HomeMy WebLinkAbout26 - Amendments Amendment Number Unknown - Jackson Contracting Group - BOGERT POOL RENOVATION PROJECTGMP AMENDMENT NO. 1
TO AGREEMENT BETWEEN OWNER AND CONSTRUCTION MANAGER
Pursuant to Subparagraphs 3.7.1-3.7.4 and 4.1 of the Preconstruction Services Conditions Agreement
between Owner and Construction Manager this amendment dated the 3rd day of June 2025, between
City of Bozeman (“Owner”) and Jackson Contracting Group (“Contractor”) for the Bogert Pool
Renovation Project, this amendment dated the 2nd of September 2026, hereby establishes a
Guaranteed Maximum Price and Contract Time for the portion of the Project as set forth below:
GUARANTEED MAXIMUM PRICE FOR BOGERT POOL RENOVATION PROJECT
The Construction Manager’s Guaranteed Maximum Price (GMP) for the Work, including the Cost of the
Work and the Construction Manager’s Fee is as follows:
Pool Area Construction $2,029,382.00
Winter Conditions (Allowance) $25,000.00
Testing & Inspections (Allowance) $6,000.00
Dewatering (Allowance) $10,000.00
Construction Subtotal $2,070,382.00
General Conditions – Construction Manager $444,992.00
City of Bozeman Plan Review / Permit Fees $23,820.00
Unforeseen Conditions / Construction Contingency $129,158.00
Payment & Performance Bond $26,445.00
General Liability Insurance $26,710.00
Procore Fee $5,153.00
CGRT (Contractor Gross Receipt Tax) $27,028.00
Construction Fee $220,297.00
Indirect Costs / Contingency Subtotal $2,973,985.00
Alternate 1 – In-fill Men’s Locker Room Opening $10,251.00
Alternate 4 – Add ADA Lift CFCI (Contractor Furnish / Contractor Install) $12,208.00
Alternate 8 – Waterproof Surge Pit $3,590.00
AMENDMENT # 1 GUARANTEED MAXIMUM PRICE $3,000,034.00
CONTRACT TIME
The date for the Certificate of Occupancy for the Work outlined above is June 18th, 2027
EXHIBITS
Exhibit A – GMP Summary
Exhibit B – Executive Summary
Exhibit C – Schedule
Docusign Envelope ID: 2C879851-D09E-842B-81DA-76F89BC36B86
OWNER: CONTRACTOR:
City of Bozeman Jackson Contracting Group
121 N. Rouse Ave. 146 Laura Louise Lane
Bozeman, MT 59715 Bozeman, MT 59718
By:__________________________ By: __________________________
Chuck Winn, City Manager Rylan Oakland, Director of Operations
Docusign Envelope ID: 2C879851-D09E-842B-81DA-76F89BC36B86
Final GMP Summary - EXHIBIT ABogert Pool Renovations
Updated 9/1/2026
PRECONSTRUCTION GMP AMENDMENT
Base Contract
Assessment Estimate -
COB Budget Narrative 95% CD Trends Accepted Final Pre-Con Budget Final SOV Values for GMP
ALT 1 - ADDIn-fill Mens Locker
Room Opening
ALT 2 - ADD
Double Rock Slide
ALT 3 - ADD
ADA Lift OFCI
ALT 4 - ADD
ADA Lift CFCI
ALT 5 - DEDUCT
Deduct ADA Ramps
ALT 6 - ADDCurb in lieu of Wheel
Stops
ALT 7 - DEDUCTAluminum Railings in
lieu of Steel
ALT 8 - ADD
Waterproof Surge Pit
ALT 9 - ADDIncrease Pool Deck
Repairs
ALT 10 - ADDPool Deck Trench
Drain Total w/ ALTs 1, 4 & 8 Notes for GMP
Preconstruction Services
Original Services 61,280.00$ -$ 61,280$ 61,280$ Original Preconstruction Agreement - amendment amount does not include
General Requirements .
General Requirements 146,802$ -$ 146,802$ 146,802$
Pool Structure - Temporary Cover for Winter Work 128,115$ 128,115$ 144,338$
Bid Items by Division
Select Demolition & Earthwork 166,623$ -$ 166,623$ 142,729$ 1,440$ 1,440$ Suggestion to take ALT#1 - Bid 2.0 Jackson Contractor Group
Structural Concrete & Flatwork 209,249$ 9,683$ 218,932$ 213,628$ Bid 3.0/3.1 Jackson Contractor GroupConcrete Pool Deck Repair & Restoration 50,601$ -$ 50,601$ 64,456$ (2,200)$ 137,742$ 4,540$ -$ Base Build Approach at Pool Deck Suggest ALT#10 via Change Order in Early Spring
Masonry Complete 93,280$ 2,871$ 96,151$ 101,770$ 1,700$ 1,700$ Suggestion to take ALT#1 Bid 4.0 Tesoro Masonry
Architectural Metals, Railings & Gates 55,600$ (6,641)$ 48,959$ 63,626$ (1,250)$ 27,582$ Bid 5.0 YMS FabricationGutters & Downspouts 10,789$ -$ 10,789$ 5,110$ No new gutters, simply downspouts per drawings, can address further w/ contingency
Doors/Hardware & Specialties 10,201$ -$ 10,201$ 23,180$ 4,380$ 5,138$ 10,280$ 4,380$ Take ALT#6, suggest ALT#10 - Trench Drain work via Change Order in early Spring
Painting & Patching 8,000$ 2,000$ 10,000$ 4,225$ 1,675$ 1,675$ No new gutters, simply downspouts per drawings, can address further w/ contingency
Pool Repair, Accessories & Vertical Filter Replacement 861,470$ 83,100$ 944,570$ 877,840$ 53,667$ 956$ 10,950$ 3,220$ 14,170$ Above Bid 7.0 The Gutter Guys - Bid 8.0 Jackson Contractor Group - Bid 13.0 Select DBC
Plumbing Complete 36,500$ -$ 36,500$ 18,750$ (705)$ Bid 22.0 Abbott Plumbing
Electrical, Grounding/Bonding & Site Lighting Complete 54,235$ 19,646$ 73,881$ 31,800$ Bid 26.0 SES Electrical
Curb, Asphalt Patching/Paving & Striping -$ 9,458$ 9,458$ 12,540$ Bid 32.0 High Country Paving
Landscaping Repair & Aluminum Fence 87,500$ 12,154$ 99,654$ 117,309$ Bid 33.0 Rivers Landscaping need relocation of irrigation box at dumpster
Allowances
Winter Conditions 15,000$ -$ 15,000$ 25,000$ Increase at Winter of 2027 is expected to be wet & long
Third Party Testing & Inspections 12,000$ -$ 12,000$ 6,000$ Reduce to more appropriate scope valueDewatering10,000$ (10,000)$ -$ 10,000$
Sewer Drain Failsafe in Mechanical Room 7,500$ (7,500)$ -$ -$
Main Drain Corrections at Deep End 25,000$ (25,000)$ -$ -$
Material Escalation & Tariffs 40,449$ (40,449)$ -$ -$
SUBTOTAL :61,280.00$ 2,028,914$ 49,322$ 2,078,236$ 2,070,382$ 9,195$ 53,667$ 956$ 10,950$ (4,155)$ 5,138$ 27,582$ 3,220$ 137,742$ 14,819$ 23,365$
In-Directs/Contingengy
General Conditions - Construction Manager 444,992$ -$ 444,992$ 444,992$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ CPM Schedule remains unchanged from original Assessment Budget
COB Plan Review/Permit Fees - By Owner 27,124$ (15,614)$ 11,510$ 23,820$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ COB will reimburse CT Payments
Design Contingency 75,238$ (75,238)$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ Reducted to zero as design is complete
Unforeseen Conditions & Construction Contingency - 6%129,158$ -$ 129,158$ 129,158$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$
Payment & Performance Bond 1%27,395$ -$ 27,395$ 26,445$ 92$ 537$ 10$ 110$ (42)$ 51$ 276$ 32$ 1,377$ 148$ 234$
General Liability Insurance 1%23,518$ -$ 23,518$ 26,710$ 93$ 542$ 10$ 111$ (42)$ 52$ 279$ 33$ 1,391$ 150$ 236$
Procore - .191%5,330$ -$ 5,330$ 5,153$ 18$ 105$ 2$ 21$ (8)$ 10$ 54$ 6$ 268$ 29$ 46$
GRT 1%27,957$ -$ 27,957$ 27,028$ 94$ 549$ 10$ 112$ (42)$ 53$ 282$ 33$ 1,408$ 151$ 239$
Contractors Fee - 8% based upon Fee Structure from Pre-con 225,890$ -$ 225,890$ 220,297$ 759$ 4,432$ 79$ 904$ (343)$ 424$ 2,278$ 266$ 11,375$ 1,224$ 1,930$
TOTAL:61,280.00$ 3,015,516$ (41,530)$ 2,973,986$ 2,973,986$ 10,251$ 59,831$ 1,066$ 12,208$ (4,632)$ 5,728$ 30,750$ 3,590$ 153,562$ 16,521$ 26,048$
DESIGN DEVELOPMENT BUDGETING ALTERNATES
EXHIBIT A
Docusign Envelope ID: 2C879851-D09E-842B-81DA-76F89BC36B86
1
Bozeman Bogert Pool – GMP Amendment -
Exhibit B
Date: September 1, 2026
Executive Summary
This document summarizes the Bozeman Bogert Pool project. The project is located at 325 South Church Avenue,
Bozeman, MT 59715.
The following referenced documents were used for pricing and planning of this summary, budget, and schedule.
1. Bogert Pool Assessment Report (August 2025), as prepared by Cushing Terrell.
2. Bogert Pool Renovation Drawings as prepared by Paul McGiel (March1974)
3. Equipotential Bonding Survey and Report as prepared by SES Electrical Systems, LLC. (June 2025)
4. Ground Penetrating Radar Survey as prepared by Bigman Geophysical, LLC & Geosearch, Inc. (June 2025)
5. Cushing Terrell CDs and Aquatic Design Group dated 7/31/2026
6. Bidding Addenda’s #1 (dated 8/6/2026), #2 (Dated 8/11/2026), and #3 (Dated 8/19/2026)
Definitions
Allowance: An allowance is an amount specified in an agreement that is allocated to a specific portion of the
work whose details are not defined when the agreement is signed. Whenever costs incurred for an item
exceed or fall short of the allowance created for that item, the contract sum will be adjusted accordingly.
The adjustment to the contract sum will reflect the difference between the cost incurred and the allowance.
Savings realized on an allowance will be returned to the owner as a reduction in the contract sum.
Contingency: An allowance in an amount or percentage of the contract held for unpredictable changes in
the project. A contingency is a helpful risk management tool that financially prepares owners for addressing
risk within the project. Contingency provides a vehicle to pay for unknown conditions such as price
escalation of a product; design changes in scope or due to errors and omissions; or necessary construction
changes that are realized on-site during construction.
Notable Risks and Challenges
Winter weather conditions. Snow removal and ice management will be required throughout construction,
adding cost and coordination.
Working in and around the occupied Bogert park spaces. Jackson Contractor Group and our subcontractors
will endeavor to avoid disturbing the community to the greatest extent possible.
This GMP assumes the work will be conducted start to finish in a single phase. No breaks for seasonal
changes or for the opening of the Bogert Pool are included in this assessment.
Unforeseen conditions
o Multiple layers of pool shell build up
o Conditional of existing pool plumbing
Docusign Envelope ID: 2C879851-D09E-842B-81DA-76F89BC36B86
2
o Due to the results of the GPR survey of the pool identifying water below the pool shell, there is
uncertainty around with the integrity of the ground under the current pool structure that is to
remain. There has been a leak, presumably coming from the main drain in the pool, for multiple
years and this water has caused an unknown amount of soil settling and pool shell undermining
o Existing landscaping does not have any current as-built drawings, so more unforeseen irrigation
modifications may be required.
o Potential cost escalation related to remediation of existing pool shell conditions, including exposed
rebar, corrosion, and structural cracking.
Potential safety and compliance risk is associated with verifying and achieving proper bonding and
grounding for all new pool fixtures and existing pool equipment.
Notable GMP Assumptions/Clarifications/Exclusions
DIVISION 1 | GENERAL CONDITIONS & GENERAL REQUIREMENTS
1. This GMP proposal includes special inspection monies as required by the State of Montana for concrete
construction.
2. This GMP proposal includes the extension/amendment of the Pre-Construction agreement with the City
of Bozeman and therefore does not alter the scope of work items already in that agreement.
3. State of Montana & City of Bozeman permitting costs are included.
4. Quality Control/Material Testing has been included as an allowance for the purposes of this GMP and
would be applicable to concrete and soils materials testing not performed by State or Local Jurisdictions.
5. GRT has been included
6. 2026 Montana Department of Labor Prevailing Wages have been included.
DIVISION 2 | EXISTING CONDITIONS
1. Demo existing drinking fountains (2).
2. Demo existing North side stairs, ramp, and landing into the building. Includes footings, foundations, and
flatwork. Footing and foundation wall of concrete landing West of stairs to remain in place.
3. Demo of asphalt paving adjacent to the concrete ramps, stairs, and landings on the North and West sides
of the building
4. Demo of West elevation handicap accessible ramps coming from pool exit.
5. Demo of all metal handrails and guardrails on the West and North sides of the building. Handrails will be
carefully cut off existing structural steel columns. Refinishing columns in divisions 5 and 9.
6. Demo of portion of East mechanical room landing and ramp.
7. Demo of existing CMU and chainlink perimeter fence around the pool deck area.
8. Demo of existing building and parking lot ADA signage.
9. Demo of select CMU brick at drinking fountains in order to cap/reroute plumbing piping.
10. Demo of concrete pool deck at locker room entrances. Approximate areas of demo are 8’x4’.
11. At existing pool deck core and remove any unnecessary metal objects coming through the concrete. Grind
down all cracks and prepare for patching back.
12. Demo of select concrete locations under CMU walls at pool deck.
13. No abatement or hazardous materials survey identified in scope of work per hazardous materials report
Docusign Envelope ID: 2C879851-D09E-842B-81DA-76F89BC36B86
3
DIVISION 3 | CONCRETE
1. Installation of new concrete footings, foundation walls, landings, and stairs at North side of building.
2. Installation of new ADA ramps on west elevation coming from North side of building and pool deck
3. Installation of new ramp going to mechanical entrance on East side of building.
4. Installation of new thickened edge sidewalk and slab on grade on North and West sides of building.
5. Installation of new slab on grade trash pad and West entrance/exit from pool to parking lot on Southwest
corner of pool
6. Installation of new structural thickened edge slab on grade under CMU wall at pool deck.
7. Pool deck repairs at cores, cracks, and removed metal objects. Patch and repair locations identified on
AD101 and AD102.
8. Replace existing control joint material throughout with new expansion joint material and sealant.
9. Construction of two 8’x4' concrete landings and ramps will be installed at each locker room to pool door
that ramps to the pool deck.
10. Anticipated spoils from new footing excavation are anticipated. COB to advise if material can remain
onsite or if it must be hauled off.
11. Furnish and install of all necessary reinforcement has been included.
DIVISION 4 | MASONRY
1. This includes 20"W x 8"D split-faced masonry columns constructed of 8" CMU, fully grouted solid with
vertical and horizontal reinforcing rebar. Columns to be Block type 1, which will have split-face CMU on
exterior faces only and smooth on other three sides. CMU Block type 2, which is smooth faced on all 4
sides, will be utilized at CMU fencing between columns. Each column and CMU pony wall will be finished
with a precast concrete cap, sloped with a drip edge.
2. Masonry patching at the demolished drinking fountains is included. CMU blocks will be provided and
installed. Painting to match existing interior and exterior of building to best of abilities.
3. Caulking and control joints as indicated.
4. No masonry sealer has not been included.
DIVISION 5 | METALS
1. Furnish and installation of new guardrails and handrails on West and North sides of the building. These
new guardrails and handrails will be made of steel including powder coated finish as requested. Guardrails
will be constructed of 2” square metal tubes and be fascia mounted to the concrete at the new landings
and ramps. Handrails will be 1 ½” diameter pipe and will be wall mounted on building side at ramps and
core and grouted where they extend past guardrails and at stairs.
2. Furnish and installation of two new ADA ramp handrails at pool deck, which will be aluminum. These
handrails will be core and grouted into the pool deck.
3. Supply and installation of cantilevered steel bench at ground elevation on the North side of the building.
DIVISION 6 | ROUGH CARPENTRY
1. Construction of a temporary pool cover consisting of wood trusses, sheathing and weather proofing has
been included to allow for the pool construction during the non-operational periods as requested by the
Owner. This temporary facility will be insulated and have propane heating and OSHA required lighting
and ventilation to allow for the pool shell rehabilitation during the winter months. As such winter
Docusign Envelope ID: 2C879851-D09E-842B-81DA-76F89BC36B86
4
conditions have been included, with respect to this is a specific scope of work. Please note winter
conditions for other exterior work (i.e concrete, masonry, etc).
DIVISION 7 | THERMAL AND MOISTURE PROTECTION
1. Exterior grade sealants have been included on the pool deck elevations and new concrete construction
interfacing with the face of the existing building. Backer rod and an exterior grade sealant will be installed
to prevent further water infiltration surface water runoff due to pool operations or typical weather cycles.
2. Six (6) new downspouts coming off the existing building gutters is included. Underground PVC for water
drainage is included in division 22. Metal trench drains will be installed at sidewalk locations for proper
drainage and to avoid slip hazards (provided by div 22 and installed by div 3).
DIVISION 8 | OPENINGS
1. Gate hardware for access control has been included at (2) new aluminum gate locations. These are
assumed to be keyed hardware and not electronic. Gate hardware package includes panic bars, security
plates, and weld on closing hinges for security purposes.
DIVISION 9 | FINISHES
1. Painting at repaired CMU block at the drinking fountain areas or other existing wall damage related to
renovation activities.
2. Repair, patch and painting will occur at exposed existing building foundation that is exposed after
existing ADA ramp is removed.
3. Painting at structural steel columns at North entry will be performed after existing handrails are
removed from columns. Prep of column for paint is located in division 5.
DIVISION 10 | SPECIALTIES
1. One surface-mounted fire extinguisher cabinet in each locker room area (Two total).
DIVISION 11 | EQUIPMENT (POOL)
1. Remove the existing Nemato vertical pool filter and replace with a Neptune Benson “Defender”
regenerative filter with automatic filter control as specified.
2. New Neptune Benson filter anchorage testing was not included in pricing.
DIVISION 12 | FURNISHINGS
1. Not Included – Pool construction includes pool accessories/furnishes currently budgeted.
DIVISION 13 | SPECIAL CONSTRUCTION (POOL)
1. Budget: 120 LF of crack isolation repair in the pool shell structure.
2. Budget: 388 LF of rebar repair in the pool shell structure.
3. Budget: 24 EA replace pool floor inlets.
4. Replace pool perimeter signage and floatation hangers.
Docusign Envelope ID: 2C879851-D09E-842B-81DA-76F89BC36B86
5
5. Includes removal of existing main drain and install new VGC-VGBA compliant main drain grates
and frames per drawings in swimming pool. Wading pool main drains to remain and be protected
in place.
6. Demo of existing pool finish down to suitable substrate. This includes removal of all existing paint,
plaster, and tile location in pool. Pool subcontractor has assumed 1 layer of plaster build up (or
tile) when pricing the prep to suitable substrate. Pool contractor has included removal of up to
½” of existing material build up at pool shell.
7. Remove the current precast gutter coping that is set in grout and install new Daldorado Silentflow
13” parallel grating is included.
8. Finish entire pool surface with two coats of white epoxy paint. This includes curbs, lane lines, and
wall targets, which will be applied per manufacturer recommendations. Resurface pool with
painted finish. Basis of Design: RAMUC Specialized Coating high built epoxy two coat process.
Racing lines and targets will be installed within 48 hours of pool coating installation.
9. Painting of new “No Diving” signage and depth markers at pool shell surface is included.
10. Chipping and removal of damaged concrete in designated areas to expose rebar. Compromised
rebar to be repair or replaced depending on condition.
11. Removal and replacement of damaged curb heads as identified in the project documents is
included in the GMP.
12. Removal of existing anchors and all other accessories is included. Pool shell will be chipped back
to allow for new anchoring and bonding (by electrician) before replacing.
13. Removal of existing floor inlets and equalizer fittings is included. Pool shell will be chipped back
to allow for new piping connections, which will allow for inspection to confirm sound and
watertight connections.
14. Pool contractor to remove and replace expansion joint with mastic complete.
15. Furnish and installation of gutter waterproofing.
16. Removal of existing and Installation of new handrails and ladders is included. Includes new
anchorage and escutcheons.
17. Remove and reinstallation of Aqua Zip and Aqua Climb is included
18. Removal of Delaware Duck slide is included.
19. Pressure testing of all existing pool piping along with new connections/equipment is included.
20. Start up, testing, balancing, and owner trainings by pool contractor are included.
21. Pool subcontractor has accounted for the cost of the chemicals for the pools for the 14 days of
startup and operation.
DIVISION 14 | CONVEYING EQUIPMENT
1. Not Included
DIVISION 21 | FIRE SUPPRESSION
1. Not Included
DIVISION 22/23 | PLUMBING/MECHANICAL
1. Removal of (2) existing drinking fountains has been included. Includes caping plumbing lines in CMU wall.
2. Installation of (1) new Elkay drinking fountain has been included. Drinking fountain has mechanical
operation, so no electrical is necessary for installation. New drink fountain is in a new location, so
Docusign Envelope ID: 2C879851-D09E-842B-81DA-76F89BC36B86
6
modifying the water supply line and drain line are required. Reworked water and drain lines will be located
in the existing CMU wall.
3. New underground PVC for controlled drainage of downspouts is included.
4. Supply of metal trench drains for downspouts will be provided in this scope of work and installed by
concrete subcontractor
DIVISION 26/27/28 | ELECTRICAL & COMMUNICATIONS
1. Demolition of the (4) existing light poles and the associated bases is included.
2. Demolition of the existing pool deck outlets and associated exterior mounted branch circuitry is included.
3. GMP includes assumed work scope around addition of (4) exterior light poles with simple controls back
to existing panels. New light pole bases are included at all new exterior light poles. New raceways to be
installed from new light pole locations back to the building. No new conduit routing for lighting circuitry
inside building is included.
4. GMP includes equipotential grounding/bonding of all pool lights, pool equipment, and other pool
accessories as required by Code.
5. New pool outlets will be furnished in CMU columns as designed.
6. The following is included in the GMP: All line voltage electrical demolition and new work associated with
the pool mechanical room and vertical filter, including shutdown/disconnect of existing filter wiring;
removal of abandoned conduit, pull boxes, switches and electrical. Work also includes new feeder,
disconnect, and conduit work.
7. A new SP or equivalent pool panel and board enclosure (NEMA 4X) is included in GMP.
8. Additional grounding and bonding of pool restoration work at gutter curb heads is included in GMP.
DIVISION 31/32/33 | EARTHWORK/EXTERIOR IMPROVEMENTS/UTILITIES
1. Subgrade prep has been included at any new structural concrete or horizontal concrete flatwork.
2. Backfill at all new concrete footings, foundations, and flatwork has been included
3. No utilities have been included.
4. Horizontal drainage will match existing elevations set by adjacent structures. If possible, fall away from
all structures will be included.
5. Furnish and install new aluminum fence panels around the perimeter of the pool deck. This package is
based on the Aluminum Fences Direct commercial-grade Appalachian fencing system, utilizing 6' x 8'
panels (6' tall by 8' wide) with 3-rail construction and 3/4" pickets, designed for durability and security
(https://aluminumfencesdirect.net/options/commercial/). The scope includes galvanized steel line,
corner, and gate posts, complete with caps. The system includes (2) 6' x 4' single-swing pedestrian gates,
each equipped with self-closing hinges and gravity latches for safety and code compliance. The system
also includes (1) double-swing maintenance gate with drop bar and lockable latch for safety and security.
6. Relocation of irrigation valve box at new trash pad location has been included.
Exclusions
1. See above Division summaries for qualifications and exclusions if applicable.
2. Unforeseen Conditions – an allowance has instead been included for Construction Contingency
3. Abatement or Hazardous Materials Removal
4. Snow removal prior to construction commencement.
5. Ground water and mitigation if encountered - an allowance has instead been included
6. Tile and plaster work in the pool, given the selected finish is epoxy paint.
7. Asphalt patching, paving and striping outside of what is shown on the contract documents.
Docusign Envelope ID: 2C879851-D09E-842B-81DA-76F89BC36B86
7
8. Building permit fee to be by owner
9. All project electrical, utilities, water, and associated utility costs to be by owner.
10. All winterization and locating of existing irrigation sprinkler heads to be by owner.
11. No snow melt or heat trace has been included in this GMP.
12. No low voltage work has been included in this GMP.
13. Pool chemicals after the first 14 days of startup and operation have been completed. Owner to provide
chemicals after the first 14 days expire.
14. Piping repairs identified during existing pool piping pressure test.
ALTERNATES
The below summary of alternates includes all mark-ups and fee for Owner inclusion into the GMP
Agreement if desired. Please note the valuations indicated below can be incorporated into the GMP as
an additional amendment up to October 25th, 2025. Any elected alternates taken thereafter will require
reassessment of cost and schedule implications, including additional General Conditions/Requirements.
ADD/ALT # DESCRIPTION GMP ADD OR (DEDUCT)
1 Infill Men’s Locker Room Door – Demo HM Door infill CMU $10,221
2 Baby Slide – Install new ADA Double Rock Slide $59,831
3 ADA Lift 1 – Owner Furnished, Contractor Installed $1,066
4 ADA Lift 2 – Contractor Furnished, Contractor Installed $12,208
5 No ADA Ramp from Locker Room – Leave concrete as is, but
keep plumbing work and new drinking fountain
($4,632)
6 Continuous Curb in Lieu of Wheel Stops – Parking along west
side of Pool
$5,728
7 (Deduct) Aluminum Guardrails and Handrails in Lieu of Steel $30,750
8 Waterproofing at Surge Chamber $3,590
9 Pool Deck Repair – Repairs per Addendum #2 sheet AD103 $153,562
10 Pool Deck Trench Drain – Add Two trench drains per P100 $16,521
ALLOWANCES
DIVISION/ITEM DESCRIPTION VALUE
Winter Conditions Site maintenance during construction See exclusion #4 $25,000
3rd Party Special
Inspections & Testing
Concrete and subgrade testing – CT may contract $6,000
Dewatering High ground water may be present during Fall start $10,000
TOTAL
Docusign Envelope ID: 2C879851-D09E-842B-81DA-76F89BC36B86
8
UNIT PRICING
Pricing is cost of work only. No markups included in the following pricing
DIVISION/ITEM DESCRIPTION PRICING
3.1 - Concrete Epoxy Crack Repair at Pool Deck. Demo Plan AD101 and 102 $72/LF
3.1 - Concrete Control Joint R&R at Pool Deck. Demo Plan AD101 and 102 $85/SF
3.1 - Concrete Existing Anchor R&R at Pool Deck. Demo Plan AD101 and 102 $188/SF
13 - Pool Crack Repair in Pool Shell. Note 17 / DP-1 $50/LF
13 - Pool Pool Shotcrete & Exposed Rebar in Pool Shell. Note 9 / DP-1 $90/SF
13 - Pool Pool Reinforcement Rust Repair. Note 17 / DP-1 $56/SF
Docusign Envelope ID: 2C879851-D09E-842B-81DA-76F89BC36B86
8/6/2026
Bogert Pool Renovation
Hunter Clark
Line Name Duration Start Finish
2026 2027
August September October November December January February March April May June JulyJuly A
6 13 20 27 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11 18 25 1 8 15 22 1 8 15 22 29 5 12 19 26 3 10 17 24 31 7 14 21 28 5 12 19 26 2
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
BOGERT POOL RENO
BOGERT POOL RENO
BOGERT POOL RENO
MILESTONES
GMP Amendment
Notice to Proceed
GMP For Pool Work Established
Final Overall GMP Established
GMP For Pool Work Accepted
Substantial Completion
Final Completion
PARK EVENTS
Pool Closes for Public Use
Irrigatrion Blowout
Pool Opens For Public Use
PRECONSTRUCTION
CITY OF BOZEMAN
DESIGN AND ENGINEERING
PERMITTING
Permitting - City of Bozeman
Demo Permit
MEP Permit
Traffic Permit
SUBMITTALS / PROCUREMENT
Hydrostatic Relief Valve and MainDrain VGB
Gutter Grate
Crack Repair Materials
Epoxy Paint Finish
Steel Fencing
LED Pole Lights
Drinking Fountains
Pool Fillter
Pool Temp Structure
North Side Handrails Shop
Drawings
SUBCONTRACTOR BIDDING
Pre-Solicitation Pool Contractor
Invitation to Bid Published
Bidding
Pool Contractor Bid
Reconciliation
Bids Due
Bid Review
385d
552ed
9eh
385d
385d
210d
5d
253d
164d
108d
29d
29d
3d
3d
3d
89d
28d
30d
21d
21d
56d
63d
35d
84d
20d
30d
21d
10d
1d
13d
5d
1d
3d
12/18/2025
12/18/2025 *
12/18/2025
12/18/2025
12/18/2025
9/4/2026 *
9/4/2026
9/4/2026
9/8/2026
6/18/2027
6/23/2027
8/21/2026
8/21/2026 *
9/28/2026 *
6/21/2027 *
1/19/2026
1/19/2026
3/2/2026
8/3/2026
8/3/2026 *
9/4/2026
9/4/2026
9/4/2026
9/9/2026
9/9/2026
9/9/2026
9/9/2026
9/9/2026
9/9/2026
9/9/2026
9/9/2026
9/9/2026
9/11/2026 *
12/3/2026
8/3/2026
8/3/2026
8/6/2026 *
8/7/2026
8/17/2026
8/26/2026
8/27/2026
6/23/2027
6/23/2027
6/23/2027
6/23/2027
12/18/2025
9/4/2026
9/4/2026
9/4/2026
9/8/2026
6/18/2027
6/23/2027
6/21/2027
8/21/2026
10/2/2026
6/21/2027
1/15/2027
9/8/2026
7/31/2026
9/11/2026
9/11/2026
9/9/2026
9/9/2026
9/9/2026
1/15/2027
10/16/2026
10/20/2026
10/7/2026
10/7/2026
11/25/2026
12/8/2026
10/27/2026
1/8/2027
10/8/2026
1/15/2027
8/31/2026
8/14/2026
8/6/2026
8/25/2026
8/21/2026
8/26/2026
8/31/2026
BOGERT POOL RENO
Notice to Proceed
GMP For Pool Work Established
Final Overall GMP Established
GMP For Pool Work Accepted
Substantial Completion
Final Completion
Pool Closes for Public Use
Irrigatrion Blowout
Pool Opens For Public Use
+
+
Permitting - City of Bozeman
Demo Permit
MEP Permit
Traffic Permit
Hydrostatic Relief Valve and Main Drain VGB
Gutter Grate
Crack Repair Materials
Epoxy Paint Finish
Steel Fencing
LED Pole Lights
Drinking Fountains
Pool Fillter
Pool Temp Structure
North Side Handrails Shop Drawings
Pre-Solicitation Pool Contractor
Invitation to Bid Published
Bidding
Pool Contractor Bid Reconciliation
Bids Due
Bid Review
BOGERT POOL RENO
Notice to Proceed
GMP For Pool Work Established
Final Overall GMP Established
GMP For Pool Work Accepted
Substantial Completion
Final Completion
Pool Closes for Public Use
Irrigatrion Blowout
Pool Opens For Public Use
+
+
Permitting - City of Bozeman
Demo Permit
MEP Permit
Traffic Permit
Hydrostatic Relief Valve and Main Drain VGB
Gutter Grate
Crack Repair Materials
Epoxy Paint Finish
Steel Fencing
LED Pole Lights
Drinking Fountains
Pool Fillter
Pool Temp Structure
North Side Handrails Shop Drawings
Pre-Solicitation Pool Contractor
Invitation to Bid Published
Bidding
Pool Contractor Bid Reconciliation
Bids Due
Bid Review
Exhibit CDocusign Envelope ID: 2C879851-D09E-842B-81DA-76F89BC36B86
8/6/2026
Bogert Pool Renovation
Hunter Clark
Line Name Duration Start Finish
2026 2027
August September October November December January February March April May June JulyJuly A
6 13 20 27 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11 18 25 1 8 15 22 1 8 15 22 29 5 12 19 26 3 10 17 24 31 7 14 21 28 5 12 19 26 2
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
CONSTRUCTION
MOBILIZATION
Job Trailer Delivery and Set Up
Job Trailer Delivery
Temporary Power and Internet
SITE PREP
Install Site Fencing and SWPPP
Plug Drain to Keep Debris Out
Pool Consultant Demolition
Inspection
Protect Building and ExistingFinishes
Pool Accessory Demolition
BLDG DEMO PREP
Demo and safe off electrical
Demo and safe off plumbing
NORTH SIDE ENTRY RAMP
Seperate Current Ramp andLanding From Building
Asphalt Saw Cutting
Demo Current Ramp, Landing,
and Stairs
Excavation & Prep for New
Concrete
Prep Footings & Stem Walls
Footings & Stem Wall Inspection
Pour Footings & Stem Walls
Removing Shoring &
Backfill/compact
Prep Flat work
Flat work Inspection
Flat work Ramp
Strip Forms & ReclaimSurrounding Area
Install Handrails at Building
(North/West)
Paint Building Waiscott and Steel
POOL REPAIRS AND UPGRADES
Pool Main Drain Investigation
Main Drain VGB Corrections at
Swimming Pool
Install Temporary Structural
Enclosure
Structural Pool Repairs
(Cracks/Degraded Rebar)
Inlets and Equalizer Modifications
Install and Bond Rope Anchors
Pool Gutter Waterproofing and
Coping
Pool Shell Wash and Cure
Pool Epoxy Painting (2 Coats)
Remove and Replace Vertical
Pool Filter
Remove Temporary Structure
182d
2d
1d
1d
1d
7d
2d
1d
1d
2d
5d
9d
5d
4d
148d
3d
1d
7d
5d
5d
1d
1d
2d
15d
1d
1d
2d
10d
5d
158d
5d
15d
15d
20d
10d
5d
20d
15d
10d
10d
10d
9/14/2026
9/14/2026
9/14/2026 *
9/15/2026
9/15/2026
9/16/2026
9/16/2026
9/16/2026
9/17/2026
9/18/2026
9/18/2026
9/17/2026
9/17/2026
9/24/2026
9/30/2026
9/30/2026
10/5/2026
10/6/2026
10/15/2026
10/22/2026
10/29/2026
10/30/2026
11/2/2026
11/4/2026
11/25/2026
11/30/2026
12/1/2026
1/18/2027
4/23/2027
9/18/2026
9/18/2026
10/19/2026
11/9/2026
12/2/2026
12/16/2026
12/31/2026
1/8/2027
2/5/2027
2/26/2027
3/12/2027
3/12/2027
6/1/2027
9/15/2026
9/14/2026
9/15/2026
9/15/2026
9/24/2026
9/17/2026
9/16/2026
9/17/2026
9/21/2026
9/24/2026
9/29/2026
9/23/2026
9/29/2026
4/29/2027
10/2/2026
10/5/2026
10/14/2026
10/21/2026
10/28/2026
10/29/2026
10/30/2026
11/3/2026
11/24/2026
11/25/2026
11/30/2026
12/2/2026
1/29/2027
4/29/2027
5/3/2027
9/24/2026
11/6/2026
12/1/2026
12/30/2026
12/30/2026
1/7/2027
2/4/2027
2/25/2027
3/11/2027
3/25/2027
3/25/2027
Job Trailer Delivery and Set Up
Job Trailer Delivery
Temporary Power and Internet
Install Site Fencing and SWPPP
Plug Drain to Keep Debris Out
Pool Consultant Demolition Inspection
Protect Building and Existing Finishes
Pool Accessory Demolition
Demo and safe off electrical
Demo and safe off plumbing
Seperate Current Ramp and Landing From Building
Asphalt Saw Cutting
Demo Current Ramp, Landing, and Stairs
Excavation & Prep for New Concrete
Prep Footings & Stem Walls
Footings & Stem Wall Inspection
Pour Footings & Stem Walls
Removing Shoring & Backfill/compact
Prep Flat work
Flat work Inspection
Flat work Ramp
Strip Forms & Reclaim Surrounding Area
Install Handrails at Building (North/West)
Paint Building Waiscott and Steel
Pool Main Drain Investigation
Main Drain VGB Corrections at Swimming Pool
Install Temporary Structural Enclosure
Structural Pool Repairs (Cracks/Degraded Rebar)
Inlets and Equalizer Modifications
Install and Bond Rope Anchors
Pool Gutter Waterproofing and Coping
Pool Shell Wash and Cure
Pool Epoxy Painting (2 Coats)
Remove and Replace Vertical Pool Filter
Remove Temporary Structure
Job Trailer Delivery and Set Up
Job Trailer Delivery
Temporary Power and Internet
Install Site Fencing and SWPPP
Plug Drain to Keep Debris Out
Pool Consultant Demolition Inspection
Protect Building and Existing Finishes
Pool Accessory Demolition
Demo and safe off electrical
Demo and safe off plumbing
Seperate Current Ramp and Landing From Building
Asphalt Saw Cutting
Demo Current Ramp, Landing, and Stairs
Excavation & Prep for New Concrete
Prep Footings & Stem Walls
Footings & Stem Wall Inspection
Pour Footings & Stem Walls
Removing Shoring & Backfill/compact
Prep Flat work
Flat work Inspection
Flat work Ramp
Strip Forms & Reclaim Surrounding Area
Install Handrails at Building (North/West)
Paint Building Waiscott and Steel
Pool Main Drain Investigation
Main Drain VGB Corrections at Swimming Pool
Install Temporary Structural Enclosure
Structural Pool Repairs (Cracks/Degraded Rebar)
Inlets and Equalizer Modifications
Install and Bond Rope Anchors
Pool Gutter Waterproofing and Coping
Pool Shell Wash and Cure
Pool Epoxy Painting (2 Coats)
Remove and Replace Vertical Pool Filter
Remove Temporary Structure
Docusign Envelope ID: 2C879851-D09E-842B-81DA-76F89BC36B86
8/6/2026
Bogert Pool Renovation
Hunter Clark
Line Name Duration Start Finish
2026 2027
August September October November December January February March April May June JulyJuly A
6 13 20 27 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11 18 25 1 8 15 22 1 8 15 22 29 5 12 19 26 3 10 17 24 31 7 14 21 28 5 12 19 26 2
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
89
90
91
92
93
94
95
96
97
98
99
100
101
102
Modify Pool Mech Room Piping
Install all Pool Entry Handrails
ADA Lift Reinstall
Climbing Wall Reinstall
Zip Line Reinstall
Small Slide Reinstall at Deep End
POOL DECK AND FENCE
Demo existing CMU Fence
Infill/Modify CMU Walls on Westand South of Building
Prep for new Concrete Footings
Place new Concrete Footings
Install CMU Walls for Fence
Install Pool Fencing at CMU
Demo, patch, and repair pool
deck concrete
Install Pool Deck Handrails
(Bathrooms)
Install new Drinking Fountain
SITE FINISHES
Rough in New LED Pool Lights
Install LED Light Pole Bases
Install LED Light Poles
West Pool ConcreteApproach/Trash Pad Prep/Install
Asphalt Paving Prep and Install
Landscaping Repairs
Asphalt Striping
CLOSEOUT & COMMISSIONING
PUNCHLIST
Clean, Fill Pool, and PerformFinal Balancing
Perform Owner Training
Pool Consultant Punchlist
Pool Consultant PunchlistCorrections
Contractor Punchlist
Contractor Punchlist Corrections
Owner/Architect Punchlist
Owner/Architect PunchlistCorrections
FINAL INSPECTIONS
Planning and Zoning Inspection
Engineering Inspection
Plumbing Inspection
Life Safety Inspection
Health Department Inspection
Final Inspection
10d
3d
1d
1d
1d
1d
139d
10d
10d
5d
2d
30d
15d
20d
5d
2d
47d
8d
8d
5d
5d
10d
12d
3d
35d
35d
14d
1d
1d
5d
2d
5d
2d
5d
5d
1d
1d
1d
1d
1d
1d
3/26/2027
4/23/2027
4/28/2027
4/29/2027
4/30/2027
5/3/2027
10/15/2026
10/15/2026
10/29/2026
12/3/2026
12/10/2026
12/14/2026
1/27/2027
3/26/2027
4/23/2027
4/30/2027
3/26/2027
3/26/2027
4/7/2027
4/19/2027
4/23/2027
4/30/2027
5/14/2027
5/14/2027
5/4/2027
5/4/2027
5/4/2027
5/24/2027
5/25/2027
5/26/2027
6/3/2027
6/7/2027
6/14/2027
6/16/2027
6/14/2027
6/14/2027
6/15/2027
6/16/2027
6/17/2027
6/17/2027
6/18/2027
4/8/2027
4/27/2027
4/28/2027
4/29/2027
4/30/2027
5/3/2027
5/3/2027
10/28/2026
11/11/2026
12/9/2026
12/11/2026
1/26/2027
2/16/2027
4/22/2027
4/29/2027
5/3/2027
6/1/2027
4/6/2027
4/16/2027
4/23/2027
4/29/2027
5/13/2027
6/1/2027
5/18/2027
6/22/2027
6/22/2027
5/21/2027
5/24/2027
5/25/2027
6/2/2027
6/4/2027
6/11/2027
6/15/2027
6/22/2027
6/18/2027
6/14/2027
6/15/2027
6/16/2027
6/17/2027
6/17/2027
6/18/2027
Modify Pool Mech Room Piping
Install all Pool Entry Handrails
ADA Lift Reinstall
Climbing Wall Reinstall
Zip Line Reinstall
Small Slide Reinstall at Deep End
Demo existing CMU Fence
Infill/Modify CMU Walls on West and South of Building
Prep for new Concrete Footings
Place new Concrete Footings
Install CMU Walls for Fence
Install Pool Fencing at CMU
Demo, patch, and repair pool deck concrete
Install Pool Deck Handrails (Bathrooms)
Install new Drinking Fountain
Rough in New LED Pool Lights
Install LED Light Pole Bases
Install LED Light Poles
West Pool Concrete Approach/Trash Pad Prep/Install
Asphalt Paving Prep and Install
Landscaping Repairs
Asphalt Striping
Clean, Fill Pool, and Perform Final Balancing
Perform Owner Training
Pool Consultant Punchlist
Pool Consultant Punchlist Corrections
Contractor Punchlist
Contractor Punchlist Corrections
Owner/Architect Punchlist
Owner/Architect Punchlist Corrections
Planning and Zoning Inspection
Engineering Inspection
Plumbing Inspection
Life Safety Inspection
Health Department Inspection
Final Inspection
Modify Pool Mech Room Piping
Install all Pool Entry Handrails
ADA Lift Reinstall
Climbing Wall Reinstall
Zip Line Reinstall
Small Slide Reinstall at Deep End
Demo existing CMU Fence
Infill/Modify CMU Walls on West and South of Building
Prep for new Concrete Footings
Place new Concrete Footings
Install CMU Walls for Fence
Install Pool Fencing at CMU
Demo, patch, and repair pool deck concrete
Install Pool Deck Handrails (Bathrooms)
Install new Drinking Fountain
Rough in New LED Pool Lights
Install LED Light Pole Bases
Install LED Light Poles
West Pool Concrete Approach/Trash Pad Prep/Install
Asphalt Paving Prep and Install
Landscaping Repairs
Asphalt Striping
Clean, Fill Pool, and Perform Final Balancing
Perform Owner Training
Pool Consultant Punchlist
Pool Consultant Punchlist Corrections
Contractor Punchlist
Contractor Punchlist Corrections
Owner/Architect Punchlist
Owner/Architect Punchlist Corrections
Planning and Zoning Inspection
Engineering Inspection
Plumbing Inspection
Life Safety Inspection
Health Department Inspection
Final Inspection