HomeMy WebLinkAbout26 - Submissions - Bozeman Library Children's Room Renovation (2)From:Mike Daines
To:Bozeman Procurement
Cc:Shane Miller; Jason Martel
Subject:[EXTERNAL]Bozeman Library Children"s Room Renovation, Martel Construction, 8/13/2026 @ 5PM MST
Date:Thursday, August 13, 2026 4:40:26 PM
Attachments:image001.pngBozeman Library Childrens Room RFP Response - Martel.pdf
CAUTION: This email originated from outside of the organization. Do not click links or open attachments unless you
recognize the sender and know the content is safe.
Hello,
Please see attached response to RFP for Bozeman Library Children’s Room Renovation.
Thank you
Mike Daines
Project Manager
Martel Construction, Inc.
1203 S. Church Avenue
Bozeman, MT 59715
www.martelconstruction.com
(406) 586-8585 – Office
(406) 223–9011 – Mobile
Polson Library
August 13, 2026
Mike Maas, City Clerk
Shane Miller, Facilities Project Coordinator
City of Bozeman
121 N. Rouse
Bozeman, MT 59715
Dear Mr. Maas and Mr. Miller,
Since Martel constructed the library in 2001, the community of Bozeman has expanded and so has the library’s needs. The last renovation, led by Mike Daines and Derral Lynch,
helped transform the library’s programming for teenagers and adults. Now, it is time for the children of Bozeman to reap those same benefits. We offer the Library and MSR the
benefit of an accelerated schedule, full knowledge of the library building and its operations, and an unmatched ability to self-perform many components of this work. Our proposed
team has worked with the library staff and understands the operational challenges they face while under construction. From safety to public interest, our goal is to meet the public’s
need with a new children’s space while accomodating the library staff’s day to day operations.
Safety: Extra care must be taken to isolate this construction zone, particularly curious children. We will erect sturdy temporary barriers, secure all tools and materials out of reach,
and strictly limit access so no children can enter the area as we did in the last renovation. Martel would propose to create a viewing window from the collections area so that the
public’s curiousity can be answered and library staff can be assured that progress is being made.
Schedule: Our team will turn this space around quickly with early procurement, using our warehouse (minutes from the library) as a storage and staging area, and working double
shifts. From our programming efforts, we have a plan to mitigate potential setbacks so the construction process is completed without any delays.
Resources: Adequate resources in personnel and equipment ensure nothing slows or stops this renovation.
Quality: Our clients value the contributions of our shop artisans, who are masters at custom architectural wood and metal finishes. We are ready to build some of the custom
pieces, such as the hanging cloud acoustical panels, faster and for less money than finding another supplier.
Martel has a proven track record of quality at the Bozeman Public Library. This has been accomplished by building trust with the staff, being transparent with our schedule and
working as a familiar team towards the finished product. Together, we will renovate the Children’s Room to stand as a place for families and their children to gather.
Sincerely,
Jason Martel, President
Bozeman Market
3
Executive Summary 5
Qualifications 6
Schedule 8
Experience 10
Exhibits 16
Attachment A � � � � � � � � 17
Bigfork Library 4
Executive Summary
Executive Summary
Consistency | The same team of construction
professionals who worked on the last Bozeman Public
Library renovation.
Safety | Martel’s commitment to library patron and staff
safety, particularly children who will be drawn by curiosity to
the construction area.
Logistics | Solving complicated construction logistics
for an accelerated schedule in an occupied facility. Our
warehouse can be used for just-in-time deliveries.
Resources | In addition to extensive self-performance,
we can fabricate some of the custom finishes and fixtures
to increase production timelines and control costs.
Design Guidance | Continued collaboration with MSR,
the library staff and the Martel team.
Self-Performance | Ability to self-perform multiple
scopes of work. This ensures quality, safety, schedule, and
budget adherence.
Engagement | Story boards to learn about their new
space, tours of the construction area, and child height
windows all bring youngsters into the process.
Follow-Up | Follow-Up and warranty fulfillment is
unmatched. The majority of our work is for past clients who
trust us to meet their needs.
Belgrade Library & Community Center
5
Qualifications of the Firm for Scope of Services & Cost
Our qualifications overcome the challenges of the Bozeman Public Library Children’s Room renovation. This includes both existing conditions and practical difficulties during
planning and execution. We are excited for the opportunity to update the space to handle the intensive use of 125,000+ annual visitors, rework the configuration for modern use,
improve safety and visibility, and provide accessible spaces for those with unique physical and learning needs.
Scheduling and Procurement
Combining the many variables that
construction brings, including design
finalization, fundraising, bidding, temporary
space logistics, and sequencing with
thorough collaboration between City of
Bozeman, Bozeman Public Library, and MSR
Design representatives.
Assistance with relocating part of the
Children’s room to the Community Room,
and setting up a temporary checkout.
Engagement with owner and design team
representatives to evaluate and select the
best furniture, fixtures, and equipment to
meet the Children’s Room’s current and
future needs.
Our accelerated schedule requires tight
sequencing of demolition, MEP upgrades,
finishes, FFE installation, and close-out while
minimizing overall schedule impact. Our
ability to self-perform much of this work
allows us to control schedule, cost, and
quality.
Budget limitations
Together with the City of Bozeman, Bozeman Public Library, and MSR, we had to return to the drawing board to create this
scaled back version of the renovation that still met most goals while remaining affordable.
We recognize the heavy reliance on private fundraising and the trust donors have in our team to maximize their investment
in our community and use money judiciously.
Maintaining cost control during the bid/award process and any subsequent change orders will be critical given the earlier
experience with over-budget designs. Our plan includes:
1. Use Clear, Complete Evaluation Criteria
Define and publish scoring criteria in advance and evaluations using a matrix system. We prefer the lowest and most
responsible partners to work with us given the short schedule.
2. Protect Against Scope Creep and Cost Surprises
Require proposers to base their pricing and schedule on the final drawings and specifications. Detailed cost breakdowns
and proposed sequencing for working inside the library space are other evaluation criteria.
3. Post Award Controls
Once a firm is selected, leverage strong change-order procedures, progress payment controls, and regular schedule
updates to ensure compliance with project requirements.
Any changes order requests will be required to use bid-day pricing and will be fully vetted by owner and design team
representatives.
Bozeman Public Library cost control evolves through transparency, thorough documentation,
consistency, and communication with all involved
Qualifications
6
Coordination & Safety
Construction coordination challenges for the Children’s Room are not unlike our
occupied work at Bozeman Health, Bozeman Airport, Billings Clinic, or other spaces
where safety, jobsite isolation, and efficiency are paramount.
Maintaining Public Access
Construction must be carefully isolated from ongoing library staff and patron access
with barriers, dust control, and clear pathways. Noise, vibration, and material deliveries
can disrupt patrons—especially families with young children—and create safety risks if
not tightly managed. We are prepared to also work nights and weekends to minimize
disruption.
Tight Sequencing
Demolition, MEP upgrades, finishes, and furniture installation must be tightly sequenced
around library hours, peak family times, and any remaining programming. Delays quickly
cascade.
Logistics
Deliveries, staging, waste removal, and worker access must avoid main entrances and
high-traffic areas. Power, HVAC, and plumbing shut downs have to be timed so they do
not affect the open portions of the library.
Communication and Flexibility
Daily coordination between Martel, library staff, city officials, and subcontractors is
critical. Unexpected conditions in an older building, material delays, or last-minute
program needs require quick adjustments without losing schedule or budget control.
These factors make the Children’s Room renovations more complex than typical
construction: the work must protect ongoing public service while still finishing on a
compressed timeline inside a constrained footprint.
Donor and Community Engagement
We treat community engagement as a core part of the job—not an afterthought. As
Bozeman Public Library’s partner, we are visible, responsive, and family-friendly while the
library stays open.
Daily Engagement
Derral Lynch, our on-site superintendent, will be available during library hours. On the
last library renovation, he had constant interactions to build trust with library staff and
users.
Supporting Temporary Children’s Services
We will actively participate in setting up temporary Children’s services in the Community
Room – as well as transition back once the work is completed. We can provide extra
hands for moving materials, clearing pathways, or other needs. We can also enforcing
quiet work periods to minimize the impacts of our work.
Daily Reports
Owner and design representatives can subscribe to our daily report that includes visual
updates, progress photos, short notes on what is happening next, and any planned
noisy days. Temporary signage that is friendly and easy for parents to understand will be
setup.
Minimize Disruption
We will schedule the noisiest or dustiest work during lower-traffic times when possible.
Our team will provide quick response to any safety or access.
Self-Perform
We are eager to support this project by providing some finishes like the acoustic cloud
panels. Our team can produce and install these to maintain schedule, quality, and cost.
7
Schedule
Upon selection, our priority is confirming our proposed
baseline schedule. This includes the full sequence of
demolition through finishes and furniture installation, and
realistic constraints around library hours and temporary
operations.
Critical path items such as long-lead materials and MEP work
must be protected by early procurement and planning.
Weekly meetings with the superintendent, Facilities
coordinator, and Library liaison help keep everyone aligned
on completed work, upcoming tasks, and any risks to the
timeline. Any schedule change that affects public access or
staff workflows should be addressed immediately.
Constant collaboration ensures delays don’t erode the short
schedule. Providing leaders with clear look-ahead plans
reduces confusion and helps contractors and library staff plan
around the work.
By combining a solid baseline schedule, frequent
coordination, and quick issue resolution, we will keep the
renovation on track to finish on time.
Schedule
8
Version Name
BPL Childrens Lib
Version Description
-
Data Date
05/31/2026
Generated On
08/13/2026 Page 1.1
S/N
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
October 2026 November 2026 December 2026
05 - 11 12 - 18 19 - 25 26 - 01 02 - 08 09 - 15 16 - 22 23 - 29 30 - 06 07 - 13 14 - 20
Start Milestone 10/05/2026
Mobilization, Temporary Protection/Dust Barriers 0d
Salvage and Remove Items 2d
Demolition 4d
Frame New Partitions (Storage/IT 120 Rated Walls C3/C4) & Infill Walls at Former Exits 3d
MEP Rough In 7d
Install Blocking/Backing for Millwork, Shelving & Equipment 2d
Install Door Frames 3d
Insulation at Rated & Acoustically Rated Partitions 2d
Hang Drywall 3d
Tape, Mud & Sand Drywall 5d
Prime Paint — Walls & Ceilings 3d
Install ACT 2x2 Ceiling Grid 3d
Install Millwork & Casework (YS Workroom, Reception, Built-Ins, Reconfigured Salvage)5d
Reinstall Salvaged Storefront Assemblies & Glazing (STFT-3)2d
Install Acoustic Wall Covering (WCVG-2)4d
Install Wood Trim/Casing (WD-2A) & Wood Veneer Panels (WD-1)3d
Install Restroom Accessories, Mirrors, Grab Bars & Partitions 2d
Flooring install 6d
Install Solid Surface Countertops (SSF-3)4d
Install Acoustic Ceiling Clouds/Baffles (Add Alternates 1 & 2, if awarded)3d
MEP Trimout 5d
Final Clean 2d
Punch List 2d
Owner Acceptance 1d
Finish Milestone 12/14/2026
Shore to Summit 71d
ELEMENT NAME DUR START DATE FINISH DATE
Shore to Summit 71 10/05/2026 12/14/2026
Start Milestone 0 10/05/2026 10/05/2026
Mobilization, Temporary Protection/Dust Barriers 0 10/05/2026 10/05/2026
Salvage and Remove Items 2 10/05/2026 10/06/2026
Demolition 4 10/05/2026 10/08/2026
Frame New Partitions (Storage/IT 120 Rated Walls C3/C4) & Infill Walls at Former Ex…3 10/09/2026 10/13/2026
MEP Rough In 7 10/14/2026 10/22/2026
Install Blocking/Backing for Millwork, Shelving & Equipment 2 10/14/2026 10/15/2026
Install Door Frames 3 10/14/2026 10/16/2026
Insulation at Rated & Acoustically Rated Partitions 2 10/23/2026 10/26/2026
Hang Drywall 3 10/27/2026 10/29/2026
Tape, Mud & Sand Drywall 5 10/30/2026 11/05/2026
Prime Paint — Walls & Ceilings 3 11/06/2026 11/10/2026
Install ACT 2x2 Ceiling Grid 3 11/11/2026 11/13/2026
Install Millwork & Casework (YS Workroom, Reception, Built-Ins, Reconfigured Salva…5 11/11/2026 11/17/2026
Reinstall Salvaged Storefront Assemblies & Glazing (STFT-3)2 11/11/2026 11/12/2026
Install Acoustic Wall Covering (WCVG-2)4 11/11/2026 11/16/2026
Install Wood Trim/Casing (WD-2A) & Wood Veneer Panels (WD-1)3 11/11/2026 11/13/2026
Install Restroom Accessories, Mirrors, Grab Bars & Partitions 2 11/16/2026 11/17/2026
Flooring install 6 11/18/2026 11/25/2026
Install Solid Surface Countertops (SSF-3)4 11/18/2026 11/23/2026
Install Acoustic Ceiling Clouds/Baffles (Add Alternates 1 & 2, if awarded)3 11/26/2026 11/30/2026
MEP Trimout 5 12/01/2026 12/07/2026
Final Clean 2 12/08/2026 12/09/2026
Punch List 2 12/10/2026 12/11/2026
Owner Acceptance 1 12/14/2026 12/14/2026
Finish Milestone 0 12/14/2026 12/14/2026
Martel Construction Inc.Shore to SummitBozeman Public Library Children's Renovation Schedule
9
Related Experience with Similar Projects
Experience
Meet our Bozeman
Public Library team
of construction
and collaboration
professionals.
Jason Martel
Principal in Charge
Derral Lynch
Superintendent
Mike Daines
Project Manager
Tyler Ragen
Senior Estimator
10
Relationships with City of Bozeman Leaders
Relationships with Bozeman Library Staff
Renovations at Bozeman Public Library
Knowledge of Bozeman Library Building
Integration with MSR Design on Programming
High Profile Public Projects
Occupied Renovations
Tight Schedules
Cost Effective Budgeting
Jason Martel
Principal in Charge
Derral Lynch
Superintendent
Mike Daines
Project Manager
Tyler Ragen
Senior Estimator
Our Team Experience
Self-Performance
Our diverse workforce of construction experts consistently delivers excellence. Martel determines whether we should self
perform or subcontract work based off of what is. in the best interest of the project but for Bozeman Library this improves
speed and quality.
We have a competitive advantage in general construction by self-performing critical scopes of work. Qualified and talented
in-house labor ensures adherence to strict quality, schedule, and budget expectations.
Encompassing knowledge and experience allow us to ensure quality and maintain accountability. We offer you a partner
that can lead the work and perform it
11
A new 52,000 square
foot library with many
environmentally friendly features
including translucent walls,
solar panels, low water use
landscaping, highly efficient
mechanical and electrical
systems, and low VOC materials
throughout.
A $4.5 million renovation
reconfigured and expanded
spaces within the building’s
existing footprint. A newly
created Hub at the center of
the Library is a gathering place
to meet and make friends,
relax, and read. Learning labs
foster hands-on creativity, from
cutting-edge technology to
cooking to art and music.
Project Type:
New | Renovation
Location:
Bozeman, MT
Project Delivery:
GCCM
Owner Contact:
Jon Henderson
(406) 582-2250
Design Contact:
Mitch Karr
(612) 359-3255
12
The new Belgrade Community
Library is a state-of-the-art facility
to serve a fast-growing town.
A model of modern library
design, it features a welcoming
lobby, gallery space, meeting
rooms, a maker space, offices, a
technology lab, play areas, and
dedicated spaces for private
reading, study, and socializing.
The library offers over 200 seats
for events like youth programs
and economic workshops,
plus a coffee shop. The site
includes parking, street frontage
improvements, a pedestrian
plaza along Main Street, an
outdoor reading plaza, and an
event area.
Project Type:
New
Location:
Belgrade, MT
Project Delivery:
GC/CM
Owner Contact:
Neil Cardwell
(406) 388-3760
Design Contact:
Matt Sedor
(406) 577-2345
13
The project converted an old
athletic gym to a library with a
new main entrance
adult education, children’s
area, teen area and more. In
addition to all new interior and
exterior finishes, a complete
replacement of the HVAC was
included. Site improvements
added asphalt other softscape
upgrades.
Project Type:
Renovation
Location:
Bigfork, MT
Project Delivery:
GC/CM
Owner Contact:
Sara Busse
(406) 253-1708
Design Contact:
Shawn Pauly
(406) 407-7781
14
This complete renovation
increased the library’s public
space by over 2,000 square
feet, adding ADA improvements
to the entrance, the restrooms,
and throughout the library. The
project expanded children’s
programming and creative
Maker’s Space and added
computer labs and community
gathering areas.
Project Type:
Renovation
Location:
Polson, MT
Project Delivery:
GCCM
Owner Contact:
Abbi Dooley
(406) 872-2063
Design Contact:
Jeff Downhour
(406) 220-5016
North Lake County Public Library
Polson, Montana
15
Exhibits
EXHIBIT
Bigfork Library
16
Attachment A
Attachment A
NONDISCRIMINATION AND EQUAL PAY AFFIRMATION
Martel Construction hereby affirms it will not discriminate on the basis of race, color,
religion, creed, sex, age, marital status, national origin, or because of actual or perceived
sexual orientation, gender identity or disability and acknowledges and understands the
eventual contract will contain a provision prohibiting discrimination as described above
and this prohibition on discrimination shall apply to the hiring and treatments or
proposer’s employees and to all subcontracts.
In addition, Martel Construction hereby affirms it will abide by the Equal Pay Act of 1963
and Section 39-3-104, MCA (the Montana Equal Pay Act), and has visited the State of
Montana Equal Pay for Equal Work “best practices” website,
https://equalpay.mt.gov/BestPractices/Employers, or equivalent “best practices
publication and has read the material.
Jason Martel
Bozeman Market President
Martel Construction, Inc.
17
Bozeman Public Library Children’s Room and Teen Corner Remodel
Bozeman,MT 59715
MSR Design #2025021BCR
00 43 23
ALTERNATES FORM
Page 1 of 2
SECTION 00 43 23
ALTERNATES FORM
PARTICULARS
1.01 THE FOLLOWING IS THE LIST OF ALTERNATES REFERENCED IN THE BID SUBMITTED BY:
1.02 (BIDDER)_______________________________
1.03 TO (OWNER ): CITY OF BOZEMAN
1.04 DATED ________________AND WHICH IS AN INTEGRAL PART OF THE BID FORM.
ALTERNATES LIST
2.01 THE FOLLOWING AMOUNTS SHALL BE ADDED TO OR DEDUCTED FROM THE BID AMOUNT. REFER TO
SECTION 01 23 00 -ALTERNATES.
ALTERNATE#1 (ACPNL-4): ADD /(DEDUCT)$________________________
ALTERNATE #2 (ACPNL-5A/B/C AND ACPNL-6A/B/C): ADD /(DEDUCT)$________________________
END OF SECTION
Bozeman Public Library Children’s Room and Teen Corner Remodel
Bozeman,MT 59715
MSR Design #2025021BCR
00 43 36
PROPOSED SUBCONTRACTORS FORM
Page 1 of 2
SECTION 00 43 36
PROPOSED SUBCONTRACTORS FORM
PARTICULARS
1.01 HEREWITH IS THE LIST OF SUBCONTRACTORS REFERENCED IN THE BID SUBMITTED BY:
1.02 (BIDDER)____________________________________
1.03 TO (OWNER ): CITY OF BOZEMAN
1.04 DATED ___________________AND WHICH IS AN INTEGRAL PART OF THE BID FORM.
1.05 THE FOLLOWING WORK WILL BE PERFORMED (OR PROVIDED)BY SUBCONTRACTORS AND COORDINATED
BY US:
LIST OF SUBCONTRACTORS
WORK SUBJECT SUBCONTRACTOR NAME
_______________________________________________________________
_______________________________________________________________
_______________________________________________________________
_______________________________________________________________
_______________________________________________________________
_______________________________________________________________
_______________________________________________________________
_______________________________________________________________
_______________________________________________________________
_______________________________________________________________
_______________________________________________________________
_______________________________________________________________
END OF SECTION