HomeMy WebLinkAbout26 - Amendments Amendment Number Unknown - HDR ENGINEERING, INC - WRF ON CALL TASK ORDER NO. 3 FOR ENGINEERING SERVICES AMENDMENT NO. 4 TO AGREEMENT WRF ON CALL TASK ORDER NO. 3 FOR ENGINEERING SERVICES WHEREAS: The CITY OF BOZEMAN (“City”) and HDR ENGINEERING, INC. (“HDR”) entered into an agreement on July 22, 2025, said agreement being Task Order No. 3 of the Professional Services Master Task Order Agreement with HDR Engineering, to perform engineering services for the final design of the WRF Non-Export Solar Power Installation Project (“WRF Solar Project”); The City desires to amend this Task Order No. 3 Agreement (the “Agreement”) in order for HDR to perform services beyond those previously contemplated; and HDR is willing to amend the Agreement and perform the additional engineering services as set forth in this Amendment No. 4 to Task Order No. 3. NOW, THEREFORE, HDR and the City do hereby agree: The Agreement and the terms and conditions therein shall remain unchanged other than those sections and exhibits listed below: Attachment A – Task Order No. 3 Scope of Work is hereby amended to add the Scope of Services attached hereto as Attachment A. The attached Scope of Services outlines HDR’s responsibilities during the construction phase of the WRF Solar Project and is incorporated into the Agreement by this reference. Exhibits A and B, attached hereto, are hereby incorporated into the Agreement by this reference and shall govern the Engineer’s construction-phase services and resident project representative services under this Amendment. Compensation Section shall be amended as follows: The tasks will be requested and directed by the City and HDR will work to complete the requests on a time and materials basis, as directed up to the funds available. Total not-to-exceed time & materials fee increase of this Amendment No. 4 to be $106,815.67, providing for an amended Agreement total of $257,302.67.
Docusign Envelope ID: 0F63C5D5-8CA2-8EC3-809D-0260CF4A000B
IN WITNESS WHEREOF, the parties hereto have executed this Amendment as of the day and year written below: HDR ENGINEERING, INC. ("HDR") ______________________ ("________") By:____________________________ By:_______________________________ Title:___________________________ Title:______________________________ Date:_________________________ Date:_____________________________
Docusign Envelope ID: 0F63C5D5-8CA2-8EC3-809D-0260CF4A000B
9/16/2026
Vice President
9/16/2026
City of Bozeman
Assistant City Manager
1
ATTACHMENT A – CITY OF BOZEMAN, MONTANA
WRF SOLAR GENERATION PROJECT CONSTRUCTION PHASE
SCOPE OF SERVICES
The scope of services identified herein are organized into the following major tasks and
associated with the construction phase of the solar generation project at the water reclamation
facility (WRF).
Task 100 Project Management
Task 200 Contract Administration
Task 300 Construction Observation
Task 400 Integration Services
A detailed description of each task, and the associated subtasks proposed in this scope of
services, follows:
Task 100. Project Management
Objective
Manage the professional services Contract to provide completion of the WRF Solar Generation
Project. This will be an increase to the current task to include project management tasks during
construction.
Subtasks
101 Project Management. Includes project startup, preparing monthly invoices, and progress
reports. Progress reports will summarize the work progress to date, the budget expenditures to
date, and identify information requirements or decisions that need to be made by the City of
Bozeman (City).
Task 100 Deliverables
• Project progress reports, budget report, and invoices.
City Involvement
• Review project status reports and approve invoices.
• Review and approve modifications to approach, schedule, and deliverables as
appropriate.
Docusign Envelope ID: 0F63C5D5-8CA2-8EC3-809D-0260CF4A000B
2
Task 200. Contract Administration
Objective
Provide Contract Administration services throughout the construction period, provide technical
consultation, and assist the City with project closeout.
Subtasks
201 Construction Administration. Specific services to be performed by HDR under this task
include the following:
• Review of Schedule of Values and Progress Schedule submitted by the Contractor, and
review of the Submittal Schedule, which shall identify shop drawings, samples and
submittals required by the contract for construction, along with the anticipated dates for
submission.
• Conduct general correspondence with the Contractor as required to facilitate the project,
for the contract duration listed in the bid documents.
202 Pay Request Review. Specific services to be performed by HDR under this task include
the following:
• Review monthly progress payment requests and submit payment recommendations.
203 Change Order Review. Specific services to be performed by HDR under this task include
the following:
• Prepare Work Change Directives (WCD) and Change Orders. Evaluate Contractor’s
proposals with independent estimates of cost and time impacts.
• Respond to Requests for Information (RFIs), inquiries, and suggestions submitted by
Contractor. Coordinate and maintain log of Contractor submittals and RFIs. Five (5) RFIs
are assumed for this effort.
204 Shop Drawing Review. Specific services to be performed by HDR under this task include
the following:
• Review shop drawings, material data, material samples, test results, operations and
maintenance manuals, and other documents submitted by the Contractor for compliance
with the construction plans and specifications. All testing to be provided by others.
205 Status Meetings. Specific services to be performed by HDR under this task include the
following:
• Conduct one (1) in-person pre-construction conference and distribute the agenda and
meeting minutes to attendees. One (1) HDR staff member will attend the pre-
construction meeting.
• Conduct bi-weekly virtual (via Teams) progress meetings with the Contractor,
Subcontractors, and City staff to review project progress, schedule, budget, information
Docusign Envelope ID: 0F63C5D5-8CA2-8EC3-809D-0260CF4A000B
3
needs, community coordination, and miscellaneous project-related items. Progress
meetings are anticipated to last for a 20-week period in total. Meetings are anticipated to
last one (1) hour and will be attended by up to two (2) HDR staff. A total of 10 meetings
are planned, and meetings will need to be limited during quiet times in the project to
preserve this effort.
206 Closeout. Specific services to be performed by HDR under this task include the following:
• Conduct substantial completion inspection, prepare punch lists, and establish the
contractual warranty period for construction work, and in accordance with the project
specifications.
• Conduct final inspection using substantial completion punch lists. The final inspection
shall take place after infrastructure has been completely installed in accordance with
approved plans and specifications.
Task 200 Deliverables
• Pre-construction Conference Agenda and Meeting Minutes.
• Copies of Reviewed Shop Drawings.
• Progress Payment Recommendations.
• Copies of RFIS, WCDS, Change Proposals, etc.
• Weekly Construction Meeting Agenda and Meeting Minutes.
Task 300. Construction Observation
Objective
Provide limited on-site observation during active construction, monitor the performance of the
Contractor, and assist in responding to events that occur during construction or during critical
construction activities.
Subtasks
301 Construction Observation. Provide general on-site observation and monitoring of
construction, and Contractor’s operation. The budgeted level of effort will be based on providing
observation for 50 (fifty) hours including travel time by local staff from the Bozeman HDR office
and two (2), six (6) hour workdays plus travel time by the electrical engineer from the Kalispell
HDR office. The intent of this schedule is to be on site during key construction activities
including foundation pull testing, vacuum excavation, notable electrical equipment installation,
and utility interconnection tie-in.
HDR's observation or monitoring portions of the work performed under construction contracts
shall not relieve the contractor from its responsibility for performing work in accordance with
applicable contract documents. HDR shall not control or have charge of, and shall not be
responsible for, construction means, methods, techniques, sequences, procedures of
construction, health or safety programs or precautions connected with the work and shall not
manage, supervise, control or have charge of construction. HDR shall not be responsible for the
acts or omissions of the contractor or other parties on the project. HDR shall be entitled to
Docusign Envelope ID: 0F63C5D5-8CA2-8EC3-809D-0260CF4A000B
4
review all construction contract documents and to require that no provisions extend the duties or
liabilities of HDR beyond those set forth in this Agreement. The City of Bozeman agrees to
include HDR as an indemnified party in the City of Bozeman’s construction contracts for the
work, which shall protect HDR to the same degree as the City of Bozeman. Further, the City of
Bozeman agrees that HDR shall be listed as an additional insured under the construction
contractor’s liability insurance policies.
Task 300 Deliverables
• Field Reports and Photos.
Task 400. Integration Services
Objective
Assist City staff with the integration of the solar generation system into the City’s existing
telemetry system and SCADA software.
Subtasks
401 Integration Services. During the construction and implementation phase of the project,
HDR integrators will perform PLC programming and software development to integrate the
telemetry system only when requested by City staff. It is assumed that this will utilize the City’s
current Ignition software platform, and that the City is completing the bulk of integration.
Services by HDR will be performed by request of the City as needed during the integration
process up to a total of 30 hours. Requested services may include:
• SCADA screen development.
• Configure and install Human Machine Interface (HMI) software including alarming
software.
• Program controllers, local operator interface terminals (OIT), and radios.
• Perform loop checks and verifications in conjunction with the electrical contractor and
Town personnel.
• Perform system startup and commissioning.
Task 400 Deliverables
• As Requested.
City Involvement
• Lead the system integration efforts.
• Provide clear scope for each requested service.
Docusign Envelope ID: 0F63C5D5-8CA2-8EC3-809D-0260CF4A000B
Fee Estimate as of 08/24/2026
Client: City of Bozeman
Project: Amendment - Construction phase tasks.
Principal 4.00
QA/QC 8.00
Electrical Engineer 158.00
Project Manager 160.00
EIT/Designer 122.00
Project Admin 8.00
Accountant 12.00
Controls/Integration 30.00
Total Hours 472.00
Total HDR Labor $103,949.83
Total ODC $2,865.84
Total Subcontractors $0.00
Total Fee $106,815.67
Docusign Envelope ID: 0F63C5D5-8CA2-8EC3-809D-0260CF4A000B
BILLING CLASSIFICATION
Principal/ Sr. Technical Advisor 250.00$ -400.00$
Sr. Engineer/ Sr. Project Manager 250.00$ -400.00$
Project Manager 180.00$ -350.00$
Project Engineer 150.00$ -250.00$
Design Engineer/EIT 100.00$ -200.00$
CADD/GIS/Technician 100.00$ -200.00$
Controls/Integration 100.00$ -300.00$
Project Admin and Support 85.00$ -200.00$
Environmental Specialist 100.00$ -250.00$
Strategic Comm/Graphics 100.00$ -250.00$
Construction Management/Inspection 100.00$ -300.00$
Economics/Project Controls 100.00$ -300.00$
Right-of-Way Specialist 100.00$ -250.00$
SUBSISTENCE (PER DIEM)
TRAVEL
Vehicles $0.88 /mile
Rental Vehicles & Aircraft $Actual Cost /mile
MONTANA AREA
Direct project expenses will be charged at the rates listed below unless a separate rate is negotiated for
a specific project.
2026 CHARGEABLE EXPENSE SCHEDULE
Subsistence such as meals and lodging while out on a project will be charged at actual cost or at the per
diem rate negotiated for a specific project.
2026 HOURLY RATE SCHEDULE
RATE RANGES
Travel expenses will be charged at the following rates unless a separate rate is negotiated for a specific
Docusign Envelope ID: 0F63C5D5-8CA2-8EC3-809D-0260CF4A000B
TELEPHONE/FAX/POSTAGE
SPECIAL EQUIPMENT CHARGES
GPS - Handheld $20 /hr.
Survey Equipment $50 /hr.
UTV $350 /day
Other equipment to be determined as necessary
SURVEYING SUPPLIES (Includes: Flagging, Stakes, Etc.)$50 /mile
SUBCONSULTANTS
OVERHEAD
Overhead costs, such as rent, insurance, utilities, office furniture, employee benefits, and taxes are
included in the hourly billing rates.
Long distance calls, telegrams, fax, cellular phone, and any special class postage will be charged at
2026 CHARGEABLE EXPENSE SCHEDULE (continued)
Subconsultants and expenses may be subject to markup
Docusign Envelope ID: 0F63C5D5-8CA2-8EC3-809D-0260CF4A000B
1
EXHIBIT A TO AGREEMENT BETWEEN OWNER AND ENGINEER FOR PROFESSIONAL SERVICES ENGINEER'S STATUS DURING CONSTRUCTION
This Exhibit is attached to, made a part of and incorporated by reference with the Agreement made on , between CITY OF BOZEMAN (OWNER) and HDR Engineering, Inc. (ENGINEER) providing for professional engineering services. ARTICLE 10 - ENGINEER'S STATUS DURING CONSTRUCTION
10.1. OWNER’S REPRESENTATIVE ENGINEER will be OWNER's representative during the construction period. The duties and responsibilities and the limitations of authority of ENGINEER as OWNER's representative during construction are set forth in the Contract Documents and shall not be extended without written consent of OWNER and ENGINEER.
10.2. VISITS TO THE SITE ENGINEER will make visits to the site at intervals appropriate to the various stages of construction to observe the progress and quality of the executed Work and to determine, in general, if the Work is proceeding in accordance with the Contract Documents. ENGINEER will not be required to make exhaustive or continuous on-site inspections to
check the quality or quantity of the Work. ENGINEER's efforts will be directed toward providing for OWNER's greater degree of confidence that the completed Work will conform to the Contract Documents. On the basis of such visits and on-site observations as an experienced and qualified design professional, ENGINEER will keep OWNER informed of the progress of the Work and will endeavor to guard OWNER against defects and deficiencies in the
Work.
10.3. PROJECT REPRESENTATION If OWNER and ENGINEER agree, ENGINEER will furnish a Resident Project Representative to assist ENGINEER in observing the performance of the Work. The duties, responsibilities and limitations of authority of any such
Resident Project Representative and assistants will be as provided in EXHIBIT B, A LISTING OF THE DUTIES, RESPONSIBILITIES AND LIMITATIONS OF AUTHORITY OF THE RESIDENT PROJECT REPRESENTATIVE. 10.4. CLARIFICATIONS AND INTERPRETATIONS ENGINEER will issue with reasonable promptness such written clarifications or interpretations of the requirements of the Contract Documents (in the form of Drawings or otherwise) as ENGINEER may determine necessary, which shall be consistent with or reasonably inferable from the overall intent of the Contract Documents. If CONTRACTOR believes that a written clarification or interpretation justifies an increase in the Contract Price or an extension of the Contract Time and the parties are unable to agree to the amount or extent thereof, CONTRACTOR may make a claim therefor as provided in the General Provisions of the construction Contract Document. 10.5. AUTHORIZED VARIATIONS IN WORK ENGINEER may authorize minor variations in the Work from the requirements of the Contract Documents which do not involve an adjustment in the Contract Price or the Contract Time and are consistent with the overall intent of the Contract Documents. These may be accomplished by a Field Order and will be binding on OWNER, and also on
CONTRACTOR who shall perform the Work involved promptly. If CONTRACTOR believes that a Field Order justifies an increase in the Contract Price or an extension of the Contract Time and the parties are unable to agree as
Docusign Envelope ID: 0F63C5D5-8CA2-8EC3-809D-0260CF4A000B
2
to the amount or extent thereof, CONTRACTOR may make a claim therefor as provided in the General Conditions of the Construction Contract. 10.6. REJECTING DEFECTIVE WORK ENGINEER will have authority to disapprove or reject Work which ENGINEER believes to be defective, and will
also have authority to require special inspection or testing of the Work as provided in the General Provisions of the construction Contract Document whether or not the work is fabricated, installed, or completed. 10.7. SHOP DRAWINGS, CHANGE ORDERS AND PAYMENT 10.7.1. The ENGINEER's responsibility for Shop Drawings and samples shall comply with the shop drawing
provisions of the General Provisions of the construction Contract Document 10.7.2. The ENGINEER's responsibilities for Change Orders shall comply with the change order provisions of the General Provisions of the construction Contract Document.
10.7.3. The ENGINEER's responsibilities for contractor's Application for Payment shall comply with the
payment provisions of the General Provisions of the construction Contract Document. 10.8. DETERMINATIONS FOR UNIT PRICES
ENGINEER will determine the actual quantities and classifications of Unit Price Work performed by CONTRACTOR. ENGINEER will review with CONTRACTOR the ENGINEER's preliminary determinations on
such matters before rendering a written recommendation thereon (by recommendation of an Application for Payment or otherwise) to OWNER.
10.9. DECISION ON DISPUTES
10.9.1. ENGINEER will be the initial interpreter of the requirements of the Contract Documents and judge of the acceptability of the Work thereunder. Claims, disputes and other matters relating to the acceptability of the Work or the interpretation of the requirements of the Contract Documents pertaining to the performance and furnishing of the Work and claims under The General Conditions of the Construction Contract in respect of changes in the Contract Price or Contract Time will be referred initially to ENGINEER in writing with a request for a formal decision in accordance with this paragraph, which ENGINEER will render in writing within a reasonable time. Written notice of each such claim, dispute and other matter shall be promptly reported and copied to the OWNER.
10.9.2. When functioning as interpreter under paragraphs 10.8 and 10.9.1, ENGINEER will not show partiality to OWNER or CONTRACTOR and will not be liable in connection with any interpretation or decision rendered in good faith in such capacity. The rendering of a decision by ENGINEER pursuant to paragraphs 10.8 and 10.9.1 with respect to any such claim, dispute or other matter will be a condition precedent to any exercise by OWNER or CONTRACTOR of such rights or remedies as either may otherwise have under the Contract Documents or by Laws or Regulations in respect of any such claim, dispute or other matter.
Docusign Envelope ID: 0F63C5D5-8CA2-8EC3-809D-0260CF4A000B
3
10.10. LIMITATIONS ON ENGINEER'S RESPONSIBILITIES 10.10.1. Neither ENGINEER's authority to act under this Article or elsewhere in the Contract Documents nor any decision made by ENGINEER in good faith either to exercise or not exercise such authority shall give rise to any duty or responsibility of ENGINEER to CONTRACTOR, any Sub-contractor, any Supplier, or any other person or organization performing any of the Work, or to any surety for any of them. 10.10.2. Whenever in the Contract Documents the terms "as ordered", "as directed", "as required", "as allowed", "as approved" or terms of like effect or import are used, or the adjectives "reasonable", "suitable", "acceptable", "proper" or "satisfactory" or adjectives of like effect or import are used to describe a requirement, direction, review or judgment of ENGINEER as to the Work, it is intended that such requirement, direction, review or judgment will be solely to evaluate the Work for compliance with the Contract Documents (unless there is a specific statement indicating otherwise). The use of any such term or adjective shall not be effective to assign to ENGINEER any duty or authority to supervise or direct the furnishing or performance of the Work or any duty or authority to undertake responsibility contrary to the provisions of paragraph 4.5.3.
Docusign Envelope ID: 0F63C5D5-8CA2-8EC3-809D-0260CF4A000B
1
EXHIBIT B TO AGREEMENT BETWEEN OWNER AND ENGINEER FOR PROFESSIONAL SERVICES A LISTING OF THE DUTIES, RESPONSIBILITIES AND LIMITATIONS OF AUTHORITY OF THE RESIDENT PROJECT REPRESENTATIVE. This Exhibit is attached to, made a part of and incorporated by reference with the Agreement made on , between CITY OF BOZEMAN (OWNER) and HDR Engineering, Inc. (ENGINEER) providing for professional engineering services. ARTICLE 11 - DUTIES, RESPONSIBILITIES AND LIMITATIONS OF AUTHORITY OF THE RESIDENT PROJECT REPRESENTATIVE ENGINEER shall furnish a Resident Project Representative (RPR), assistants and other field staff to assist ENGINEER in observing performance of the work of Contractor. Through more extensive on-site observations of the work in progress and field checks of materials and equipment by the RPR and assistants, ENGINEER shall endeavor to provide further protection for OWNER against defects and deficiencies in the work of CONTRACTOR; but, the furnishing of such services will not make ENGINEER responsible for or give ENGINEER control over construction means, methods, techniques, sequences or procedures or for safety precautions or programs, or responsibility for CONTRACTOR's failure to perform the Work in accordance with the Contract Documents and in particular the specific limitations set forth in section 4.5 of the Agreement are applicable. The duties and responsibilities of the RPR are limited to those of ENGINEER in this agreement and in the construction Contract Documents, and are further limited and described as follows: 11.1. GENERAL RPR is ENGINEER's agent at the site, will act as directed by and under the supervision of ENGINEER, and will confer with ENGINEER regarding RPR's actions. RPR's dealings in matters pertaining to the on-site work shall in general be with ENGINEER and CONTRACTOR keeping OWNER advised as necessary. RPR's dealings with subcontractors shall only be through or with the full knowledge and approval of CONTRACTOR. RPR shall generally communicate with OWNER with the knowledge of and under the direction of ENGINEER. 11.2. DUTIES AND RESPONSIBILITIES OF RPR 11.2.1. Schedules: Review the progress schedule, schedule of Shop Drawing submittals and schedule of values prepared by CONTRACTOR and consult with ENGINEER concerning acceptability. 11.2.2. Conferences and Meetings: Attend meetings with CONTRACTOR, such as preconstruction conferences, progress meetings, job conferences and the project-related meetings, and prepare and circulate copies of minutes thereof. 11.2.3. Liaison: 11.2.3.1. Serve as ENGINEER's liaison with CONTRACTOR, working principally through CONTRACTOR's superintendent and assist in understanding the intent of the Contract Documents; and assist ENGINEER in serving as OWNER's liaison with CONTRACTOR.
Docusign Envelope ID: 0F63C5D5-8CA2-8EC3-809D-0260CF4A000B
2
11.2.3.2. Assist in obtaining from OWNER additional details or information, when required for proper execution of the Work. 11.2.4. Shop Drawings and Samples: 11.2.4.1. Record date of receipt of Shop Drawings and samples.
11.2.4.2. Receive samples which are furnished at the site by CONTRACTOR, and notify ENGINEER of availability of samples for examination. 11.2.4.3. Advise ENGINEER and CONTRACTOR of the commencement of any Work requiring Shop Drawing or sample if the submittal has not been approved by
ENGINEER. 11.2.5. Review of Work, Rejection of Defective Work, Inspections and Tests: 11.2.5.1. Conduct on-site observations of the Work in progress to assist ENGINEER in determining if the Work is in general proceeding in accordance with the Contract Documents.
11.2.5.2. Report to ENGINEER whenever RPR believes that any Work is unsatisfactory, faulty or defective or does not conform to the Contract Documents, or has been damaged, or does not meet the requirements of any inspection, test or approval required to be made; and advise ENGINEER of Work that RPR believes should be corrected or rejected or should be uncovered for observation, or requires special testing, inspection or approval.
11.2.5.3. Verify that tests, equipment and systems startup and operating and maintenance training are conducted in the presence of appropriate personnel, and the CONTRACTOR maintains adequate records thereof; and observe, record and report to ENGINEER appropriate details relative to the test
procedures and startup.
11.2.5.4. Accompany visiting inspectors representing public or other agencies having jurisdiction over the Project, record the results of these inspections and report to ENGINEER. 11.2.6. Interpretation of Contract Documents: Report to ENGINEER when clarifications and interpretations of the Contract Documents are needed and transmit to CONTRACTOR clarifications and interpretations as issued by ENGINEER.
11.2.7. Modifications: Consider and evaluate CONTRACTOR's suggestions for modifications in Drawings or Specifications and report with RPR's recommendations to ENGINEER. Transmit to CONTRACTOR decisions as issued by ENGINEER. 11.2.8. Records: 11.2.8.1. Maintain at the job site orderly files for correspondence, reports of job conferences, Shop Drawings and samples, reproductions of original Contract Documents including all Work Directive Changes, Addenda, Change Orders, Field Orders, additional Drawings issued subsequent to the execution of the Contract, ENGINEER's clarifications and interpretations of the Contract Documents, progress reports, and other Project related documents. 11.2.8.2. Keep a detailed and accurate diary or log book, recording CONTRACTOR hours on the job site, weather conditions, prime and subcontractor daily work force, daily log of equipment onsite or on standby, data relative to questions of Work Directive Changes, Change Orders or changed conditions, list of job site visitors, daily activities, decisions, observations in general, and specific
Docusign Envelope ID: 0F63C5D5-8CA2-8EC3-809D-0260CF4A000B
3
observations in more detail as in the case of observing test procedures; and send copies to ENGINEER. 11.2.8.3. Record names, addresses and telephone numbers of all CONTRACTORS, subcontractors and major suppliers of materials and equipment.
11.2.9. Reports: 11.2.9.1. Furnish ENGINEER periodic reports as required of progress of the Work and of CONTRACTOR's compliance with the progress schedule and schedule of Shop Drawing and sample submittals.
11.2.9.2. Consult with ENGINEER in advance of scheduled major tests, inspections or start of important phases of the Work. 11.2.9.3. Draft proposed Change Orders and Work Directive Changes, obtaining backup material from CONTRACTOR and recommend to ENGINEER Change Orders, Work Directive Changes,
and Field Orders. 11.2.9.4. Report immediately to ENGINEER and OWNER upon the occurrence of any accident.
11.2.10. Payment Requests: Review applications for payment with CONTRACTOR for compliance with the established procedure for their submission and forward with recommendations to ENGINEER, noting
particularly the relationship of the payment requested to the schedule of values, Work completed and materials and equipment delivered at the site but not incorporated in the Work. 11.2.11. Certificates, Maintenance and Operation Manuals: During the course of the Work, verify that certificates, maintenance and operation manuals and other data required to be assembled and furnished by CONTRACTOR are applicable to the items actually installed and in accordance with the Contract
Documents, and have this material delivered to ENGINEER for review and forwarding to OWNER prior to final payment for the Work. 11.2.12. Completion: 11.2.12.1. Submit to CONTRACTOR, and ENGINEER a list of observed items requiring
completion or correction before ENGINEER may issue a Certificate of Substantial Completion. 11.2.12.2 Assess completion or correction of items noted under 11.2.12.1, advise ENGINEER on their status, and make recommendation to Engineer regarding issuance of a Certificate of Substantial completion. 11.2.12.3. Conduct final inspection in the company of ENGINEER, OWNER, and CONTRACTOR and prepare a final list of items to be completed or corrected. 11.2.12.4. Observe that all items on final list have been completed or corrected and make
recommendations to ENGINEER concerning final acceptance. 11.3. LIMITATIONS OF AUTHORITY Resident Project Representative:
11.3.1. Shall not authorize any deviation from the Contract Documents or substitution of materials or equipments, unless authorized by ENGINEER.
Docusign Envelope ID: 0F63C5D5-8CA2-8EC3-809D-0260CF4A000B
4
11.3.2. Shall not exceed limitations of ENGINEER's authority as set forth in the Agreement or the Contract Documents. 11.3.3. Shall not undertake any of the responsibilities of CONTRACTOR, subcontractors or CONTRACTOR's superintendent.
11.3.4. Shall not advise on, issue directions relative to or assume control over any aspect of the means, methods, techniques, sequences or procedures of construction unless such advice or directions are specifically required by the Contract Documents. 11.3.5. Shall not advise on, issue directions regarding or assume control over safety precautions and
programs in connection with the Work. 11.3.6. Shall not accept Shop Drawing or sample submittals from anyone other than CONTRACTOR.
11.3.7. Shall not authorize OWNER to occupy the Project in whole or in part.
11.3.8. Shall not participate in specialized field or laboratory tests or inspections conducted by others except as specifically authorized by ENGINEER.
Docusign Envelope ID: 0F63C5D5-8CA2-8EC3-809D-0260CF4A000B