Contents, by volume, of major constituents.
4. Warning labels.
5. VOC content.
PART 2 - PRODUCTS
2.1
ACCEPTABLE MANUFACTURERS
.
A. Subject to compliance with the Contract Documents, only the following manufacturers are
acceptable:
00.. .52713-00123
Bozeman WRF Phase 1 Early Out Priority Improvements
09905 - 3
5n212007
1. High performance industrial coatings:
a. Tnemec.
b. Ameron Protective Coatings Div.
c. leI Devoe.
d. Carboline Protective Coatings.
e. Sherwin Williams.
f. Dampney Company, Inc.
B. Submit request for substitution in accordance with Specification Section 01640.
2.2 MATERIALS
.
A. All materials used must contain not more than 2.08 LBS/GAL VOC unless noted otherwise.
B. For unspecified materials such as thinner, provide manufacturer's recommended products.
C. Paint Systems - General:
1. P = prime coat.
2. Fl, F2 . . . Fn = first finish coat, second finish coat. . . . nth finish coat, color as selected by
Engineer.
3. If two (2) finish coats of same material are required, Contractor may, at his option and by
written approval from paint manufacturer, apply one (1) coat equal to mil thickness of two
(2) coats specified.
D. HPIC products specified are manufactured by Tnemec.
E. Paint Systems (Systems not shown are not used):
1. SYSTEM #1
a. Prime coat:
1) PI = Tnemec Series N69 Hi Build Epoxoline II, at 5 mls DFTI.
b. Finish coat(s):
1) Interior:
a) Fl = Tnemec Series N69 Hi~Build Epoxoline II, at 5 mils DFT.
b) F2 = Tnemec Series N69 Hi-Build Epoxoline II, at 5 mils DFT.
2) Exterior:
a) Fl = Tnemec Series N69 Hi-Build Epoxoline II, at 5 mils DFT.
b) F2 = Tnemec Series 73 Endura-Shield II, at 3 mils DFT.
2. SYSTEM #2
a. Ferrous Metal, 24 IN below the L.L. water line and up.
1) Holding Primer:
2) At the option of the contractor to hold a prepared surface. Tnemec Series N69
Epoxoline Applied at 3.0 to 5.0 mils or to cover blast profile.
b. Primer:
1) Tnemec Series 435 Perm a Glaze Applied at 15.0 to 20.0 mils dry film thickness.
c. Finish:
1) Tnemec Series 35 Perma Glaze Applied at 15.0 to 20.0 mils dry film thickness.
.
Note: Finish coat is to be monolithic and pinhole free. Final system is to be tested for pinholes per
NACE RPO 188-90
d. Ferrous metal, 24" Below the L.L. Waterline and Down
1) Surface Preparation: SSPC SPIO Near White Metal Blast Cleaning
2) Primer: Tnemec Series N69 Epoxoline applied at 6.0 to 8.0 mils DFT
3) Finish: Tnemec Series N69 Epoxoline applied at 6.0 to 8.0 mils DFT
Note: All weld seams, sharp edges and angles are to be brushed with either the wet prime or fmish
coat to ensure complete millage and a monolithic finish coat.
.
00...52713-00123
Bozeman WRF Phase 1 Early Out Priority Improvements
09905 - 4
5/22/2007
.
PART 3 - EXECUTION
3.1 ITEMS TO BE PAINTED
A. Exposed Interior Surfaces including:
1. Cast iron (sluice gate).
2. Miscellaneous ferrous metal surfaces.
3. Clarifier steel surfaces where existing coatings systems are affected by demolition and
construction activities.
3.2 SCHEDULE OF ITEMS TO BE PAINTED AND PAINTING SYSTEMS
A. Structural Steel:
1. Non~immersion surfaces subject to corrosive or highly corrosive environment: SYSTEM #2.
2. Immersion surfaces subject to corrosive or highly corrosive environment:
SYSTEM #2.
B. Sluice Gate (Cast iron) SYSTEM # 1.
3.3 PREPARATION
.
A. General:
I. Prepare surfaces to be painted in accordance with coating manufacturer's instructions and this
Section unless noted otherwise in the Specification.
2. Remove all dust, grease, oil, compounds, dirt and other foreign matter which would prevent
bonding of coating to surface.
B. Protection:
1. Protect surrounding surfaces not to be coated.
2. Remove and protect hardware, accessories, plates, fixtures, finished work, and similar items;
or provide ample in-place protection.
C. Prepare and Paint Before Assembly: Where component is subject to corrosive or highly corrosive
environment, prepare and paint, before assembly, all surfaces which may be subject to
environment which are inaccessible after assembly.
D. Ferrous Metal:
1. Prepare ductile iron pipe in accordance with pipe manufacturer's recommendations and
AWWA.
2. Complete fabrication, welding or burning before beginning surface preparation.
a. Chip or grind off flux, spatter, slag or other laminations left from welding.
b. Remove mill scale.
c. Grind smooth rough welds and other sharp projections.
3. Solvent or water jet and detergent clean in accordance with SSPC SP 1 or
SSPC SP 12/NACE NO.5 all surfaces scheduled to receive additional SSPC surface
preparation.
4. Surfaces subject to corrosive or highly corrosive environment and all surfaces subject to
immersion service:
a. Near-white blast clean in accordance with SSPC SP 10/NACE No.2.
5. All interior and exterior surfaces:
a. Minimum commercial blast clean in accordance with SSPC SP 6/NACE No.3.
6. Surfaces subject to high temperatures.
a. Heat in excess of600 DegF: SSPC SP 10/NACE No.2.
b. Heat in excess of200 DegF but less than 600 DegF: SSPC SP 6/NACE No.3.
7. Surfaces of steel joists and steel trusses:
a. Commercial blast clean the major portion of the truss in accordance with
SSPC SP 6/NACE No.3.
b. Power tool or hand tool clean tight connection areas and other difficult to access areas in
accordance with SSPC SP 2 or SSPC SP 3.
.
00...52713-00123
Bozeman WRF Phase 1 Early Out Priority Improvements
09905 - 5
5/22/2007
E. Hollow Metal:
1. Clean in accordance with SSPC SP 1 or SSPC SP 12!NACE No.5 and in accordance with
hollow metal manufacturer.
F. Abrasive blast clean the following equipment or surfaces regardless of previous fmish, ifany.
G. Preparation by Abrasive Blasting:
1. All abrasive-blasted ferrous metal surfaces shall be inspected immediately prior to
application of paint coatings.
a. Inspection shall be performed to determine cleanliness and profile depth of blasted
surfaces and to certify that surface has been prepared in accordance with these
Specifications.
2. Schedule the abrasive blasting operation so blasted surfaces will not be wet after blasting and
before painting.
3. Perform additional blasting and cleaning as required to achieve surface preparation required.
a. Prior to painting, reblast Surfaces allowed to set overnight and surfaces that show rust
bloom.
b. Surfaces allowed to set overnight or surfaces which show rust bloom prior to painting
shall be reinspected prior to paint application.
4. Profile depth of blasted surface: Not less than I mil or greater than 2 mils unless required
otherwise by coating manufacturer.
5. Provide compressed air for blasting that is free of water and oil.
a. Provide accessible separators and traps.
6. Confine blast abrasives to area being blasted.
a. Provide shields of polyethylene sheeting or other such barriers to confine blast material.
b. Plug pipes, holes, or openings before blasting and keep plugged until blast operation is
complete and residue is removed.
7. Protect nameplates, valve stems, rotating equipment, motors and other items that may be
damaged from blasting.
8. Reblast surfaces not meeting requirements of these Specifications.
9. Abrasive blasting media may be recovered, cleaned and reused providing Contractor submits,
for Engineer's review, a comprehensive recovery plan outlining all procedures and equipment
proposed in reclamation process.
10. Properly dispose of blasting material contaminated with debris from blasting operation not
scheduled to be reused.
3.4 APPLICATION
A. General:
1. Thin, mix and apply coatings by brush, roller, or spray in accordance with manufacturer's
installation instructions.
a. Application equipment must be inspected and approved in writing by coating
manufacturer.
2. Temperature and weather conditions:
a. Do not paint surfaces when surface temperature is below 50 DegF unless product has
been formulated specifically for low temperature application and application is approved
in writing by Engineer and paint manufacturer's authorized representative.
b. A void painting surfaces exposed to hot sun.
c. Do not paint on damp surfaces.
3. Provide complete coverage to mil thickness specified.
a. Thickness specified is dry mil thickness.
b. All paint systems are "to cover." In situations of discrepancy between manufacturer's
square footage coverage rates and mil thickness, mil thickness requirements govern.
c. When color or undercoats show through, apply additional coats until paint film is of
uniform finish and color.
4. If so directed by Engineer, do not apply consecutive coats until Engineer has had an
opportunity to observe and approve previous coats.
5. Apply materials under adequate illumination.
00.. .52713-00123 Bozeman WRF Phase 1 Early Out Priority Improvements 5/22/2007
09905 - 6
.
.
.
.
6. Evenly spread to provide full, smooth coverage.
7. Work each application of material into comers, crevices, joints, and other difficult to work
areas.
8. Avoid degradation and contamination of blasted surfaces and avoid intercoat contamination.
a. Clean contaminated surfaces before applying next coat.
9. Smooth out runs or sags immediately, or remove and recoat entire surface.
10. Allow preceding coats to dry before recoating.
a. Recoat within time limits specified by coating manufacturer.
b. Ifrecoat time limits have expired reprepare surface in accordance with coating
manufacturer's printed recommendations.
11. Allow coated surfaces to cure prior to allowing traffic or other work to proceed.
B. Prime Coat Application:
1. Prime all surfaces indicated to be painted.
a. Apply prime coat in accordance with coating manufacturer's written instructions and as
written in this Section.
2. Ensure field-applied coatings are compatible with factory-applied coatings.
a. Ensure new coatings applied over existing coatings are compatible.
b. Employ services of coating manufacturer's qualified technical representative.
1) Certify through material data sheets.
2) Perform test patch.
c. If field-applied coating is found to be not compatible, require the coating manufacturer's
technical representative to recommend, in writing, product to be used as barrier coat,
thickness to be applied, surface preparation and method of application.
d. At Contractor's option, coatings may be removed, surface reprepared, and new coating
applied using appropriate paint system listed in Paragraph 2.2E.
1) All damage to surface as result of coating removal shall be repaired to original
condition or better by Contractor at no additional cost to Owner.
3. Prime ferrous metals embedded in concrete to minimum of 1 IN below exposed surfaces.
4. Back prime all wood scheduled to be painted, prior to installation.
5. After application of primer to gypsum board surfaces, inspect surface and repair in
accordance with Article 3.4.
a. Re-prime repaired surfaces to uniform finish before application of finish coat(s).
6. Apply zinc-rich primers while under continuous agitation.
7. Ensure abrasive blasting operation does not result in embedment of abrasive particles in paint
film.
8. Brush or spray bolts, welds, edges and difficult access areas with primer prior to primer
application over entire surface.
9. Touch up damaged primer coats prior to applying finish coats.
a. Restore primed surface equal to surface before damage.
10. All surfaces of steel lintels and steel components of concrete lintels used in wall construction
shall be completely painted with both prime and finish coats prior to placing in wall.
C. Finish Coat Application:
1. Apply finish coats in accordance with coating manufacturer's written instructions and in
accordance with this Section; manufacturer instructions take precedent over these
Specifications.
2. Varnish:
a. Apply first coat of varnish: Gloss.
I) Allow to dry a minimum of 48 HRS.
b. Apply second and third coats of varnish: Satin.
1) Allow a minimum of 48 HRS between each coat.
c. Lightly sand between coats as required then dust clean.
3. Touch up damaged finish coats using same application method and same material specified
for finish coat. .
a. Prepare damaged area in accordance with Article 3.4.
.
.
00...52713-00123
Bozeman WRF Phase 1 Early Out Priority Improvements
09905 - 7
5/22/2007
4. SC application:
a. For new gypsum board surfaces:
1) Apply at rate recommended by manufacturer and approved by mock~up panel.
b. For new concrete and masonry surfaces:
1) Apply SC at rate recommended by manufacturer and approved by mock-up panel.
3.5 FIELD QUALITY CONTROL
.
A. Maintain Daily Record:
1. Provide the following information for each coat of paint applied:
a. Date, starting time, end time, and all breaks taken by painters.
b. For exterior painting:
1) Sky condition.
2) Wind speed and direction.
c. Air temperature.
d. Relative humidity.
e. Moisture content of substrate prior to each coat.
f. Provisions utilized to maintain work area within manufacturer's recommended
application parameters.
g. Surface temperature of substrate to which paint is being applied.
2. Format for daily record to be computer generated.
B. Measure wet coating with wet film thickness gages.
C. Measure coating dry film thickness in accordance with SSPC P A 2 using Mikrotest gage
calibrated against NBS "Certified Coating Thickness Calibration Standards."
1. Engineer may measure coating thickness at any time during project to assure conformance
with Specifications.
D. Measure surface temperature of items to be painted with surface temperature gage specifically
designed for such.
E. Measure substrate humidity with humidity gage specifically designed for such.
F. Provide wet paint signs.
.
3.6 CLEANING
A. Clean paint spattered surfaces.
1. Use care not to damage finished surfaces.
B. Upon completion of painting, replace hardware, accessories, plates, fixtures, and similar items.
C. Remove surplus materials, scaffolding, and debris.
1. Leave areas broom clean.
END OF SECTION
.
00...52713-00123
Bozeman WRF Phase 1 Early Out Priority Improvements
09905 - 8
5/22/2007
.
.
DIVISION 13
SPECIAL CONSTRUCTION
.
.
.
.
SECTION 13342
SECONDARY CLARIFIER MECHANISM IMPROVEMENTS
PART 1. GENERAL
1.1 SUMMARY
A. Scope:
1. Improvements to the Secondary Clarifier No.4 influent diffusion will directional baffles.
2. Re-coating metal surfaces in accordance with Section 09905
B. Related Sections:
I. Division 0 - Bidding Requirements,
2. Division 1 - General Requirements.
3. Section 02072 - Demolition, Cutting and Patching.
PART 2 - PRODUCTS
2.1 IMPROVEMENTS TO SECONDARY CLARIFIER NO.4
A. Verify unit can be taken out of service a minimum of 10 days prior to proceeding.
B. Refer to existing Walker Power Equipment drawing of existing mechanism, appendix, this
section.
C. Schedule of rehabilitation:
1. Submit prior to proceeding.
2. List all equipment to be used.
3. Approval required by Engineer and Owner.
D. Draining and Washdown of Basins:
1. Owner responsible for dewatering tanle Contractor shall clean the tank and existing
equipment for installation of new equipment coatings and facilities.
2. Liquid in basin and washdown water may be returned to treatment process via Contractor
provided pumping as approved.
E. Wire wheel or Sandblast all exposed metal surfaces per SSPC-SPlO, including damages coatings
areas and diffusion well directional baffle area to be modified by metal cutting.
F. Oemolish existing steel diffusion well directional baffles and install new outlet impingement
plates as shown on Details I and 2 appended to this section. Typical of 8 locations.
G. Paint all impacted existing submerged metal surfaces per Section 09905.
PART 3. EXECUTION
3.1 IMPROVEMENTS TO SECONDARY CLARIFIERS NO.4
A. Contractor shall enlist services of the Engineer to inspect the rehabilitation equipment prior to
startup.
B. Contractor shall provide required equipment to inspect, realign, and adjust all applicable
components prior to startup.
END OF SECTION
00. _ .52713-00123
Bozeman WRF Phase 1 Early Out Priority Improvements
13342 - 1
5/22/2007
.
.
.
i;]
29'-1 1/2- I.R.
Of" SCOW BM"f'LE
-------
W(JR PlATE
SCV... BAfl1.E
..
SI:UI 0UlEl
~.~
4612.68"
1U> Of WAUCWAY
~ 4611.33'
1U> Of 1_
. ~ W.L 4600.76' *
STAlInIlf\Y
Dlf (NOT BY WP L.)
'- 6' SCUM PIP[
(NOT BY ..P.E.)
, ,
. ,
."
Sl(IWW[R ASSD>lBL Y
..:"
'. SKIMMER SUPPORT
'j.
;,'*
. - .
. .-
..'
. .
:. ~:. .::.~ ~.~ :. ::": ".
( ':-.
. "~7.61'
: ....... ;., .'1':.:...... : :~':". TOP Of GROVT
~
, 4595.02'
TOP Of CROuT
...."~, "K~
(NOT BY w.P.E.)
1 I
12
SLOPE
n
11'011
~
3/6' lHlO( PLAT[ X 13 3/'" X 3'-5' Le. - SIiOP WfLOED TO
BRIOCE (CliS1OUER TO PROI.1DE \II.P.L WITH L0CA1KJN '"
QUANTllY OF STAJl'WAY MOUNTING HOlES,)
BRIDGE
SLlOE: Pt.A n:
.. - --~ 4611.33'
~ANCHOR BOLT
DETAIL A
CE:Nl[I~ COLl)....
2- CROUT" . LEvElJNC NlIT
L . ~~
II
I L---MIOJOR BOLT
II
I~:::J
DETAIL B
* BAStD tw PEAl( DAY AvtRACE Of 3,6 f./.C.O,
Wolker Process Equipment
Oivi5ioo of Jo.t<;Nish Corporotion
AURORA, ILLINOIS U.S.A.
CENERAL ARRANGEMENT
65'-0' DIA. CLARIFlER - rtFE 'HS-S'
BOZrloAAN . MONTANA
eo< """CT
NOIIIOA
.
.
~
::;:
uJ
N
o
en
cO
co
en
(0
o
....
o
"0
55
.
~
90
o
DEMOLITION AT DIFFUSION
WELL DIRECTIONAL BAFFLES
(lYP OF 8)
Q;
E
"0;
.<::
::i
n..
'"
'l"
,:..:
o
'"
.....
C)
C)
~
~
..,
:J
~
'"
--'
t
....
"
u::
DEMOLITION AT DIFFUSION WELL DIRECTIONAL BAFFLES
HR
DEMOLITION AT DIFFUSION WELL
DIRECTIONAL BAFFLES
DATE
5/18/07
FIGURE
DETAIL 1
.
.
....
Q)
E
"v
.c
:i
0-
<0
,....
m
,....
.;f
.....
o
o
C'!
;;S
:;
o
>.
~
t
N
CJ
u::
u.J
N
o
lD
iii
<0
en
<D
o
,....
o
"
;jS
.
~
u
REMOVE 8" OF STL.
DIFFUSER WELL
DIRECTIONAL BAFFLE
WALL (BOTTOM REMAINS)
DIFFUSION WELL
DIRECTIONAL
BAFFLE (lYP OF S)
5/S" @ SST
BOLTS w /NYLOK
NUTS AND WASHERS
(lYP OF 2)
4"
If)
I
=
0'1
-
.--
COAT STL EDGES AT
DEMOLITION LOCATIONS
PER SECTION 09905
~
1'-4"
fLEVATlON
DIRECTIONAL BAFFLE MODIFICATION DETAIL
SCALE 1-1/2" = l'
HR
DIRECTIONAL BAFFLE
MODIFICT A TION DETAIL
DETAIL 2
8"
3/S"X 24"X 17"
STL PLATE. COAT
PER SECTION 09905
DATE
FIGURE
5/18/07
2
.
.
.
SECTION 15116
SLUICE GATE REPAIR AND REHABILITATION
PART 1 - GENERAL
1.1
SUMMARY
1.2
A. Scope:
1. The Contractor shall repair and rehabilitate the existing Sluice Gates and Operators (SOO-4-
00 I, SGOA-002 & SGOw4w003) per plan and specification. The Repair and Rehabilitation
shall include but not be limited to:
a. The Contractor shall submit a method of repair and rehabilitation to the Owner and
Engineer for review prior to commencement of work.
b. Coordinate the schedule of rehabilitation with the Owner.
c. The Contractor shall disassemble, clean, repair and rehabilitate the existing sluice gates
and operators so that they are fully functioning and operable.
d. If the Contractor encounters any ferrous metals, the Contractor shall clean and paint
according to Sections 09905.
e. The Contractor shall provide all materials, equipment, tools, facility, labor and
appurtenances for a complete and operable Sluice Gate and Operator system.
f. The work shall be considered complete when the Sluice Gate and Operators are fully
functional and all punch list items are complete.
R Related Sections include but are not necessarily limited to:
1. Division 0 - Bidding Requirements, Contract Forms, and Conditions of the Contract.
2. Division 1 w General Requirements.
3. Section 11005 - Equipment: Basic Requirements.
QUALITY ASSURANCE
A. Referenced Standards:
I. ASTM International (ASTM):
a. AI26, Standard Specification for Gray Iron Castings for Valves, Flanges, and Pipe
Fittings.
2. American Water Works Association (AWWA):
a. C50I, Cast-Iron Sluice Gates.
1.3 SUBMITTALS
A. Method of Repair:
1. See Section 01340 for requirements for the mechanics and administration of the submittal
process.
2. Contractor's method of repair.
3. Schedule of rehabilitation
4. List all materials and equipment to be used for the repair.
1.4 PROJECT CONDITIONS
A. Existing Sluice Gates
1. Waterman Industries, Inc. gates, installed initially in 1981.
2. Waterman Model No. 5-55-20-FF, 48 IN x 36 IN:
3. Number: 3 each.
4. Reference equipment data sheets 1-3 appended to this section.
00...52713-00]23
Bozeman WRF Phase] Early Out Priority Improvements
15116-1
5/2212007
PART 2. PRODUCTS
.
2.1 SLUICE GATE REHABILITATION AND REPAIR
A. Verify units can be taken out of service a minimum of 10 days prior to proceeding. Only one
unit may be removed from service at a time.
B. Schedule of Rehabilitation:
1. Submit prior to proceeding.
2. List all equipment to be used.
3. Coordinate the draining and wash down of basins with the Owner.
4. The Schedule of Rehabilitation must be approved by the Owner.
C.Equipment Inspection Report:
1. The Contractor shall inspect the existing sluice gates and operators (SGO-4-00 1, SGO-4-
002 & SGO-4-003) prior to removal of any facilities.
2. The Contractor shall provide an opinion of the condition of the sluice gates and operators.
D. Draining and Wash Down of Basins:
1. It shall be the Owner's responsibility to dewater and drain the existing Aeration Basin Cells.
It shall be the Contractor's responsibility to coordinate the Schedule of Rehabilitation with
the Owner. The Contractor shall clean the existing basin cells and equipment prior to
performing work with wash down water. It shall be assumed that dewatering of each
aeration basin cell pair will take a single calendar -day for each basin shutdown.
2. Liquid in basins and wash down water may be returned to the treatment process via
contractor provided pumping as approved by the Owner.
E. Repair and Rehabilitate Sluice Gates:
1. Dismantle sluice gates and operators.
2. Clean buff and repair the sluice gate and operator surfaces.
3. Adjust wedges and hand operator as necessary.
4. Realign equipment.
5. Adjust all applicable components.
6. Test the operation of the gates.
.
PART 3 - EXECUTION
3.1 INSTALLATION AND REHABILITATION
A. The aeration basin mixer support rails, hoist and associated mounting equipment shall be
installed at the same time the sluice gates are rehabilitated. See Specification Section 11948.
3.2 FIELD QUALITY CONTROL
A. Contractor shall enlist services of reputable equipment manufacturer to furnish a factory trained .
representative to inspect the rehabilitation of the equipment prior to startup.
B. Contractor shall provide required equipment to inspect, realign, and adjust all applicable
components prior to startup or filling the basins.
3.3 FIELD SERVICE
A. When trouble develops either in the installation, operation, or performance of the equipment, the
installation manual and drawings should be checked to determine if the equipment has been
installed properly. If proper performance and operation cannot be obtained, and assistance from
the factory is desired, please contact the factory and REFERENCE THE JOB NUMBER R-
9378. so that we may locate the project records and better assist you. Company may be
contacted at:
.
00...52713-00123
Bozeman WRF Phase 1 Early Out Priority Improvements
15116.2
5/22/2007
.
.
.
WATERMAN INDUSTRIES, INC.
P.O. Box 458
Exeter, CA 93221
Phone: (209) 592-3174
(209) 562-1331
B. Arrangements will be made to send a man to the jobsite if this is required. This man will make a
thorough examination of the problem and if the equipment is faulty in workmanship or material,
the necessary repairs or adjustments will be made by the factory at no cost to the purchaser. If,
however, the problem is due to faulty installation or adjustment, the cost of the field service will
be charged to the purchaser.
C. Ifrepairs are made in the field by the purchaser or authorized by the purchaser, back charges for
these repairs will not be accepted by the company unless the company has been notified prior to
the incurring of these costs and has accepted the responsibility for these repairs. Any
unauthorized repairs or changes to equipment will automatically void warranty.
D. The company will not be liable for contingent costs or costs of delay due to the faulty equipment
and the repairs thereof
3.4 FIELD SERVICE CHARGES
A. Field service charges begin from the time of departure until the return of the service man and
include a daily rate plus travel and subsistence expenses. Premium day and hourly rates will be
charged on Saturdays, Sundays, and Holidays and for time spent before 6 a.m. or after 5 p.m. or
over eight hours per day. A schedule ofField Service charges can be obtained by calling
Waterman Industries.
B. If service personnel are required for equipment produced by another manufacturer (i.e. for
electric motor operator), that manufacturer's standard service charge will prevail.
END OF SECTION
00...52713-00123
5/22/2007
Bozeman WRF Phase 1 Early Out Priority Improvements
15116 - 3
i I . ~r l,
41
lE,C'l-ON
41
A-A
r
11 ~
ft./ ~sfl!]
,ce' 1/;', <~ ,
H!. 'B4'" l 7~ - 0.") <El
~Ar~ '~~L, OPeN
l~ '" "', '
;;"',
1':
~'~l~'
~'.,
u..;I' ,
,",..
~lY" : ,
2,J"I,,-
j
21Mt:
j' ','
,,;,'''':, "
J1.; 1 ~
',,'
'.
~R.A5S: gRIP
f" REYOL,VINf-
. ....-...
. T,
'_, ,,-':, (R,EF)
'~r~
'..1..."
$
ill
"; .
~NoTE:HANoRAll (gf ,
NOt 5HOWft CONiR
lNcaURE: PRpPgR ~,CLE
BETwEeN HAttDRAll '
, HA'NOCRANK. , '
l - ..
. ,
o
'I"
'""Jfif', '
..' ,1.
",:",1-
~ ,I..,
3~ti
:.-r..;'
,. .
.. ,;uli81M
'"'~&'2!1 ' .
...;. .
c: klil)',:... ..p.!, '. '
THRb'D!O'
;, "\$I'!
, ".120 4;; & .~
SLE'E'VrrtiY, ~~T~'
'{t"~'i"';"
, .'
, ( i
...'t,'
'"
.,'.'0
~::
It.
,"'"
.' ~',: J ,
., ;'1:"
~ .., .~:~\:, ',.'
H.'" ~,'
..t:' 'k:, ,,\
" '~I 'I" ;,:J,
, I' ,/'1 ;',';i.,
"1.,::'
".' .:
; ;1
~ '(.,i"
",,~1 '
, ,f.ois.'
,,'
" ,
,;. ~,'~"':' ,...
)' , ..,~, tIII"ACt>;j
,:C:,:":"111
:;. . '. <:.. " ,.. '.':'., :c,;;:.." ':~;{I:"
A:~'~'/:"~
,..,.~lC~ ''VI!
, ';t"
r,
;"
,,./. !'."
.;'1'
';"':':
..1....
'..",
. ~.\ "
';!C:~t=Si!'~' ..
'';;'"
',i.),., I.r:,'.. .:"'.
, "
; ~,. .'
,I,
an. ,
;' Awastew, at~~ Tht,' ~1'!;~1i Pi~nt
'r Bozeman, MT "
," " EPA No. C3002{)8 " '
,Thomas,,' Dean ~ Hosk~s,' Inri..
Engineers '
, '
, ,
, / 48')(; :iP "
I .' "
, ..
MTERMAftf ,MOOEL':""';,::,
S' ,,'oJf'r:', ;1""i~[;;.. , '"'{\).., .,
. ~'~'(;.)"~"~~~'}'"
. .. ~. .
'~l:_,':"."'~:"':": -~'A:TC" , ,
~t:1~~ . VJi't:I!~c;;. ','o ",.'o
"'''~.. -,>'';\!\~c,':~'<_::::;
,'_ ,_',.' ~':D,
, - '~I'''.~'' ,~f,'~._.~
p!Q
. ":1' "
,.....;.. ,.
"
~ t;:
(~ ~ :."
',;: ,.,i'i'
B<:I:i1
. ~'/~
8Q~
. i/ ~..:'~~r.
,. 'If
. ...., .f~.
. ., '. .
,,~;tiiD,,'o"'o
~(~
;.
. ,
'.' :;. ~.~... \:~L. n.::. ::_\:'., ..... ;. ;~; ~. , " t. I;, _.. I. .\' J. . ,_
',. > :~:I~~tf~~~8ty . I .", r~~,';: .~~~~: :'f~N::'.'h .m~\~UI~ e~W~ '. '::-,i.:~;.r..
, . bt ft~~, I' t:. J~~..,.t._Q. . c.......,... "". ..
:.,...., " ,', "i' ,!\.::,,>,:<::'),,"'1,f'.,;.'HoJ..,,,:"'/J!!iE. ", ,'') .' :irrNIP:/: ".'.;,~{;;:;~
:I","" \.,,~;. ,':' ... .... ,;: '..' 'i~':f' :~'j';' :~:ti.~j..'.tt.:..,~ .;,,~.;.:,,; :;~..~":,:,:,,,",':'" ':;',..". ,"<"...:':; :;...,
.~.~,.~:"'" :'f:~~1t .,,' .....,t.,:, ':.'. . ',: ..,).1..,. ,.... ,,-c.' .:.~.:.~ .t. ~_. ..... 10t.... ,,,,,r;."~ ....J ~~_lJOS ".t,'
'"'~t:I'" ~ . . ",.'".... .,,' .0<3. "3 ., ,,...7.~..,/llf"''';';' I" :PUt:, . . '.' . '. I >.
1/J. ~ a..iIl;L . .,i;$Tt:~ :,*i'_~,..)..i~.t~'a::~J:;1 ~')''',:,'i ,J"; :;~~" t:K:;.~:i>ipjji.trpr. .' .'. ~'t.'".
, . .~. "'.-. . .,,~. ,,' n:T'if.:.' '~'..~~.'~ 1~~:1~:: '2 " .. ,,,,,,i}':... "l'/)' . X....'.,. ~"., ..,. '. .' f" '.' .
I ~ - .3 .,,'T" , '..H:. .., ~ . . 't )'1:j''f.~~ . .;J!' -I;::) -rr -G:/; ". .' . I .,. . I ' " " j'
" . :. :.::: "'. ".;.~:t.N:"';';l!~~K~X:;:':'.~:,< .~;,.'.' . ,:',':'",'.f'~ ~~;~i ~:::~l'~,~''''.-j'', ";:.#'~~f~:.~~,3.~~~;'~'r/~~':'}':l';"":';;
. .. , .; .' .,~:t;!;< '(TrH'ttiS~t ". . ,., "'I.e' . ./" ;'.'fir l', r'lt.p".TKlIYDEEP,t t
'. /~_..:~m~,'::, ,/;~.~r"l:~.!,'.:.r~C).,. .i <1~~;>;:~4 ('tf~:~~ ::'.;.~':~~~>...>..'.,-':. ':7", '<'" . :i~\
V . : '. .'., , .'. .'. ..,' .'. '>":~H.""i..";r., ", .' '. .' ' :'.:~1 .~..:. (.Il~~<=i . ..,0, " ,1;;.. , '2. ; .1."
. . . .' '.:~~l.,/:.,:i' , 'I.At; ,2,j';~ <;.J.~\"j\~" .' d . );,G.:. \'. '. '.' ,....',h.4..... ',..' ~'.' :
"'ANemIt., "'1 './tit'. ':t;Mi'...~ ."...~:~G ,_
i...:~~.'.,f...... .1.:J:.,~..,.i.l.L...:,N .~..', '. }::: '::' :.i"" . , -. . ~7,::~::,',i '~"~~{! :<':';".: :,:.\:'~":::':'.':l~...',;,\.. ,;,. '.
jt4::A .'.~' ':;:;:If~:r.. '... . · .,i~!~ ;.~I{ .~~. ::I~:,... .' . .\: ,,/',
~rrE"...' ~.~~, .Et;~::'~OO.Oh' . ,,'~~~gl '. .111,1 ;:;1:;, :;U, ':'&1..'
M!~G ~> . ."'. .' '.' . .......:: ' ..,...... . .; ......,,' ;';:, . '.'. . ,...
. I ',. -. ": ,~,,:,
. ; :. ".,~~,. ,. ....
Jlfr '. . . .' ..... ...' .' "C1'T'~'. " ,'.,. ". ,., ,~. ,::".. '. ' " '~. ::~' .'...:;:.;""~'" "
,',,' ,.IW,tLf;",4.~Il~U;~', ,:....~..~.r1i!l.~rt~~
-1.Vg:"S "c.I<<>lit-.HOttta:~'" ,'>:11' '~A;"'" :';_~~\~"~;:'i~'"!;~::'fI~;~:i~.''t5.''.''' , ....
. ,.' '.' -'. ...:,4..._.T..~::'~..I:;. 'rP,:......;.. ,:;(,...~~l..n.tt. ,.......
.;..;..T.....t~f...,i:..(f9) ;.'~' :.;'nlMEH6fdN' ...~iIDEs... ...."FO.. "'~,"*D.
. . !ii/8,~'.,+'p';es: ':b' cpNTR, rOI/t:f?l'FV <<," SUPPhY .:. ,
..,..~. ,~., .' I'
. -j'Q:','.'tOf GA.... .
. . -PrROJ 2'~
1...:..."....,..
... . CS
:,,:. .. . '.; "> . ,.4 ,pt" .... . .
. '.k.'~4 PtC~
. ':"a' ,~*'PLrs
\, "
~t
. ~ -, ...
;,
,.) ,;.
r..
') .
-""
I ,.
'--'
.i,
J '
'tQ.W. Q.. ~~..~It. .
, , . ..,..'/,. /' .
:," ':.~.';
. '-
. ..2.
SOOT .'
," ",
..~:~.,.:;:;.;\.:~,,, I'
:'2,.
-
~.~
""1"~' ::;,
'1, ;8.;:,'
1-' ", """.t.','.
" ft;;, '.' "
': .'. ',: ~"..;
. , '< \ .. ,~
. '} .
cAtr~ctto~ t'. .
Ix.47 'j'.
r't Wi' · 591;~~ ' .,,'
1'-'
",
,,,
"
, ,
" .
.' .
,4;90
..
. .~ j' '. .:"'0 I, . .'; _ . . ...., _ .
~;,:,:,;,.< :.:i;:'::';'":~~~_'::li;i;'l~i;".:.'
.
.
'a;
E
'15
..c:
:i
0..
'<t
N
N
'<t
N
....
C>
C>
~
N
in
o
a:
<:i
~
""'<
~
C>
C>
U.
c::
~
~
C)
:;
N
C>
"0
~
,
o
~
9.
o
ci
<>:
l:::
al
~
'"
~
...,
0>
~
:I:
Hl~
HDR Engineering, Inc.
1715 S. RESERVE SlREEr
SUITE C
MISSOUlA, MT 59801-4708
Contract Drawings For
Water Reclamation Facility
Phase 1
Early Out Improvements
Structural/
Process/Mechanical
Project No.
000000000052713
Bozeman, MT
May, 2007
I
I,INDEX OF DRAWINGS
GENERAL
1 TITLE, LOCATION MAP AND DRAWING INDEX
2 STANDARD SYUBOLS AND ABBREVIATIONS
J SITE LOCATION AND STAGING MEA
! AERATION BASIN MODIFICATIONS
~ tOl MIXER INSTAllATION &: SLUICE GAlE
, REPAIR PLAN AND SECTIONS
102 t.lIXER I NSTAllATlON SECTIONS
I
I
1
I
N
~
PROJECT
LOCATION
HWY. 191
~'
r-
"--LJ
VICINITY MAP
NO SCALE
~'.MORRISON
.~.,." MAIERLE, INC.
A:> EmpIoy=-Owuod Qxopoay
.
.
....
o
o
~
<Xl
Ln
'0
a:
~
"C
N
o
o
LL
a::
~
~
OJ
:;j:
N
~
o
.
~
9.
U
Q;
E
Qj
.<=.
:i
<C
<Xl
N
U;
<:=!
;::
Ale
AlE
A
AS
ABC
ABAN
At:.
At:.K
At:.P
At:.ST
AD
ADDL
ADH
ADJ
i'F
MF
i'FG
AGGR
AI
AlC
ALIG
ALUM
ALT
AM
AMB
ANC
N'
N'RX
APVD
ARCH
ASS'(
AT
ATC
ATM
AUTO
MlX
AVE
AVG
AWG
AWl
B/B
BAL
BaD
Be
BD
BE
BF
BITUM
BKG
BL
BLOG
BLK
BLKG
BM
BOC
BOD
BOG
BOL
BOP
BOR
BOT
BOU
BP
BRG
BRGP
BRKT
as
8TU
8TW
BTWLD
au
BUR
8W
BYP
C TO C
C&:G
C
CAB
eN'
CAT
CAV
CB
CCB
CCW
CDF
CE
CER
CF
CFL
CHFR
CHBD
CHD
CHH
CI
CIP
CIPB
CIRC
CJ
CKT
CL
CLG
CLJ
CLKG
AIR CON DmONING
ARCHITECT/ENGINEER
ARCHITECTURAL (OWG DISCIPLINE), AMP
ANCHOR BOLT
AGGREGATE BASE COURSE
ABANDON
ALTERNATING CURRENT
ACKNOWLEDGE
ACOUSTIC CEILING PANEl,
ASPHALTIC CONCRETE PAVEMENT
ACOUSTIC
ADDENDUM, AREA 0 RAIN
ADDmONAL
ADHESIVE
ADJUSTABLE. ADJAt:.ENT
AM P FRAME, AMP FUSE
ABOVE FI NISH flOOR
ABOVE FlNlSH GRADE
AGGREGATE
AREA INLET
AMPS I NTlERRU PTI N G CN'ACITY
ALlGNM ENT
ALUMINUM
ALTERNATIE, AL TIITU DE
At:.OUSTlCAL MATlERIAL
AMBIENT
ANCHOR
ACCESS PANEL
N'PROXl IdA TE
N'PROVED
ARCHITECTIU RAL
ASSEMBLY
AM P TRIP
ACOUSTICAL TILE CEILING
ATMOSPHERE
.wTOIdATIC
MJXIUARY
AVENUE
AVERAGE
AMERICAN WlRE GAGE
ACOUSTICAL WAlL TILE
BACK TO BACK
BALANCE
BULLETIN BOARD
BASE CABINET, BOTTOM CHORD,
BOLT CENTER, BOLT CIRCLE
BOARD
BOTIH ENDS, BEUL END
80TIH FAt:.ES, BOTTOU FAt:.E,
BLIND FLANGE, BOARD FEET
BfTUM INDUS
BACKING
BASE LINE
BUILDING
BLOCK
BLOCKiNG
BENCHMARK, BEAM
BACK OF CURB
BOTTOM OF DUCT
BOTTOU OF GRilli
BOTTOM OF LOUVER
BOTTOM OF PIPE
BOTTOM OF REGISTER
BOTTOM
BOTTOM OF UN IT
BASE PLATE
BEARING
BEARING PLATIE
BRAC KET
BOTIH SIDES
BRmsH TlHERMAL UNIT
BETWEEN
BUTT WELID
BELL UP , BUILT UP
BUI LT -UP ROOFING
BOTIH WAYS
BYPASS
CENTIER TO CENTER
CURB &: GUTTER
CHAN N EL SfW'E, CENTIGRADE,
CONDUIT, CIVIL (DRAWlNG DISClPLlN E)
CABINET
CN'ACITY
CATALOG
CAVITY
CATCH BASI N
CONCRETE BLOCK
COUNTlER CLOCKWISE
CONTROLLED DENSITY FILL
CONCRETE EDGE
CERAMIC
CUBIC FEET (FOOT)
COUNTIER FlASHING
CHAMFER
CHALKBOARD
CHORD
COMM UNICATlON HANDHOLE
CURB IN LET
CAST -IN-PLACE
CONCRETE INTERLOCKING PAVER
BALLAST
CIRCULATION, CIRCULAR
CONSTRUCTION JOINT
CIRCUIT
CENTIERLlNE, CLASS, CLOSE
CEILING
CONTROL JOINT
CAULK1NG
~...<<J" MORRISON
.... MAIERLE, INC,
....-...o...r_
fiR
HeR Englnuring, In:..
1715 S. RESEJM: SIltED
SLm: C
l.ISSOUI..A. wr Ss:I1-47'C1!-
CLR
CIdH
CIdU
CO
COL
COld
COIdB
COIdM
COMP
CONe
CONN
CONST
CONT
CooR
CORR
CP
CPLG
CRL
CSC
CSK
CSS
CT
CTR
CTRL
CVT
CU
CW
CY
d
o
08
DBA
08L
DC
DEG
OEG C
DEG F
DEMO
DEP
DEPT
DET
DI
DIA
DIAG
DIFF
DIId
DISCH
DIST
DIV
DL
DMJ
DMPF
DN
DO
DP
DPDT
DPST
OS
DT
DUP
DWG
OM.
DWR
E
EA
EC
ECC
ED
EDB
EE
IT
EFF
EHH
ElFS
EJ
EL
ELEC
EldBD
EIdER
EMH
ENCIL
ENGR
ENTR
EOP
EQ
EQUIP
EQU IV
ES
ESEW
EST
EW
EWe
EWEF
EWT8
EXC
EXH
EXST
EXP
EXl
2
CLEAR
COIdMUNICATlON MANHOLE
CONCRETE MASONRY UNIT
CUEAN OlIT, CONCRETE OPENING
COWIdN
COUMON
COM BINATlON
COMIdUNICATlON
COMPOsmON, COIdPRESSIBLE,
COMPOSITE
CONcrNTRIC, CONCRETE
CONNECTION
CONSTRUCTION
CONTINUOUS
COORDINATE
CORROSIVE, CORRUGATED
CHECKER PLA TIE, CONTROL POINT
COUPLING
CORROSION RESISTANT LINING
COMPRESSION SLEEVE COUPlLNG
COUNTERSIN K
C1UNIC SERVICE SI NK
CERAMIC TILE
CENTIER
CONTROL
CU LVERT
COPPER, CUBIC
CLOCKWISE
CU BIC YARD
PENNY (NAIL MEASURE)
DEEP, DIFFUSER
DUCT BANK, DECIBEl, DRY BUUB
DEFORMED BAR ANCHOR
DOUBLE
DIRECT CURRENT
DEGREE
DEGREE CENTIGRADE
DEGREE FAHRENHEIT
DEMOLITION
DEPRESSED
DEPARTM [NT
DETAIL
DROP INLET, DUCTILE IRON
DIAAI ITER
DIAGONAL, DIAGRAM
DIFFERENTIAL, DIFFERENCE
DIIdENSlON
DISCHARGE
DISTANCE, DISTRIBUTION
DMSION
DEAJD LOAD
DOU BLE MECHANICAL JOINT
DAMP PROOFING
DOWN
DISSOLVED OXYGEN, DmO
DEPTIH
DOU BLE POLE. DOU BLE TH ROW
DOU BLE POlE, SINGLE TlHROW
DOWN SPOlIT
DOU BLE TIE[, DRIP TIRAP ASSEMBLY
DUPLlCATIE
DRAWING
DOWEL
DRAWER
EAST, ELECTRICAL (DWG DISCIPUNE)
EACH, EXHAUST AIR
ELECTRICAL CONTRACTOR
ECCENTIRlC
EQUIPMENT ORAl N
ELECTRfCAL DUCT BANK
EACH END
EACH FACE
EFFLUENT, EmCIENCY
ELECTRK:AL HANDHOLE
EXTERIOR INSULATION &:
FI NISH SYSTEId
EXPANSlO N JOINT
EUBOW, ELEVATI ON
ELECTRICAL
EM BEDDED
EM ERGENCY
ELECTRfCAL IdANHOLE
ENCLOSURE
ENGINEER
ENTRANCE
EDGE OF PAVEM [NT
EQUAL
EQU I PMENT
EQU IVALENT
EACH SIDE, EQUAL SPACE,
EIdERGENCY SHOWER
EMERGENCY SHOWER AN D EYE WASH
ESTIMATE
EACH WAY, EMERGENCY
EYE/FACE WASH
ELECTRIC WATIER COOLER
EACH WAY, EACH FAt:.E
EACH WAY, TOP AND BOTTOId
EXCAVATlON
EXHAUST
EXISTING
EXPANSION, EXPOSED
EXTERIOR, EXTERNAL. EXTENSION
ISSUE DATE
DESCRIPTION
F&:B
F TO F
FAB
Fa
FaD
FaG
F8Id
F80
FC
FCA
FD
FlOC
FDTN
FlDR
FIE
FlEC
RES
FIEXT
FF
FG
FIG
FH
FIN
FJT
Fl
FUEX
FlG
FlOR
FIUR
FILS
FN
FO
FOB
FOC
FOF
FOM
FOS
FOT
FPT
FIR
FlRP
FIRTId
FS
FT
FTG
FUR
FURN
FlIT
FV
FW
FWD
FWE
FXTR
G
GA
GAL
GALV
GB
GC
GO
GEN
GFCI
GFMU
GG
GJ
GL
Gl8
GND
Gl'
GR
GRTIG
GSB
GT
GVL
GWB
GYP
H
HB
HBD
HC
HC
HDR
HOW
HEX
HGR
HH
HID
HM
HORlZ
HP
HPC
HPS
HPT
HR
HS
HSS
HT
HTG
HIV
H1VAC
HWO
HM.
HYD
H7
3
FACE &: BYPASS
FACE TO FAt:.E
FABRlCATIE
flOOR BEAM
FIBERBOARD
FIBERGLASS
BOARD FOOT MEASURE
FU RNISHED BY OWNER
flUSHING CONNECTION
FlANGED COUPLING ADN'TIER
flOOR DRAIN
FlEXIBLE DUCT CONNECTION
FOU NDATlON
FEEDER
FLANGED END
FlRE EXTINGUISHER CABIN ET
FlARED END SECTION
FIRE EXTINGUISHER
FAA FAt:.E, FACTORY FINISH, FLAT FAt:.E
FINISHED GRADE
FIGURE
FlRE HYDRANT
FINISH
flUSH JOINT
FLOW, FlOW LINE
FlEXIBLE
FLANGE
FLUORESCENT
flOOR
FlASHING, flUSH
RENCE
Fl N ISHED OPENING
FENCE FlAT ON BOTTOM
FACE OF CONCRETE, FACE OF CURB
FACE OF FINISH
FACE OF MASONRY
F At:.E OF STIU OS
FLAT ON TOP
FEMALE PIPE TlHREAD
FRAME
FIBERGLASS REINFORCED PLASTIC
FIRE RETARDANT TREATlED IdATlERIAL
flOOR SINK, FAR SIDE
FEET, FOOT
FOOTING, FITTING
FU RRED, FURRING
FU RNITURE, FURN ISH
FUTURE
FACE VELOCITY
FIELD WELID, FIRE WAlL
FORWARD
FU RNISHED WITH EQUI PMENT
FlKTlURE
GRILLE, GROU ND,
GEN ERAL (DWG DISCIPLlN E)
GAGE (METAL THICKNESS)
GALLON
GALVANIZED
GRAB BAR. GRADE BREAJK
GROOVED COUPLING
GUARD
GENERAL
GROUND FAULT CIRCU IT INTERRUPTER
GROUND FACE MASONRY UNIT
GUTTER GRADE
GROOVED JOINT
GLASS
GLASS BLOCK
GROUND
GUY POLE
GRADE
GRATING
GYPSUId SH EATH ING BOARD
GREASE TIRAP
GRAVEL
GYPSUId WALIUBOARD
GYPSUId HARDBOARD
HIGH
HOSE 81B
HARDBOARD
HANDlCN'PED, HOLLOW CORE,
HORIZONTAL CU RYE
HORIZONTAL CENTERU N E
HEADER
HARDWARE
HEXAGONAL
HANGER
HANDHOLE
HIGH INTENSITY DISCHARGE
HOULOW METAL
HORIZONTAL
HIGH POINT, HORSEPOWER
HORIZONTAL POINT OF CU RVATlJRE
HIGH PRESSURE SODlU Id
HORIZONTAL POINT OF TANGENCY
HOSE REEl, HOUR
H EAJDED STlUD, HIGH STREN GTIH
HOLLOW STRUCTlURAL SfW'E
HEIGHT
HEATING
HIGH VOLTAGE
H EATING, VENTILATION &:
AIR CONDmONING
HARDWOOO
HIGH WATlER LEVEL
=U~ClES PER ~F""~n
PROJ ECT MANAGER DAN HARIdON
J. MANION
K, SIMON
PROJ ECT NUMBER 00...52713
I
10
IE
IF
IH
IIdP
IN
INC
INF
INSTR
INSUL
INT
INTR
INV
IPS
IPT
IR
IRR
ISO
JB
JCT
JF
JST
JT
K
KB
KCMIL
KD
KO
KSI
L
LAD
LAId
LATIL
LIB
LCTB
LIOG
LIOR
LE
LF
LG
UH
UN
L1Q
LLH
LLV
LldLU
LING
LOC
LP
LPS
UR
LT
LID
LTIG
LTIL
liNG
LV
LVR
LW
LWC
LWL
M
IdA
IdACH
IdAINT
MAN
IdATIL
!.lAX
IdB
IdBR
IdC
MCB
MCJ
MOW
MECH
MED
MFR
MH
MIN
MIR
MISC
MJ
MLO
MIdB
MO
MOO
MON
MPT
MRGWB
idS
IdSL
IdT
MU
MULL
J.N
MW
4
INSTRUM ENTATION (DWG DISCIPLINE)
INSIDE DlAIdETER, INTERIOR DIMENSION
INVERT ELEVATION
INSIDE FACE
INTAKE HOOD
IMPAt:.T
INCH
INCLUDE, INCANDESCENT
INflUENT
INSTRUM ENTATION
INSUtA Tl ON
ImERlO R, INTERSECTION
INTERt.I EDIATIE, INTlERIOR
INVERT
IRON PIPE SIZE
INTERNAL PIPE THREAJD
INSIDE RADIUS
IRRIGATION
ISOIdETRIC
JUNCTON BOX
JUNCTON
JOINT FILLER
JOIST
JOINT
KIP
KNEE BRACE
TlHOUSAN 0 CIRCULAR IdILS
KNOCK DOWN
KNOCK OUT
KIPS PER SQUARE INCH
ANGLE, LENGTH, LAVATORY
LADDER
LAId INATIE
LATERAL
LAG BOLT, POUND
LIQUID CHALK AND TACK BOARD
LANDING
LEADER
LIFTING EYE
LINEAR FOOT
LONG
LEFT HAND
LINEAR
LIQUID
UONG LEG HORIZONTAL
LONG LEG VERTICAL
LIQUID IdARKER LECTURE UNIT
LONGITUDI NAL
LOCATION
LOW POINT
LOW PRESSURE SODlUM
LONG RAD I US
LEFT
L1M ITED
L1GHTI NG
L1NITEL
LIGHTNING
LOW VOLTAGE
LIOWER
LIGHTWEIGHT
L1GHTWElG HT CONCRETE
LOW WATER LEVEL
IdECHiWICAL (owe DISCIPLlN E)
IdIXEO AIR
IdAt:.HINED
IdAI NTENANCE
MAN UAL
MATERIAL
MAXIMUM
IdAt:.HIN E BOLT
MEMBER
MECHAN ICAL CONTRAt:.TOR,
MECHANICAL COUPLING
METAL CORN ER BEAD
IdASON RY CONTROL JOINT
MODIFIED DOU BLE Id ECHANICAL JOINT
MECHANICAL
MEDIUM
MANUFACTUREIR
MANHOLE, METAL HALIDE
MINIMUM
MIRROR
M ISCEULANEOUS
M ECHiWICAL JOINT
IdAIN LUGS ONLY
MEMBRA.~E
MASONRY OPENING
1d0DULAR, MODIFY
1d0NUt.!ENT
MALE PIP E TlHREAD
1d0ISTURE RESISTANT
GYPSU Id WALIUBOARD
MOP SIN K
MEAN SEA LEVEL
IdOU NT
MASONRY UNIT
MUWON
MEDIUM VCL TAGE
MONITORING WELL
5
N
NA
NAT
NC
NEG
NF
NIC
NO
NOId
NPS
NPT
NS
NTS
N'M.
o TO 0
OA
DC
OCPD
00
OED
OF
OG
OH
OPNG
OPP
OPT
OR
ORD
ORIG
0VFl
DVHG
OZ
P
PA
PAR
PB
PBD
PC
PCC
PCF
PCT
PE
PED
PEN
PERF
PERM
PERP
PF
PFMU
PH
PI
PKG
PL
PLAS
PLAT
PLBG
PLF
PNEIJ
POL
POS
PP
PRC
PREF
PREFAB
PRELlId
PREP
PRES
PRI
PROP
PROT
PS
PSF
PSI
PSIA
PSIG
PST
PT
PTN
PVC
PI/MT
PWO
PWJ
PZ
Q
QT
QTR
QTY
QUAL
6
NORTIH, NEUTRAL
NOT N'PUCABLE
NATlURAL
NORIdAlLY CLOSED
NEGATIVE
NEAR F At:.E, NON-FlJSED
NOT IN CONTRACT
NORIdAlL Y OPEN, NUM BER
NOMINAL
NOMINAL PIPE SIZE
NATIONAL PIPE THREAJD
N EAR SIDE
NOT TO SCALE
NORMAL WATIER LEVEL
OlIT -TO-OUT
OUTSI DE AIR, OVERALL
ON CENTER
OVER CU RRENT PROTECTION DEVICE
OUTSI DE DIAMETER
OPEN END DUCT
OUTSIDE FACE, OFFICE FURNISHING
ORIGINAL GROUND
OVERHEAD
OPENING
OPPOSITE
OPTIONAL
OUTSIDE RADIUS
OVERFLOW ROOF DRAIN
ORIGINAL
OVERFLOW
OVERHANG
OUNCE
PAINT, PROCESS (DWG DISCIPLlN E)
PU BLlC ADDRESS
PARALJUEL. PARN'ET
PANIC BAR, pULL BOX
PARTICLE BOARD
POINT OF CURVE, PI ECE, PRECAST
POINT OF COM POUND CURVATlURE
POUNDS PER CUBIC FOOT
PERCENT
PLAIN END
PlEOESTAL
PENETRATION
PERFORATED
PERMAN ENT
PERPENDICULAR
POWER FAt:.TCR
PREFACED MASONRY UNIT
PHASE
POINT OF INTERSECTION
PAt:.KAGE
PLATE, PROPERTY LINE
PLASTIER
PLATIFORM
PLUM BING
POU N OS PER LI N EAR FOOT
PN EUMATlC
POUSH
POSITIVE, POsmON
POLYPROPYLENE, POWER POLE
POINT OF REVERSE CURVATlURE
PREFlNISHED
PREFABRICATlED
PREUIdINARY
PREPARE
PRESSURE
PRI MARY
PROPERTY
PROTECTION
PIPE SUPPORT
POUNDS PER SQUARE FOOT
POUNDS PER SQUARE INCH
POUNDS PER SQUARE INCH ABSOlUTE
POUNDS PER SQUARE INCH GAGE
PRESTRESSED
POINT, POINT OF TANGENCY
PARTITION
POLYVINYL CHLORIDE
PAVEMENT
PL '!'WOOD
PLYWOOD WEB JOIST
PIEZOMETER
RATE OF flOW
QUARRY TILE
QUARTIER
QUANTITY
QUALITY
~
fI
C1 ~
~ * . ,,- - *
~o '!._; _='r. 3 ~
or -- --...
~.(' ~~'V.
'f~ co. ~
"'="
R&:R
R&S
R
RA
RB
RCPT
RD
REC
RECD
RECT
RED
REF
REINF
REM
REOD
RESIL
RET
REV
RF
RFG
RFl
RGH
RGS
RGS-PVC
RH
RL
RLFA
RND
RNG
RO
ROW
RPM
RR
RSP
RT
RVT
RY
S
SA
SAMU
SAN
SB
SC
SCH
SCHEId
SCN
SE
SEC
SECT
SEP
SF
SG
SH
SHT
SHTG
SJL
SlM
Sl
SLID
SLV
SMLS
SOG
SP
SPA
SPEC
SPLY
SPST
SPT
SQ
SR
SS
ssr
ST
STA
STID
STlF
STIR
STIL
STOR
STR
SUB
SUC
SUSP
SY
SYM
SYMId
SYN
SYS
T&:B
T&:G
T
TA
TAN
TlBId
TeE
TlEF
TlEMP
TlHD
THK
THRESH
THRU
TlKBD
7
REMOVE AND REPLACE
REMOVE AND SALVAGE
RADIUS, REGISTER, RISER
RETURN AIR
RESILIENT BASE, ROCK BERM
i :~~~
i RECESS
RECEIVED
RECTANGULAR
REDUCER
i ~~~~G
, REMOVE
I REQUIRED
,t RESILIENT
" RETAINING, RETIJRN
, REVISION, REVERSE
RESIUENT FUDORING
, ROOFING
i =fED, REFlECTOR
, RIGID GALVANIZED STEEL
\ ~J~D,R~k HAND,
i RELATIVE HUIdIDITY
~ REQUIRED UIJ'
l' RElUEF AIR
ROUND
(RUNNING
ROUGH OPEN I NG
RIGHT OF WAY
" REVOLUTIONS PER M INUTIE
1_. =~OPE PROTECTION
t RESILIENT VINYL llLE
REAlDY
l
SOUTIH, S1NK, STRUCTIU RAL
(OWG DISCIPU NE)
SUPPLY AIR
SOUND ABSORBING MASON RY UNIT
SANITARY
SPl.ASH BLOCK
SOLID CORE
! SCliEDULE
r SCliEIdATlC
I SCREEN
STmjALUMINUM EDGE
r SECONDARY, SECONDS
SECTION
SEPARATE
SQUARE FOOT
I SHEET GLASS, SEALANT GROOVE
I SHOWER
SHEET
I SHEA TlHI NG
SlLENCE
SlMILAR
SLOPE
SUDTTED
SLEEVE
SEAMLESS
SLAB ON GRADE
SOUN DPROOF, STANDPI PE
SPACING
SPECIFICA nON
SUPPLY
SINGLE POLE SINGLE TH ROW
I SET POI NT
SQUARE
i ~=t~~~S
STAI NLESS STEEL
STREET
! STATION
STANDARD
, STIFFENER
STIRRUP
I STEEL
I STORAGE
STRUCTlURAl, STRAGHT
SUBSTITIUTE
i SUCTION
SUSPENDIEO
SQUARE YARD
SYMBOL
SYMIdETRICAL
SYNTHETIC
I SYSTEId
,I TOP AN D BOTTOM
I TONGUE AND GROOVE
I TILE. TlREAD
, ~'8NTAt:.CESSORY, TEMPERED AIR
! ~~g= ~~~~DN EASEMENT
I' TROWELED EPOXY FLOORING
TlEMPORARY, TEM PERATIU RE
TlHREAD
I THICK
! ii:~~~LD
TACK BOARD
8
TOB TOP OF BOLT, TOP OF BANK,
TOP OF BEAM
roc TOP OF CURB, TOP OF CONCRETE
TOO TOP OF OUCT
TOF TOP OF FOOTING
TOG TOP OF GRATING
TOL TOLERANCE, TOP OF LEDG ER
TOM TOP OF IdASON RY
TOP TOP OF PLATIE
TOPO TOPOGRN'HY
TOS TOP OF SLAB, TOP OF STEEL
TOW TOP OF WAUL
TIP TOI LET PARTITION, TELEPHONE POLE,
TOE PLATIE, TIRAP PRIMER
TlPD TOI LET PN'ER DISPENSER
TlPG TOPPI NG
TR ~SOId
~S ~smON
TlRD TlRENCH DRAIN
TYP TYPICAL
D
U URINAL
UG UN DERGROUND
UL T UlTlMATIE
U NFN UN FINISH ED
UNO UN LESS NOTED OTlHERWISE
UTlL UTILITY
,!
V VENT, VELOCITY, VOLT
VA VOLT AMPERE
VAt:. VACUUId
VAR VARNISH, VARIABLE,
VOLT AMPERES REACTIVE
VB VN'OR BARRI ER, VINYL BASE,
VALVE BOK
VC VERTICAL CURVE
vcr VINYL COMPOSITION TILE,
VERTICAL CENTlERLlNE
VEL VELOCITY
VENT VENTILATION
VERT VERTICAL
va VERTICAL GRAIN
VlF VERIFY IN FI ELD
VlN VI NYL
VS VERSES, VAPOR SEAL
VOL VOLU idE
VPC VERTICAL POINT OF CURVATlURE
VPI VERTICAL POINT OF INTERSECTION
VPT VERTICAL POINT OF TANGENCY
VIR VENT TlHROUGH ROOF
VWC VINYL WALL COVERING
c
W/ WITH
W /0 WITHOlIT
W WATT, WEST, WlDE, WINDOW, WI RE,
WIDE FLANGE BEAM
WB WOOD BASE
WC WATIER CLOSET, WATlER COLUMN
WD WOOD, WlDTH
WF WIDE FlANGE, WASH FOUNTAI N
WG WI RE GLASS, WATER GAGE
WH WAlL HYDRANT, WEEP HOLE
WI WROUGHT IRON
WL WATlER LEVEL
WLD wruoED
WId WIRE MESH
WP WATERPROOF, WORKING POINT
WTlHP WEATHERPROOF
WS WATIERSTOP, WATlER SURFAt:.E
WSCT WAINSCOT
Wi WEIGHT, WATER TIGHT
WWF WELDED WIRE FABRIC
B
XP EXPLOSION PROOF
XS 8nRA STRONG
XXS DOUBLE EXTIRA STRONG
XSECT CROSS SECTION
YH YARD HYDRANT
YS YI ELD STRENGTH
GENERAL NOTES:
1. THESE ABBREVIATIONS AP PLY TO TlHE ENT RE SET
OF CONTRAt:.T DRAWINGS,
2, USTlNG OF ABBREVlATlO NS OIOES N OT IMPLY ALL
ABBREV1A noNS ARE USED IN TH E CO NTRACT
DRAWINGS.
3. ABBREVIATIONS SHOWN ON TlHIS SHEET INCLUDE
VARIATIONS OF TlHE WORD. FOR EXAM PlE, "IdOD
MAY MEAN MODIFY OR MODIFICATION; "lNC" MAY
MEAN INCLUDED OR INCLUDING; "RElNF" MAY
MEAN EITHER REINFORCE OR REI NFORCI NG,
4. SCREEN I NG OR SHADING OF WORK IS USED TO
INDICATE EXISTING COMPONENTS OR TO
DE -EIdPHASlZE PROPOSED IMPROVEMENTS TO
HIGHLIGHT SELECTED TRADE WORK. REFER TO
CONTEXT OF EACH SH EET FOR USAGE.
5. SEE P&:ID LEGEND SHEET FOR PROJECT SPECIFIC
EQUIPMENT SYMBOLS, EQUIPMENT ABBREVIATIONS
AND PIPING SYSTEM ABBREVIATIONS.
A
WATER RECLAMATION FACILITY
PHASE 1 - EARLY OUT IMPROVEMENTS
STANDARD SYMBOLS AND ABBREVIATIONS
CITY OF BOZEMAN, n~T
o
I"""""'!I
1"
~
2" FlLENPJdE IBWRF 002
I SCALE I NON E
I SHEET 2
.
.
Q;
E
'jjj
J::
:i
a..
N
'<t
~
N
;.;
.....
C>
C>
N
in
<0
15
ii:
~
"C
,..;
<:>
<:>
LL
a:
$:
ell
ai
:;;;:
N
~
~
C>
"C
4:
w
..
~
~
(j
BOZEMAN WASTEWATER FACILITY/PHASE 1
I" = 60'-0"
EARLY OUT SITE MAP
PROJ EeT MANAGER OAN HARt.!ON
J. t.lANION
K. SI !.ION
o
1""""""1
~'"
~I~=~~c.
....---..-
Hl~
CITY OF BOZEMAN, +T
HDR~inet!ring.lnc.
171:5s..ItE5ERYE~
S<II1E C
.IiIS:i:X/U,. IrII" SQ!ID1-47Oll1
ISSUE
DESCRIPTION
PROJECT NUt.! BER 00.. .52713
O,o,TE
7
8
N
~
PROJECT GENERAL NOTES
D
1. ELEV,o,TlONS G1\IEN ON DR,o,W1NG AAE B.>SEO UPON
ELEVATIONS PROVlDED IN THE 200+ WNrP It.lPROVEMENTS
CONSTRlJC1"lOM DOCUM ENTS, MORRISON-WJERLE, INC. !!.'SIN
FLOOR ELEVA TIDN SHALL BE USED FOR T1Er.lPORARY BENCHMARK.
2. SECURITY FENCING AROUND PlANT PERlldETER SHALL BE
MAlNT....NED AT ALL TlI.IfS.
3. CONTRI\CTDR TO ldAlNTAlN ACCESS FOR P1ANT STAFF AND
EQUIPldENT AT ALL TIM ES. ALL PlANT ROADS AND SITE lWMGED
BY CONTR,o,CTOR'S OPER,o,TlON SIW..l BE RESTORED TO ORIGINAL
CONOmON.
4. ALL DEBRS RESULTING FROt.! WORK SIW..l BE PROt.IPTLy
REMOVED FROld THE SITE ANO DSPOSED OF IN AN APPROVED
ldANNER.
KEY NOTES
O TEMPORARY STAGING AAEA WITHIN OWNER'S SECONDAAY FENCE.
CONTR,o,CTOR UMIT STAGING AAEA TO UldITS SHOWN AND
COORDINATE KEY ACCESS WITH OWNER.
;-;\. EXSTNG FENCE ACCESS G6.TES. CONTRACTOR COORDINATE
~ ACCESS WITH OWNER.
O SWICE G6.TE REP....RS, (BID ITEM NO.1). IN AER,o,TION s,o,slN NO.1
AND NO.2. SEE SHEETS 101 '" 1 02.
O AERATION BASIN MIXER INSTAI..lATION, (BID ITEId NO.2). SEE
SHEETS 101 '" 1 02. ELECTRICAL INSTAI..lAlION B'f OWN ER SEE
SECTION 01011, OWNER FURNlSHED EOUIPldENT.
;-;\. MODIFICATIONS TO SECONOAAY CLARIFIER NO.4 lllECHANISld
\::...J INflUENT CENTERWELL BAfflE5. (BID ITEr.l NO.3). SEE SECTION
01010 AND SECTION 13342
c
B
A
WATER RECLAMATION FACILITY
PHASE 1 - EARLY OUT IMPROVEMENTS
SITE LOCATION AND STAGING AREA
1"
,o.s NOTED
3
2"
BWRF 003
SHEET
.
.
C)
-0
~
.
~
g,
u
N
~
; ;1
~--~----
mlf2\
!~'-O" ~ liD' 24'-0"
~ II ~ - .
~~--=:---jJ,lid ,
j! ~
2
i lilt
:---': 'I
"-- ; I
i II !~-- ---
Ui : r- ;
! -~- ; -- .-
~ I ~... .._ ..c'~HC^n-._~ .
f !:
c
h
::-~
'--I
II
; , II Ir
f t ~
~--LJ
c ' ~I
------~-~--~
f---- - -~~ - ~-- -tt - -~--- -.
) if---- m~
I
o
'"
'"
a;
E
'0;
.c:
::i
0-
0>
Lrl
M
N
M
.....
o
o
'::!
'!2
<C
;
~~II...... ..............
i! '
1 i
-!
~
'5
o
>.
'"
--'
~
'!
o
~
L>-
a:
~
m
m
::;
N
l"j.
~j MORRISON
.... MAIERLE,lNc,
....----
i
II /
uti l----
V
.-- .~- !
~
n
Ii
----4t-- - .-------~.-~.-
1j _'n
'I
0000_00 ~H-~-- ---
i
II
-+L
<"-LLL IlV, J
II
-. --mm----ii--~- --~- -
~t-
___~---m---
ij
~i
;;
------_._-----~~~---
U
".
49' .:}.'
fiR
HCREngiirwerrng,1nc.
l71~ S. RESERoE STREET
...,. C
~MI'.5!a8D1-47C1!1
-- "<00'-\ ~k +1,t_~.;~~~ .i:r-l~ ~~:~~.~
;:f
i it!
r.1 ~ ~
i i
~ i
l ~i r ~
3
4
~
Ii
,
i
I
J
H -4-0021
- - 2'!
! \ I \ ,
: w ,"=' ~ "'....oo'!' :
r. ..~-t~1 e
tu:......~.~!r-?I
1= __.mf-_U.~il
--+t ,
-- -_~1i - I
__~~_~_~t-F--SOO4=OO1-t ~:J
- V~ __.~m_
---~._--~--
i:
I
j,
I'
!
1
~
i:
I
;
~ i
H
"
~
I
,
,
i
I
I
I
n
ii
iI
r-~
j
I
!
.J
- ..___: I __
i+--
+l-
~__ ___ n_+L
--------------' i---
irl
:r
- !I
!'
1
-- - ---- _.~~
~~---==:xx:j
=
!
- _. ._.._ ...1
i
.,.".
_00_
... __m~
"'->LLL iV. L
II '
~. ...:~:: == . ..-111
=_.--:,v--~~03 L '~-'-i '-1 ~-:.:v~QO~-~~-~ ~ .....:i rl
____~.h-=---4 H 4-003 'l~~--t H-4-004 I
I -~~ R-4-003 '-/ h: R 4-004 I
! I I 21 0 T 24 0 I
o
~
1
6' . "'~
~~
W49'4
IC\
UQU
MIXER & STOP GATE PLAN
3/32" = l' -0"
t5SUE
.llillES:.
o THE CONTRACTOR SHALL PROTECT
THE EXISTING AERATION GRID
DURING THE SLUICE GATE
REHABILITATION AND THE MIXER
AND RAIL INSTALLATION.
o INSTALL 4 EACH OWNER
FURNISHED AERATION BASIN
MIXER IN ACCORDANCE WITH
SECTION 01011.
PROJECT MANAGER DAN HARMON
J. MANION
K. SlMON
DATE
OESC RI PTION
PROJECT NUMB ER 00...52713
~~
~ t j
""
Ni
i
,
~
!
,
,
,
,
, . .
XXx:::t::X'~~...i
5
5
7
. ~ . ..... ., ~
I t~
!.!'~l.J !
, i I
; '"11 i
i "I I
. " ,
: ';I i
r-,~_,-/~::t:~_~=~~~~:I_ ~ I._=~,
<,.
CELL NO.
MIX -4-00 1
3
102 ,lYP Of 4
MIXER SECTION
3/16" = 1'-0"
ffi
EL: 4516,31 \
\
\
\
\
------'-
-- -,.r -
i 8
l
I
,
~~~
~---_._-- p----=--=.-
::..1
s....:..~ -:....A...._...:
._-_.~- ---=-=f<-~---=--rr::::::: --
i
1
:j
1
~ i
;,,1
I I
Nl
~l
.;
;
~ .j
CELL
NO, 2
I
I
i
I
"A;' ._ '.l.--:-.-~ ';O:_-::~~~
MIXER SECTION
3/16" = 1'-0"
ffi
8
,lYP OF 4
D
"i 1
~ ,
;',I,.!,
~
I ~t 1
H1
I::t;
i i.
! .","l
c
I
H W
bd
j.....
r~
l~ i
l.i
t .Ii.
I;-i
I.'j
t. ~I
'.]
',j
.
,
,
,
,
I
i
~,
i
i
! A
j
_ ti~- ~- . ::-~ .~~. ._1_59~5.~_____o-
WATER RECLAMATION FACILITY
PHASE 1 - EARLY OUT IMPROVEMENTS
STOP GATE, MIXER INSTALLATION & SLUICE GATE
REPAIR PLAN AND SECTIONS
,
CITY OF BOZEMAN, ~T
I"
2"
o
1""""""1
BWRF 101
SHEET
/oS NOTED
101
.
.
t
E
'(5
..<:
::i
<l:
<D
<'l
,:..:
Oci
.....
CI
CI
N
~
N
LO
~
::>
o
>.
'"
..J
cii
~
-0
N
CI
~
LL
a:
~
cD
:;
N
~
;;
-0
~
.
a:
o
~
g,
o
'-- ~- : ::::
SEE DETAIL
2
HOIST SECTION
1" = 1'-0"
MORRISON
MAIERLE, INC,
A.a.ErnpJo~C~
Hl"1
HDREI19lI!leINing.Inc.
'71:; s.. RESERVE mEET"
sure C
WIS$Ol..U." Ii.ff 5.'il801-4708
ISSUE
QJ
DATE
DESCRI PTI 0 N
3
4
5
;00-<-0" \ __
ee -.~,e ....:~,~ ..... ~l-==:t:::F--r
.........._~-,'j------_._._._._._._.-~i~-._._.^._----'---"-=-jr'-~i - ~'-J-'H~"""~J----~ -"'1~'- '~--~-i~=_y_'-'~'?---=-'~--=T'~-"
r-.--......;;;:;r.~-..
(~F'-l i
~ , -....
: ~' ;. ....
/
v"- ..._.~-
/ .--.:;;::::r----...:.::;;------------'.....
..---.::;:7......-... "'9 '''-'',
...^..>......_~...... ....
.....:...~.^ .......
GATE SECTION
3/16" = 1'-0"
NOTES:
~
o
(3)
0)
o
~ ..
~ ,
.'
~ ....
..... '
i+ ...
i .. .
! .-
, ..
,
! .'
r ~.. .
'. ,
". .";
~4.. : . i
:... .
,TYP
MIXER SECTION
1 1/2" = 1'-0"
OJ
PROJECT t.lANAG ER DAN HARMON
J. MANION
K. SI MON
PROJECT NUMBER 00...52713
6
7
8
D
..v..........
.-r:;;;;r---.........H..V. ...........~,
c-E;...L ~~n
~ "STAINLESS STEEL EPOXY
EM BEO,
,TYP
c
THE CONTRACTOR SHALL PROTE~THE EXISTlNc;1
AERATION GRID DURING THE SLU GATE :
REHABiUTATlON AND THE MIXER RAIL :
INSTAlLLATION, j
~~~IUTAT1E EXISTING SWICE ~~JE PER SECT1~
EXISTING AERATION GRID PIPI NG DIFFUSER ~OT
SHOWN,
: HOIST MOUNTING
INTS
BRACKET [jd
lD1
E]
~.m
B
o
(WALL MOUNTING BRACKET
2
101
,lYP
A
LOOR MOUNTING BRACKET 3
102
CITY OF BOZEMAN,
SH EEl
WATER RECLAMATION FACILITY
PHASE 1. EARLY OUT IMPROVEMENTS
STOP GATE, MIXER INSTALLATION & SLUICE GATE
REPAIR SECTIONS
BWRF 102
o I"
.----
2"
,
102
AS NOTED