Loading...
HomeMy WebLinkAbout000.02 - Response to City CONR CommentsPlan Review - Review Comments Report Project Name: 25784 Diamond 8 CONR Workflow Started: 12/29/2025 1:54:10 PM Report Generated: 02/05/2026 09:45 AM REF #CYCLE REVIEWED BY TYPE FILENAME DISCUSSION STATUS 1 1 Fire Department Shane Brandhorst 12/31/25 10:20 AM Comment Can you provide a detail showing fire hydrants in and around the subdivision Info Only 2 1 Forestry Division Alex Nordquest 1/14/26 10:48 AM Changemark Tree Species Recommendations To minimize trees adding to litter/maintenance concerns near athletic fields, recommend the use of evergreens (they don't shed leaves) and species with compound leaves (honeylocust, black locust, kentucky coffeetree, yellowwood). Compound leaves are smaller so leaf litter is reduced. 003 - C-3_NORTH SITE PLAN.pdf Info Only 3 1 Addressing Jenny Connelley 1/16/26 9:39 AM Comment The paved alleys will need to be named so that structures can be addressed off of them. Street names will need to be approved through Gallatin County GIS as they have the master road name list for Gallatin County. Info Only 4 1 Addressing Jenny Connelley 1/16/26 9:40 AM Comment On the north side, there will be one address for the parcel, and then any buildings that require a building permit will need to be assigned an address. Info Only 5 1 Water and Sewer Division Nick Pericich 1/16/26 3:15 PM Changemark W/S Water Service Material HDPE is not an acceptable water service material. In this case, we would allow a service that is copper to a meter pit just inside the property. Then you could install HDPE into the buildings. You could configure this for one service and meter pit or two if necessary. 003 - C-3_NORTH SITE PLAN.pdf Info Only 6 1 Water and Sewer Division Nick Pericich 1/16/26 3:15 PM Changemark W/S Pressure zones The pressure directly to the east at a fire hydrant in Northwest crossing is close to 100 psi. That puts this area on the boundary of needing a pressure reducing valve (110 psi). It will need to be analyzed to see if one is needed in this area. 003 - C-3_NORTH SITE PLAN.pdf Info Only REVIEW COMMENTS Created in ProjectDox version 9.4.9.931 Plan Review - Review Comments Report Project Name: 25784 Diamond 8 CONR Workflow Started: 12/29/2025 1:54:10 PM Report Generated: 02/05/2026 09:45 AM REF #CYCLE REVIEWED BY TYPE FILENAME DISCUSSION STATUS 7 1 Stormwater Division Russ Smith 1/20/26 8:20 AM Comment BMC. 38.220.080.2.g(9) Site plan submittals must include a grading and drainage plan with provisions for on-site retention/detention and water quality improvement facilities. BMC. 38.220.080.g. Site plan submittal requirements. Location, identification, and dimension of the following existing and proposed data, on-site and to a distance of 100 feet (1) Contours min 2 ft; (8) Surface Water (9) Grading and Drainage plan (18) Landscaping (20) Snow Storage- DCS. 6.9.1 requires infiltration of the 0.5" water quality storm to the extent practical, or designed to remove 80% TSS if not. Detention can also be designed to “stack” on top of Wet Ponds in elevated water tables (see Wet Detention Basin in Montana Post-Construction Storm Water BMP Design Guidance Manual - bozeman.net) where temporarily stored runoff will drain down to the original wet pond water surface elevation at a controlled outflow rate, after the storm passes. Further details of permanent water quality BMPs are provided in Section 6.9 BMC. 38.220.080.2.g(9) Site plan submittals must include a grading and drainage plan with provisions for on-site retention/detention and water quality improvement facilities Info Only 8 1 Northwestern Energy David Fuentes 1/21/26 11:39 AM Comment Show proposed 10' wide utility easement locations for electric. Easements are preferred in landscaped areas with no permanent structures. Variations will require coordination with and approval from NWE’s Construction Engineering Department. Info Only 9 1 Northwestern Energy David Fuentes 1/21/26 11:40 AM Comment Show proposed 10' wide utility easement locations for electric. Easements are preferred in landscaped areas with no permanent structures. Variations will require coordination with and approval from NWE’s Construction Engineering Department. Info Only 10 1 Water Conservation Division Eric Neustrup 1/22/26 12:49 PM Comment If this project is submitted as a private development project, it will need to apply for the Open Space Recreation Area Departure from the City of Bozeman Landscaping and Irrigation Performance and Design Standards Manual. See Section 1.4 Departures. Info Only Created in ProjectDox version 9.4.9.931 Plan Review - Review Comments Report Project Name: 25784 Diamond 8 CONR Workflow Started: 12/29/2025 1:54:10 PM Report Generated: 02/05/2026 09:45 AM REF #CYCLE REVIEWED BY TYPE FILENAME DISCUSSION STATUS 11 1 Water Conservation Division Eric Neustrup 1/22/26 12:58 PM Comment On June 15th, 2024, Ordinance 2155 and Resolution 5586 were adopted by the Bozeman City Commission as well as the associated City of Bozeman Landscape and Irrigation Performance and Design Standards Manual. Projects not deemed "adequate” by June 15, 2024 are now subject to these new code requirements. To familiarize yourself with these requirements please visit https://www.bozeman.net/departments/utilities/water- conservation/new-development-standards-3620. Info Only 12 1 Transportation Candace Mastel 1/23/26 12:17 PM Comment Applicant should utilize the PRAT Wayfinding Plan, the Design and Construction Standards document, and staff guidance to install active transportation-based signage for the Shared Use Paths along Baxter Lane, east and west sides of Laurel Parkway and Harvest Parkway. These signs can be combined with other recreational based signs where appropriate, like at trail crossings, as necessary and required by Parks and Recreation. Info Only 13 1 Transportation Candace Mastel 1/23/26 2:12 PM Changemark Candace Mastel Item 2 Provide a crossing for the Shared Use Path across Laurel Parkway 003 - C-3_NORTH SITE PLAN.pdf Info Only 14 1 Building Division Ben Abbey 1/28/26 11:19 AM Changemark 2021 IBC Chapter 11 Accessible Route 2021 IBC Chapter 11 1111.4 Recreational facilities. - Recreational facilities shall be accessible and shall be on an accessible route to the extent specified in this section. 1111.4.2 Team or player seating. - At least one wheelchair space shall be provided in team or player seating areas serving areas of sport activity. 2017 ICC A117.1 with Supplement 1 Accessible and Usable Buildings and Facilities 1001.2.2 Area of sport activity. - Areas of sport activity shall be served by an accessible route and shall not be required to be accessible except as provided in this chapter. Within areas of sports activity exempted in this chapter, the floor and ground surfaces shall not be required to comply with Section 302. Within areas of sports activity exempted in this chapter, changes in level shall not be required to comply with Section 303. 003 - C-3_NORTH SITE PLAN.pdf Info Only Created in ProjectDox version 9.4.9.931 Plan Review - Review Comments Report Project Name: 25784 Diamond 8 CONR Workflow Started: 12/29/2025 1:54:10 PM Report Generated: 02/05/2026 09:45 AM REF #CYCLE REVIEWED BY TYPE FILENAME DISCUSSION STATUS 15 1 Planning Zachary Moon 1/28/26 12:44 PM Comment Planning response to questions (note that questions applicable to other departments will be left to those departments): 1. Please provide a robust phasing plan with any formal submittal clearly delineating timing. There are concerns with the existing proposal in relation to the onsite wetlands, and minimum connectivity required to host games. I believe that other departments will provide more in-depth clarification, but some issues with the existing phasing include construction of fields prior to wetland delineation, providing incomplete streets during a phase where games are proposed to be played, and a lack of clarity on when/if these improvements remain private or if they are dedicated to public and which portions are dedicated to parks. 2. The new UDC does not utilize 'adequacy' anymore. The closest equivalent to adequacy is completeness, or when an application has all required materials to determine substantial compliance. A Master Site Plan application must be determined to be substantially compliant before subsequent applications may be submitted, and must receive final approval before subsequent site plans may be determined to be substantially compliant themselves. The subdivision application will need to meet minimum parkland dedication requirements. A phasing plan for the Master Site Plan which explicitly delineates how and when elements will be transferred to City Parks will be critical to determine how a subdivision may proceed. 3. Parks 4. Engineering 5. We are looking into this matter. 6. Engineering 7. Engineering Info Only 16 1 Planning Zachary Moon 1/28/26 12:47 PM Comment Please note that in a formal submittal, a critical part of any narrative for this lot will be indicating how the proposal complies with Bozeman Municipal Code, Section 38.410.010.B. which requires that natural terrain, drainage, topsoil, trees, and other natural features be preserved to the maximum extent possible. Please include a robust response to this criteria in any formal submittal. Info Only 17 1 Planning Zachary Moon 1/28/26 12:57 PM Comment Pursuant to planning's responses to questions, please ensure that a phasing plan delineates how, when, and if any portions of the site will be dedicated as parklands. If there are elements which will remain private, these portions will likely require subdivision review to remain on a separate private lot. Info Only 19 1 Planning Zachary Moon 1/28/26 1:10 PM Comment This parcel is split zoned R-C/R-D. In a formal submittal please provide an exhibit which shows where proposed improvements will occur in relation to the respective zoning districts. Info Only Created in ProjectDox version 9.4.9.931 Plan Review - Review Comments Report Project Name: 25784 Diamond 8 CONR Workflow Started: 12/29/2025 1:54:10 PM Report Generated: 02/05/2026 09:45 AM REF #CYCLE REVIEWED BY TYPE FILENAME DISCUSSION STATUS 20 1 Planning Zachary Moon 1/28/26 1:14 PM Comment There were not density calculations provided for the southern portion of the proposed subdivision. Please provide calculations as delineated in BMC Section 38.260.030.A.4. in a formal submittal. Info Only 21 1 Planning Zachary Moon 1/28/26 1:15 PM Comment The parcel is split zoned R-C/R-D. In any formal submittal, please ensure that, if residential lots are proposed, that the proposed density complies with the minimum density requirements of Section 38.240.040.A.2. and 050.A.2. for each respective district. Info Only 22 1 Planning Zachary Moon 1/28/26 1:22 PM Comment In addition to ensuring that minimum densities are met for any residential lots created, in a formal submittal, if mixed use development is desired, please indicate the proposed uses for large sites on the southeastern portion of the site. This is critical to ensure that both required densities are met and that all uses comply with the respective R-C and/or R-D district that the lot is proposed within. Info Only 23 1 Planning Zachary Moon 1/28/26 1:26 PM Comment The existing layout of the residential subdivision is not compliant with BMC Section 38.410.030.I. as the western most lots do not have a legal frontage as they only have frontage along an alley. In order to have minimum legal access, a lot would be required to have frontage along an alley and approved street or along an alley and an approved greenway/ trail corridor or shared use path meeting all code standards. In a formal submittal, if you show subdivision lots, please ensure that all lots depicted conform to all standards of Bozeman Municipal Code. Info Only 24 1 Planning Zachary Moon 1/28/26 1:29 PM Comment In the proposed design there are many elements which do not comply with zoning elements. Please be aware that, in order to approve a Master Site Plan, a formal submittal must comply with any underlying zoning districts. As it has been indicated that time is a critical component for this proposal. It may be possible to provide less detail in an initial formal submittal, however there may be additional Modifications required in the future to clarify the desired improvements. Info Only 25 1 Planning Zachary Moon 1/28/26 1:34 PM Comment The application indicates that there is an intent to achieve a Zone Map Amendment at some point for this application. As previously stated, all elements of a Master Site Plan must comply with the applicable zoning in order to achieve preliminary and ultimately final plan approval. It may be possible to achieve a ZMA in the future, but it is worth noting that the City cannot approve plans based on a potential future zone map amendment. If a zone map amendment is required for a desired development path, this would likely be the first step required in a formal application process. Info Only Created in ProjectDox version 9.4.9.931 Plan Review - Review Comments Report Project Name: 25784 Diamond 8 CONR Workflow Started: 12/29/2025 1:54:10 PM Report Generated: 02/05/2026 09:45 AM REF #CYCLE REVIEWED BY TYPE FILENAME DISCUSSION STATUS 26 1 Transportation Candace Mastel 1/28/26 1:48 PM Comment BMC 38.530.070 "Number of bicycle parking spaces required" (new UDC, February 1, 2026): Provide bicycle parking for the project. It would be prudent to spread out the bicycle parking to locations where users will want to access the multiple buildings or ballfields vs. one singular location. Info Only 27 1 Engineering Simon Lindley 1/28/26 2:38 PM Comment Phasing Plan: Please break out the phasing in the engineering design reports (water, sewer, stormwater and traffic impact study) to show how each phase will function separately and at full buildout. Info Only 28 1 Engineering Simon Lindley 1/28/26 2:39 PM Comment Concurrent Construction: Updated UDC 38.780.030 All public infrastructure improvements must be installed prior to the issuance of a building permit, except when concurrent construction is an identified purpose of the initial project review and approved pursuant to the criteria. The applicant has not indicated whether they intend to apply for concurrent construction with this project. Keep in mind future development lots must trigger a site plan review to be eligible to apply for concurrent construction. Bonding may be required through the infrastructure review process or concurrent construction requirements for certain larger public infrastructure items. If the applicant intends to apply for concurrent construction, please reference the latest concurrent construction checklists on the planning website and submit a request with the relevant information with the master site plan. Info Only 29 1 Engineering Simon Lindley 1/28/26 2:42 PM Comment Ditch Noticing Checklist: Updated UDC 38.310.010 The applicant must fill out the Ditch Noticing Checklist found on the planning website and provide the relevant documentation with the subsequent applications. As of June 18, 2025, the checklist is required with all concept reviews, site plans, master site plans, subdivision pre-applications, subdivision preliminary plats, and PDZs. Info Only 30 1 Engineering Simon Lindley 1/28/26 2:44 PM Comment City of Bozeman Design and Construction Standards Chapter 1.4 - Plans, specifications, and submittals for public infrastructure and fire service lines must be submitted by the professional engineer to the City Engineering Department through the engineering Project Dox Portal for infrastructure/fire service line review. The site plan or preliminary plat application must reach adequacy according to the review engineer prior to initial infrastructure submittal. Please see the infrastructure review fee schedule on the City Engineering website. Info Only Created in ProjectDox version 9.4.9.931 Plan Review - Review Comments Report Project Name: 25784 Diamond 8 CONR Workflow Started: 12/29/2025 1:54:10 PM Report Generated: 02/05/2026 09:45 AM REF #CYCLE REVIEWED BY TYPE FILENAME DISCUSSION STATUS 31 1 Engineering Simon Lindley 1/28/26 2:54 PM Comment Engineering Design Reports: (1) City of Bozeman Design and Construction Standards Chapter 3.2 Design Reports: The applicant must submit water and sewer design reports with the master site plan, site plans and preliminary plat applications. Please reference the requirements in this chapter. (2) City of Bozeman Design and Construction Standards - Storm Drainage Design The applicant must provide a stormwater report with the master site plan, site plans and preliminary plat applications. Please reference the stormwater drainage report and maintenance plan requirements in chapter 6.4 and attachment B. (3) The applicant must submit a transportation impact study (TIS) with the master site plan. Please reference the updated UDC requirements in 38.710.050.A.11.g. The TIS must identify when mitigation measures are required in relation to the proposed phasing. Info Only 32 1 Engineering Simon Lindley 1/28/26 2:55 PM Comment Updated UDC 38.530.020.L - Snow removal storage areas: Please review the code section and provide the following information with the site plan. Snow storage areas are not shown on the concept site plan. All parking facilities containing 5 or more parking spaces must provide a snow management plan. The plan must contain the following: 1. Locations for snow storage, which may include on-site landscaped areas, and other open space for at least 15 % of the total area of the site used for parking, access drives, walkways and other paved surfaces; 2. Snow storage is not allowed: a. In the public right-of-way; b. Where it would obstruct line of sight or vision triangle; c. In a location where it blocks fire hydrants, emergency vehicle access or access to other properties; d. Where it will cause unmanageable freeze/thaw and icing of sidewalks, pathways and other paved surfaces; e. Where it obstructs on-site amenities, including but not limited to points of egress, mailboxes, storage areas, and trash enclosures; f. Within any access easement; g. Where placed in a manner which violates the Clean Water Act (CWA) and/or the Montana Pollutant Discharge Elimination System (MPDES), and/or any other federal, state or local law or statute; or h. Where it will cause damage to trees located in the public right-of-way. Info Only Created in ProjectDox version 9.4.9.931 Plan Review - Review Comments Report Project Name: 25784 Diamond 8 CONR Workflow Started: 12/29/2025 1:54:10 PM Report Generated: 02/05/2026 09:45 AM REF #CYCLE REVIEWED BY TYPE FILENAME DISCUSSION STATUS 33 1 Engineering Simon Lindley 1/28/26 2:55 PM Comment BMC 38.410.070.B - The length of water services lines from the main to the structure may not exceed 150 feet in length unless approved in writing by the city. When the city's municipal water main is extended, the length of a dead-end water main typically may not exceed 500 feet in length, unless approved in writing by the city. The applicant may request an administrative waiver in chapter 1.9 of the City of Bozeman Design and Construction Standards during the master site plan review. Please note the city doesn't have a standard form. The request should be submitted in the form of a certified memo, and address the requirements in chapter 1.9.2 and evaluate the water pressures during each phase of development. Please reference chapter 4.2 for the design criteria. Info Only 34 1 Engineering Simon Lindley 1/28/26 2:56 PM Comment City of Bozeman Design and Construction Standards – Chapter 4.2.9 – Water service pipe shall be type “K” copper for sizes less than 4-inch, and ductile iron for services 4-inch and larger. HDPE pipe shown on the concept plan is not allowed. Please revise the pipe material with subsequent submittals. Info Only 35 1 Engineering Simon Lindley 1/28/26 2:58 PM Comment Water Main Sizing: 1) The 2015 Water Facility Plan identifies a 12-inch water main in Laurel Parkway from Oak to Baxter. Please change the water main size from 10 to 12. This improvement is eligible for oversizing reimbursement, however the applicant must submit the request prior to the pre-construction meeting. 2) The 2015 Water Facility Plan identifies a transmission main in Baxter Lane. The applicant must install a 12-inch water main adjacent to the development when the Baxter Lane street section is constructed. This improvement is eligible for oversizing reimbursement, however the applicant must submit the request prior to the pre-construction meeting. 3) It is unclear why the applicant is proposing a 10-inch water main in Harvest Parkway. This is not identified in the Water Facility Plan. The applicant is advised to look at the water pressures during each phase of development. Info Only Created in ProjectDox version 9.4.9.931 Plan Review - Review Comments Report Project Name: 25784 Diamond 8 CONR Workflow Started: 12/29/2025 1:54:10 PM Report Generated: 02/05/2026 09:45 AM REF #CYCLE REVIEWED BY TYPE FILENAME DISCUSSION STATUS 36 1 Engineering Simon Lindley 1/28/26 3:00 PM Comment The 2024 Wastewater Facility Plan identifies the 21-inch Aajker Basin Diversion Interceptor through the subject development. The 21-inch interceptor must convey a peak flow rate of 1,650 gpm (3.68 cfs) and meet the 75% depth over diameter requirement. As presented, the city is in general agreement with the layout, however a detailed review of the profile and layout will be completed with the master site plan. The applicant must provide a provide a plan view and vertical profile with the master site plan. This improvement is eligible for oversizing reimbursement, however the applicant must submit the request prior to the pre-construction meeting. Info Only 37 1 Engineering Simon Lindley 1/28/26 3:04 PM Comment The applicant did not provide a proposed stormwater design with the concept review for engineering to review and provide comments. The applicant will need to follow the latest City of Bozeman Design and Construction Standards and provide stormwater treatment for the proposed public roads and development areas. Please reference the stormwater drainage report and maintenance plan requirements in chapter 6.4 and attachment B. Info Only 38 1 Engineering Simon Lindley 1/28/26 3:05 PM Comment Pursuant to BMC 38.410.080.C, stormwater systems serving multiple lots in separate ownership (the phase 2 subdivision) must not be located on private lots or public rights-of-way. Stormwater retention or detention ponds must be maintained by the property owners' association. Info Only 39 1 Engineering Simon Lindley 1/28/26 3:09 PM Comment Updated UDC 38.710.070.C.7.h - The developer must complete a wetland delineation of on-site wetlands consistent with the process in 38.610. Please submit the WETLAND REVIEW CHECKLIST with the master site plan and preliminary plat. The checklist can be found on the planning website. Please reference the concept comments from the citys wetland consultant which have been uploaded to the city documents folder. Please address the wetland consultant comments with subsequent submittals. Info Only 40 1 Engineering Simon Lindley 1/28/26 3:11 PM Comment Updated UDC 38.620.D.2c.(3) - The city recognizes the applicant’s intent to avoid the existing natural resources as much as possible while balancing the need for public infrastructure. The city believes there is still opportunity to optimize the design of Laurel Parkway to further minimize impacts to natural resources. The applicant is proposing to construct the northern section of Laurel Parkway along the alignment of the identified irrigation ditch and wetlands. The street alignment for Laurel Parkway may need to shift to the west. The City prioritizes as listed the avoidance, minimization and mitigation of impacts for natural resources. Info Only Created in ProjectDox version 9.4.9.931 Plan Review - Review Comments Report Project Name: 25784 Diamond 8 CONR Workflow Started: 12/29/2025 1:54:10 PM Report Generated: 02/05/2026 09:45 AM REF #CYCLE REVIEWED BY TYPE FILENAME DISCUSSION STATUS 41 1 Engineering Simon Lindley 1/28/26 3:12 PM Comment City of Bozeman Design and Construction Standards (DCS) Table 7.1.1 - Local streets shall have a minimum face-of-curb to face-of-curb width of 35’ where on-street parking is allowed and where off-street parking is reduced. Harvest Parkway and Forestglen Drive do not meet the required 35-foot width. Please revise the street section with subsequent submittals. Info Only 42 1 Engineering Simon Lindley 1/28/26 3:16 PM Comment The Engineering Division does not support the 22-foot wide Laurel Parkway street section during phase 1B. The full 40-foot wide Laurel Parkway street section from Oak to Baxter must be constructed with the applicable phase. A half street will not be accepted as shown during phase 1B. Key concerns include the lack of curbing adjacent to the ditch/wetlands, and the high likelihood for illegal parking during baseball games. Info Only 43 1 Engineering Simon Lindley 1/28/26 3:19 PM Comment The applicant is advised that when Oak Street is widened adjacent to the subject development, Oak Street must also be widened to the east of this project to connect to the existing street section. The applicant is advised to coordinate with the Northwest Crossing Subdivision. Info Only 44 1 Engineering Simon Lindley 1/28/26 3:20 PM Comment BMC Table 38.400.090-1 – The access spacing on Harvest Parkway between Forestglen Drive and the east entrance to the west parking lot for the baseball fields does not meet the minimum separation. Info Only 45 1 Engineering Simon Lindley 1/28/26 3:22 PM Comment The Laurel Parkway and Baxter Lane street sections shown with the concept review are missing 10-foot shared use path on both sides of the street. Please see the street section table in the city documents folder and revise the plans with subsequent submittals. Info Only 46 1 Engineering Simon Lindley 1/28/26 3:23 PM Comment Applicant Question 4: Please reference section 38.620 in the updated UDC for the latest watercourse setback requirements. There are several figures at the end of this section which illustrate how the watercourse setback is determined. Info Only Created in ProjectDox version 9.4.9.931 Plan Review - Review Comments Report Project Name: 25784 Diamond 8 CONR Workflow Started: 12/29/2025 1:54:10 PM Report Generated: 02/05/2026 09:45 AM REF #CYCLE REVIEWED BY TYPE FILENAME DISCUSSION STATUS 47 1 Engineering Simon Lindley 1/28/26 3:27 PM Comment Applicant Question 6: In general, if the applicant is proposing to avoid impacts to the wetlands and watercourses to the maximum extent possible, the city would allow the applicant to submit with phasing. If there are impacts with the phasing, then the necessary permits would be required with the applicable phase. A wetland delineation report will be required with the master site plan, however the required streambed, streambank or wetlands permits will not be required until construction of the applicable phase which shows impacts to natural resources. With the concept review the applicant is showing wetland impacts with the initial phase (phase 1A). If the applicant intends to pursue an early grading site plan to start work as soon as possible, the phasing plan should show an initial phase with no wetland and watercourse impacts. It's the applicants job to provide all the necessary supporting documentation and exhibits that can help support city staff in making determinations for each phase. Info Only 48 1 Engineering Simon Lindley 1/28/26 4:04 PM Comment Applicant Question 7: Updated UDC 38.620.D.2.c - Paved trails must generally be located outside of zone 2 of the watercourse setback unless the trail connection is necessary for the purpose of protecting public health and safety, or the trail is an active transportation pathway. Please reference comment 14 from the building department for accessibility requirements with this project. Info Only 49 1 Engineering Simon Lindley 1/28/26 4:05 PM Comment Exempt Wells: The applicant is advised that for the proposed use of exempt irrigation wells, an approved Notice of Intent to Appropriate Groundwater (Form No. 602I) must be obtained from MT DNRC. Respective site plan applications for master site plan phases in which an exempt irrigation well provides irrigation water supply will not be considered complete until a DNRC-approved 602I is provided. The applicant is encouraged to obtain a 602I approval prior to master site plan approval to avoid a master site plan amendment in the event DNRC denies the 602I. Info Only Created in ProjectDox version 9.4.9.931 Plan Review - Review Comments Report Project Name: 25784 Diamond 8 CONR Workflow Started: 12/29/2025 1:54:10 PM Report Generated: 02/05/2026 09:45 AM REF #CYCLE REVIEWED BY TYPE FILENAME DISCUSSION STATUS 50 1 Engineering Simon Lindley 1/28/26 4:06 PM Comment Irrigation Water Rights: The applicant is advised that it will be required to use existing irrigation water rights on the property to irrigate field turf and other publicly accessible irrigated landscaped areas of the master site plan, including city parkland. Access to the City’s municipal water system to provide irrigation water supply for these areas will only be considered for supplemental or backup uses. The applicant is advised that city-owned and -maintained irrigation systems must be discrete and separate from privately owned and maintained systems. The applicant should consider the implications of this requirement in its irrigation master plan and infrastructure planning to avoid future system retrofits or potential water right changes with MT DNRC. Info Only 51 1 Engineering Simon Lindley 1/28/26 4:06 PM Comment Irrigation Water Rights: The applicant is advised that the master site plan application must contain information describing the proposed approach to using the existing irrigation water rights on the property. The legal elements of the water rights must be evaluated to determine the quantity of water available to meet the irrigation water requirement for field turf, and other publicly accessible irrigated areas of the master site plan, including parkland. Water right conveyance from the source of supply to the place of use must be evaluated and identify any conveyance improvements, conveyance agreements, or easements that are necessary. The legal elements of the water rights must be evaluated to determine whether any water right changes are needed with MT DNRC. The ownership elements of the water rights must be evaluated to determine whether any water right ownership splits are necessary. Info Only 52 1 Engineering Simon Lindley 1/28/26 4:54 PM Comment Private Utility Easements: Front setback utility easements must be 10 feet wide, and must always be provided unless written confirmation is submitted to the community development department from all utility companies providing service indicating that front setback easements are not needed. The concept review doesn't show the 10-foot private utility easements. Please coordinate with Northwestern Energy and other utility providers. Please show the 10 foot private utility easement along all street frontage with subsequent submittals. Info Only Created in ProjectDox version 9.4.9.931 Plan Review - Review Comments Report Project Name: 25784 Diamond 8 CONR Workflow Started: 12/29/2025 1:54:10 PM Report Generated: 02/05/2026 09:45 AM REF #CYCLE REVIEWED BY TYPE FILENAME DISCUSSION STATUS 53 1 Parks Department Ross Knapper 1/30/26 11:47 AM Changemark Parks The Parks and Recreation Department in principal supports the approach of future public dedication of the privately constructed baseball facility to meet parkland dedication requirements associated with subsequent residential development. To qualify as parkland dedication at time of subsequent residential development, the baseball facility and improvements will need to meet all applicable Parks and Recreation requirements and subdivision requirements in effect at that time including but not limited to the following: 1) BMC Sec. 38.420. – Parks and recreation requirements; 2) BMC Sec. 38.710.050.A.14. – Parks and recreation facilities; 3) BMC Sec. 38.710.090. – Submittal requirements for landscape and irrigation plans; 4) BMC Sec. 38.780.030. – Completion of improvements; 5) BMC Sec. 38.780.050. – Acceptance of improvements; 6) BMC Sec. 38.780.100. – Warranty; 7) Current Park Design Manual; 000 - Diamond 8 Narrative.pdf Info Only 54 1 Parks Department Ross Knapper 1/30/26 11:48 AM Changemark Parks Applicant is highly encouraged to consult with the Parks and Recreation Department prior to any subsequent site development submittals to ensure final project designs will meet park design standards, completion and acceptance standards, water adequacy requirements, and overall department needs. 000 - Diamond 8 Narrative.pdf Info Only 55 1 Parks Department Ross Knapper 1/30/26 11:49 AM Changemark Parks An executed MOU between applicant and Parks and Recreation Department detailing the future parkland dedication proposal, agreement on facility designs and features, clarity of ownership, and long-term operation and maintenance agreement will be required prior to final site plan approval, if applicant wishes to propose baseball facility as future parkland dedication. 000 - Diamond 8 Narrative.pdf Info Only 56 1 Parks Department Ross Knapper 1/30/26 11:59 AM Changemark Parks MSP application must include a detailed narrative describing the proposal for future dedication of the private baseball facility to meet anticipated park and recreation requirements. Proposal must include a map showing the anticipated residential development(s) subject to future parkland dedication, along with an preliminary parkland tracking table listing anticipated park and recreation requirements, and a draft improvements-in-lieu package with preliminary improvement costs. 000 - Diamond 8 Narrative.pdf Info Only Created in ProjectDox version 9.4.9.931 Plan Review - Review Comments Report Project Name: 25784 Diamond 8 CONR Workflow Started: 12/29/2025 1:54:10 PM Report Generated: 02/05/2026 09:45 AM REF #CYCLE REVIEWED BY TYPE FILENAME DISCUSSION STATUS 57 1 Planning Zachary Moon 2/2/26 11:15 AM Comment Per Section 38.510.040.B. all proposed buildings must provide pedestrian connections to a sidewalk. Please ensure that in any formal phasing plan, pedestrian connectivity is shown to all baseball fields and buildings prior to these facilities being utilized. Info Only 58 1 Planning Zachary Moon 2/2/26 11:22 AM Comment Per BMC Section 38.410.040.B-D. the block lengths between Baxter Lane and Harvest Parkway is approximately 1,650ft. Block length and width requires that blocks must not be longer than 1,320. Subsection D allows that pedestrian rights of way may be utilized in lieu of vehicular rights of way in order to mitigate block lengths in excess of the allowed maximum. In a formal submittal, please provide a compliant pedestrian right-of-way which aligns with Touchstone Lane in order to comply with this standard. Info Only Created in ProjectDox version 9.4.9.931