Exhibit A to Professional Services Agreement
TASK ORDER NUMBER 01
Issued under the authority of Professional Services Agreement between the City of Bozeman and HDR Engineering, Inc. for: City of Bozeman Hyalite/ Sourdough Water Treatment Plant Power Study
Implementation
, 2026 between City of Bozeman (City) and This Task Order is dated August 18th
HDR Engineering, Inc. (Contractor).
The following representatives have been designated for the work performed under this Task Order:
City: Griffin Nielsen Contractor: Jarrett Moran
SCOPE OF WORK: (attach additional sheet(s) as required)
1.See Attachment No. 1 for Task Order No. 1 Scope of Services.2.See Attachment No. 2 for Task Order No. 1 Fee Estimate.
COMPENSATION:
The anticipated level of effort for the above Task Order items is based upon the hour projection and expense projection presented in Attachment No. 2.
The anticipated cost for services for the above Task Order items, to be completed on a Time and Materials
Basis not to exceed without prior authorization, is as presented in Attachment No. 2.
Contractor shall be reimbursed on a Time and Materials basis not to exceed the budget amounts presented,
without prior written authorization from the City of Bozeman. Contractor shall notify the City of Bozeman prior to executing additional work and shall not proceed with additional work without written authorization from the City of Bozeman. Contractor shall invoice no more often than monthly for services provided in the
prior month.
The provisions of the Professional Services Master Task Order Agreement and any Special Terms and Conditions and/or Exhibits or Attachments to this Task Order shall govern the Work.
IN WITNESS WHEREOF, the parties authorized to commit resources of the companies have executed this Task Order:
City of Bozeman HDR Engineering, Inc.
By: By: Title: Title: Date: Date:
Fed. ID. No.
Docusign Envelope ID: 91ABE853-A086-8668-82A1-59F377498626
47-0680568
8/20/2026
Vice PresidentCity Manager
8/21/2026
City of Bozeman | WTP On-Call
Hyalite/Sourdough WTP
Power Study Implementation
Scope of Services
hdrinc.com 2150 Analysis Drive, Suite A, Bozeman, MT 59718-3820
(406) 577-5015
1
Attachment No. 1
Hyalite/Sourdough WTP Power Study Implementation
Scope of Services
Introduction
The City of Bozeman (City) Hyalite/Sourdough Water Treatment Plant (WTP) has surge protective
devices (SPDs) located within their motor control centers (MCCs) that have failed at an unusual
rate. This task order is intended to provide coordination and support for the implementation of the
recommendations from the 2023 Power Quality Study, which includes the replacement of eight
(8) failed SPDs and verification of proper operation following installation, review of the installation
of the harmonics filter, including recommended maintenance and adjustments, as needed to
reduce current distortion, by a Schneider Electric Field Representative.
Task 100 – Project Management
Objective and Approach
Provide project management and administrative activities throughout the duration of the task
order that will generally include the following:
• Invoicing, work planning, and administrative activities to manage scope, budget, and
schedule relative to activities summarized within this scope of services.
Deliverables
• Monthly invoices.
• Memoranda and meeting notes, as required.
City Involvement
• Participate in telephone calls and meetings.
• Participate in project meetings.
• Review project status reports and invoices.
• Review modifications to approach, schedule, and deliverables as appropriate.
Task 200 – Power Study Implementation Support
Objective and Approach
Provide coordination and support for the implementation of the 2023 Power Quality Study
recommendations.
Subtask 201 - Surge Protective Device (SPD) Support
Provide coordination and support for the City, Schneider Electric, and the City’s selected On-
Call Electrical Contractor (Electrical Contractor) to procure and install new modules
(TVS4IMA16M) and displays (TVS3DSPVC) for eight (8) failed SPD units, and to provide
technical assistance and post-installation verification of new SPD operation and diagnostic
indications. It is anticipated that the procurement of new equipment by the Electrical Contractor
Docusign Envelope ID: 91ABE853-A086-8668-82A1-59F377498626
City of Bozeman | WTP On-Call
Hyalite/Sourdough WTP
Power Study Implementation
Scope of Services
hdrinc.com 2150 Analysis Drive, Suite A, Bozeman, MT 59718-3820
(406) 577-5015
2
will be through Schneider Electric’s Warranty Claim Process, and a Schneider Electric
Distributor.
SUBTASK 201 ASSUMPTIONS
• HDR will perform visual verification of installed SPD modules and displays during the
site visit. Detailed electrical testing beyond manufacturer startup procedures is excluded.
• Meetings:
o Two (2) 1-Hour Meetings for Two (2) HDR Staff (PM and Electrical Engineer).
• Site Visits:
o One (1) 4-Hour Site Visit for One (1) HDR Staff (Electrical Engineer).
Subtask 202 – Harmonic Filter Evaluation, Maintenance, and Adjustment Support
Provide coordination and support for the City and a Schneider Electric Field Representative to
evaluate the existing AccuSine harmonic filter and components located at the main switchgear,
and provide recommended maintenance and adjustments (e.g., tune filter, verify filter control
settings, balance system loading, increase filter capacity, verify resonance conditions, etc.) to
evaluate existing harmonic filter performance, identify factors contributing to elevated current
distortion, implement adjustments where feasible, and document resulting system performance.
If evaluation determines that additional equipment, filter modifications, or system upgrades are
required to achieve target harmonic performance levels, HDR will document recommendations
for future consideration by the City.
SUBTASK 202 ASSUMPTIONS
• Schneider Electric will provide technical recommendations and necessary
measurements associated with harmonic filter evaluation activities.
• Meetings:
o Two (2) 1-Hour Meetings for Two (2) HDR Staff (PM and Electrical Engineer).
• Site Visits:
o One (1) 2-Hour Site Visit for PM.
o One (1) 8-Hour Site Visit for Electrical Engineer.
• There is potential for supply-side adjustment recommendations based on the harmonic
filter evaluation. Supply-side adjustment recommendations will be noted in the technical
memorandum.
Deliverables
• Technical Memorandum documenting harmonic filter evaluation findings, observed
harmonic performance, recommendations provided by Schneider Electric, and any
recommended future actions.
Task 200 Assumptions
• Additional power quality assessment, analysis, or monitoring services are not anticipated
as part of Task Order No. 1. The scope of work is limited to the activities identified
herein. Should subsequent findings indicate a need for further power quality studies,
extended monitoring, or additional engineering analysis, such services will be addressed
separately and may require separate authorization and funding approval by the City.
Docusign Envelope ID: 91ABE853-A086-8668-82A1-59F377498626
City of Bozeman | WTP On-Call
Hyalite/Sourdough WTP
Power Study Implementation
Scope of Services
hdrinc.com 2150 Analysis Drive, Suite A, Bozeman, MT 59718-3820
(406) 577-5015
3
• Work associated with Task Order No. 1, including the removal of existing equipment and
installation of any new equipment, will be performed by the City’s Electrical Contractor.
The Contractor shall be responsible for all field labor, installation activities, and
coordination necessary to complete the Work in accordance with applicable codes,
specifications, and manufacturer requirements.
• It is anticipated that the eight (8) failed SPD units will be replaced through Schneider
Electric’s Warranty Claim Process. However, if Schneider Electric does not honor the
good-faith replacement commitment discussed and documented in an April 27, 2023,
email, new SPD units will be procured through the City’s Electrical Contractor. In that
event, the City will be responsible for material, labor, and installation costs associated
with the replacement of the failed units.
• The City will be responsible for service charges, including labor, travel, and any
expenses associated with the evaluation, adjustment, troubleshooting, and maintenance
of the harmonic filter performed by a Schneider Electric Field Representative.
• Review of power quality measurements generated by existing plant instrumentation
following harmonic filter adjustments is included. Additional long-term monitoring or
deployment of temporary power quality analyzers is excluded.
• The Power Quality Study completed in 2023 identified elevated current distortion but did
not establish the root cause of the condition, the specific corrective actions required to
achieve desired harmonic performance cannot be fully defined until Schneider Electric
completes its evaluation. If additional corrective measures, equipment modifications, or
engineering analysis are determined to be necessary, HDR will provide
recommendations and assist the City in developing an appropriate path forward under a
separate scope authorization, if requested.
City Involvement
• Participate in telephone calls and meetings.
• Participate in project meetings.
• Provide access, as required, for work associated with Subtask 201 and 202.
• Provide access to available plant power monitoring data and assist with coordination of
Schneider Electric field service visits.
Docusign Envelope ID: 91ABE853-A086-8668-82A1-59F377498626
Attachment No. 2
Client:
Project:
Project Manager Electrical
Engineer Accountant Project Admin Total Hours Labor TOTAL DIRECT
EXPENSES Total Fee
$267.00 $245.00 $134.00 $126.00
Task
100
101 4 6 6 16
4 6 16 2,628
200
201
201.1 2 10 12 2,984
201.2 2 2 4 1,024
201.3 16 16 3,920
201.4 2 2 2,004
202
202.1 4 6 10 2,538
202.2 2 2 4 1,024
202.3 2 20 22 5,434
12 58 70 18,928
16 58 6 86
21,556$ 1,778$ 23,334$
DIRECT EXPENSES $QTY Total Cost
Travel Expenses
Meals (per day)$25.00 4.00 $100.00
Lodging (per day)$300.00 2.00 $600.00
Vehicle Mileage (per mile)$0.88 1225.00 $1,078.00
$1,778.00
August 5, 2026
Project Management
Project Management
Power Study Implementation Support
Subtotal Project Management
City of Bozeman
HyaliteSourdough WTP Power Study Implementation Fee Estimate
Task Description
Billable Rate
TOTAL DIRECT EXPENSES
Surge Protective Device (SPD) Support
General Coordination
Meetings
Site Visits
Harmonic Filter Evaluation, Maintenance, and Adjustment Support
Technical Memorandum
Subtotal Power Study Implementation Support
General Coordination
Meetings
Total Fee
Total Hours
Site Visits