HomeMy WebLinkAbout26 - Amendments Amendment Number Unknown - HDR Engineering, Inc. - Valley Center Lift Station and Force Main Project1
Amendment No. 2 to Professional Services Agreement
For Valley Center Lift Station and Force Main Project
THIS AGREEMENT is made as of this 25th day of August, 2026, between THE CITY OF
BOZEMAN, a Municipal Corporation, Bozeman, Montana, herein referred to as OWNER and
HDR Engineering, Inc., an Engineering Consulting Firm of Bozeman, Montana, herein referred
to as ENGINEER.
WHEREAS, the parties have entered into a Professional Services Agreement dated November
14th, 2023, herein referred to as Original Agreement for professional engineering services; and
WHEREAS, the parties desire to further amend the provisions of this Agreement.
NOW, THEREFORE, IN CONSIDERATION OF THE MUTUAL COVENANTS
CONTAINED HEREIN, the parties agree as follows:
ARTICLE 1 - ENGINEERING SERVICES
Section 1.3 and Section 1.4 are added to the Original Agreement as follows:
1.3. Bid Phase, Contract Administration, and Construction Services – The scope of services
under this contract is set forth in this Agreement and the attached EXHIBIT C “Valley
Center Lift Station & Force Main Project – Bid Phase, Contract Administration, and
Construction Services – Scope of Services” and EXHIBIT D “Valley Center Lift Station
& Force Main Project – Bid Phase, Contract Administration, and Construction Services –
Fee Estimate”.
1.4. Exhibit A – Engineer’s Status During Construction and Exhibit B – A listing of the
Duties, Responsibilities and Limitations of Authority of the Resident Project
Representative.
ARTICLE 4 - BASIC ENGINEERING SERVICES
Articles 4.4, 4.5, and 4.6 are added to the Agreement as follows:
4.4 BIDDING OR NEGOTIATING PHASE
After written authorization to proceed with the Bidding or Negotiating Phase, ENGINEER shall:
4.4.1. Assist OWNER in advertising for and obtaining bids or negotiating proposals for
construction contract(s) and record prospective bidders to whom Bidding Documents
have been issued, receive and process deposits for Bidding Documents and conduct
pre-bid conferences.
4.4.2. Provide interpretation or clarification to prospective bidders regarding the Bidding
Documents, and issue addenda as appropriate.
Docusign Envelope ID: 0989F0C0-8726-8554-836C-91CEF05A53FC
2
4.4.3. Consult with and advise OWNER as to the acceptability of the prime contractor,
subcontractors, suppliers and other persons and organizations proposed by the prime
contractor(s) (herein call "Contractor(s)") for those portions of the work as to which such
acceptability is required by the Bidding Documents.
4.4.4. Consult with OWNER concerning and determine the acceptability of substitute
materials and equipment proposed by Contractor(s) when substitution prior to the award
of contracts is allowed by the Bidding Documents.
4.4.5. Attend the bid opening, prepare bid tabulation, evaluate bids, assess bidders'
responsiveness and responsibility and make award recommendation to OWNER.
4.4.6 Facilitate contract award, and the execution and distribution of the contract
documents for construction, materials, equipment and services. Furnish Owner two
original signature sets of executed contract documents (including design drawings,
specifications and contracts). Furnish contractor with one set of original signature
executed contract documents and up to three sets of construction documents.
4.5 CONSTRUCTION PHASE
The responsibilities of the ENGINEER during the Construction Phase are summarized as
follows:
4.5.1. General Administration of Construction Contract. ENGINEER shall consult with
and advise OWNER and act as OWNER'S representative as provided in EXHIBIT A -
ENGINEER'S STATUS DURING CONSTRUCTION, attached to and made part of
this Agreement and may be further provided under the General Conditions of the contract
documents. The extent and limitations of the authority, duties, and responsibilities of the
ENGINEER on the construction job site as described here-in shall not be modified except
as the ENGINEER and OWNER may otherwise agree in writing. All of OWNER's
instruction to Contractor(s) will be issued through ENGINEER who will have authority
to act on behalf of OWNER to the extent provided in the General Conditions except as
otherwise provided in writing.
In addition to the services provided under Article 10 (Exhibit A) the ENGINEER shall
provide the following services during construction:
4.5.1.1 Schedule and conduct a pre-construction conference.
4.5.1.2 Provide personnel, equipment and supplies for construction layout and
control, including establishment of line, grade, and blue top control staking.
Docusign Envelope ID: 0989F0C0-8726-8554-836C-91CEF05A53FC
3
4.5.1.3 Review Contractors' construction schedules and operations, and the
Contractors' traffic control plans and its implementation prior to the start of
construction.
4.5.1.4 Ascertain that the Contractor has secured required permits needed to
accomplish his work.
4.5.1.5 Prepare and provide weekly activity and progress reports to the City's
Task Director.
4.5.1.6 ENGINEER shall provide OWNER copies of all correspondence between
the ENGINEER and Contractor.
4.5.1.7 Issue stop and resume work orders, in whole or in part, when work is not
or cannot be performed in accordance with the Contract Documents.
4.5.1.8 Review and approve, for conformance with the project technical
specifications all shop drawings, and other Contractor submittals required by the
Contract Documents.
4.5.1.9 During construction review Contractors' construction schedules and
evaluate conformance and progress under the Contract time provisions.
4.5.1.10 Prepare for OWNER'S approval any plan and specification changes
which due to any initial design or engineering deficiencies are required to
complete the project original design concept.
4.5.1.11 Inspect the project and when appropriate, and after conferring with
OWNER, issue a Certificate of Substantial Completion to the Contractor.
4.5.1.12 Prior to recommending final payment, schedule and conduct with the
OWNER a final project inspection and submit a report to the OWNER
documenting any outstanding items or deficiencies requiring correction prior to
final payment. Upon satisfactory project completion, ENGINEER shall certify in
writing to the OWNER, and any required regulatory agencies, that the
construction was completed in accordance with the approved plans and
specifications and is performing in accordance with the design concept.
4.5.1.13 Twenty-three months after project substantial completion schedule and
conduct with the Owner a Two-Year Warranty Inspection of the project and
advise the owner in writing whether project deficiencies exist and if the project is
performing in accordance with the design concept.
4.5.2. Resident Project Representative. ENGINEER shall provide a qualified Resident
Project Representative at the job site to provide observation of the work as provided in
Docusign Envelope ID: 0989F0C0-8726-8554-836C-91CEF05A53FC
4
EXHIBIT B - A LISTING OF THE DUTIES, RESPONSIBILITIES AND
LIMITATIONS OF AUTHORITY OF THE RESIDENT PROJECT
REPRESENTATIVE, attached to and made part of this Agreement.
The ENGINEER shall submit to the OWNER, for review and acceptance, the resume of
each Resident Project Representative who may be assigned to the job site during the
course of the Project not less than 10 calendar days prior to the pre-construction meeting.
Any subsequent change in the resident representative shall also be subject to the
OWNER'S approval.
4.5.3 Limitations of Responsibilities. ENGINEER will not be responsible for
CONTRACTOR's means, methods, techniques, sequences or procedures of construction,
or the safety precautions and programs incident thereto, and ENGINEER will not be
responsible for CONTRACTOR's failure to perform or furnish the Work in accordance
with the Contract Documents; however, nothing contained in this Agreement shall be
construed to release ENGINEER from liability for failure to properly perform duties and
responsibilities assumed by ENGINEER in the Contract Documents.
4.6. PROJECT DOCUMENTATION
ENGINEER shall furnish OWNER with (a) one mylar copy, two paper copies, and an electronic
copy of the Project Record Drawings ("As-Builts"), (b) written monthly progress reports, and (c)
a project notebook containing such correspondence and documentation as requested by OWNER.
ARTICLE 6 - COMPENSATION FOR ENGINEERING SERVICE
Article 6.2 is added to the Agreement as follows:
6.2 DIRECT LABOR COST PAYMENT FOR BASIC SERVICES AND EXPENSES
OF ENGINEER.
Construction and project documentation services performed as Basic Engineering Services under
sections 4.4 through 4.6 including General Administration of Construction Contract, Resident
Project Representation, Project Documentation, and Construction Testing, shall be compensated
in accordance with the following:
6.2.1 The OWNER shall pay for Construction Phase and Project Documentation Services
an amount not to exceed $262,201 except as provided under 6.2.1.2 and 6.2.4.
6.2.1.1 Costs Compensation. Compensation for these services shall be based on
the ENGINEER's Direct Labor Cost times a factor of 3.30 for services rendered
which shall cover Direct Labor, Direct Labor Overhead, General &
Administrative Overhead and Profit.
6.2.1.2 Notification. At any time during the construction that it becomes apparent
that the Construction Phase and Project Documentation Services rendered under
Docusign Envelope ID: 0989F0C0-8726-8554-836C-91CEF05A53FC
5
this Agreement will exceed the negotiated compensation for these services, and
prior to performing services in excess of the contract ceiling, the ENGINEER
shall give OWNER written notice thereof. Promptly thereafter OWNER and
ENGINEER shall review the scope and progress of the project work.
ENGINEER shall obtain written authorization from OWNER, prior to any
additional costs being incurred under paragraph 6.2.1.3. If it is determined that
due to a change in project scope under paragraph 5.2.1, the ENGINEER is entitled
to additional compensation, OWNER and ENGINEER may negotiate terms as
provided under 6.2.1.1. The amount and terms of any additional compensation
under 6.2.1.1 or 6.2.1.3 shall be negotiated and agreed in writing pursuant to 9.16.
6.2.1.3 Costs Exceeding Estimated Compensation. Except as allowed under 5.2.1,
when the total cost of the original scope Construction Phase and Project
Documentation Services exceeds the negotiated compensation for these services,
the OWNER shall pay only for the direct costs incurred in excess of the estimated
compensation. These costs consist of an amount equal to the ENGINEER'S
Direct Labor Cost times a factor of 2.85 for services rendered which shall include
Direct Labor, the federally audited payroll Direct Labor Overhead, and General &
Administrative Overhead costs, but shall not include any allowance for profit.
6.2.2. Reimbursable Expenses, as defined in section 7.4 of this Agreement, for Basic
Services and Approved Additional Services shall be paid to the ENGINEER by the
OWNER in the actual amount of the costs incurred up to an amount not to exceed $8,757
which includes reimbursable expenses. The estimated reimbursable expenses are
identified in Exhibit D “Valley Center LS & FM – Bid Phase, Contract Administration,
and Construction Services – Fee Estimate”.
6.2.3. Failed Test Expenses. The ENGINEER shall maintain and provide to the OWNER,
a record of the costs associated with failing quality control tests performed for the
OWNER during the course of the construction of the project and recommend an amount
the OWNER deduct from the contractor(s) payments.
6.2.4 The OWNER shall pay an amount for Additional Services rendered by the
ENGINEER and approved in writing by the OWNER on the basis of the ENGINEER'S
Direct Labor Costs times a factor of 3.30, or an amount otherwise negotiated at the time
such services are requested and approved by the OWNER.
ARTICLE 7 – MEANING OF TERMS
Article 7.3 is added to the Agreement as follows:
7.3 DIRECT LABOR COSTS
Direct Labor Costs used as a basis for payment mean the actual salaries and wages paid to all
ENGINEER's personnel engaged directly on the Project, including, but not limited to, engineers,
architects, surveyors, designers, drafters, specification writers, estimators, other technical and
Docusign Envelope ID: 0989F0C0-8726-8554-836C-91CEF05A53FC
6
business personnel; but does not include indirect payroll related costs or fringe benefits. For the
purposes of this Agreement the principals and employees of the ENGINEER maximum billable
Direct Labor Costs are:
Principals $ 95.00 /hour
Project Manager $ 85.00 /hour
Senior Engineer $ 90.00 /hour
Staff Engineer $ 60.00 /hour
Junior Engineer $ 40.00 /hour
SCADA/Programming $ 65.00 /hour
CADD/BIM $ 65.00 /hour
Accountant $ 45.00 /hour
Project Administration $ 40.00 /hour
Except as specifically amended herein, the original agreement shall remain in full force
and effect and the Parties shall be bound by all terms and conditions therein.
IN WITNESS WHEREOF, the parties hereto do make and execute this Agreement on the
day and year first above written.
CITY OF BOZEMAN
By:
______________________________________
Chuck Winn
City Manager
ATTEST:
________________________________________
Mike Maas
City Clerk
APPROVED AS TO FORM
By:____________________________________
Greg Sullivan
City Attorney
ENGINEER
By:_______________________________________
Tim Erickson, PE
Vice President
ATTEST:
By:___________________________________
Docusign Envelope ID: 0989F0C0-8726-8554-836C-91CEF05A53FC
7
EXHIBIT A
TO AGREEMENT BETWEEN OWNER AND ENGINEER FOR PROFESSIONAL
SERVICES
ENGINEER'S STATUS DURING CONSTRUCTION
This Exhibit is attached to, made a part of and incorporated by reference with the Agreement
made on , between CITY OF BOZEMAN (OWNER) and HDR Engineering, Inc.
(ENGINEER) providing for professional engineering services.
ARTICLE 10 - ENGINEER'S STATUS DURING CONSTRUCTION
10.1. OWNER’S REPRESENTATIVE
ENGINEER will be OWNER's representative during the construction period. The duties and
responsibilities and the limitations of authority of ENGINEER as OWNER's representative
during construction are set forth in the Contract Documents and shall not be extended without
written consent of OWNER and ENGINEER.
10.2. VISITS TO THE SITE
ENGINEER will make visits to the site at intervals appropriate to the various stages of
construction to observe the progress and quality of the executed Work and to determine, in
general, if the Work is proceeding in accordance with the Contract Documents. ENGINEER
will not be required to make exhaustive or continuous on-site inspections to check the quality or
quantity of the Work. ENGINEER's efforts will be directed toward providing for OWNER's
greater degree of confidence that the completed Work will conform to the Contract Documents.
On the basis of such visits and on-site observations as an experienced and qualified design
professional, ENGINEER will keep OWNER informed of the progress of the Work and will
endeavor to guard OWNER against defects and deficiencies in the Work.
10.3. PROJECT REPRESENTATION
If OWNER and ENGINEER agree, ENGINEER will furnish a Resident Project Representative
to assist ENGINEER in observing the performance of the Work. The duties, responsibilities
and limitations of authority of any such Resident Project Representative and assistants will be as
provided in EXHIBIT B, A LISTING OF THE DUTIES, RESPONSIBILITIES AND
LIMITATIONS OF AUTHORITY OF THE RESIDENT PROJECT REPRESENTATIVE.
10.4. CLARIFICATIONS AND INTERPRETATIONS
ENGINEER will issue with reasonable promptness such written clarifications or interpretations
of the requirements of the Contract Documents (in the form of Drawings or otherwise) as
ENGINEER may determine necessary, which shall be consistent with or reasonably inferable
Docusign Envelope ID: 0989F0C0-8726-8554-836C-91CEF05A53FC
8
from the overall intent of the Contract Documents. If CONTRACTOR believes that a written
clarification or interpretation justifies an increase in the Contract Price or an extension of the
Contract Time and the parties are unable to agree to the amount or extent thereof,
CONTRACTOR may make a claim therefor as provided in the General Provisions of the
construction Contract Document.
10.5. AUTHORIZED VARIATIONS IN WORK
ENGINEER may authorize minor variations in the Work from the requirements of the Contract
Documents which do not involve an adjustment in the Contract Price or the Contract Time and
are consistent with the overall intent of the Contract Documents. These may be accomplished
by a Field Order and will be binding on OWNER, and also on CONTRACTOR who shall
perform the Work involved promptly. If CONTRACTOR believes that a Field Order justifies
an increase in the Contract Price or an extension of the Contract Time and the parties are unable
to agree as to the amount or extent thereof, CONTRACTOR may make a claim therefor as
provided in the General Conditions of the Construction Contract.
10.6. REJECTING DEFECTIVE WORK
ENGINEER will have authority to disapprove or reject Work which ENGINEER believes to be
defective, and will also have authority to require special inspection or testing of the Work as
provided in the General Provisions of the construction Contract Document whether or not the
work is fabricated, installed, or completed.
10.7. SHOP DRAWINGS, CHANGE ORDERS AND PAYMENT
10.7.1. The ENGINEER's responsibility for Shop Drawings and samples shall comply with
the shop drawing provisions of the General Provisions of the construction Contract
Document
10.7.2. The ENGINEER's responsibilities for Change Orders shall comply with the change
order provisions of the General Provisions of the construction Contract Document.
10.7.3. The ENGINEER's responsibilities for contractor's Application for Payment shall
comply with the payment provisions of the General Provisions of the construction Contract
Document.
10.8. DETERMINATIONS FOR UNIT PRICES
ENGINEER will determine the actual quantities and classifications of Unit Price Work
performed by CONTRACTOR. ENGINEER will review with CONTRACTOR the
ENGINEER's preliminary determinations on such matters before rendering a written
recommendation thereon (by recommendation of an Application for Payment or otherwise) to
OWNER.
Docusign Envelope ID: 0989F0C0-8726-8554-836C-91CEF05A53FC
9
10.9. DECISION ON DISPUTES
10.9.1. ENGINEER will be the initial interpreter of the requirements of the Contract
Documents and judge of the acceptability of the Work thereunder. Claims, disputes and
other matters relating to the acceptability of the Work or the interpretation of the
requirements of the Contract Documents pertaining to the performance and furnishing of the
Work and claims under The General Conditions of the Construction Contract in respect of
changes in the Contract Price or Contract Time will be referred initially to ENGINEER in
writing with a request for a formal decision in accordance with this paragraph, which
ENGINEER will render in writing within a reasonable time. Written notice of each such
claim, dispute and other matter shall be promptly reported and copied to the OWNER.
10.9.2. When functioning as interpreter under paragraphs 10.8 and 10.9.1, ENGINEER will
not show partiality to OWNER or CONTRACTOR and will not be liable in connection with
any interpretation or decision rendered in good faith in such capacity. The rendering of a
decision by ENGINEER pursuant to paragraphs 10.8 and 10.9.1 with respect to any such
claim, dispute or other matter will be a condition precedent to any exercise by OWNER or
CONTRACTOR of such rights or remedies as either may otherwise have under the Contract
Documents or by Laws or Regulations in respect of any such claim, dispute or other matter.
10.10. LIMITATIONS ON ENGINEER'S RESPONSIBILITIES
10.10.1. Neither ENGINEER's authority to act under this Article or elsewhere in the
Contract Documents nor any decision made by ENGINEER in good faith either to exercise
or not exercise such authority shall give rise to any duty or responsibility of ENGINEER to
CONTRACTOR, any Sub-contractor, any Supplier, or any other person or organization
performing any of the Work, or to any surety for any of them.
10.10.2. Whenever in the Contract Documents the terms "as ordered", "as directed", "as
required", "as allowed", "as approved" or terms of like effect or import are used, or the
adjectives "reasonable", "suitable", "acceptable", "proper" or "satisfactory" or adjectives of
like effect or import are used to describe a requirement, direction, review or judgment of
ENGINEER as to the Work, it is intended that such requirement, direction, review or
judgment will be solely to evaluate the Work for compliance with the Contract Documents
(unless there is a specific statement indicating otherwise). The use of any such term or
adjective shall not be effective to assign to ENGINEER any duty or authority to supervise or
direct the furnishing or performance of the Work or any duty or authority to undertake
responsibility contrary to the provisions of paragraph 4.5.3.
Docusign Envelope ID: 0989F0C0-8726-8554-836C-91CEF05A53FC
10
EXHIBIT B
TO AGREEMENT BETWEEN OWNER AND
ENGINEER FOR PROFESSIONAL SERVICES
A LISTING OF THE DUTIES, RESPONSIBILITIES AND
LIMITATIONS OF AUTHORITY OF THE RESIDENT PROJECT REPRESENTATIVE.
This Exhibit is attached to, made a part of and incorporated by reference with the Agreement
made on , between CITY OF BOZEMAN (OWNER) and HDR
Engineering, Inc. (ENGINEER) providing for professional engineering services.
ARTICLE 11 - DUTIES, RESPONSIBILITIES AND LIMITATIONS OF AUTHORITY
OF THE RESIDENT PROJECT REPRESENTATIVE
ENGINEER shall furnish a Resident Project Representative (RPR), assistants and other field
staff to assist ENGINEER in observing performance of the work of Contractor.
Through more extensive on-site observations of the work in progress and field checks of
materials and equipment by the RPR and assistants, ENGINEER shall endeavor to provide
further protection for OWNER against defects and deficiencies in the work of CONTRACTOR;
but, the furnishing of such services will not make ENGINEER responsible for or give
ENGINEER control over construction means, methods, techniques, sequences or procedures or
for safety precautions or programs, or responsibility for CONTRACTOR's failure to perform the
Work in accordance with the Contract Documents and in particular the specific limitations set
forth in section 4.5 of the Agreement are applicable.
The duties and responsibilities of the RPR are limited to those of ENGINEER in this agreement
and in the construction Contract Documents, and are further limited and described as follows:
11.1. GENERAL
RPR is ENGINEER's agent at the site, will act as directed by and under the supervision of
ENGINEER, and will confer with ENGINEER regarding RPR's actions. RPR's dealings in
matters pertaining to the on-site work shall in general be with ENGINEER and CONTRACTOR
keeping OWNER advised as necessary. RPR's dealings with subcontractors shall only be
through or with the full knowledge and approval of CONTRACTOR. RPR shall generally
communicate with OWNER with the knowledge of and under the direction of ENGINEER.
11.2. DUTIES AND RESPONSIBILITIES OF RPR
11.2.1. Schedules: Review the progress schedule, schedule of Shop Drawing submittals and
schedule of values prepared by CONTRACTOR and consult with ENGINEER concerning
acceptability.
Docusign Envelope ID: 0989F0C0-8726-8554-836C-91CEF05A53FC
11
11.2.2. Conferences and Meetings: Attend meetings with CONTRACTOR, such as
preconstruction conferences, progress meetings, job conferences and the project-related
meetings, and prepare and circulate copies of minutes thereof.
11.2.3. Liaison:
11.2.3.1. Serve as ENGINEER's liaison with CONTRACTOR, working principally
through CONTRACTOR's superintendent and assist in understanding the intent of the
Contract Documents; and assist ENGINEER in serving as OWNER's liaison with
CONTRACTOR.
11.2.3.2. Assist in obtaining from OWNER additional details or information, when
required for proper execution of the Work.
11.2.4. Shop Drawings and Samples:
11.2.4.1. Record date of receipt of Shop Drawings and samples.
11.2.4.2. Receive samples which are furnished at the site by CONTRACTOR,
and notify ENGINEER of availability of samples for examination.
11.2.4.3. Advise ENGINEER and CONTRACTOR of the commencement of
any Work requiring Shop Drawing or sample if the submittal has not been app
approved by ENGINEER.
11.2.5. Review of Work, Rejection of Defective Work, Inspections and Tests:
11.2.5.1. Conduct on-site observations of the Work in progress to assist ENGINEER in
determining if the Work is in general proceeding in accordance with the Contract
Documents.
11.2.5.2. Report to ENGINEER whenever RPR believes that any Work is unsatisfactory,
faulty or defective or does not conform to the Contract Documents, or has been damaged,
or does not meet the requirements of any inspection, test or approval required to be made;
and advise ENGINEER of Work that RPR believes should be corrected or rejected or
should be uncovered for observation, or requires special testing, inspection or approval.
11.2.5.3. Verify that tests, equipment and systems startup and operating and maintenance
training are conducted in the presence of appropriate personnel, and the CONTRACTOR
maintains adequate records thereof; and observe, record and report to ENGINEER
appropriate details relative to the test procedures and startup.
Docusign Envelope ID: 0989F0C0-8726-8554-836C-91CEF05A53FC
12
11.2.5.4. Accompany visiting inspectors representing public or other agencies having
jurisdiction over the Project, record the results of these inspections and report to
ENGINEER.
11.2.6. Interpretation of Contract Documents: Report to ENGINEER when clarifications and
interpretations of the Contract Documents are needed and transmit to
CONTRACTOR clarifications and interpretations as issued by ENGINEER.
11.2.7. Modifications: Consider and evaluate CONTRACTOR's suggestions for
modifications in Drawings or Specifications and report with RPR's recommendations
to ENGINEER. Transmit to CONTRACTOR decisions as issued by ENGINEER.
11.2.8. Records:
11.2.8.1. Maintain at the job site orderly files for correspondence, reports of job
conferences, Shop Drawings and samples, reproductions of original Contract Documents
including all Work Directive Changes, Addenda, Change Orders, Field Orders, additional
Drawings issued subsequent to the execution of the Contract, ENGINEER's clarifications
and interpretations of the Contract Documents, progress reports, and other Project related
documents.
11.2.8.2. Keep a detailed and accurate diary or log book, recording CONTRACTOR
hours on the job site, weather conditions, prime and subcontractor daily work force, daily
log of equipment onsite or on standby, data relative to questions of Work Directive
Changes, Change Orders or changed conditions, list of job site visitors, daily activities,
decisions, observations in general, and specific observations in more detail as in the case
of observing test procedures; and send copies to ENGINEER.
11.2.8.3. Record names, addresses and telephone numbers of all CONTRACTORS,
subcontractors and major suppliers of materials and equipment.
11.2.9. Reports:
11.2.9.1. Furnish ENGINEER periodic reports as required of progress of the Work and of
CONTRACTOR's compliance with the progress schedule and schedule of Shop Drawing
and sample submittals.
11.2.9.2. Consult with ENGINEER in advance of scheduled major tests, inspections or
start of important phases of the Work.
11.2.9.3. Draft proposed Change Orders and Work Directive Changes, obtaining backup
material from CONTRACTOR and recommend to ENGINEER Change Orders, Work
Directive Changes, and Field Orders.
Docusign Envelope ID: 0989F0C0-8726-8554-836C-91CEF05A53FC
13
11.2.9.4. Report immediately to ENGINEER and OWNER upon the occurrence of any
accident.
11.2.10. Payment Requests: Review applications for payment with CONTRACTOR for
compliance with the established procedure for their submission and forward with
recommendations to ENGINEER, noting particularly the relationship of the payment
requested to the schedule of values, Work completed and materials and equipment
delivered at the site but not incorporated in the Work.
11.2.11. Certificates, Maintenance and Operation Manuals: During the course of the Work,
verify that certificates, maintenance and operation manuals and other data required to
be assembled and furnished by CONTRACTOR are applicable to the items actually
installed and in accordance with the Contract Documents, and have this material
delivered to ENGINEER for review and forwarding to OWNER prior to final
payment for the Work.
11.2.12. Completion:
11.2.12.1. Submit to CONTRACTOR, and ENGINEER a list of observed items requiring
completion or correction before ENGINEER may issue a Certificate of Substantial
Completion.
11.2.12.2 Assess completion or correction of items noted under 11.2.12.1, advise
ENGINEER on their status, and make recommendation to Engineer regarding issuance of
a Certificate of Substantial completion.
11.2.12.3. Conduct final inspection in the company of ENGINEER, OWNER, and
CONTRACTOR and prepare a final list of items to be completed or corrected.
11.2.12.4. Observe that all items on final list have been completed or corrected and make
recommendations to ENGINEER concerning final acceptance.
11.3. LIMITATIONS OF AUTHORITY
Resident Project Representative:
11.3.1. Shall not authorize any deviation from the Contract Documents or substitution of
materials or equipment, unless authorized by ENGINEER.
11.3.2. Shall not exceed limitations of ENGINEER's authority as set forth in the Agreement
or the Contract Documents.
11.3.3. Shall not undertake any of the responsibilities of CONTRACTOR, subcontractors or
CONTRACTOR's superintendent.
Docusign Envelope ID: 0989F0C0-8726-8554-836C-91CEF05A53FC
14
11.3.4. Shall not advise on, issue directions relative to or assume control over any aspect of
the means, methods, techniques, sequences or procedures of construction unless such advice
or directions are specifically required by the Contract Documents.
11.3.5. Shall not advise on, issue directions regarding or assume control over safety
precautions and programs in connection with the Work.
11.3.6. Shall not accept Shop Drawing or sample submittals from anyone other than
CONTRACTOR.
11.3.7. Shall not authorize OWNER to occupy the Project in whole or in part.
11.3.8. Shall not participate in specialized field or laboratory tests or inspections conducted
by others except as specifically authorized by ENGINEER.
Docusign Envelope ID: 0989F0C0-8726-8554-836C-91CEF05A53FC
1
EXHIBIT C
CITY OF BOZEMAN, MONTANA
VALLEY CENTER LIFT STATION AND FORCE MAIN PROJECT
BID PHASE, CONTRACT ADMINISTRATION, AND
CONSTRUCTION OBSERVATION SERVICES
AMENDMENT NO. 2 – SCOPE OF SERVICES
Scope of Services
The scope of services identified herein is for the Bid Phase, Contract Administration, and
Construction Observation related to the Valley Center Lift Station and Force Main Project.
Task 1000. Project Management
HDR will provide project management and administrative activities throughout the duration of the
Bid Phase, Contract Administration, and Construction Observation of the construction project and
generally include the following:
• Invoicing, work planning, and administrative activities to manage, to the extent possible,
scope, budget, and schedule relative to activities summarized within this scope of
services.
Task 1000 Deliverables
• Monthly invoices.
• Memoranda and meeting notes, as required.
Task 1100. Bid Phase Services
HDR will provide bid phase services to assist the City in the selection of a Contractor for the
construction of the project. These services will consist of the following:
Subtask 1101 – Bidding Administrative Assistance
Prepare Bid Documents and facilitate online bid services through QuestCDN for prospective
bidders. Develop and implement procedures for receiving and answering bidders' questions and
requests for additional information. The procedures shall include a log of bidders’ questions and
requests and the response thereto. HDR will provide technical interpretation of the Bid Documents
and will prepare proposed responses to bidders’ questions and requests, which may be in the
form of addenda, and assist the City in arranging and conducting a pre-bid conference. HDR will
develop the agenda and content of the pre-bid conference and will record minutes and document
the results of the pre-bid conference. Budget assumes seventy-two (72) hours total over the
bidding period.
Docusign Envelope ID: 0989F0C0-8726-8554-836C-91CEF05A53FC
2
Subtask 1102 – Bid Opening Assistance
Conduct the bid opening at the date and time specified in the solicitation. HDR will electronically
open bids, using QuestCDN’s secure bid opening function, and will publicly read and publish the
names of bidders, base bids, and other required bid items as applicable. Bid results will be
recorded, and a bid tabulation prepared. Budget assumes two (2) hours total over the bidding
period.
Subtask 1103 – Post-Bid Administrative Assistance
Review and evaluate bids for responsiveness and bid amount. HDR will also verify through
reasonable investigation the financial and performance history documentation submitted by the
apparent low bidder and provide a Recommendation to Award to the City and Issue Notice of
Award. Budget assumes twenty (20) hours total over the bidding period.
Task 1100 Deliverables
• Pre-Bid Conference Agenda and Minutes.
• Plan Holders List.
• Addenda, as needed.
• Recommendation to Award and Certified Bid Tab.
• Notice of Award.
Task 1200. Construction Services
Subtask 1201 – Contract Administration
The overall objective of Contract Administration services to be provided by HDR is to provide
technical consultation during construction.
Specific services to be performed by HDR under this task include the following:
1201.1 Contract Administration
• Contractor coordination and correspondence as required to facilitate the project, for the
contract duration listed in the Bid Documents.
• Review requests for payments submitted by the Contractor for compliance with the work
performed. This task assumes up to seven (7) requests for payment based on the contract
duration listed in the Bid Documents.
• Budget assumes fifty-six (56) hours total over the construction duration.
1201.2 Conformed Documents
• Develop Conformed Documents for the Contractor’s use. Budget assumes six (6) hours
for Conformed Document development.
Docusign Envelope ID: 0989F0C0-8726-8554-836C-91CEF05A53FC
3
1201.3 Pre-Construction Meeting
• Conduct one in-person (1) pre-construction meeting with the Owner, Contractor and other
interested parties in the Owner’s office or at the project site. Two (2) HDR staff will attend
the pre-construction meeting. Budget assumes one (1) pre-construction meeting, two (2)
hours total, for the pre-construction meeting.
1201.4 Progress Meetings
• Attend virtual bi-weekly progress meetings with the Contractor to discuss schedule,
progress, problems, and coordination of activities with construction of the pump station.
HDR will develop meeting minutes for monthly progress meetings. Two (2) HDR staff will
attend each monthly progress meeting. Budget assumes fourteen (14) progress meetings;
twenty-eight (28) hours total, over the construction duration.
1201.5 Shop Drawing Review
• Review shop drawings, equipment submittals, and construction drawings submitted by the
Contractor for compliance with the construction plans and specifications. Approximately
75 original technical submittals and 25 technical re-submittals are assumed for this effort.
This includes Schedule of Values, Progress Schedule, Submittal Schedule, technical shop
drawings, O&M manual submittals, performance test. Major substitution submittals,
instrumentation and control submittals, various equipment submittals based on previous
design discussions will be shared with the City for review and comment upon receipt from
the Contractor. Budget assumes 216 hours total over the construction duration.
1201.6 Requests for Information (RFIs) and Work Change Directives (WCD)
• Respond to Requests for Information (RFIs), inquiries, and suggestions submitted by the
Contractor. Coordinate and maintain log of Contractor submittals and RFIs. Approximately
10 RFIs are assumed for this effort.
• Resolve changed site conditions, design conflicts, and prepare supplemental drawings
and sketches to resolve conflicts.
• Prepare Work Change Directives (WCD) and Change Orders. Evaluate Contractor’s
proposals with independent estimates of cost and time impacts. Approximately 3 WCDs
are assumed for this effort.
• Budget assumes forty (40) hours total over the construction duration.
1201.7 Startup Coordination
• Conduct substantial completion inspection, prepare punch lists, and establish the
contractual warranty period for construction work. Conduct final inspection using
substantial completion punch lists. The final inspection shall take place after infrastructure
has been completely installed in accordance with approved plans and specifications.
Budget assumes twelve (12) hours total over the construction duration.
• Upon completion of the project, HDR will coordinate the preparation of final record
drawings based on construction records. HDR will furnish the Contractor with a half-size
copy of the project drawings for recording construction information. Progress payment
Docusign Envelope ID: 0989F0C0-8726-8554-836C-91CEF05A53FC
4
processing will be predicated upon the status of the Contractor’s record drawings. HDR
will submit the final approved record drawings. Records drawings will include one (1) full-
size set on paper, and an electronic version in .pdf format. These drawings will be based
on construction records from the Contractor and construction observations. Budget
assumes sixty (60) hours total over the construction duration.
Subtask 1202 – Construction Observation
The objective of Construction Observation services is to provide on-site observation during active
construction and to monitor the performance of the Contractor and assist in responding to events
that occur during construction or during critical construction activities.
1202.1 Construction Observation
• It is assumed for budgeting purposes that on-site observation will consist of a seven-month
construction duration for four (4) hours per day for onsite field observation for a total of
150 workdays (600 hours) and four (4)-hour-site visits by the Project Manager to observe
ongoing work by the Contractor (timing of Project Manager site visits to align with critical
construction activity) for a total of eight (8) workdays (32 hours). Eight (8)-hour-site visits
(including travel time) for specific disciplines (e.g., structural, electrical, and I&C
observation/coordination) from HDR’s Missoula Office for onsite observation and/or
coordination for a total of four (4) workdays (32 hours). Budget assumes 680 hours total
over the construction duration.
1202.2 Special Inspections
• Perform special inspections in accordance with the International Building Code (IBC). A
Schedule of Special Inspections will be completed and submitted to the City of Bozeman
Building Official, including the Statement of Special Inspections. Eight (8)-hour-site visits
(including travel time) for structural special inspections from HDR’s Missoula Office for a
total of two (2) workdays (16 hours). Budget assumes sixteen (16) hours total over the
construction duration.
HDR’s observation and monitoring portions of the work performed under construction contracts
shall not relieve the Contractor from its responsibility for performing work in accordance with
applicable contract documents. HDR shall not control, have charge of, and shall not be
responsible for, construction means, methods, techniques, sequences, procedures of
construction, health or safety programs or precautions connected with the work and shall not
manage, supervise, control or have charge of construction. HDR shall not be responsible for the
acts or omissions of the Contractor or other parties on the project.
Exclusions
• Construction materials testing and compaction testing will be performed by the City’s
testing firm (Morrison-Maierle, Inc.).
Docusign Envelope ID: 0989F0C0-8726-8554-836C-91CEF05A53FC
5
Subtask 1203 – SCADA Programming and Integration
The overall objective of SCADA Programming and Integration is to include application
programming (PLC, OIT, and HMI) to incorporate and integrate the capability and functionality
defined in the project documents, integrate new infrastructure into the City’s existing system
(Ignition), and to work with the City’s Information Technology (IT) Department for network support.
Subtask 1203 will include the following:
• Review sample code provided by the City to develop programming consistency with
programming that is currently in use at other City lift stations, and in accordance with
applicable City standards. Provide programming in accordance with the developed IO lists
and project documentation, incorporating the capability and functionality as defined in the
Contract Documents.
• Prepare functional descriptions to facilitate development and programming associated
with the System Integrator-provided control panel utilizing the City’s SCADA standards.
• Integrate the Package Lift Station controller, provided by Others, into the Valley Center
Lift Station PLC. HDR assumes communication with the Package Lift Station controller
will be via EtherNet/IP and that the Contractor’s submittal will include documentation of
the required data registers necessary to monitor and control the lift station.
• Program and configure the Valley Center Lift Station PLC program, incorporating the City’s
standard User Defined Data Types (UDT) in the PLC.
• Develop an OIT application using ISA standards for high-performance graphics, unless
otherwise directed by the City. This application will include no more than ten (10) screens
and will be configured for monitoring only. OIT screens shall include Alarms, Overview,
Pump Status, PLC Overview, and Maintenance.
• HDR understands that the City utilizes a Master PLC (City Shops) that polls remote lift
stations into a common point that is then referenced by the City’s SCADA system. HDR
will make the necessary modifications to the Master PLC logic to include the Valley Center
Lift Station into the polling routine. HDR assumes means of communication are defect free
between the Master PLC and the Valley Center Lift station and that the connection
between those two points will be made by Others.
• Provide support during installation and equipment start-up.
• Coordinate with electrical and instrumentation of Contractors/Subcontractors and
equipment suppliers regarding equipment calibration and equipment configuration
necessary for PLC programing.
• Coordinate instrumentation and control (I&C) and programming with the City’s SCADA
Manager.
• Budget assumes 156 hours total (for programming and SCADA integration) and 16 hours
total (for PM and I&C Engineer) over the construction duration.
Docusign Envelope ID: 0989F0C0-8726-8554-836C-91CEF05A53FC
6
Exclusions
• VFD commissioning and configuration of parameters to be performed by the VFD supplier.
• Ignition programming will be performed by the City (e.g., alarm notification programming
and software programming).
• Automated reporting.
• Networking, network appliance configuration, radio installation, radio configuration and
switch configuration.
Subtask 1204 – Project Closeout / Certification / Warranty
Inspection
• Develop a list of observed construction deficiencies for the construction of the
infrastructure. Provide observation of the correction of these deficiencies, review final
payment applications, and assist in making recommendations for final payment. Submit
contract closeout paperwork and provide certification of project completion as required by
Montana Department of Environmental Quality (DEQ). Attend a one (1) and two (2) year
warranty inspection walkthrough. Budget assumes sixteen (16) hours total for Project
Closeout / Certification / Warranty Inspection.
Task 1200 Deliverables
• Pre-construction Conference Agenda and Meeting Minutes.
• Copies of Reviewed Shop Drawings.
• Progress Payment Recommendations.
• Copies of RFIs, WCDs, Change Proposals, etc.
• Bi-Weekly Construction Meeting Agenda and Meeting Minutes.
• Daily Field Reports and Photos.
Docusign Envelope ID: 0989F0C0-8726-8554-836C-91CEF05A53FC
EXHIBIT D
Client:
Project:
Project
Manager
Junior Engineer
(EIT)
Electrical / I&C
Engineer
Structural
Engineer
SCADA /
Programming CADD/BIM Accountant Project Admin Total Hours Labor TOTAL DIRECT
EXPENSES Total Fee
Task
1000
1000 24 16 4 44
24 16 4 44 9,056.00
1100
1101 32 24 4 12 72 14,660
1102 2 2 534
1103 12 8 20 4,196
46 32 4 12 94 19,390.00
1200
1201.1 32 24 56 11,520
1201.2 2 4 6 1,310
1201.3 2 2 4 782
1201.4 28 28 56 10,948
1201.5 48 96 40 32 216 42,296
1201.6 6 30 2 2 40 6,282
1201.7 8 4 60 72 14,272
1202.1 32 600 24 24 680 94,464
1202.2 16 16 3,248
1203 8 8 156 172 36,176
1204 12 4 16 3,700
178 788 74 74 156 64 1,334 224,998.00
248 820 74 78 156 76 16 4 1472
253,444$ 8,757$ 262,201$ Total Fee
Construction Services
Contract Administration
Construction Observation
SCADA Programming and Integration
Project Closeout / Certification / Warranty Inspection
Subtotal Construction Services
Conformed Documents
Pre-Construction Meeting
Progress Meetings
Shop Drawing Review
Requests for Information (RFIs) and Work Change Directives (WCD)
Startup Coordintation
Special Inspections
July 17, 2026
Project Management
Project Management
Task Description
Total Hours
City of Bozeman
Valley Center Lift Station and Force Main Fee Estimate
Bidding Administrative Assistance
Bid Opening Assistance
Post-Bid Administrative Assistance
Subtotal Project Management
Bid Phase Services
Subtotal Bid Phase Services
Docusign Envelope ID: 0989F0C0-8726-8554-836C-91CEF05A53FC