Water Main Extension and Replacement
Engineering Report
6814 Greenwood Avenue N T 206.522.9510
Seattle, WA 981093 www.pacland.com
Prepared By:
Bill Fortunato, P.E.
August 2025
Per the requirements of the Montana Department of Environmental Quality (DEQ) Water Main Extension
and Replacement Certified Checklist, this engineering report has been prepared to address Sections 1.1.1
through 1.1.14 of DEQ-1. These sections are addressed below:
1.1.1. General Information:
a. Description of the existing water works and sewer facilities:
• An 8” ductile iron water main runs north-south through the center of the site, and a 24”
polyethylene sewer pipe runs from the southeast to northwest along the eastern edge of the
site.
b. Identification of the municipality or area served:
• City of Bozeman
c. Name and mailing address of the owner, developer and official custodian:
• Owner/Developer: Discount Tire (Colten Ellsworth)
• 20225 N Scottsdale Rd
• Scottsdale, AZ 85255
• Engineer/Applicant: PACLAND (Bill Fortunato)
• 6814 Greenwood Avenue N
• Seattle, WA 98103
d. Imprint of professional engineer’s seal:
1.1.2. Extent of water works system, including:
a. Description of the nature and extent of the area to be served:
• The proposed scope of work involves removing an existing hydrant that would limit the
available development area and installing a new 26 LF 6” water main to provide fire
protection for the proposed development. The existing easement would be revised to
include the new hydrant and remove the portion around the existing easement.
b. Provisions for extending the water works system to include additional areas:
• No provisions for extending the water system to additional areas are proposed.
c. Appraisal of the future requirements for service, including existing and potential industrial,
commercial, institutional, and other water supply needs:
• Future requirements for the service will remain unchanged. Adjacent properties are
currently developed and served by existing water mains and fire hydrants. The proposed
hydrant is only required in order to provide fire protection for the proposed commercial
development.
1.1.3. Alternate plans:
Where two or more solutions exist for providing public water supply facilities, each of which is
feasible and practicable, discuss the alternate plans. Give reasons for selecting the one
recommended, including financial considerations, and a comparison of the minimum
classification of water works operator required for operation of each alternative facility.
• The alternate plan evaluated was to retain the existing hydrant and utilize it for fire
protection. However, this would push the proposed building footprint to the east and limit
the developable area, and would also run counter to direction from the City of Bozeman to
locate the building as close as possible to the drive aisle that runs north-south on the west
side of the building.
1.1.4. Site Conditions:
Soil, ground water conditions, and foundation problems, including a description of:
a. The character of soil through which water mains are to be laid.
• On-site soils have been classified as generally being Topsoil overlaying Sandy Lean Clay,
medium stiff to very stiff, with sand and scattered gravels and traces of organics (CL)
overlaying a layer of Clayey Gravel with Sand, medium dense to very dense (GC), overlaying
a layer of Well Graded Gravel with Silt and Sand, saturated, medium dense to very dense,
with sand and clay lenses (GW-GM).
b. Foundation conditions prevailing at sites of proposed structures.
• On-site soils are suitable for foundations with a maximum net allowable bearing pressure of
3,500 pounds per square foot. Proposed structure will utilize shallow footings and a floor
slab.
c. The approximate elevation and flow direction of ground water in relation to subsurface structures.
• During geotechnical investigation, groundwater was typically encountered between 6’ and
7.5’ below existing grade. Based on existing topography, it is assumed that groundwater
flows to the north and west.
1.1.5. Water use data, including:
a. A description of the population trends as indicated by available records, and the estimated
population which will be served by the proposed water supply system or expanded system, a
minimum of 20 years in the future in five year intervals or over the useful life of the critical
structures and equipment.
• The proposed main extension will not affect the water supply system, as it will be replacing
a similar existing hydrant.
b. Present water consumption and the projected average and maximum daily demands or peak
instantaneous demand where appropriate, including fire flow demand (see Section 1.1.6).
• Per the City of Bozeman Design and Construction Standards, Section 4.2.7, the required fire
flow based on the project land use (Central Business) is 4,000 gallons per minute. The
standards reference the International Fire Code, which states that fire flows are to be based
on a 20 psi residual pressure, for a duration of 2 hours (based on building size). Since the
proposed fire hydrant would replace the existing hydrant, no change would be experienced
in the demand.
• The fire flow value provided in the referenced section above are guidelines only and may not
be indicative of the requirements for specific developments or buildings. Fire demand for
specific developments shall be in accordance with International Fire Code (IFC) and as
approved by the COB Fire Chief.
c. Present and/or estimated yield of the sources of supply.
• The City of Bozeman relies on snowpack and surface water for its water supply, receiving
80% of its water from the Gallatin Mountains and 20% from developed springs in the
Bridger Mountains. In 2020, total annual metered production was approximately 6,822 ac-
ft.
d. Unusual occurrences.
• The proposed water main extension is only expected to be utilized during emergency fire
conditions.
e. Current estimated percent of unaccounted water for the system and the estimated reduction of
unaccounted water after project completion, if applicable, i.e., project is to replace aged water
mains, leaking storage, or other improvements that will result in reduced water loss.
• The proposed water main extension is not anticipated to reduce water loss. No significant
impact to the amount of unaccounted water is anticipated.
1.1.6. Flow Requirements
a. Hydraulic analyses based on flow demands and pressure requirements (See Section 8.2.1).
• As outlined in 1.1.5.b, fire flow demand for the project is 4,000 gpm at a residual pressure of
20 psi for 2 hours.
b. Fire flows, when fire protection is provided, meeting the recommendations of the fire protection
agency in which the water system is being developed, or in the absence of such a recommendation,
the fire code adopted by the State of Montana. Documentation from the fire protection agency
may be required if the flow requirements vary significantly from typical values.
• Per a fire flow test performed on April 03,2025 at the existing on-site fire hydrant, a flow of
1,600 gpm at 114.2 psi (including a 10% factor of safety) was measured. The calculated
flow for a pressure of 20 psi would be 3,744 GPM. This flow rate is below the required fire
flow value of 4,000 gpm identified in 1.1.6.a. however it is also noted in that section that
the provided value is a guideline. Minimal friction losses due to pipe lengths, valves, bends,
etc. are anticipated, but will not significantly affect the available fire flow. no change would
be experienced in the demand, it is expected that no change would be experienced in the
demand.
1.1.7. Sources of water supply
Describe the proposed source or sources of water supply to be developed, the reasons for their
selection, and provide information as follows:
1.1.7.1 Surface water sources
a. Hydrological data, stream flow and weather records.
b. Safe yield, including all factors that may affect it.
c. Maximum flood flow, together with approval for safety features of the spillway and dam from the
appropriate reviewing authority.
d. Description of the watershed, noting any existing or potential sources of contamination (such as
highways, railroads, chemical facilities, land/water use activities, etc.) which may affect water
quality.
e. Summarized quality of the raw water with special reference to fluctuations in quality, changing
meteorological conditions, etc.
f. Source water protection issues or measures, including erosion and siltation control structures that
need to be considered or implemented.
g. A source water assessment report for surface water sources.
• No surface water sources are appropriate for the proposed water main extension.
1.1.7.2 Ground water sources
a. Sites considered.
b. Advantages of the site selected.
c. Elevations with respect to surroundings.
d. Probable character of formations through which the source is to be developed through nearby well
logs;
e. Geologic conditions affecting the site, such as anticipated interference between proposed and
existing wells.
f. Summary of source exploration, test well depth, and method of construction; placement of liners or
screen; test pumping rates and their duration; water levels and specific yield; water quality.
g. Sources of possible contamination, such as sewers and sewage treatment/disposal facilities,
highways, railroads, landfills, outcroppings of consolidated water-bearing formations, chemical
facilities, waste disposal wells, agricultural uses, etc.
h. A preliminary assessment for proposed ground water sources that may be under the direct
influence of surface water, prepared in accordance with PWS-5, "Assessment of Ground Water
Sources Under the Direct Influence of Surface Water".
i. A source water assessment report prepared in accordance with PWS-6.
• No ground water sources are appropriate for the proposed water main extension.
1.1.8. Proposed treatment processes
Summarize and establish the adequacy of proposed processes and unit parameters for the
treatment of the specific water under consideration. Alternative methods of water treatment
and chemical use should be considered as a means of reducing waste handling and disposal
problems. Bench scale tests, pilot studies, or demonstrations will generally be required to
establish adequacy for some water quality standards.
• Treatment for the City of Bozeman’s water system is provided by two treatment plants, the
Sourdough Creek Water Treatment Plant and the Lyman Creek Water Treatment Plant.
Approximately 5,000+ water quality samples per year are taken from the distribution
system, with 25,000+ water quality tests are performed each year. Per water quality
reports, system test results indicate water being within the acceptable range for all
contaminants evaluated.
1.1.9. Sewage System available
Describe the existing or proposed sewage collection system and sewage treatment works, with
special reference to their relationship to existing or proposed water works structures which may
affect the operation of the water supply system, or which may affect the quality of the supply.
• An existing sewer system will service the proposed commercial development. However, the
proposed water main extension is solely related to fire flow, and is not affected by the
sewage system.
1.1.10. Waste Disposal
Discuss the various wastes from the water treatment plant, their volume, proposed treatment,
and disposal locations. If discharging to a sanitary sewer system, verify that the system,
including any lift stations, is capable of handling the flow to the sewage treatment works and
that the treatment works is capable and will accept the additional loading.
• No discharge to the sanitary sewer system is proposed as part of the main extension.
1.1.11. Automation
Provide supporting data justifying automatic equipment, including the servicing and operator
training to be provided. Manual override must be provided for any automatic controls. Highly
sophisticated automation may put proper maintenance beyond the capability of the plant
operator, leading to equipment breakdowns or expensive servicing. Adequate funding must be
assured for maintenance of automatic equipment.
• No automation is proposed.
1.1.12. Project sites
a. Discussion of the various sites considered and advantages of the recommended ones
• No alternate sites were considered for the development.
b. The proximity of residences, industries, and other establishments.
• The project site is located within a commercial area. Hotels are adjacent to the property to
the north and south. The site is also bounded by the I-90 off-ramp to the east and E Valley
Center road to the west. No residential properties are present in the vicinity of the project
site.
c. Any potential sources of pollution that may influence the quality of the supply or interfere with
effective operation of the water works system, such as sewage absorption systems, septic tanks,
privies, cesspools, sink holes, sanitary landfills, refuse and garbage dumps, etc.
• No sources of pollution are known.
1.1.13. Financing
Provide financial information for new systems or significant improvements with economic
impacts as required in Appendix A.
• The proposed main extension is very minor in nature, and is not considered a significant
system improvement to necessitate providing financial information as outlined in Appendix
A of the Montana Circular DEQ 1.
1.1.14. Future extensions
Summarize planning for future needs and services.
• No future extensions are anticipated. The proposed main extension will provide fire hydrant
coverage for the proposed development.